CN110524662A - A kind of wood moulding flanging production system and production technology - Google Patents
A kind of wood moulding flanging production system and production technology Download PDFInfo
- Publication number
- CN110524662A CN110524662A CN201910901687.9A CN201910901687A CN110524662A CN 110524662 A CN110524662 A CN 110524662A CN 201910901687 A CN201910901687 A CN 201910901687A CN 110524662 A CN110524662 A CN 110524662A
- Authority
- CN
- China
- Prior art keywords
- station
- flanging
- glue
- wood moulding
- slot position
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B27—WORKING OR PRESERVING WOOD OR SIMILAR MATERIAL; NAILING OR STAPLING MACHINES IN GENERAL
- B27C—PLANING, DRILLING, MILLING, TURNING OR UNIVERSAL MACHINES FOR WOOD OR SIMILAR MATERIAL
- B27C9/00—Multi-purpose machines; Universal machines; Equipment therefor
- B27C9/04—Multi-purpose machines; Universal machines; Equipment therefor with a plurality of working spindles
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B27—WORKING OR PRESERVING WOOD OR SIMILAR MATERIAL; NAILING OR STAPLING MACHINES IN GENERAL
- B27G—ACCESSORY MACHINES OR APPARATUS FOR WORKING WOOD OR SIMILAR MATERIALS; TOOLS FOR WORKING WOOD OR SIMILAR MATERIALS; SAFETY DEVICES FOR WOOD WORKING MACHINES OR TOOLS
- B27G11/00—Applying adhesives or glue to surfaces of wood to be joined
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B27—WORKING OR PRESERVING WOOD OR SIMILAR MATERIAL; NAILING OR STAPLING MACHINES IN GENERAL
- B27M—WORKING OF WOOD NOT PROVIDED FOR IN SUBCLASSES B27B - B27L; MANUFACTURE OF SPECIFIC WOODEN ARTICLES
- B27M1/00—Working of wood not provided for in subclasses B27B - B27L, e.g. by stretching
- B27M1/08—Working of wood not provided for in subclasses B27B - B27L, e.g. by stretching by multi-step processes
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B27—WORKING OR PRESERVING WOOD OR SIMILAR MATERIAL; NAILING OR STAPLING MACHINES IN GENERAL
- B27M—WORKING OF WOOD NOT PROVIDED FOR IN SUBCLASSES B27B - B27L; MANUFACTURE OF SPECIFIC WOODEN ARTICLES
- B27M3/00—Manufacture or reconditioning of specific semi-finished or finished articles
- B27M3/08—Manufacture or reconditioning of specific semi-finished or finished articles of specially shaped wood laths or strips
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Wood Science & Technology (AREA)
- Forests & Forestry (AREA)
- Mechanical Engineering (AREA)
- Manufacturing & Machinery (AREA)
Abstract
The present invention relates to moulding processing technical fields, it is therefore an objective to provide a kind of wood moulding flanging production system and production technology, high degree of automation, cost of labor is low, high yield rate.Above-mentioned production system includes feeder and folding brake, the folding brake successively includes left and right fixed width station along production line, determine datum level milling station in left and right, step surface milling station, left and right slot position rough mills station, left and right slot position finish-milling station, slot position dedusting station, gluing station, flanging station and pressure maintaining station, the left and right fixed width station, the left and right slot position rough mills station and the left and right slot position finish-milling station is provided with by separately-driven two cutter shaft of left and right of two motors, the transport mechanism of the folding brake includes that several sections are correspondingly arranged and the upper servo power belt feeder and lower servo power belt feeder of Synchronous Transmission along production line.The present invention solves that the existing productive manpower is at high cost, the low problem of yield rate.
Description
Technical field
The present invention relates to moulding processing technical fields, more particularly to a kind of wood moulding flanging production system and production
Technique.
Background technique
Wood moulding is the common decoration timber of indoor decoration industry, including smallpox printed line, wall surface line, door line etc..It is existing
Wood moulding is vertically to be fit together to be process by two blocks of timber mostly, and main technological steps include passing through babe orchid line
Two blocks of timber are carried out 90 ° of fittings by machine;Lines milling type is carried out by four sides planer;Sand is carried out to lines using irregular sanding machine
Light;PVC cladding is carried out to lines using PUR laminating machine;The processes such as essence section, test package are carried out later.Above-mentioned technical process is multiple
Miscellaneous, the feeding of every procedure, blanking are all carried by processing staff, and essence cut process completely by manual operation, manually at
This height, production efficiency is low, and product quality variance is larger, and yield rate cannot be guaranteed.
