CN110512788A - A kind of clean operating room assembled electrolysis steel plate linked system and its construction method - Google Patents
A kind of clean operating room assembled electrolysis steel plate linked system and its construction method Download PDFInfo
- Publication number
- CN110512788A CN110512788A CN201910837062.0A CN201910837062A CN110512788A CN 110512788 A CN110512788 A CN 110512788A CN 201910837062 A CN201910837062 A CN 201910837062A CN 110512788 A CN110512788 A CN 110512788A
- Authority
- CN
- China
- Prior art keywords
- keel
- wall
- steel plate
- assembled
- top plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/001—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by provisions for heat or sound insulation
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/006—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation with means for hanging lighting fixtures or other appliances to the framework of the ceiling
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/04—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation comprising slabs, panels, sheets or the like
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/04—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation comprising slabs, panels, sheets or the like
- E04B9/045—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation comprising slabs, panels, sheets or the like being laminated
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/06—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/0801—Separate fastening elements
- E04F13/0803—Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/0875—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements having a basic insulating layer and at least one covering layer
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/0889—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements characterised by the joints between neighbouring elements, e.g. with joint fillings or with tongue and groove connections
- E04F13/0891—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements characterised by the joints between neighbouring elements, e.g. with joint fillings or with tongue and groove connections with joint fillings
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Electrolytic Production Of Non-Metals, Compounds, Apparatuses Therefor (AREA)
Abstract
The invention discloses a kind of clean operating room assembled electrolysis steel plate linked system and its construction method, linked system includes that the top plate keel being connected under top plate, the wall body keel being connected on the inside of wall, the diagonal brace being connected between wall and wall body keel and the assembled being connected on top plate keel and wall body keel are electrolysed steel plate;Assembled electrolysis steel plate piecemeal is assembled, and assembled is electrolysed steel plate and connects respectively with top plate keel and wall body keel mounting;The end of adjacent assembled electrolysis steel plate is provided with flange, and flange is connected with corresponding top plate keel or wall body keel.When construction, on the other hand assembled electrolysis steel plate of the present invention can guarantee the installation tightness of electrolysis steel plate by hanging and welding dual connection type, on the one hand convenient construction;By the setting of top plate keel and wall body keel, wall body keel is connect with top plate and bottom plate by corner fittings respectively, and diagonal brace is provided between wall body keel and wall, further enhances the stable connection of wall body keel.
Description
Technical field
The present invention relates to operation room wallboard construction technology, in particular to a kind of clean operating room assembled electrolysis steel plate connection
System and its construction method.
Background technique
Operating room is that the important place of operation and rescue is provided for patient.The form of operating room is also from distributed hand before
Art room sum aggregate intermediate surgeries room develops clean operating room till now.For clean operating room, the construction one of metope and top plate
As constructed by whole welding type, but when whole welding type operating room is constructed, electrolysis steel plate used in metope and top plate needs
Welded by on-site consolidation, electric welding field and spraying operation amount are larger, more demanding to construction personnel's handicraft, and construction period compared with
It is long, it is time-consuming;In addition, piece weld be easy to cause paint topcoat because expanding with heat and contract with cold in the integrally welding of electrolysis steel plate
Cracking, poly-putty base, which is dealt with improperly, is easy to cause antibiotic paint to chemically react with metal, floating trace occurs.In addition, In
In integral solder construction, it is unfavorable for door-window opening for change design and construction;And assembly construction method, have and meets batch
The characteristics of construction and saving working hour.Therefore, in conjunction with fabricated construction, clean operating room functional requirement, again can be met by providing one kind
It can convenient construction usage and the firm clean operating room electrolysis steel plate linked system of installation quality and its construction method.
Summary of the invention
The present invention provides a kind of clean operating room assembled electrolysis steel plate linked system and its construction methods, to solve
Assembled electrolysis steel plate assembly mounting, top plate and wall body keel are reinforced and the technologies such as assembled electrolysis steel plate design installation are asked
Topic.
To achieve the above object, the present invention adopts the following technical scheme:
A kind of clean operating room assembled is electrolysed steel plate linked system, comprising be connected under top plate top plate keel, be connected to wall
It the wall body keel of internal side, the diagonal brace being connected between wall and wall body keel and is connected on top plate keel and wall body keel
Assembled is electrolysed steel plate;Assembled electrolysis steel plate piecemeal is assembled, assembled be electrolysed steel plate respectively with top plate keel and
Wall body keel mounting connection, wherein connected between assembled electrolysis steel plate and wall body keel by wall pendant, assembled is electrolysed steel plate
It is connect between top plate keel by connector;
Adjacent assembled electrolysis steel plate connecting sewing is arranged at top plate keel or wall body keel, adjacent assembled electrolysis steel plate connection
It is filled with sealant at seam, the end of adjacent assembled electrolysis steel plate is provided with flange, flange and corresponding top plate keel or wall
Keel connection.
Further, the assembled electrolysis steel plate includes the plasterboard that electrolysis steel plate is connected with the back side, is connected on plasterboard
It is stupefied to be connected to steel back;The electrolysis steel plate surface layer is high-pressure electrostatic anti-bacterial powder baking vanish.
Further, the wall body keel includes wall centre keel and the wall transom being vertically connected on wall centre keel
Keel are mounted with wall;The top of the wall centre keel is connect by corner fittings with top plate, and bottom end is connected in wall transom.
Further, wall mounting keel correspond to assembled electrolysis steel plate and wall hole setting, wall mount keel and
Wall pendant is connected between assembled electrolysis steel plate;The wall mounting keel are angle-shaped piece, and angle-shaped piece inner corner trim is towards wall, angle-shaped piece
One side is flushed with wall centre keel, another side vertical wall centre keel.
