CN110485237A - A kind of production method of fabricated permeable pavement concrete slab - Google Patents

A kind of production method of fabricated permeable pavement concrete slab Download PDF

Info

Publication number
CN110485237A
CN110485237A CN201910625855.6A CN201910625855A CN110485237A CN 110485237 A CN110485237 A CN 110485237A CN 201910625855 A CN201910625855 A CN 201910625855A CN 110485237 A CN110485237 A CN 110485237A
Authority
CN
China
Prior art keywords
concrete
concrete slab
matts
recessed portion
fabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910625855.6A
Other languages
Chinese (zh)
Inventor
黄明
温学钧
史春华
王潇婷
史啸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201910625855.6A priority Critical patent/CN110485237A/en
Publication of CN110485237A publication Critical patent/CN110485237A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/22Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
    • E01C11/224Surface drainage of streets
    • E01C11/225Paving specially adapted for through-the-surfacing drainage, e.g. perforated, porous; Preformed paving elements comprising, or adapted to form, passageways for carrying off drainage
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C15/00Pavings specially adapted for footpaths, sidewalks or cycle tracks
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C5/00Pavings made of prefabricated single units
    • E01C5/22Pavings made of prefabricated single units made of units composed of a mixture of materials covered by two or more of groups E01C5/008, E01C5/02 - E01C5/20 except embedded reinforcing materials

Abstract

The invention discloses a kind of production methods of fabricated permeable pavement concrete slab, mold is made first, the mould upstream is template cavity, bottom is equipped with matts recessed portion, screw shell of the embedment as hole for hoist in matts recessed portion, pouring reinforcement concrete in matts recessed portion, then surface after the completion of casting reinforced concrete, the polyphenylene sulfide resin lotion of sprinkling finally completes pouring for subsequent pervious concrete in the top template cavity of mold.Fabricated permeable pavement concrete slab of the invention can be fabricated to the bigger size of more existing paving brick, existing pavement facing brick paving skid resistance can be improved and flatness is insufficient, achieve the purpose that rainwater permeate in time, comfortable and panel durability of walking it is strong, and pavement process is rapid in construction, base's surface layer is not necessarily to conditioned time, and open to traffic immediately is completed in construction.