For this purpose, there is a kind of folding brake in the prior art, as disclosed one kind in Chinese patent literature CN109227815A
Full-automatic V groove cutting folding brake, including gantry base and transmission device, the gantry base and the fixed company of the transmission device
Connect, in the gantry base along fuselage length direction be successively arranged cutting apparatus, preheating device, point glue equipment, heating device with
And crimping unit, the preheating device are fixedly connected with the gantry base, the point glue equipment and the gantry base side
It is fixedly connected, the heating device is fixedly connected with the gantry base, and the crimping unit and the gantry base are detachable
Connection, the cutting apparatus are equipped with lifting device, and the lifting device is fixedly connected with the cutting apparatus, the lifting dress
It sets and is fixedly connected with the gantry base side, the point glue equipment is equipped with white glue rifle, yellow glue rifle and colloid stirring device,
The white glue rifle and the yellow glue rifle are fixedly connected with the gantry base, and the colloid stirring device disposes on the ground, institute
Colloid stirring device is stated to be fixedly connected with the white glue rifle and the yellow glue rifle.
But this folding brake has the following deficiencies: (1) timber after flanging process forms wood moulding directly off life
Producing line is easy cracking, influences yield rate since glue may be not yet firmly bonded at this time at the flanging of wood moulding;(2) it is transmitted
Mode is that top is unpowered idler wheel, the power idler wheel that lower part is motor control, and upper bottom roller cooperates together pushes down timber in life
It moves in producing line, since top is unpowered follower rollers, is influenced by mechanical oscillation etc., in transmit process, unpowered idler wheel
It is easy to generate relative displacement between timber, leads to the decoration surface wear of timber, scratch occurs, influence product quality;(3) it is milled
Cutting station is six, i.e., 2 cutter shafts, 2 cutter shaft of left and right refine, 1 cutter shaft of bench port are slightly repaired in 1 cutter shaft of fixed width, left and right, wherein left and right is slightly repaired
2 cutter shafts also by same motor driven, cause left cutter shaft and the right side of slightly repairing slightly to repair cutter shaft by same motor driven, 2 cutter shaft of left and right refine
Between and the distance between left refine cutter shaft and right refine cutter shaft position it is unadjustable, prevent the equipment from for difference
The timber flexible modulation working width of size leverages its and is applicable in scope, and due to be it is same motor-driven, it is left thick
Repairing cutter shaft and the right setting position for slightly repairing cutter shaft cannot be staggered, and the setting position of same left refine cutter shaft and right refine cutter shaft is not yet
It can be staggered, prevent otherwise the slot that the cutter shaft of the equipment is deeper from milling size is easy to cut decoration such as the deep trouth of 20-30mm
Film (PVC overlay film), leads to scrap of the product;(4) its flanging mode is slowly to be oriented to flanging using directive wheel, and efficiency is lower, most fastly
It can only achieve 10m/min.
Therefore, existing wood moulding production system and technique cannot since process equipment and technological design are unreasonable at present
Guarantee the quality of product, yield rate is lower, and production efficiency is not also high.
Summary of the invention
For this purpose, technical problem to be solved by the present invention lies in the wood moulding production system and technique of the prior art, finished product
Rate is lower, and product quality is difficult to ensure, and production efficiency is not also high, and product quality, yield rate can be guaranteed by providing one kind
High, high production efficiency wood moulding flanging production system and production technology.
In order to solve the above technical problems, The technical solution adopted by the invention is as follows:
A kind of wood moulding flanging production system, feeder and folding brake including production line connection, the folding brake is along raw
Producing line successively includes that left and right fixed width station, left and right determine datum level milling station, step surface milling station, left and right slot position and rough mill work
Position, left and right slot position finish-milling station, slot position dedusting station, gluing station, flanging station and pressure maintaining station, the left and right fixed width work
Position, the left and right slot position rough mills station and the left and right slot position finish-milling station is provided with by two separately-driven left and right of motor
Two cutter shafts, the transport mechanism of the folding brake include that several sections are correspondingly arranged and the upper servo power skin of Synchronous Transmission along production line
Band machine and lower servo power belt feeder.
Preferably, several flanging wheels, ipsilateral flanging wheel installation are correspondingly arranged in the two sides of the flanging station
On a drive rod, flanging servo motor drives the drive rod and the flanging wheel to do 90 ° of arcs upwards by cam structure
Line movement, makes the flanging wheel become vertical state from horizontality.
Preferably, the flanging station is additionally provided with the photoelectric sensor for controlling the flanging time.
Preferably, it is provided in the two sides of the pressure maintaining station and top several for keeping the wood moulding flanging state
Pressure maintaining directive wheel.
Preferably, the gluing station is provided with the hot melt adhesive machine for spraying hot-melt adhesive, and the hot melt adhesive machine includes glue
Case, control panel, glue pump, sebific duct and glue rifle;
The glue case includes that the hot melt adhesive of thawing is pressed to the upper pressure that the glue pumps for applying pressure from top
Cylinder and glue bucket for hot melt adhesive described in heating and melting;
The glue pump is mounted on the bottom of the glue case, for extracting the hot melt after melting in glue bottom portion
Glue, and progress glue spraying at the glue rifle is delivered to by the sebific duct;
The sebific duct connects the glue pump and the glue rifle, and the sebific duct has heating and heat preserving function;
The glue rifle is used under the control of control system built in the control panel, the sebific duct is conveyed described in coming
Hot melt adhesive being sprayed in processing groove continuously or intermittently.