Further, the wall pendant includes upper L shape part and the lower L shape part being connected to below L shape part;Wherein, upper L shape
Part is right angle, and the corresponding formula electrolysis steel plate that is linked and packed in the long side face of upper L shape part, the short side end of upper L shape part connects lower L shape part
Long side top;Lower L shape part inner corner trim is obtuse angle, and lower L shape part external corner and upper L shape part long side extended line horizontal distance adapt to wall mounting dragon
Bone side thickness.
Further, be connected with wall between the wall pendant and assembled electrolysis steel plate and connect part, the wall connect part by U-shaped part and
Alternately connection is combined into inverted U-shaped part;The sealing side of U-shaped part and inverted U-shaped part alternative one is connected on assembled electrolysis steel plate, separately
One sealing side is connect with the upper L shape part long side of wall pendant;The thickness that wall connects part adapts to assembled electrolysis steel plate and wall mounts keel
Between horizontal width.
Further, the connector includes the adapter of the connecting rod connecting with top plate and connection boom end connection;Institute
It states adapter to connect with top plate keel upper side, adapter is that L hooks part, angle-shaped piece or connecting plate.
Further, the flange downside that the assembled electrolysis steel plate is connect with top plate keel is connected with top even part, top
Even anchoring piece is connected between part and adapter;Even part is angle-shaped piece or connecting plate on the top, and anchoring piece is bolt or pin rod.
Further, the top plate keel in the top plate surrounding and corner are connected with diagonal brace, diagonal brace and wall between wall respectively
Body is connected by corner fittings;Top plate keel are connect at inner corner trim with wall body keel is connected with corner fittings.
Further, the construction method of a kind of clean operating room assembled electrolysis steel plate linked system, specific steps
It is as follows:
Step 1: checking clean operating room region spatial position and size according to clean operating room architectural drawing, scene is drawn
Measurement figure;By in-site measurement figure, the Deepen Design of clean operating room is carried out;When clean operating room design in-depth, carry out top plate
The design of keel and wall body keel, and according to wall and the demands such as mounting of roof plate equipment or ventilation setting wall hole and top plate hole
Mouth and the electrolysis steel plate typesetting of corresponding progress assembled and lattice portal design;
Step 2: production assembled is electrolysed steel plate, the electrolysis steel plate back side is connected into plasterboard, connects steel back in gypsum back
It is stupefied, and high-pressure electrostatic anti-bacterial powder baking vanish is made in electrolysis steel plate surface layer;By the assembled to complete electrolysis steel plate according to row
Version carries out various sizes of division production, and the assembled of each plate is electrolysed plating numerals;
Step 3: making according to Deepen Design drawing and installing wall body keel;Line core is controlled to wall body keel on clean operating room
After examination is received, the wall transom of wall body keel bottom end is fixed on bottom plate, after verification wall transom position is errorless, by the perpendicular dragon of wall
Bone top is fixed on top plate using corner fittings, and bottom end is fixed in wall transom;Using wall corner as wall body keel starting point,
It is sequentially arranged wall centre keel, wall transom and wall mounting keel, wherein wall mounts spine arrangement spacing and assembled is electrolysed steel plate
Sub-cell width is consistent, highly selected according to actual needs;
Step 4: making according to Deepen Design drawing and installing top plate keel;After top plate keel control line verifies examination, according to
The layout drawing of top plate keel pops up top plate Keel Line on bottom plate, is projected with laser by by bottom plate upper plate keel control line
On top board surface, along top plate keel control line installation connecting element;Top plate keel and root are well placed by bottom plate unwrapping wire position is corresponding
According to design drawing assembly, after the completion of assembled, top plate keel is lifted by crane by two chain blocks, are lifted at connector, school
After core meets error requirements, top plate keel and wall are connected with diagonal brace;Wherein, there is flat top imperial design on top plate keel
Bone, arc top plate keel or air-blow ceiling hole keel, carry out the handover transition and hanging of variant top plate keel junction
Point Encryption Design;Junction is installed for top plate keel and wall body keel, corner fittings is installed at inner corner trim below the junction;
Step 5: the assembled on installation wall body keel is electrolysed steel plate, connection wall pendant in advance is first electrolysed on steel plate in assembled
Connect part with wall, is placed in the corresponding assembled electrolysis steel plate of each wall of clean operating room accordingly according still further to Deepen Design drawing
Position;First from door opening place side according to clockwise successively perimeter mounted formula electrolysis steel plate and wall body keel mount,
Then it smooths, be straightened, then the flange of assembled electrolysis steel plate is connect with wall body keel;Finally, wall and bottom plate corner
Assembled electrolysis steel plate is installed on corner, and corresponding installation waterproof layer;
Step 6: the assembled on installation top plate keel is electrolysed steel plate, even part is pushed up in installation on assembled electrolysis steel plate in advance, then
Assembled electrolysis steel plate is sequenced according to Deepen Design drawing, first carries out the assembled electrolysis hoisting steel plate of plane at no hole,
The assembled electrolysis steel plate being equipped at top plate hole again;Top even part is connect with connector by anchoring piece after lifting up,
The flange of assembled electrolysis steel plate is connect with wall body keel again;Finally by the top plate keel on periphery assembled electrolysis steel plate with
The assembled electrolysis steel plate opposite joint connection installed on wall body keel, and corresponding installation insulating layer;
Step 7: the filling with sealant at each splicing seams, and the assembled electrolysis steel plate on wall body keel and top plate keel is spelled
Seam carries out verification adjustment;Then, check and modify engineering defect when installing on assembled electrolysis steel plate;Further installation dress
Decorations property attachment and corresponding installation door and window, lamps and lanterns and other equipment at wall hole and top plate hole, finally carry out cleaning and tidying
With dyestripping gluing.