Description

A kind of production method of fabricated permeable pavement concrete slab
Technical field
The present invention relates to a kind of production methods of fabricated permeable pavement concrete slab, belong to road engineering technology neck Domain.
Background technique
With Urbanization Progress, a large amount of road construction projects are located at densely populated, heavy traffic region, at present road surface Layer, base layer construction are all that scene paves construction, construct, curing cycle it is longer, keep the traffic pressure of construction period peripheral path rapid Increase, and ambient enviroment is produced bigger effect, including fugitive dust and noise problem.Meanwhile in huge highway and urban road, Annual a large amount of road is needed repairing, reinforces or is widened, this can bring very big inconvenience to daily traffic, break off a friendship, not only can detour Traffic disturbance is caused, but also will cause user's delay time at stop and unnecessary fuel consumption.Therefore, it creates, reconstruct and extends In road engineering, it is desirable that guarantee to shorten the construction period as far as possible under the premise of quality, minimal interference traffic.
Assembled technology has that component standardization, on-site construction time be short, environment influences small characteristic, building, bridge, It has been promoted and applied in the engineerings such as tunnel.Using prefabrication, field erected large size prefabricated part pavement pavement technique by Growing interest, quick with work progress, environmental perturbation is small, and construction quality is easily controllable, and durability smaller size brick is more excellent The features such as.Prefabricated assembled technology has some researchs and application on driveway, but grinds in complicated mating formation for pavement Study carefully less.Due to that need to guarantee walking comfort, the pre-assembled formula technology on pavement need to consider antiskid and permeable effect, therefore use Prefabricated pervious concrete is the optimal selection of tradeoff.
Summary of the invention
The present invention is the rapid and spongeization realizing pavement and mating formation, and the object of the present invention is to provide a kind of assembled is saturating The production method of water pavement concrete slab can make more nervous or to the smaller situation of environmental perturbation requirement in construction period Under, rapid construction is carried out, in use, rainwater, which penetrates, penetrates into sand rubble under assembling water permeable sidewalk concrete slab Bed course is pooled in water pipe, and road face in pavement is without ponding in the case where accomplishing middle or small rainfall.
To achieve the above object, technical scheme is as follows: a kind of system of fabricated permeable pavement concrete slab Make method, it is characterised in that the described method includes:
A, mold is made, the mould upstream is template cavity, and bottom is equipped with matts recessed portion;
B, the steel bar stress in mold bottom matts recessed portion, then casting concrete to the top of matts recessed portion Portion;
C, the polyphenylene sulfide resin lotion of 0.1L/ ㎡ is sprayed on surface after the completion of casting reinforced concrete;
D, 3-5min is completed in step C be poured pervious concrete 0.5-1cm;
E, the polyphenylene sulfide resin lotion of 0.1L/ ㎡ is sprayed on the thick casting pervious concrete face 0.5-1cm immediately;
F, pouring for subsequent pervious concrete is completed in mold, and fabricated permeable pavement concrete slab is made.
Further, the production method of polyphenylene sulfide resin lotion are as follows: 1, room temperature be solid polyphenylene sulfide resin system For at 0.6mm flour sand below;2, common cation or anion surface active types of emulsifiers are selected;3, by polyphenylene sulphur Ether resin flour sand and emulsifier are placed in colloid mill jointly, and colloid mill storehouse temperature controls the lotion discharging at 70-80 DEG C, after grinding 60-80 DEG C of temperature.
Further, for the emulsifier volume of polyphenylene sulfide resin lotion in 1-5%, polyphenylene sulfide resin content is 2- 17%, remaining is water.
Preferably, in polyphenylene sulfide resin lotion, the volume of cationic emulsifier is 4% or anion emulsifier Volume is 5%, and polyphenylene sulfide resin content is 11%.
Further, the whole thickness deviation after molding initial set is between ± 3mm, and (3 meters straight for surface smoothness≤5mm Ruler method).The blind way of precast slab is using impression protrusion and concave processing, blind item protrusion 5mm;Blind way setting on panel Seated position should meet accessibility designs specification (GB50763-2012) requirement;In custom mold, it is real that exclusive cover board should be customized The processing of existing impression.The coefficient of permeability of precast slab entirety is 0.1-0.2mm/s, permeable using GB/T 25993-2010 Coefficient testing method.
Further, the material requirements of the matts frame part of armored concrete is as follows: saturation compression strength >= 40MPa is saturated flexural strength >=2.5MPa;Reinforcing bar reaches HRB400 grades;Reinforcing bar resists tensile stress when lifting, and reinforcing bar is buried to common At the above 3-5cm of concrete bottom;Thickness >=5cm of pervious concrete surface layer.
The material of pervious concrete surface layer and armored concrete has gradual transition section, and the gradual transition section is impregnated with polyphenyl Base sulfide resin lotion;So that sufficiently merge between pervious concrete and armored concrete, regenerated aggregate and commonly gather materials it Between discharge shrinkage stress in advance.Gradual transition section can adjust according to the actual situation with a thickness of 1-2cm, not do rigid setting.
Further, the regenerated aggregate of 30-50% is selected in pervious concrete part, and the flat-elongated particles of regenerated aggregate contain Measure < 8%, crush values < 25%, Los Angeles abrasion loss < 25%.The other materials performance removed except regenerated aggregate should all Meet the requirement of " water-permeable cement concrete pavement technique regulation " (CJJ/T135-2009).
Further, the main component of polyphenylene sulfide resin is polyphenylene thioether, and purity is 60% or more, impurity According to the difference of synthesis technology including but not limited to polyether-ether-ketone (PEEK), polysulfones (PSF), polyimides (PI), polyphenylene sulphur The density of ether resin is 1.0-1.4g/cm3
The main component of above-mentioned polyphenylene sulfide resin is polyphenylene thioether, molecular structural formula are as follows:
Further, the method for paving of fabricated permeable pavement concrete slab of the invention, is laid with gradation on ground Blotter, granular cushion bottom set flexible porous tube, then utilize hole for hoist by this fabricated permeable pavement coagulation Native plate is lifted into above granular cushion, and after the completion of lifting, between the concrete slab of adjacent fabricated permeable pavement Longitudinal piece is reserved, sand or heated bitumen are filled in longitudinal piece or patch fills flexible material.
Further, after the completion of the lifting of fabricated permeable pavement concrete slab, screw thread first is blocked with rubber plug at hole for hoist Then the bitumen layer of about 8~12mm thickness is perfused in sleeve, finally filled and led up with prefabricated pervious concrete;Later period replaces concrete slab When, the closure at hole for hoist is pulled out, lifting replacement is carried out.
Further, in the curved section on pavement, fabricated permeable pavement concrete slab is arranged to trapezoidal in the plane.
Further, the two sides reserved space of fabricated permeable pavement concrete slab is filled out with kerbstone and with cobblestone band It mends.
Further, when being filled up with cobblestone band, the cobblestone of 2-4cm diameter is selected, and is embedded in mortar, cobblestone Partial denudation.
The advantage of the invention is that this concrete slab can be fabricated to the bigger size of more existing paving brick, existing people can be improved Trade facing brick paving skid resistance and flatness are insufficient, achieve the purpose that rainwater permeate in time, walks comfortably and panel durability is strong, And pavement process is rapid in construction, base's surface layer is not necessarily to conditioned time, and open to traffic immediately is completed in construction.Assembly of the invention Formula water permeable sidewalk concrete slab improves the mechanical property in common water-permeable brick pavement face, flatness, utmostly reduces Seam improves walking comfort;The stage for largely needing health is transferred to factory in prefabrication practice to complete, high degree Shorten and the duration and ensure that the quality of concrete.Fabricated permeable pavement of the present invention concrete slab and its paving structure are another Tool infiltration row's performance is significant, and the feature that anti-slippery effect is excellent, durability is good can be relieved the status that pavement is wet and slippery under medium and small rain condition condition, It can be used for the pavement and square, parkway of all grade roads.
Detailed description of the invention
Fig. 1 is present invention design fabricated permeable concrete slab perspective view;
Fig. 2 is present invention design fabricated permeable concrete slab plan view;
Fig. 3 is present invention design fabricated permeable concrete slab arrangement of reinforcement;
Fig. 4 is design reinforcement elevation of the present invention;
Fig. 5 is present invention design fabricated permeable concrete slab deflecting plate (example, 3 × 2 meters of trapezoidal plates realize 2 ° of steerings);
Fig. 6 is present invention design fabricated permeable concrete sidewalk face structure chart;
Fig. 7 is that present invention design fabricated permeable concrete sidewalk buffers cobblestone band.
Specific embodiment