Preferably, the feeder includes portal frame, and the lower parallel of the portal frame is provided with full tray rolling bar, empty support
Disk rolling bar, lateral transfer belt feeder and the material-dividing and delivery that keeps to the side are arranged between the full tray rolling bar and the empty pallet rolling bar
There is the transverse translation jacking chain for moving pallet, is provided between the full tray rolling bar and the lateral transfer belt feeder
Top chuck device, the material-dividing and delivery that keeps to the side are connect with the production line of the folding brake.
A kind of wood moulding production technology using above-mentioned wood moulding flanging production system, comprising:
(1) the single timber for being covered with decorating film is transported in the transport mechanism of folding brake by feeding;
(2) it slots, opens processing groove on the predetermined position of the timber;
(3) it keeps the temperature for the first time, preheats the timber and the decorating film;
(4) gluing, the gluing in each processing groove;
(5) it keeps the temperature for second, for preventing glue premature setting;
(6) the timber two sides are folded up, form the wood moulding by flanging;
(7) third time is kept the temperature, for stablizing the temperature and ductility of the decorating film;
(8) pressure maintaining, for keeping the flanging form of the wood moulding.
It preferably, is 80-100N, dwell time 5-8s to the dwell pressure of the wood moulding in the pressure holding step;
It is to the holding temperature of the wood moulding in the first time heat preservation, second of heat preservation and the third time incubation step
120-150℃。
Preferably, the glue application step uses interrupted gluing mode or continuous gluing mode, and the glue used includes white
Glue and hot melt adhesive.
Preferably, the grooving step includes that left and right fixed width-left and right datum level milling-step surface milling-left and right slot position is thick
Milling-left and right slot position finish-milling-slot position dedusting.
The above technical solution of the present invention has the following advantages over the prior art:
(1) wood moulding flanging production system provided by the invention passes through sub-material using automatic charging machine flood timber feeding
Mechanism enters folding brake progress lines processing after carrying out sub-material, and finally by being accomplished manually finished product blanking, overall process is using full-automatic
Change production equipment, manpower intervention is few, can substantially save cost of labor, production efficiency is significantly improved, and can ensure that product quality,
High yield rate.
(2) wood moulding flanging production system provided by the invention, the cutter shaft of each milling station, including left and right fixed width station
Left and right cutter shaft, left and right slot position rough mills the left and right cutter shaft of station and the left and right cutter shaft of left and right slot position finish-milling station, be all to have not
It being driven respectively with motor, the distance between each cutter shaft is adjustable, and it can be suitable for various sizes of timber and process, Er Qieyou
Distance is adjustable between the left and right cutter shaft of each station, enables this production equipment to process deep trouth and can not damage Wood surface
Decorating film.
(3) wood moulding flanging production system provided by the invention, folding brake along production line be provided with several positions it is corresponding and
The upper servo power belt feeder and lower servo power belt feeder of Synchronous Transmission, for transmitting timber, upper servo power belt feeder and
Lower servo power belt feeder is formed to laminated structure, and synchronous force feed timber is moved forward along production line, can prevent timber from producing
Positional shift occurs on line, protects decorating film, it is ensured that yield rate.
(4) wood moulding flanging production system provided by the invention, folding brake are provided with several flangings in flanging station two sides
Wheel, is driven with side edgefold wheel by a drive rod, can disposable flanging, convert into high-efficient, 40m/min, flanging can be reached
Servo motor drives drive rod and flanging wheel by cam structure, and it is high to convert into stability, and can guarantee equivalent dynamics and essence
Degree.
(5) wood moulding flanging production technology provided by the invention, increases pressure maintaining process after flanging process, and You Liangtai is watched
It takes that motor control is vertical, distance of horizontal direction is adjusted to adapt to the different wood moulding of size, utilizes the left and right sides and top
Irony directive wheel guarantees that product is not shaken, do not scratched when pressure maintaining, so that it is guaranteed that the flanging form of wood moulding, reduces wood moulding cracking
Risk improves yield rate.
Detailed description of the invention
In order to make the content of the present invention more clearly understood, it below according to specific embodiments of the present invention and combines
Attached drawing, the present invention is described in further detail, wherein
Fig. 1 is the schematic diagram of wood moulding flanging production system of the present invention;
Fig. 2 is the schematic diagram of feeder in wood moulding flanging production system of the present invention;
Fig. 3 is the schematic diagram of folding brake in wood moulding flanging production system of the present invention;
Fig. 4 is the schematic diagram of folding brake transport mechanism in wood moulding flanging production system of the present invention;
Fig. 5 is the timber schematic diagram that folding brake carries out glue application step in wood moulding flanging production system of the present invention;
Fig. 6 is the schematic diagram of folding brake flanging station in wood moulding flanging production system of the present invention.