The beneficial effects of the present invention are embodied in:
1) present invention is electrolysed the setting of steel plate by assembled, and electrolysis surface of steel plate is sprayed high-pressure electrostatic anti-bacterial powder baking vanish,
Cleaning in clean operation room, comfortable and environmentally friendly functionalization requirement can be met;And assembled electrolysis steel plate passes through hanging and welding
Dual connection type, on the one hand avoid integral solder construct technological problems, on the other hand can guarantee convenient construction and electrolysis
The installation tightness of steel plate;
2) present invention passes through the setting of top plate keel and wall body keel, and wall body keel is connected with top plate and bottom plate by corner fittings respectively
It connects, diagonal brace is provided between wall body keel and wall, further enhance the stable connection of wall body keel;Top plate keel respectively with
It is provided with diagonal brace between wall and top plate, and is provided with reinforcer between top plate keel and wall body keel, formula is electrolysed steel to be linked and packed
Plate provides reliable support system;
3) it when the present invention passes through construction, first to the installation hole of needed equipment or structure at wall body keel and top plate keel, carries out
It reserves and is designed for changing, then steel plate is electrolysed by assembled and carries out preparatory typesetting and design, so that can in formally installation
Guarantee the installation quality at hole and saves the construction time;
In addition, the present invention in construction and installation, because of its functionalization demand, is provided with waterproof layer in bottom comers, in top corners
It is provided with insulating layer, and is filled with sealant between adjacent electrolysis steel plate, conducive to the use of clean operating room;The present invention is using dress
With formula technique, site workload is small, and construction quality is high, is conducive to mass production, reduces construction cost;Other feature of the invention
It will be illustrated in the following description with advantage, and partly as will become apparent from the description, or by implementing this
It invents and understands;The main object of the present invention and further advantage can be realized by scheme specifically noted in the description and
It obtains.
Detailed description of the invention
Fig. 1 is clean operating room assembled electrolysis steel plate linked system vertical profile figure;
Fig. 2 is the vertical distribution schematic diagram of wall body keel;
Fig. 3 is that top plate and assembled are electrolysed steel plate connection schematic diagram;
Fig. 4 is that bottom plate and assembled are electrolysed steel plate connection schematic diagram;
Fig. 5 is that assembled electrolysis steel plate and wall mount keel connection schematic diagram.
Appended drawing reference: 1- top plate, 2- wall, 3- bottom plate, 4- top plate keel, 5- wall body keel, 51- wall centre keel, 52- wall
Transom, 53- wall mounting keel, 6- diagonal brace, 7- assembled electrolysis steel plate, 71- electrolysis steel plate, 72- plasterboard, 73- sealant,
8- connector, 81- connecting rod, 82- adapter, 9- insulating layer, 10- waterproof layer, 11- wall hole, 12- corner fittings, 13- wall connect
L shape part, the top 15- connect part, 16- anchoring piece under part, 14- wall pendant, the upper L shape part of 141-, 142-.
Specific embodiment
By taking certain clean operating room as an example, as shown in Figure 1, being electrolysed the company with top plate 1 and wall 2 respectively of steel plate 7 for assembled
Connect sectional view.Clean operating room assembled electrolysis 7 linked system of steel plate includes the top plate keel 4 being connected under top plate 1, is connected to
The wall body keel 5 of the inside of wall 2, the diagonal brace 6 being connected between wall 2 and wall body keel 5 and it is connected to top plate keel 4 and wall
Assembled on keel 5 is electrolysed steel plate 7;Assembled be electrolysed 7 piecemeal of steel plate it is assembled, assembled be electrolysed steel plate 7 respectively with top
Board keel 4 and the mounting connection of wall body keel 5, wherein assembled is electrolysed between steel plate 7 and wall body keel 5 and is connected by wall pendant 14,
It is connected between assembled electrolysis steel plate 7 and top plate keel 4 by connector 8.
In the present embodiment, assembled is electrolysed steel plate 7 and does substrate by electrolysis steel plate 71, electrolysis 71 thickness of steel plate have 1.0mm,
1.2mm and tri- kinds of 1.5mm in 71 backing high-strength waterproof gypsum board 72 of electrolysis steel plate and reinforce C-type steel back cord, and surface layer is that high pressure is quiet
Electric anti-bacterial powder baking vanish.This assembled, which is electrolysed steel plate 7, has good thermal insulation, is not likely to produce and gathers electrostatic, and surface is flat
Cunning is not easy dust, is not easy adhesive dust and is easy to remove dust.
In the present embodiment, adjacent assembled electrolysis 7 connecting sewing of steel plate is arranged at top plate keel 4 or wall body keel 5, adjacent
Assembled, which is electrolysed at 7 connecting sewing of steel plate, is filled with sealant 73, and the end of adjacent assembled electrolysis steel plate 7 is provided with flange, turns over
Side is welded to connect with corresponding top plate keel 4 or wall body keel 5.
As shown in Fig. 2, wall body keel 5 includes wall centre keel 51 and the horizontal dragon of the wall being vertically connected on wall centre keel 51
Bone 52 and wall mount keel 53, and wherein wall centre keel 51 and wall transom 52 are made for square steel tube, and junction is using welding;
The top of wall centre keel 51 is bolted by corner fittings 12 with top plate 1, and bottom end is welded or is bolted in wall transom 52.Wall
Transom 52 is distributed in 51 bottom end of wall centre keel and top furred ceiling or hangs canopy position, and wall transom 52 passes through bolt or pre-buried
Part is connect with bottom plate 3;Wall mounts the corresponding assembled electrolysis steel plate 7 of keel 53 and wall hole 11 is arranged, wall mount keel 53 with
Wall pendant 14 is connected between assembled electrolysis steel plate 7;It is angular steel part that wall, which mounts keel 53, and angle-shaped piece inner corner trim is towards wall 2, angle
Shape part one side is flushed with wall centre keel 51, another side vertical wall centre keel 51.