Three-dimensional plate body as shown in Figure 1, including three parts: armored concrete matts frame 1;Pervious concrete surface layer 2;(3) hole for hoist 3;The cement concrete of the generally prefabrication formula mold construction production of prefabricated pervious concrete plate, uses The mold of pre-production forms casting.Longitudinal reinforcement 4 and transverse steel 5, reinforcing bar are embedded in armored concrete matts frame 1 The material requirements of concrete matts frame 1 is as follows: saturation compression strength >=40MPa is saturated flexural strength >=2.5MPa;Reinforcing bar Up to HRB400 grades;Reinforcing bar resists tensile stress when lifting, and reinforcing bar is buried to the above 3-5cm of concrete bottom, and reinforcing bar generally uses 14 reinforcing bar of Φ.Wherein thickness >=5cm of pervious concrete surface layer;Pervious concrete surface layer and armored concrete matts frame it Between have changeover portion;Changeover portion 1-2cm, can adjust according to the actual situation, not do rigid setting.
The production method of fabricated permeable pavement concrete slab of the invention, it is characterised in that the described method includes:
A, mold is made, the mould upstream is template cavity, and bottom is equipped with matts recessed portion;
B, the steel bar stress in mold bottom matts recessed portion, then casting concrete to the top of matts recessed portion Portion;
C, the polyphenylene sulfide resin lotion of 0.1L/ ㎡ is sprayed on surface after the completion of casting reinforced concrete;
D, 3-5min is completed in step C be poured pervious concrete 0.5-1cm;
E, the polyphenylene sulfide resin lotion of 0.1L/ ㎡ is sprayed on the thick casting pervious concrete face 0.5-1cm immediately;
F, pouring for subsequent pervious concrete is completed in mold.
Further, the production method of polyphenylene sulfide resin lotion are as follows: 1, room temperature be solid polyphenylene sulfide resin system For at 0.6mm flour sand below;2, common cation or anion surface active types of emulsifiers are selected;3, by polyphenylene sulphur Ether resin flour sand and emulsifier are placed in colloid mill jointly, and colloid mill storehouse temperature controls the lotion discharging at 70-80 DEG C, after grinding 60-80 DEG C of temperature.
Further, for the emulsifier volume of polyphenylene sulfide resin lotion in 1-5%, polyphenylene sulfide resin content is 2- 17%, remaining is water.
The regenerated aggregate of pervious concrete part selection 30-50%, the flat-elongated particles content < 8% of regenerated aggregate, Crush values < 25%, Los Angeles abrasion loss < 25%.Other materials performance except removing regenerated aggregate should all meet " permeable Cement concrete pavement technical regulation " (CJJ/T135-2009) requirement.
Whole thickness deviation after molding initial set is between ± 3mm, surface smoothness≤5mm (3 meters of ruler methods).It is prefabricated The blind way of concrete slab is using impression protrusion and concave processing, blind item protrusion 5mm;Setting position of the blind way on panel should expire Sufficient accessibility designs specification (GB50763-2012) requires;In custom mold, the place that exclusive cover board realizes impression should be customized Reason.The coefficient of permeability of precast slab entirety is 0.1-0.2mm/s, using GB/T 25993-2010 coefficient of permeability test side Method.
Hole for hoist uses M12 screw shell, screw shell lower part and 1 inside steel bar stress of armored concrete matts frame Connection, top are lower than normal concrete surface layer 10mm, first block screw shell with rubber plug at hole for hoist, and about 10mm thickness is then perfused Bitumen layer, finally filled and led up with prefabricated pervious concrete, the later period replace when, the closure at hole for hoist is pulled out, is lifted Replacement.As shown in fig. 6, being laid with granular cushion 6 (screed-coat containing microlith) on ground, granular cushion bottom sets soft Then fabricated permeable pavement of the present invention concrete slab 7 is lifted into above granular cushion, and is lifting by water-permeable pipe 8 After the completion, longitudinal piece 10mm is reserved, the flexible materials such as sand or heated bitumen or patch encapsulating patch are filled in longitudinal piece.
Curved section on pavement calculates total angle of turning and the edge lengths up and down of plate according to turning radius, The plane of plate be arranged to it is trapezoidal, as shown in figure 5,2 ° of steering can be achieved in 2 meters × 3 meters of monolithic block in case.Assembled is saturating Enough spaces are reserved in the two sides of water pavement concrete slab, and fabricated permeable pavement concrete slab is smoothly put It sets to screed-coat, it is subsequent to fill up vacant irregular unilateral part according to kerbstone and with cobblestone band, as shown in Figure 7.Select 2- The cobblestone 11 of 4cm diameter, and be embedded in mortar 10, cobblestone partial denudation.9 be foundation soil in figure.
The advantage of the invention is that this concrete slab can be fabricated to the bigger size of more existing paving brick, existing people can be improved Trade facing brick paving skid resistance and flatness are insufficient, achieve the purpose that rainwater permeate in time, walks comfortably and panel durability is strong, And pavement process is rapid in construction, base's surface layer is not necessarily to conditioned time, and open to traffic immediately is completed in construction.The present invention is by adopting With fabricated permeable pavement concrete slab and its paving structure, improves the mechanical property in common water-permeable brick pavement face, puts down Whole degree, utmostly reduces seam, improves walking comfort;The stage of health will be largely needed to shift in prefabrication practice It is completed to factory, shortening for high degree and ensure that the quality of concrete at the duration.Fabricated permeable pavement of the present invention is mixed Concrete board and its paving structure separately have infiltration row performance it is significant, the feature that anti-slippery effect is excellent, durability is good can be relieved medium and small rain condition condition The wet and slippery status in lower pavement.It can be used for the pavement and square, parkway of all grade roads.
Embodiment 1
Certain town road, two-way pavement, protoplast trade need to be transformed, people's row that wherein span width is 3.2 meters wide Mated formation using 2 meters wide and 3 meters long fabricated permeable pavement of the present invention concrete slab and its structure in road.
The saturation compression strength of armored concrete is 48MPa, and saturation flexural strength is 2.8MPa;Reinforcing bar is HRB400 grades; Reinforcing bar resists tensile stress when lifting, and reinforcing bar is buried to the above 3cm in normal concrete bottom surface;The wherein thickness of pervious concrete part Degree >=5cm;Pervious concrete and the material of armored concrete have the Chong Die transitional region 2cm of gradual change.Precast slab entirety Coefficient of permeability is 0.2mm/s.Suspension centre uses M12 screw shell, and after the completion of lifting, longitudinal piece 10mm is reserved, in longitudinal direction Sand processing is filled in piece.Other steps are not specifically limited.
Embodiment 2
Certain town road, two-way pavement, protoplast trade need to be transformed, people's row that wherein span width is 2.1 meters wide Mated formation using 1.3 meters wide and 2 meters long fabricated permeable pavement of the present invention concrete slab and its structure in road.
The saturation compression strength of armored concrete is 48MPa, and saturation flexural strength is 2.8MPa;Reinforcing bar is HRB400 grades; Reinforcing bar resists tensile stress when lifting, and reinforcing bar is buried to the above 3cm in normal concrete bottom surface;The wherein thickness of pervious concrete part Degree >=5cm;Pervious concrete and the material of armored concrete have the Chong Die transitional region 2cm of gradual change.Precast slab entirety Coefficient of permeability is 0.15mm/s.Suspension centre uses M12 screw shell, and after the completion of lifting, longitudinal piece 10mm is reserved, in longitudinal direction Sand processing is filled in piece.Other steps are not specifically limited.
Comparative example
Certain town road, two-way pavement, protoplast trade need to be transformed, people's row that wherein span width is 2.1 meters wide The part way in road is mated formation using 6cm thickness homogeneity brick.Screed-coat uses 3cm medium coarse sand, and cement stabilizing is respectively adopted in base Rubble and graded broken stone.
Successively the flatness of embodiment 1,2 and comparative example, flexural strength, compression strength and speed of application are detected and commented Valence.
Technical solution Flatness Flexural strength Compression strength Speed of application
Embodiment 1 2mm 2.8MPa 48MPa 2d/500m
Embodiment 2 3mm 2.8MPa 48MPa 2d/500m
Comparative example 8mm 0.4MPa 15MPa 27d/500m
From inspection result as can be seen that fabricated permeable pavement concrete slab and its paving structure that the present invention is shown , mechanical property high with flatness be excellent and the quick advantage of construction.
The present invention improves common water-permeable brick people by using fabricated permeable pavement concrete slab and its paving structure Mechanical property, the flatness in trade face, utmostly reduce seam, improve walking comfort;It in prefabrication practice will be big Amount needs the stage of health to be transferred to factory's completion, and shortening for high degree and ensure that the quality of concrete at the duration.This hair Bright fabricated permeable pavement concrete slab and its paving structure separately have infiltration row performance it is significant, anti-slippery effect is excellent, durability is good Feature can be relieved the status that pavement is wet and slippery under medium and small rain condition condition.It can be used for the pavement and square, park of all grade roads Road.

Claims (5)

1. a kind of production method of fabricated permeable pavement concrete slab, it is characterised in that the described method includes:
A, mold is made, the mould upstream is template cavity, and bottom is equipped with matts recessed portion;
B, the steel bar stress in mold bottom matts recessed portion, the interior embedment of mold bottom matts recessed portion is as hole for hoist Screw shell, screw shell lower part are connect with steel bar stress, and top is lower than 8 ~ 12mm of die top, then in matts recessed portion Interior casting concrete is to the top of matts recessed portion;
C, the polyphenylene sulfide resin lotion of 0.1L/ ㎡ is sprayed on surface after the completion of casting reinforced concrete;
D, 3-5min is completed in step C be poured pervious concrete 0.5-1cm;
E, the polyphenylene sulfide resin lotion of 0.1L/ ㎡ is sprayed on the thick casting pervious concrete face 0.5-1cm immediately;
F, pouring for subsequent pervious concrete is completed in the top template cavity of mold, the fabricated permeable with hole for hoist is made Pavement concrete slab.
2. a kind of production method of fabricated permeable pavement concrete slab according to claim 1, it is characterised in that: step In rapid E, the production method of polyphenylene sulfide resin lotion are as follows: a, room temperature are that solid polyphenylene sulfide resin is prepared into 0.6mm Flour sand below;B, common cation or anion surface active types of emulsifiers are selected;C, by polyphenylene sulfide resin powder Sand and emulsifier are placed in colloid mill jointly, and colloid mill storehouse temperature controls the lotion drop temperature 60- at 70-80 DEG C, after grinding 80℃。
3. a kind of production method of fabricated permeable pavement concrete slab according to claim 2, it is characterised in that: poly- The emulsifier volume of aralkyl sulfid resin emulsion is 2-17% in 1-5%, polyphenylene sulfide resin content, remaining is water.
4. a kind of production method of fabricated permeable pavement concrete slab according to claim 1, it is characterised in that: field The material requirements of the armored concrete of word lattice recessed portion is as follows: saturation compression strength >=40MPa, and saturation flexural strength >= 2.5MPa;Reinforcing bar reaches HRB400 grades;Reinforcing bar resists tensile stress when lifting, and reinforcing bar is buried to the above 3-5cm in normal concrete bottom surface Place;Thickness >=5cm of pervious concrete surface layer.
5. a kind of production method of fabricated permeable pavement concrete slab according to claim 1, it is characterised in that: dress After the completion of the lifting of formula water permeable sidewalk concrete slab, screw shell first is blocked with rubber plug at hole for hoist, then it is perfused about 8 ~ The bitumen layer of 12mm thickness, is finally filled and led up with prefabricated pervious concrete;When later period replaces concrete slab, by the closure at hole for hoist It pulls out, carries out lifting replacement.
CN201910625855.6A 2019-07-11 2019-07-11 A kind of production method of fabricated permeable pavement concrete slab Pending CN110485237A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910625855.6A CN110485237A (en) 2019-07-11 2019-07-11 A kind of production method of fabricated permeable pavement concrete slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910625855.6A CN110485237A (en) 2019-07-11 2019-07-11 A kind of production method of fabricated permeable pavement concrete slab

Publications (1)

Publication Number Publication Date
CN110485237A true CN110485237A (en) 2019-11-22

Family

ID=68547056

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910625855.6A Pending CN110485237A (en) 2019-07-11 2019-07-11 A kind of production method of fabricated permeable pavement concrete slab

Country Status (1)

Country Link
CN (1) CN110485237A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112959459A (en) * 2021-02-24 2021-06-15 中煤远大淮北建筑产业化有限公司 Preparation method of assembled pervious concrete road board
CN114808593A (en) * 2022-03-31 2022-07-29 武汉理工大学 Multilayer composite prefabricated permeable pavement slab and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202945521U (en) * 2012-09-10 2013-05-22 云南建工集团有限公司 Permeable pavement brick produced by building solid waste aggregates
US20140272302A1 (en) * 2013-03-15 2014-09-18 Romeo Ilarian Ciuperca Architectural finish, recycled aggregate coating and exterior insulated architectural finish system
CN107022938A (en) * 2017-04-26 2017-08-08 中国十九冶集团有限公司 Precast concrete road system and construction method
CN108265587A (en) * 2018-03-27 2018-07-10 湖南大学 Saturating storage functional surface brick and manufacture craft based on building waste crushed material
CN108532406A (en) * 2018-05-08 2018-09-14 深圳市市政工程咨询中心有限公司 Can rapid construction high-bearing capacity pervious surface and laying method
CN109914742A (en) * 2019-04-03 2019-06-21 苏维鼎 A kind of prefabricated high-strength concrete floor tile system and its construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202945521U (en) * 2012-09-10 2013-05-22 云南建工集团有限公司 Permeable pavement brick produced by building solid waste aggregates
US20140272302A1 (en) * 2013-03-15 2014-09-18 Romeo Ilarian Ciuperca Architectural finish, recycled aggregate coating and exterior insulated architectural finish system
CN107022938A (en) * 2017-04-26 2017-08-08 中国十九冶集团有限公司 Precast concrete road system and construction method
CN108265587A (en) * 2018-03-27 2018-07-10 湖南大学 Saturating storage functional surface brick and manufacture craft based on building waste crushed material
CN108532406A (en) * 2018-05-08 2018-09-14 深圳市市政工程咨询中心有限公司 Can rapid construction high-bearing capacity pervious surface and laying method
CN109914742A (en) * 2019-04-03 2019-06-21 苏维鼎 A kind of prefabricated high-strength concrete floor tile system and its construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘荣贵,蔡亚祥: "《五金交电化工建材商品实用手册 建筑材料篇》", 31 January 1997 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112959459A (en) * 2021-02-24 2021-06-15 中煤远大淮北建筑产业化有限公司 Preparation method of assembled pervious concrete road board
CN114808593A (en) * 2022-03-31 2022-07-29 武汉理工大学 Multilayer composite prefabricated permeable pavement slab and construction method thereof

Similar Documents

Publication Publication Date Title
CN204530365U (en) There is the permeable road structure of curb
CN107905254A (en) The construction method of mould trolley in a kind of pipe gallery formwork integrated hydraulic
CN103352400A (en) Prefabricated embedded type rail plate
CN111764216A (en) Construction method and application of fabricated concrete road plate
CN110485237A (en) A kind of production method of fabricated permeable pavement concrete slab
CN110438914A (en) Water tank culvert and its construction method are crossed on soft soil foundation
CN202482730U (en) Permeable brick
CN104358202B (en) Road surface structare layer and its paving method
CN103343503B (en) Bridge-type prefabricated reinforced concrete trough slab wear resistant road surface structural system and construction method
CN208362832U (en) A kind of spongeization road structure of cracking resistance
CN110485238A (en) A kind of fabricated permeable pavement concrete slab
CN110820466A (en) Quick repairing method for cement concrete pavement
CN204589745U (en) The thick brick of a kind of composite ceramics
CN213538565U (en) Road bridge linkage segment becomes rigidity road bed
CN115198589A (en) Ultra-thin pavement structure based on ultra-high-toughness cement-based composite material and implementation process
KR20120103266A (en) Water permeable block and producing method thereof
CN112030652A (en) Preparation method of ecological water-permeable concrete pavement
CN206467755U (en) A kind of permeable cover plate of steel plate carbon fiber reinforced concrete
CN206477545U (en) Floor structure
CN109972467A (en) A kind of building waste road cushion and its casting method
CN215857035U (en) Active powder concrete composite permeable sidewalk brick
CN104727200A (en) Composite ceramic thick brick and manufacturing method thereof
CN220352535U (en) Municipal road construction roadbed drainage structure
CN216404949U (en) Cement prefabricated part for road quick repair
JPH0646008U (en) Permeable cement curb

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191122

RJ01 Rejection of invention patent application after publication