Appended drawing reference indicates in figure are as follows:
1- feeder, 101- portal frame, 102- full tray rolling bar, 103- empty pallet rolling bar, 104- transverse translation jack chain
Item, 105- lateral transfer belt feeder, 106- keep to the side material-dividing and delivery, 107- top chuck device;
2- folding brake, 201- or so fixed width station, 202- or so determine datum level milling station, 203- step surface milling work
Position, 204- or so slot position rough mill station, 205- or so slot position finish-milling station, 206- slot position dedusting station, 207- gluing station,
208- flanging station, 209- pressure maintaining station, 210- infrared hot plate, the upper servo power belt feeder of 211-, servo power under 212-
Belt feeder, 213- flanging wheel, 214- drive rod, 215- cam structure, 216- flanging servo motor;
3- timber, 301- decorating film, 302,303- glue sites.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
As shown in Figure 1, being a kind of preferred embodiment of wood moulding flanging production system of the present invention, the wood moulding flanging is raw
Production system includes the feeder 1 and folding brake 2 of production line connection.As shown in Fig. 2, the feeder 1 includes portal frame 101, institute
The lower parallel for stating portal frame 1 is provided with full tray rolling bar 102, empty pallet rolling bar 103, lateral transfer belt feeder 105 and keeps to the side
Material-dividing and delivery 106 is provided with the cross for moving pallet between the full tray rolling bar 102 and the empty pallet rolling bar 103
Chain 104 is jacked to translation, is provided with top chuck between the full tray rolling bar 102 and the lateral transfer belt feeder 105
Device 107, the material-dividing and delivery 106 that keeps to the side are connect with the production line of the folding brake 2.The top chuck device 107 is used
In being drawn one layer of material by the full tray rolling bar 102 to the lateral transfer belt feeder 105, the material-dividing and delivery that keeps to the side
106 will be delivered to the subsequent folding brake 2 after the flood Material distribution that comes of the lateral transfer belt feeder 5 conveying.
As shown in figure 3, the folding brake 2 successively includes left and right fixed width station 201 along production line, controls and determine datum level milling
Station 202, step surface milling station 203, left and right slot position rough mill station 204, left and right slot position finish-milling station 205, slot position dedusting work
Position 206, gluing station 207, flanging station 208 and pressure maintaining station 209.All process steps are completed on a machine body, are subtracted
Few artificial participation, saves personnel cost.
As shown in figure 4, the transport mechanism of the folding brake 2 includes that several sections are correspondingly arranged and Synchronous Transmission along production line
Upper power belt machine 211 and lower servo belt feeder 212, the upper power belt machine 211 and the lower formation of servo belt feeder 212
To laminated structure, common force feed timber along production line move forward, can effectively prevent timber occur positional shift and caused by dress
Film is adornd to scratch.
The left and right fixed width station 201 include symmetrically arranged two cutter shafts, two cutter shafts respectively by be horizontally mounted two
A high-speed motor driving, is used for milling timber two sides, carries out timber width direction scale cun.Determine datum level milling work in the left and right
Position 202 includes symmetrically arranged two cutter shafts, and position is driven by the high-speed motor being horizontally mounted respectively in notch surface, two cutter shafts
It is dynamic, be used for processing datum, for subsequent step surface, rough mill, the processing of finish-milling provides unified standard, guarantee machining accuracy.Institute
Stating step surface milling station 203 includes one cutter shaft, is driven by vertically arranged high-speed motor, carries out water relative to material plane
Milling square to processing, for socket step surface.It includes symmetrically arranged two knives that the left and right slot position, which rough mills station 204,
Axis, two cutter shafts are driven by the high-speed motor that is horizontally mounted respectively, for rough milling respectively to converting into slot at two.The left and right
Slot position finish-milling station 205 includes symmetrically arranged two cutter shafts, and two cutter shafts are driven by the high-speed motor being horizontally mounted respectively, used
In respectively to the place's of rough milling progress finish-milling.Position adjustment can be carried out by servo with the motor of finish-milling by rough milling, and make the left and right slot position
It rough mills station 204, the left and right slot position finish-milling station 205 and the left and right and determines the milling cutter of datum level milling station 202 in same
On one horizontal line.All high-speed motor pedestals of above-mentioned five stations are respectively mounted on the slide rail, can be adjusted on motor according to demand
The position of lower left and right, and at each groove milling under datum level be all made of air-flotation type elastic process platform, guarantee datum level, error
Meanwhile also solving the problem of product surface scratches.The slot position dedusting station 206 using dust pelletizing system in slot dust,
Particle is purged, and is blown comprising positive pressure, negative inspiratory pressure two-part structure, and positive pressure air blowing is matched using compressed air and air gun
It closes and blows in alignment slot, after evoking fugitive dust, using depression dust-removing, dust removal port point speed requires to reach 35m/s.