As shown in figure 3, connector 8 includes to connect with the bolted connecting rod 81 of top plate 1 and 81 bottom bolts of connecting rod
Adapter 82;Adapter 82 is that steel L shape hooks part and welds with 4 upper side of top plate keel, in addition, adapter 82 can also be angle
Shape part or connecting plate are welded or are bolted with corresponding top plate keel 4;Assembled is electrolysed what steel plate 7 was welded with top plate keel 4
Flange downside is welded with top even part 15, and even part 15 is steel angle-shaped piece or junction steel plate on top;Top, which connects, is welded with anchoring on part 15
Part 16, anchoring piece 16 are bolt or pin rod.When installation, anchoring piece 16 and adapter 82 are connected and fixed.In addition, 1 surrounding of top plate
And the top plate keel 4 in corner are connected with diagonal brace 6 between wall 2 respectively, diagonal brace 6 is connect with wall 2 by corner fittings 12, and diagonal brace 6 is
Rectangular steel tube production;Top plate keel 4 are connect at inner corner trim with wall body keel 5 is connected with corner fittings 12, and corner fittings 12 is square steel part.
As shown in Figure 4 and Figure 5, wall pendant 14 is steel component, and wall pendant 14 includes upper L shape part 141 and is connected to L shape
The lower L shape part 142 of 141 lower section of part;Wherein, upper L shape part 141 is right angle, and the long side face of upper L shape part 141 corresponds to assemble welding
Formula is electrolysed steel plate 7, and the short side end welding of upper L shape part 141 or integral production connect lower 142 long side top of L shape part;Lower L shape part
142 inner corner trims are obtuse angle, and lower 142 external corner of L shape part and upper 141 long side extended line horizontal distance of L shape part adapt to wall and mount 53 side of keel
Side thickness.
In the present embodiment, it is connected with wall between wall pendant 14 and assembled electrolysis steel plate 7 and connects part 13, it is steel structure that wall, which connects part 13,
Part, wall connects part 13, and by U-shaped part and inverted U-shaped part, alternately welding or integral production are formed;The envelope of U-shaped part and inverted U-shaped part alternative one
Mouth side is welded on assembled electrolysis steel plate 7, and upper 141 long side of L shape part of another sealing side and wall pendant 14 is welded;Wall connects part 13
Thickness adapt to assembled electrolysis steel plate 7 and wall mounting keel 53 between horizontal width.
In conjunction with Fig. 1 to Fig. 5, a kind of construction party of clean operating room assembled electrolysis steel plate linked system is further illustrated
Method, the specific steps are as follows:
Step 1: checking clean operating room region spatial position and size according to clean operating room architectural drawing, scene is drawn
Measurement figure;By in-site measurement figure, the Deepen Design of clean operating room is carried out;When clean operating room design in-depth, top plate is carried out
The design of keel 4 and wall body keel 5, and the demands such as equipment or ventilation are installed according to wall 2 and top plate 1,11 He of wall hole is set
Top plate hole, and electrolysis 7 typesetting of steel plate of corresponding progress assembled and lattice portal design.
In reference line construction, cleaning installation setting-out place keeps bottom plate 3 smooth clean, not influence snap the line as principle.Root
According to in-depth drawing, find out reference line, generally using metope where clean operating room gate as benchmark line, from doorframe draw lines,
It successively finishes in a clockwise direction.Each central point, right angle and oblique angle mark are drawn, to install.Entire construction technology is carried out
The installation node full-page proof of keypoint part is drawn in detailed planning, in conjunction with typesetting figure and spine arrangement figure, is drawn assembled and is electrolysed steel
7 unwrapping wire full-page proof of plate.
Step 2: production assembled is electrolysed steel plate 7, electrolysis 71 back side of steel plate is connected into plasterboard 72, is carried on the back in plasterboard 72
It is stupefied that face connects steel back, and makes high-pressure electrostatic anti-bacterial powder baking vanish in electrolysis 71 surface layer of steel plate;By the assembled to complete electricity
It solves steel plate 7 and various sizes of division production is carried out according to typesetting, and the assembled of each plate electrolysis steel plate 7 is numbered.
Step 3: making according to Deepen Design drawing and installing wall body keel 5;To 5 base of wall body keel on clean operating room
After quasi- control line verifies examination, the wall transom 52 of 5 bottom end of wall body keel is fixed on bottom plate 3, checks wall transom 52
Set it is errorless after, 51 top of wall centre keel is fixed on top plate 1 using corner fittings 12, bottom end is weldingly fixed in wall transom 52;
Using 2 corner of wall as 5 starting point of wall body keel, it is sequentially arranged wall centre keel 51, wall transom 52 and wall mounting keel 53;Wall
It mounts keel 53 and arranges that spacing is consistent with assembled electrolysis 7 sub-cell width of steel plate, it is highly selected according to actual needs.
Wherein, the control of 51 spacing of wall centre keel is highly selected according to actual needs between 600mm ~ 1200mm.Check wall
After 51 position of centre keel is errorless, spacing is determined according to 51 layout drawing of clean operating room wall centre keel, 51 top of wall centre keel uses
It is fixed on 1 bottom surface of top plate with the expansion bolt of M8 × 60 after the welding of 4# angle bar, lower end is welded in wall transom 52;Wall centre keel 51
Middle part interval is fixed on wall 2 using diagonal brace 6;Adjacent metope if it is be wall body keel 5 then be used in keel between weld connect, shape
At stablizing truss;Every wall centre keel 51 is both needed to both direction and hangs plumb line, and error is not more than 2mm.Wall transom 52 and wall are hung
53 spacing of building sequence bone controls between 600mm ~ 1200mm;After the completion of 52 wall line of wall transom is checked and accepted, by control line expanding screw
Bolt is fixed on bottom plate 3.When welding wall transom 52 at skirt, skirting keel use dedicated wall transom 52, the horizontal dragon of wall
Bone 52 is welded between wall centre keel 51, and 52 center of wall transom is 85mm with a distance from wall centre keel 51.
Step 4: making according to Deepen Design drawing and installing top plate keel 4;The verification of 4 benchmark control line of top plate keel is tested
After receipts, 4 line of top plate keel is popped up on bottom plate 3 according to the layout drawing of top plate keel 4, is pressed with laser by bottom plate 3 upper plate dragon
4 control line of bone projects on 1 surface of top plate, along 4 control line installation connecting element 8 of top plate keel;It is corresponding to press 3 unwrapping wire position of bottom plate
It is well placed top plate keel 4 and top plate keel 4 is risen by two chain blocks after the completion of assembled according to design drawing assembly
It hangs, is lifted at connector 8, after check meets error requirements, connect top plate keel 4 and wall 2 with diagonal brace 6;For top plate dragon
Bone 4 and wall body keel 5 install junction, install corner fittings 12 at inner corner trim below the junction.
Wherein, top plate keel 4 include arc top plate keel, flat top keel and air-blow ceiling top plate keel;Wall 2
Top wall transom 52 joins transition with arc top plate keel, flat top keel or air-blow ceiling top plate keel respectively;In addition,
Flat top keel 4 arrange the arrangement that consider the equipment such as lamps and lanterns and preprocessing air-blow ceiling on top plate 1, and to top plate keel 4
Make design in reasonable sling point position.
Air-blow ceiling is the integrated clean air conditioner air outlet of an independent design, and cavity wall is electrolysed steel plate by assembled
7 is totally-enclosed, seam gluing encapsulation process, forms clean chamber;Air-blow ceiling is hung on top plate 1, quadrangle and the top fixed
The angle steel of the four corners of 4 skeleton of board keel is bolted.
Step 5: the assembled on installation wall body keel 5 is electrolysed steel plate 7, first connected in advance on assembled electrolysis steel plate 7
Wall pendant 14 and wall connect part 13, and the clean operating room corresponding assembled of each wall 2 is electrolysed steel plate 7 according still further to design in-depth drawing
It is placed in corresponding position;First from door opening place side according to clockwise successively perimeter mounted formula electrolysis steel plate 7 with
Wall body keel 5 mounts, and then smooths, is straightened, then the flange of assembled electrolysis steel plate 7 is connect with wall body keel 5;Finally, handle
Wall 2 and 3 corner assembled of bottom plate electrolysis steel plate 7 are installed on corner, and corresponding installation waterproof layer 10, waterproof layer 10 use
Water-resistant gypsum board is formed with assembled electrolysis 7 integral production of steel plate.
Wherein, it after assembled electrolysis steel plate 7 checks level, is welded and fixed with 2 bottom end wall transom 52 of wall.Wall base
The assembled electrolysis steel plate 7 of seat is 5mm smaller than metope assembled electrolysis 7 thickness of steel plate, thus can be formed at metope skirt hiding
Formula skirt facilitates and furls head on the PVC roll material at bottom plate 3 under waterproof layer 10;After the bottom plate 3 is using the pretreatment of 2mm Self-leveling,
Paving import antistatic rubber coiled material, and it is integral using homogeneous electrode welding, and bottom plate 3 is connecting corner smearing with wall 2
Cement fillet.
The corresponding assembled electrolysis steel plate 7 of each metope of clean operating room is placed in corresponding position, from gate door opening institute
Side according to clockwise successively with locking pliers periphery wallboard and wall mounting keel 53 fix.Assembled is electrolysed steel plate
7 smoothings, alignment design piece 3mm wide between holding plate and plate, then flange and wall with electric weld handle assembled electrolysis steel plate 7
Keel 5 are welded and fixed.Assembled electrolysis steel plate 7 in corner is attached on angle, and electricity consumption solid welding is set, the horizontal dragon of the wall of bottom and skirt
Bone 52 and pedestal electrolysis steel plate spot welding connect, and are polished flat with grinding machine and fill antirust being welded with protrusion metope.
Step 6: the assembled on installation top plate keel 4 is electrolysed steel plate 7, top is installed on assembled electrolysis steel plate 7 in advance
Assembled electrolysis steel plate 7 is sequenced according still further to Deepen Design drawing, first carries out the assembled electrolysis of plane at no hole by even part 15
Steel plate 7 lifts, then is equipped with the assembled electrolysis steel plate 7 at top plate hole;Top even part 15 is led to connector 8 after lifting up
The connection of anchoring piece 16 is crossed, then the flange of assembled electrolysis steel plate 7 is connect with wall body keel 5;Finally by the top plate keel 4 on periphery
Assembled electrolysis 7 opposite joint of steel plate installed on upper assembled electrolysis steel plate 7 and wall body keel 5 is connect, and corresponding installation insulating layer
9, insulating layer 9 is electrolysed 7 integral production of steel plate using self binding thermal insulation plate and assembled.
Wherein, steel plate 7 is electrolysed for flat top keel installation assembled, sequences assembled electrolysis on the ground according to drawing
Steel plate 7.It is connected in order between M5 key screw assembled electrolysis steel plate 7 and between assembled electrolysis steel plate 7 and connector 8
Good, error is no more than 0.5mm between plate and plate;The smoothing of assembled electrolysis steel plate 7, alignment, guarantee piece between plate and plate
3mm wide, then with electric weld handle assembled electrolysis steel plate 7 and top plate keel 4 be welded and fixed, with grinding machine be welded with protrusion metope beat
It polishes and fills antirust.
Steel plate 7 is electrolysed for arc top plate keel and air-blow ceiling top plate keel installation assembled, is first existed by drawing sequence
Corresponding circular arc and air-blow ceiling top plate keel are sequenced, is first connect top plate keel 4 with top plate or wall 2 with M5 screw, then use
M5 screw is connect with assembled electrolysis steel plate 7.The assembled electrolysis steel plate 7 installed need to guarantee design flatness and leakproofness,
No more than 0.5mm, assembled electrolysis steel plate 7 is welded and fixed convex-concave with top plate keel 4, using guarantor's type weather proofing sealant to plate and
Edge joint position between plate carries out snapping gluing.
Step 7: being filled at each splicing seams and supplementing sealant 73, and to the dress on wall body keel 5 and top plate keel 4
Verification adjustment is carried out with formula electrolysis 7 splicing seams of steel plate;Then, check and modify engineering when installing on assembled electrolysis steel plate 7
Defect;Further install ornamental accessories and at wall hole 11 and top plate hole corresponding installation door and window, lamps and lanterns and other set
It is standby, finally carry out cleaning and tidying and dyestripping gluing.
In addition, being both needed at screwed joint or at welded connecting etc. fill antirust oil, guaranteeing the normal of component and making for a long time
With.In the construction process, the customizable processing of a variety of materials used, finished product is neatly packed at the scene, operation process Plays
Construction, thus, it can be ensured that the construction of construction site civilization highly effective and safe.
The foregoing is merely the preferable specific embodiments of the present invention, but scope of protection of the present invention is not limited thereto,
The change or replacement that anyone skilled in the art is expected in the technical scope disclosed by the present invention should all be contained
Lid is within protection scope of the present invention.
Claims (10)
1. a kind of clean operating room assembled is electrolysed steel plate linked system, which is characterized in that include the top being connected under top plate (1)
Board keel (4), the wall body keel (5) being connected on the inside of wall (2), the diagonal brace being connected between wall (2) and wall body keel (5)
(6) and be connected on top plate keel (4) and wall body keel (5) assembled electrolysis steel plate (7);The assembled is electrolysed steel plate
(7) piecemeal is assembled, and assembled is electrolysed steel plate (7) and connects respectively with top plate keel (4) and wall body keel (5) mounting, wherein
Assembled is electrolysed steel plate (7) and is connect between wall body keel (5) by wall pendant (14), and assembled is electrolysed steel plate (7) and top plate dragon
It is connected between bone (4) by connector (8);
Adjacent assembled electrolysis steel plate (7) connecting sewing is arranged at top plate keel (4) or wall body keel (5), adjacent assembled electricity
It solves and is filled with sealant (73) at steel plate (7) connecting sewing, the end of adjacent assembled electrolysis steel plate (7) is provided with flange, flange
It is connected with corresponding top plate keel (4) or wall body keel (5).
2. a kind of clean operating room assembled is electrolysed steel plate linked system as described in claim 1, which is characterized in that the assembly
Formula electrolysis steel plate (7) includes the plasterboard (72) that electrolysis steel plate (71) is connected with the back side, and it is stupefied to be connected with steel back on plasterboard (72);
Electrolysis steel plate (71) surface layer is high-pressure electrostatic anti-bacterial powder baking vanish.
3. a kind of clean operating room assembled is electrolysed steel plate linked system as described in claim 1, which is characterized in that the wall
Keel (5) include wall centre keel (51) and the wall transom (52) and wall that are vertically connected on wall centre keel (51) mounting dragon
Bone (53);The top of the wall centre keel (51) is connect by corner fittings (12) with top plate (1), and bottom end is connected to wall transom (52)
On.
4. a kind of clean operating room assembled is electrolysed steel plate linked system as claimed in claim 3, which is characterized in that the wall is hung
Corresponding assembled electrolysis steel plate (7) of building sequence bone (53) and wall hole (11) setting, wall mounts keel (53) and assembled is electrolysed
Wall pendant (14) are connected between steel plate (7);Wall mounting keel (53) is angle-shaped piece, and angle-shaped piece inner corner trim is towards wall (2), angle
Shape part one side is flushed with wall centre keel (51), another side vertical wall centre keel (51).
5. a kind of clean operating room assembled is electrolysed steel plate linked system as claimed in claim 4, which is characterized in that the wall is hung
Part (14) includes upper L shape part (141) and the lower L shape part (142) being connected to below L shape part (141);Wherein, upper L shape part
(141) be right angle, corresponding formula electrolysis steel plate (7) that is linked and packed in the long side face of upper L shape part (141), upper L shape part (141) it is short
Side end portion connects lower L shape part (142) long side top;Lower L shape part (142) inner corner trim is obtuse angle, lower L shape part (142) external corner and upper L shape
Part (141) long side extended line horizontal distance adapts to wall and mounts keel (53) side thickness.
6. a kind of clean operating room assembled is electrolysed steel plate linked system as claimed in claim 5, which is characterized in that the wall is hung
It is connected with wall between part (14) and assembled electrolysis steel plate (7) to connect part (13), the wall connects part (13) and handed over by U-shaped part and inverted U-shaped part
It is combined into for connection;The sealing side of U-shaped part and inverted U-shaped part alternative one is connected in assembled electrolysis steel plate (7), another sealing
Side is connect with upper L shape part (141) long side of wall pendant (14);Wall connect part (13) thickness adapt to assembled electrolysis steel plate (7) with
Wall mounts horizontal width between keel (53).
7. a kind of clean operating room assembled is electrolysed steel plate linked system as described in claim 1, which is characterized in that the connection
Part (8) includes the adapter (82) of the connecting rod (81) connecting with top plate (1) and the connection of connecting rod (81) end;The adapter
(82) it is connect with top plate keel (4) upper side, adapter (82) is that L hooks part, angle-shaped piece or connecting plate.
8. a kind of clean operating room assembled is electrolysed steel plate linked system as described in claim 1 or 7, which is characterized in that described
The flange downside that assembled electrolysis steel plate (7) is connect with top plate keel (4) is connected with top even part (15), and top connects part (15) and turns
Anchoring piece (16) are connected between fitting (82);The top even part (15) is angle-shaped piece or connecting plate, anchoring piece (16) be bolt or
Pin rod.
9. a kind of clean operating room assembled is electrolysed steel plate linked system as described in claim 1, which is characterized in that the top plate
(1) the top plate keel (4) in surrounding and corner are connected with diagonal brace (6) between wall (2) respectively, and diagonal brace (6) and wall (2) pass through angle
Part (12) connection;Top plate keel (4) connect at inner corner trim with wall body keel (5) and are connected with corner fittings (12).
10. a kind of construction party of clean operating room assembled electrolysis steel plate linked system as described in claim 1 to 9 any one
Method, which is characterized in that specific step is as follows:
Step 1: checking clean operating room region spatial position and size according to clean operating room architectural drawing, scene is drawn
Measurement figure;By in-site measurement figure, the Deepen Design of clean operating room is carried out;When clean operating room design in-depth, top plate is carried out
The design of keel (4) and wall body keel (5), and wall is arranged according to wall (2) and top plate (1) the installation demands such as equipment or ventilation
Hole (11) and top plate hole, and electrolysis steel plate (7) typesetting of corresponding progress assembled and lattice portal design;
Step 2: production assembled electrolysis steel plate (7), by electrolysis steel plate (71) back side connection plasterboard (72), in plasterboard
(72) connection steel back in the back side is stupefied, and makes high-pressure electrostatic anti-bacterial powder baking vanish in electrolysis steel plate (71) surface layer;By what is completed
Assembled is electrolysed steel plate (7) and carries out various sizes of division production according to typesetting, and the assembled of each plate is electrolysed steel plate (7)
Number;
Step 3: making according to Deepen Design drawing and installing wall body keel (5);Wall body keel on clean operating room (5) are controlled
After line core examination processed is received, the wall transom (52) of wall body keel (5) bottom end is fixed on bottom plate (3), wall transom is checked
(52) after position is errorless, wall centre keel (51) top is fixed on top plate (1) using corner fittings (12), bottom end is fixed on the horizontal dragon of wall
On bone (52);Using wall (2) corner as wall body keel (5) starting point, it is sequentially arranged wall centre keel (51), wall transom (52)
Keel (53) are mounted with wall, wherein wall mounts keel (53) and arranges that spacing is consistent with assembled electrolysis steel plate (7) sub-cell width,
Height is selected according to actual needs;
Step 4: making according to Deepen Design drawing and installing top plate keel (4);Top plate keel (4) control line, which is verified, to be checked and accepted
Afterwards, top plate keel (4) line is popped up on bottom plate (3) according to the layout drawing of top plate keel (4), being pressed with laser will be on bottom plate (3)
Top plate keel (4) control line projects on top plate (1) surface, along top plate keel (4) control line installation connecting element (8);The bottom of by
Plate (3) unwrapping wire position is corresponding to be well placed top plate keel (4) and passes through two hands after the completion of assembled according to design drawing assembly
It draws cucurbit that top plate keel (4) are lifted by crane, is lifted at connector (8), after check meets error requirements, connected and pushed up with diagonal brace (6)
Board keel (4) and wall (2);Wherein, there are flat top keel, arc top plate keel for design on top plate keel (4) or send
Wind ceiling roof keel, carry out handover transition and the sling point Encryption Design of variant top plate keel (4) junction;For top
Junction is installed in board keel (4) and wall body keel (5), installs corner fittings (12) at inner corner trim below the junction;
Step 5: the assembled in installation wall body keel (5) is electrolysed steel plate (7), first connect in advance in assembled electrolysis steel plate (7)
It connects wall pendant (14) and wall connects part (13), according still further to Deepen Design drawing by the corresponding assembled of each wall of clean operating room (2)
Electrolysis steel plate (7) is placed in corresponding position;Elder generation is from door opening place in side according to clockwise successively perimeter mounted formula
It is electrolysed steel plate (7) and wall body keel (5) to mount, then smooths, is straightened, then the flange and wall of assembled electrolysis steel plate (7)
Keel (5) connection;Finally, wall (2) and bottom plate (3) corner assembled electrolysis steel plate (7) are installed on corner, and corresponding
It installs waterproof layer (10);
Step 6: the assembled in installation top plate keel (4) is electrolysed steel plate (7), installed in assembled electrolysis steel plate (7) in advance
Top even part (15), according still further to Deepen Design drawing sequences assembled electrolysis steel plate (7), first carries out the assembly of plane at no hole
Formula is electrolysed steel plate (7) lifting, then is equipped with assembled electrolysis steel plate (7) at top plate hole;By top even part after lifting up
(15) it is connect with connector (8) by anchoring piece (16), then the flange of assembled electrolysis steel plate (7) and wall body keel (5) is connected
It connects;Finally the assembled installed in assembled electrolysis steel plate (7) and wall body keel (5) on the top plate keel (4) on periphery is electrolysed
The connection of steel plate (7) opposite joint, and corresponding installation insulating layer (9);
Step 7: filling with sealant (73) at each splicing seams, and to the assembled on wall body keel (5) and top plate keel (4)
Electrolysis steel plate (7) splicing seams carry out verification adjustment;Then, check and modify engineering when installing in assembled electrolysis steel plate (7)
Defect;Further install ornamental accessories and at wall hole (11) and top plate hole corresponding installation door and window, lamps and lanterns and other
Equipment finally carries out cleaning and tidying and dyestripping gluing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910837062.0A CN110512788A (en) | 2019-09-05 | 2019-09-05 | A kind of clean operating room assembled electrolysis steel plate linked system and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910837062.0A CN110512788A (en) | 2019-09-05 | 2019-09-05 | A kind of clean operating room assembled electrolysis steel plate linked system and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110512788A true CN110512788A (en) | 2019-11-29 |
Family
ID=68629998
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910837062.0A Pending CN110512788A (en) | 2019-09-05 | 2019-09-05 | A kind of clean operating room assembled electrolysis steel plate linked system and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110512788A (en) |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2005251A1 (en) * | 1988-12-13 | 1990-06-13 | Robert Sampson | Skylight construction |
KR20010087827A (en) * | 2001-06-26 | 2001-09-26 | 정진황 | The operation method of metal lath bonding exterior insulation and finishing system |
CN2721222Y (en) * | 2004-08-04 | 2005-08-31 | 格满林(南京)实业有限公司 | Assembled cleaning room |
CN201883633U (en) * | 2010-12-02 | 2011-06-29 | 苏州净化工程安装有限公司 | Operating room wall surface hanging plate |
CN204299218U (en) * | 2014-12-17 | 2015-04-29 | 铭铉(江西)医疗净化科技有限公司 | Precast combined operating room |
CN105839876A (en) * | 2016-05-25 | 2016-08-10 | 北京城建六建设集团有限公司 | Decorative construction system of wall body and roof board for clean operating room and construction method of decorative construction system |
WO2017020676A1 (en) * | 2015-07-31 | 2017-02-09 | 北新集团建材股份有限公司 | Modular wall and erection method thereof |
CN206987268U (en) * | 2017-07-14 | 2018-02-09 | 上海品宅装饰科技有限公司 | A kind of assembled indoor wall finished system |
CN207436346U (en) * | 2017-11-06 | 2018-06-01 | 马会 | A kind of clean operating room suspended ceiling mounting structure |
CN108204070A (en) * | 2018-02-07 | 2018-06-26 | 苏州通快净化科技有限公司 | A kind of hanging top plate mounting structure |
CN208725157U (en) * | 2017-11-06 | 2019-04-12 | 聂莉莉 | A kind of medical apparatus cabinet mounting structure applied to clean operating room |
CN210798029U (en) * | 2019-09-05 | 2020-06-19 | 北京城建六建设集团有限公司 | Clean operating room assembled electrolysis steel sheet connected system |
-
2019
- 2019-09-05 CN CN201910837062.0A patent/CN110512788A/en active Pending
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2005251A1 (en) * | 1988-12-13 | 1990-06-13 | Robert Sampson | Skylight construction |
KR20010087827A (en) * | 2001-06-26 | 2001-09-26 | 정진황 | The operation method of metal lath bonding exterior insulation and finishing system |
CN2721222Y (en) * | 2004-08-04 | 2005-08-31 | 格满林(南京)实业有限公司 | Assembled cleaning room |
CN201883633U (en) * | 2010-12-02 | 2011-06-29 | 苏州净化工程安装有限公司 | Operating room wall surface hanging plate |
CN204299218U (en) * | 2014-12-17 | 2015-04-29 | 铭铉(江西)医疗净化科技有限公司 | Precast combined operating room |
WO2017020676A1 (en) * | 2015-07-31 | 2017-02-09 | 北新集团建材股份有限公司 | Modular wall and erection method thereof |
CN105839876A (en) * | 2016-05-25 | 2016-08-10 | 北京城建六建设集团有限公司 | Decorative construction system of wall body and roof board for clean operating room and construction method of decorative construction system |
CN206987268U (en) * | 2017-07-14 | 2018-02-09 | 上海品宅装饰科技有限公司 | A kind of assembled indoor wall finished system |
CN207436346U (en) * | 2017-11-06 | 2018-06-01 | 马会 | A kind of clean operating room suspended ceiling mounting structure |
CN208725157U (en) * | 2017-11-06 | 2019-04-12 | 聂莉莉 | A kind of medical apparatus cabinet mounting structure applied to clean operating room |
CN108204070A (en) * | 2018-02-07 | 2018-06-26 | 苏州通快净化科技有限公司 | A kind of hanging top plate mounting structure |
CN210798029U (en) * | 2019-09-05 | 2020-06-19 | 北京城建六建设集团有限公司 | Clean operating room assembled electrolysis steel sheet connected system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208792663U (en) | A kind of room finishing system | |
CN103510631A (en) | Indoor sound insulation construction structure and construction method thereof | |
CN103031964A (en) | Modularized clean operating room and installation technology thereof | |
CN107447939A (en) | A kind of construction method of exterior-wall heat insulation stone decoration integrated board architectural surface | |
CN111042392A (en) | Construction method of SDHH type disassembly-free formwork foam concrete partition wall | |
CN101906858B (en) | Seamless installation process for polyline artistic GRC (Glass-fiber Reinforced Composite) board | |
CN107740553B (en) | Hard plate material mounts construction method | |
CN110512788A (en) | A kind of clean operating room assembled electrolysis steel plate linked system and its construction method | |
CN108915136A (en) | A kind of construction method of open stone curtain wall | |
CN113338518A (en) | Construction method of GRG material acoustic suspended ceiling in large-scale construction project | |
CN210798029U (en) | Clean operating room assembled electrolysis steel sheet connected system | |
CN209568581U (en) | A kind of assembly type low power consuming curtain wall system | |
CN102493620B (en) | Through long folded fastener type wall body connecting piece of heat insulation integrated plate and mounting method thereof | |
CN108729580B (en) | Wall manufacturing method | |
CN205663072U (en) | Aluminium honeycomb welt stainless steel curtain | |
CN115653168A (en) | Double-curved-surface honeycomb aluminum plate structure and mounting method thereof | |
CN214461491U (en) | Arc light partition wall | |
CN204510701U (en) | A kind of imitative stone material GRC integrated plate for heat insulation hanging structure | |
CN1314870C (en) | Method of dry construction of energy saving walls with 3D adjustment | |
CN212866706U (en) | Assembled aluminum plate dry hanging structure | |
CN112922257A (en) | ECP wallboard mounting construction method | |
CN209082824U (en) | A kind of light lath | |
CN205935805U (en) | Moving as a whole formula standard curing room | |
CN212656450U (en) | Ceiling internal corner groove assembly type closing-in system | |
CN221001633U (en) | Telescopic partition plate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |