CN110485410A - Foundation pile pile making method - Google Patents

Foundation pile pile making method Download PDF

Info

Publication number
CN110485410A
CN110485410A CN201910772179.5A CN201910772179A CN110485410A CN 110485410 A CN110485410 A CN 110485410A CN 201910772179 A CN201910772179 A CN 201910772179A CN 110485410 A CN110485410 A CN 110485410A
Authority
CN
China
Prior art keywords
threaded rod
cement slurry
hole
drilling
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910772179.5A
Other languages
Chinese (zh)
Inventor
林威
洪斯琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN JIANYAN ROCK AND SOIL ENGINEERING Co Ltd
Original Assignee
TIANJIN JIANYAN ROCK AND SOIL ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN JIANYAN ROCK AND SOIL ENGINEERING Co Ltd filed Critical TIANJIN JIANYAN ROCK AND SOIL ENGINEERING Co Ltd
Priority to CN201910772179.5A priority Critical patent/CN110485410A/en
Publication of CN110485410A publication Critical patent/CN110485410A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to technical field of building construction more particularly to a kind of foundation pile pile making methods, comprising the following steps: one, using drilling machine bore the hole that diameter is greater than 0.3 meter on ground;Step 2: injecting cement slurry in hole;Three, before cement slurry is not dry, it is put into threaded rod in hole, has screw thread, the top welded connections of threaded rod around threaded rod;Four, threaded rod is set in cement slurry i.e. basis of formation.Neighboring buildings are not influenced using this method, are not take up the space of surrounding buildings, can be constructed in minimum space, large scale equipment, the construction of the small space especially suitable for old residential area are not used.

Description

Foundation pile pile making method
Technical field
The present invention relates to technical field of building construction more particularly to a kind of foundation pile pile making methods.
Background technique
Currently, in the transformation process in old city, for example, installing elevator additional in old residential area, it is necessary to elevator Install basis, currently used mode or traditional piling mode additional, i.e., first ground makes a call to a depth and stirs stake, then takes advantage of stake and do not do feelings Be put into a cement pole under condition, the shortcomings that such structure is: will use large scale equipment, ambient enviroment is required it is relatively high, for The construction of old residential area at present is simultaneously not suitable with.If this mode is more infeasible by the way of drilling again descending reinforcing cage, drilling It can not drill, underground water can make to collapse around hole, need to do the sealing of surrounding, and project amount is very big, and cost is also especially high. Thus, it would be highly desirable to research and develop a kind of convenient, the especially small foundation pile pile making method of occupied space of construction.
Summary of the invention
It is an object of the invention to overcome the shortcomings of above-mentioned technology, and provide a kind of foundation pile pile making method.
The present invention to achieve the above object, using following technical scheme: a kind of foundation pile pile making method, it is characterised in that: The following steps are included:
Step 1: boring the hole that a diameter is greater than 0.3 meter on ground using drilling machine;
Step 2: injecting cement slurry in hole;
Step 3: being put into threaded rod in hole before cement slurry is not dry, having screw thread, threaded rod around threaded rod Top welded connections;
Step 4: threaded rod is set in cement slurry i.e. basis of formation.
Preferably, in step 2, side drilling marginal not enters cement slurry.
Preferably, in step 2, the drilling rod of drilling machine is hollow structure, is equipped with leakage fluid dram, cement slurry in the front end of drilling rod Enter out of drilling rod, is injected into hole from leakage fluid dram.
The beneficial effects of the present invention are: not influencing using this method on neighboring buildings, it is not take up the space of surrounding buildings, It can construct in minimum space, it is only necessary to a drilling machine, small space especially suitable for old residential area Construction.
Detailed description of the invention
Fig. 1 is working state figure of the invention;
Fig. 2 is the structural schematic diagram of drilling rod in the present invention;
Fig. 3 is the installation status diagram of threaded rod in the present invention.
Specific embodiment
With reference to the accompanying drawing and the preferred embodiment specific embodiment that the present invention will be described in detail.As shown in Figure 1-3,
A kind of foundation pile pile making method, comprising the following steps: be greater than Step 1: boring a diameter on ground using drilling machine 0.3 meter of hole;Drilling machine uses middle-size and small-size drilling machine, and overall volume is not especially big.The drilling rod of drilling machine is using currently used Drilling rod 1, bottom have Counterboring apparatus, that is, rubber belt 2, and drilling rod lower part enters, Step 2: In with outlet for cement slurry Cement slurry 3 is injected in hole, by the way of drilling marginal not enters cement slurry using side.Specifically, the drilling rod of drilling machine is hollow structure, boring The lower part of bar is equipped with outlet 4, and cement slurry enters out of drilling rod top entrance 5, is injected into hole from leakage fluid dram.
Step 3: being put into threaded rod 6 in hole before cement slurry is not dry, having screw thread, threaded rod around threaded rod Top welded connections;Connector is used to be attached with the equipment on top.
Step 4: threaded rod is set in cement slurry i.e. basis of formation.Cement slurry is complete with the threaded rod in hole after having done Beauty combines, and side grinding resistance is very big, so this foundation pile can be very secured.
Neighboring buildings are not influenced using this method, are not take up the space of surrounding buildings, it can be in minimum space Construction does not use large scale equipment, the construction of the small space especially suitable for old residential area.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (3)

1. a kind of foundation pile pile making method, it is characterised in that: the following steps are included:
Step 1: boring the hole that a diameter is greater than 0.3 meter on ground using drilling machine;
Step 2: injecting cement slurry in hole;
Step 3: being put into threaded rod in hole before cement slurry is not dry, having screw thread, the top of threaded rod around threaded rod Portion's welded connections;
Step 4: threaded rod is set in cement slurry i.e. basis of formation.
2. foundation pile pile making method according to claim 1, it is characterised in that: in step 2, side drilling marginal not enters water Mud.
3. foundation pile pile making method according to claim 2, it is characterised in that: in step 2, the drilling rod of drilling machine is sky Core structure is equipped with leakage fluid dram in the front end of drilling rod, and cement slurry enters out of drilling rod, is injected into hole from leakage fluid dram.
CN201910772179.5A 2019-08-21 2019-08-21 Foundation pile pile making method Pending CN110485410A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910772179.5A CN110485410A (en) 2019-08-21 2019-08-21 Foundation pile pile making method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910772179.5A CN110485410A (en) 2019-08-21 2019-08-21 Foundation pile pile making method

Publications (1)

Publication Number Publication Date
CN110485410A true CN110485410A (en) 2019-11-22

Family

ID=68552589

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910772179.5A Pending CN110485410A (en) 2019-08-21 2019-08-21 Foundation pile pile making method

Country Status (1)

Country Link
CN (1) CN110485410A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4378752B2 (en) * 2003-03-25 2009-12-09 三谷セキサン株式会社 Ready-made piles for large-diameter ready-made concrete pile foundations
CN103266603A (en) * 2013-05-27 2013-08-28 浙江城建建设集团有限公司 Construction method for pre-drilling hole-forming base-expanding and grouting of prestressed concrete special-shaped pile
CN107023002A (en) * 2016-08-30 2017-08-08 北京荣创岩土工程股份有限公司 Down-the-hole impacts churning composite pile pile making method
CN108978641A (en) * 2018-08-17 2018-12-11 江苏劲桩基础工程有限公司 The construction method of compound strength stake
CN109853524A (en) * 2019-01-14 2019-06-07 江苏东合南岩土科技股份有限公司 A kind of construction method of the composite special-shaped stake of enlarged footing stiffness soil cement

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4378752B2 (en) * 2003-03-25 2009-12-09 三谷セキサン株式会社 Ready-made piles for large-diameter ready-made concrete pile foundations
CN103266603A (en) * 2013-05-27 2013-08-28 浙江城建建设集团有限公司 Construction method for pre-drilling hole-forming base-expanding and grouting of prestressed concrete special-shaped pile
CN107023002A (en) * 2016-08-30 2017-08-08 北京荣创岩土工程股份有限公司 Down-the-hole impacts churning composite pile pile making method
CN108978641A (en) * 2018-08-17 2018-12-11 江苏劲桩基础工程有限公司 The construction method of compound strength stake
CN109853524A (en) * 2019-01-14 2019-06-07 江苏东合南岩土科技股份有限公司 A kind of construction method of the composite special-shaped stake of enlarged footing stiffness soil cement

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
唐业清等: "《建筑物改造与病害处理》", 31 October 2000, 中国建筑工业出版社 *

Similar Documents

Publication Publication Date Title
CN102926770A (en) Underground draining and grouting process in thin bedrock and thick loose sand layer rich water areas
CN107747312B (en) Method for drilling and grouting construction of gravel stratum
CN102444118A (en) Construction method for grouting reinforcement of sleeve valve pipe
CN206627405U (en) The double embolism original position injection pressure water penetration detectors of expansion type
CN109853538B (en) Concrete cast-in-place pile foundation reinforcing and reinforcing structure and construction method thereof
CN206015669U (en) Pile foundation reinforcement system based on reinforcement synthesis pillared clay
CN109060073A (en) Single hole observes Karst Mountain bilayer level of ground water device and method
CN104912065A (en) Underwater anchor pile construction method
CN114233385A (en) Treatment method for mud burst and water burst of inclined shaft
CN111254933B (en) Karst grouting construction method for sleeve valve pipe
CN109577380B (en) Construction method for basement bottom plate water seepage under karst landform condition
CN113250249B (en) Construction method of existing building anti-floating system based on embedded self-advancing anchor rod
US20130064610A1 (en) Suspension extraction device
CN203613568U (en) Anti-floating cement soil pile and anti-floating anchor rod combined anti-floating system
CN110485410A (en) Foundation pile pile making method
CN101858074A (en) Construction method and device for on-site water injection test
CN101161947A (en) Integration method of lagging pile and dewatering well for foundation ditch support
CN108533213A (en) It is a kind of to block the device and its method for blocking for disclosing the drilling of coating artesian water
CN210104753U (en) Ultra-deep karst grouting device
CN104047285A (en) Technical device and construction method for improving bearing capacity of CFG pressure pouring piles
CN208847278U (en) Single hole observes Karst Mountain bilayer level of ground water device
CN206233232U (en) A kind of upper and lower part expansion type soil cement is combined pile tube
CN208364097U (en) It is a kind of to block the device for disclosing the drilling of coating artesian water
CN203891785U (en) Special joint pipe assembly for throwing of gravels in pipe of hydrogeological water well
CN210564650U (en) Assembled slurry storage device for filling underwater deep closed space

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191122