The gluing station 207 is provided with the hot melt adhesive machine for spraying hot-melt adhesive, and the hot melt adhesive machine includes control plane
Plate, glue case, glue pump, sebific duct and glue rifle.Control system built in the control panel is mainly used for being responsible for hot melt adhesive machine each unit
Control, as glue box temperature degree vision-control, sebific duct temperature display adjust, glue rifle temperature display adjust, by control glue revolution speed come
Control the glue-spread size etc. of glue rifle.The glue case includes pressing to the hot melt adhesive of thawing for applying pressure from top
The upper air cylinder that the glue pumps and the glue bucket for hot melt adhesive described in heating and melting.The glue pump is mounted on the bottom of the glue case
Portion, for glue bottom portion extract melt after the hot melt adhesive, and by the sebific duct be delivered at the glue rifle into
Row glue spraying.The sebific duct connects the glue pump and the glue rifle, and the sebific duct has heating and heat preserving function, guarantees hot-melt adhesive glue
Temperature in conveying.The glue rifle is used under the control of control system built in the control panel, and the sebific duct is conveyed
The hot melt adhesive being sprayed in processing groove continuously or intermittently come.
Several flanging wheels 213, the ipsilateral flanging wheel 213 peace are correspondingly arranged in the two sides of the flanging station 208
On a drive rod 214, flanging servo motor 216 drives the drive rod 214 and the flanging by cam structure 215
Wheel 213 does 90 ° of movements in a curve upwards, so that the flanging wheel 213 is become vertical state from horizontality, the flanging wheel 213 is complete
It is acted at flanging.The flanging servo motor 216 is for controlling equivalent dynamics and precision.The flanging station 208 is additionally provided with
For controlling the photoelectric sensor of flanging time, calculated using photoelectric sensor and linear velocity data, controls the equivalent time, guarantee
Yield rate.
It is provided in the two sides of the pressure maintaining station 209 and top several for keeping the guarantor of the wood moulding flanging state
Press directive wheel, the pressure maintaining directive wheel of the left and right sides is arranged on the pressing plate of 209 two sides of pressure maintaining station, two sides it is described
Pressing plate is respectively driven by two servo motors, can adjust the spacing and height of two pressure plates, to realize the guarantor of different size lines
Function is pressed, the pressure maintaining directive wheel is unpowered irony pinch roller, for preventing wood moulding from shaking.
In addition, before the gluing station 207, between the gluing station 207 and the flanging station 208 and
It is provided with infrared hot plate 210 on position after the flanging station 208, is provided on the infrared hot plate 210 red
The temperature of additional thermolamp, the infrared hot plate 210 is constant, and can be adjusted according to room temperature.
Using the above production system carry out wood moulding processing wood moulding flanging production technology the following steps are included:
(1) the single timber 3 for being covered with decorating film 301 is transported in the transport mechanism of folding brake 2 by feeding;
The pallet for being loaded with the placement of more timber is placed on full tray rolling bar 102 and enters feeder 1, reaches specific bit
It postpones, one layer of timber is drawn by top chuck device 107 and is transported to lateral transfer belt feeder 105, lateral transfer belt feeder 105 is horizontal
Material is moved to the material-dividing and delivery 106 that keeps to the side, timber is divided into single rear feeding folding brake 2 by the material-dividing and delivery 106 that keeps to the side, and top is inhaled
Disk device 107 repeats sucking action after pallet is without timber, and empty pallet is moved to empty pallet by transverse translation jacking chain 104
Rolling bar 3 is carried out feeder 1.
Before feeding, every timber be intended to cladding decorating film 301, the decorating film 301 be usually PVC film (PVC,
Polyvinyl chloride, polyvinyl chloride).
(2) it slots, opens processing groove on the predetermined position of the timber 3;
After single timber enters folding brake 2, first passes through left and right fixed width station 201 and carry out basic width direction milling;It
Datum level station 202, which is determined, by left and right afterwards carries out slot position top reference face processing at two;It is then passed through step surface milling station 203
Lines socket is processed;It is then passed through left and right slot position and rough mills the roughing that station 204 carries out slot position, reduce subsequent finishing
Milling amount, guarantee machining accuracy;Pass through slot position dedusting work after milling out final moulding finally by left and right slot position finish-milling station 205
Remove all dusts, particle in position 206.
Wherein, the precision of finish-milling can reach within 10 μm, and material notch must accomplish inverted triangle tip density board after milling
It all eliminates, PVC decorative Film is intact, just can guarantee subsequent gluing, equivalent yield rate.
(3) it keeps the temperature for the first time, preheats the timber 3 and the decorating film 301;
Single timber carries out timber and decorating film 301 by first piece of infrared hot plate 210 after notch dust has been handled
Preheating guarantees that the temperature of subsequent glue application, holding temperature are 120-150 DEG C, preferably 135 DEG C.
(4) gluing, the gluing in each processing groove;
Timber 3 enters gluing station 207, respectively to position applying hot melt adhesives and white glue in Fig. 5 two, glue sites 302
White glue is applied, glue sites 303 apply hot melt adhesive, interrupted gluing mode or continuous gluing mode can be used as needed, the present invention
Technique saves glue using interrupted gluing mode, and the timber after gluing is neatly clean.
(5) it keeps the temperature for second, for preventing glue premature setting;
Timber is kept the temperature by second piece of infrared hot plate 210, for preventing glue premature setting, is guaranteed equivalent effect, is protected
Temperature is 120-150 DEG C, preferably 130 DEG C.
(6) 3 two sides of timber are folded up, form the wood moulding by flanging;
Timber enters equivalent station 208, and flanging servo motor 216 drives drive rod 214 and flanging by cam structure 215
Wheel 213 does 90 ° of movements in a curve upwards, and the two sides of timber 3 are folded up by flanging wheel 213, realizes disposable equivalent, formation wood strip
Item.
(7) third time is kept the temperature, for stablizing the temperature and ductility of the decorating film 301;
Timber is kept the temperature by third block infrared hot plate 210, for stablizing the temperature and ductility of decorating film 301, makes PVC
There is not blushing after decorating film is equivalent.Holding temperature is 120-150 DEG C, preferably 125 DEG C.
(8) pressure maintaining, for keeping the flanging form of the wood moulding;
Timber enters pressure maintaining station 209, for keeping the flanging form of the wood moulding, makes glue bonding securely, guarantees
Product quality.According to production requirement, dwell pressure 80-100N, dwell time 5-8s, preferably dwell pressure are 90N, pressure maintaining
Time is 6s.
Obviously, the above embodiments are merely examples for clarifying the description, and does not limit the embodiments.It is right
For those of ordinary skill in the art, can also make on the basis of the above description it is other it is various forms of variation or
It changes.There is no necessity and possibility to exhaust all the enbodiments.And it is extended from this it is obvious variation or
It changes still within the protection scope of the invention.
Claims (10)
1. a kind of wood moulding flanging production system, it is characterised in that: feeder (1) and folding brake (2) including production line connection,
The folding brake (2) successively includes left and right fixed width station (201) along production line, controls and determine datum level milling station (202), step
Facing cut cuts station (203), left and right slot position rough mills station (204), left and right slot position finish-milling station (205), slot position dedusting station
(206), gluing station (207), flanging station (208) and pressure maintaining station (209), the left and right fixed width station (201), the left side
Right slot position rough mills station (204) and the left and right slot position finish-milling station (205) is provided with by two separately-driven left sides of motor
Right two cutter shafts, the transport mechanism of the folding brake (2) include that several sections are correspondingly arranged and the upper servo of Synchronous Transmission along production line
Power belt machine (211) and lower servo power belt feeder (212).
2. wood moulding flanging production system according to claim 1, it is characterised in that: in the flanging station (208)
Two sides are correspondingly arranged on several flanging wheels (213), and the ipsilateral flanging wheel (213) is mounted on a drive rod (214), folding
Side servo motor (216) drives the drive rod (214) and the flanging wheel (213) to do 90 ° upwards by cam structure (215)
Movement in a curve makes the flanging wheel (213) become vertical state from horizontality.
3. wood moulding flanging production system according to claim 2, it is characterised in that: the flanging station (208) also sets
It is equipped with the photoelectric sensor for controlling the flanging time.
4. wood moulding flanging production system according to claim 2, it is characterised in that: in the pressure maintaining station (209)
Two sides and top are provided with several for keeping the pressure maintaining directive wheel of the wood moulding flanging state.
5. wood moulding flanging production system according to claim 1, it is characterised in that: gluing station (207) setting
There is the hot melt adhesive machine for spraying hot-melt adhesive, the hot melt adhesive machine includes glue case, control panel, glue pump, sebific duct and glue rifle;
The glue case includes that the hot melt adhesive of thawing is pressed to the upper air cylinder that the glue pumps for applying pressure from top
And the glue bucket for hot melt adhesive described in heating and melting;
The glue pump is mounted on the bottom of the glue case, for extracting the hot melt adhesive after melting in glue bottom portion, and
Progress glue spraying at the glue rifle is delivered to by the sebific duct;
The sebific duct connects the glue pump and the glue rifle, and the sebific duct has heating and heat preserving function;
The glue rifle is used under the control of control system built in the control panel, the hot melt that sebific duct conveying is come
Glue being sprayed in processing groove continuously or intermittently.
6. wood moulding flanging production system according to claim 1, it is characterised in that: the feeder (1) includes gantry
Frame (101), the lower parallel of the portal frame (1) are provided with full tray rolling bar (102), empty pallet rolling bar (103), lateral transfer
Belt feeder (105) and the material-dividing and delivery that keeps to the side (106), between the full tray rolling bar (102) and the empty pallet rolling bar (103)
It is provided with transverse translation jacking chain (104) for moving pallet, the full tray rolling bar (102) and the lateral transfer skin
It is provided with top chuck device (107) between band machine (105), the material-dividing and delivery that keeps to the side (106) and the folding brake (2)
Production line connection.
7. a kind of wood moulding production technology using any wood moulding flanging production system of claim 1-6, feature exist
In, comprising:
(1) the single timber (3) for being covered with decorating film (301) is transported in the transport mechanism of folding brake (2) by feeding;
(2) it slots, opens processing groove on the predetermined position of the timber (3);
(3) it keeps the temperature for the first time, preheats the timber (3) and the decorating film (301);
(4) gluing, the gluing in each processing groove;
(5) it keeps the temperature for second, for preventing glue premature setting;
(6) timber (3) two sides are folded up, form the wood moulding by flanging;
(7) third time is kept the temperature, for stablizing the temperature and ductility of the decorating film (301);
(8) pressure maintaining, for keeping the flanging form of the wood moulding.
8. wood moulding production technology according to claim 7, it is characterised in that: to the wood moulding in the pressure holding step
Dwell pressure be 80-100N, dwell time 5-8s;The first time heat preservation, second of heat preservation and the third time
It is 120-150 DEG C to the holding temperature of the wood moulding in incubation step.
9. wood moulding production technology according to claim 8, it is characterised in that: the glue application step uses interrupted gluing side
Formula or continuous gluing mode, the glue used include white glue and hot melt adhesive.
10. wood moulding production technology according to claim 9, it is characterised in that: the grooving step includes left and right fixed width-
Left and right datum level milling-step surface milling-left and right slot position rough mills-left and right slot position finish-milling-slot position dedusting.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910901687.9A CN110524662B (en) | 2019-09-23 | 2019-09-23 | Wood strip edge folding production system and production process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910901687.9A CN110524662B (en) | 2019-09-23 | 2019-09-23 | Wood strip edge folding production system and production process |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110524662A true CN110524662A (en) | 2019-12-03 |
CN110524662B CN110524662B (en) | 2021-08-24 |
Family
ID=68669743
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910901687.9A Active CN110524662B (en) | 2019-09-23 | 2019-09-23 | Wood strip edge folding production system and production process |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110524662B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113579052A (en) * | 2021-07-27 | 2021-11-02 | 山东清特金仓保温科技有限公司 | Equipment and method for preparing heating material |
CN114308545A (en) * | 2022-01-06 | 2022-04-12 | 江苏鑫城包装科技有限公司 | Dispensing equipment for wine box |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2263251A1 (en) * | 1972-12-23 | 1974-06-27 | Lehbrink Fa Wilhelm | METHOD AND DEVICE FOR MANUFACTURING FRAMES, PROFILES OR PLATES WITH A SIDE-SIDE UNINTERRUPTED TOP LAYER |
JPH10100113A (en) * | 1996-10-01 | 1998-04-21 | Hiromi Shibata | Manufacture of wooden fittings material and wooden furniture material or the like, and adhesive scraping mechanism in manufacturing line of wooden fittings material and wooden furniture material and so on |
CN1639039A (en) * | 2002-02-26 | 2005-07-13 | 柯尼格及包尔公开股份有限公司 | Folding drums of a folding device |
CN203048272U (en) * | 2013-01-11 | 2013-07-10 | 上海昀丰新能源科技有限公司 | Lead-acid cell automatic board package machine and diaphragm transporting clamping mechanism thereof |
JP2013146868A (en) * | 2012-01-17 | 2013-08-01 | Daiken Corp | Method for producing decorative material |
CN203711982U (en) * | 2014-03-12 | 2014-07-16 | 宁波市鄞州多凡国际贸易有限公司 | Semi-automatic slitting cutter striping material-out guiding machine |
CN205187301U (en) * | 2015-11-12 | 2016-04-27 | 青岛铸英特陶科技有限公司 | From turn tray conveyor |
CN205330102U (en) * | 2016-01-04 | 2016-06-22 | 江山欧派门业股份有限公司 | Hem lines |
CN205380756U (en) * | 2015-11-25 | 2016-07-13 | 江山欧派门业股份有限公司 | Right angle socket lines production line |
CN105857718A (en) * | 2016-06-16 | 2016-08-17 | 吉林省农业机械研究院 | Layered film-covering finishing device of dried bean curd |
CN109051777A (en) * | 2018-07-16 | 2018-12-21 | 江苏力维智能装备有限公司 | A kind of gantry sucker automatical feeding system |
CN208666375U (en) * | 2018-06-07 | 2019-03-29 | 贵阳普天物流技术有限公司 | A kind of positioning device for ensuring manipulator and grabbing special-shaped object |
-
2019
- 2019-09-23 CN CN201910901687.9A patent/CN110524662B/en active Active
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2263251A1 (en) * | 1972-12-23 | 1974-06-27 | Lehbrink Fa Wilhelm | METHOD AND DEVICE FOR MANUFACTURING FRAMES, PROFILES OR PLATES WITH A SIDE-SIDE UNINTERRUPTED TOP LAYER |
JPH10100113A (en) * | 1996-10-01 | 1998-04-21 | Hiromi Shibata | Manufacture of wooden fittings material and wooden furniture material or the like, and adhesive scraping mechanism in manufacturing line of wooden fittings material and wooden furniture material and so on |
CN1639039A (en) * | 2002-02-26 | 2005-07-13 | 柯尼格及包尔公开股份有限公司 | Folding drums of a folding device |
JP2013146868A (en) * | 2012-01-17 | 2013-08-01 | Daiken Corp | Method for producing decorative material |
CN203048272U (en) * | 2013-01-11 | 2013-07-10 | 上海昀丰新能源科技有限公司 | Lead-acid cell automatic board package machine and diaphragm transporting clamping mechanism thereof |
CN203711982U (en) * | 2014-03-12 | 2014-07-16 | 宁波市鄞州多凡国际贸易有限公司 | Semi-automatic slitting cutter striping material-out guiding machine |
CN205187301U (en) * | 2015-11-12 | 2016-04-27 | 青岛铸英特陶科技有限公司 | From turn tray conveyor |
CN205380756U (en) * | 2015-11-25 | 2016-07-13 | 江山欧派门业股份有限公司 | Right angle socket lines production line |
CN205330102U (en) * | 2016-01-04 | 2016-06-22 | 江山欧派门业股份有限公司 | Hem lines |
CN105857718A (en) * | 2016-06-16 | 2016-08-17 | 吉林省农业机械研究院 | Layered film-covering finishing device of dried bean curd |
CN208666375U (en) * | 2018-06-07 | 2019-03-29 | 贵阳普天物流技术有限公司 | A kind of positioning device for ensuring manipulator and grabbing special-shaped object |
CN109051777A (en) * | 2018-07-16 | 2018-12-21 | 江苏力维智能装备有限公司 | A kind of gantry sucker automatical feeding system |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113579052A (en) * | 2021-07-27 | 2021-11-02 | 山东清特金仓保温科技有限公司 | Equipment and method for preparing heating material |
CN114308545A (en) * | 2022-01-06 | 2022-04-12 | 江苏鑫城包装科技有限公司 | Dispensing equipment for wine box |
Also Published As
Publication number | Publication date |
---|---|
CN110524662B (en) | 2021-08-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106926340B (en) | A kind of manufacturing process and manufacturing device of plate fitment | |
CN110563320B (en) | Large-breadth glass cutting and splitting device adopting laser | |
CN104818350B (en) | Full-automatic leather print cuts machine and its print blanking method | |
KR100845113B1 (en) | Glass cutting system | |
CN205058038U (en) | Seven manipulators and seven manipulator cnc engraving and milling machine | |
CN109130329A (en) | A kind of five layers of corrugated paper production line | |
CN206678456U (en) | A kind of disposable carton forming machine | |
CN206567973U (en) | curved surface automatic polishing machine | |
CN108558194A (en) | A kind of glass processing system | |
CN110524662A (en) | A kind of wood moulding flanging production system and production technology | |
CN108495470A (en) | A kind of automatic production line that pcb board nailing is encapsulated | |
CN211197878U (en) | Glass pretreatment production line | |
CN107082142A (en) | A kind of sheet material covering film system and film covering method | |
CN102642232B (en) | Automatic L-shaped line molding machine | |
CN110745553A (en) | Glass pretreatment production line | |
CN107378731A (en) | A kind of automatic profiling sander | |
CN115649919A (en) | Hot-melting cutting machine and cutting method thereof | |
CN110355837B (en) | Plywood numerical control assembly line overall structure | |
CN205272869U (en) | Vulcanize laser marking machine of signing | |
CN208827135U (en) | Two-sided coating production line | |
CN108820424B (en) | Angle strip workpiece machining system | |
CN110877245B (en) | Fiberboard sanding machine capable of improving smoothness and working method thereof | |
CN108943290B (en) | Full-automatic high-speed line production system | |
CN212765431U (en) | Plate engraving machine | |
CN216271890U (en) | Glass snatchs automated production equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |