CN110410095B - Material residue soil transportation method for tunnel construction of Tunnel Boring Machine (TBM) - Google Patents

Material residue soil transportation method for tunnel construction of Tunnel Boring Machine (TBM) Download PDF

Info

Publication number
CN110410095B
CN110410095B CN201910759749.7A CN201910759749A CN110410095B CN 110410095 B CN110410095 B CN 110410095B CN 201910759749 A CN201910759749 A CN 201910759749A CN 110410095 B CN110410095 B CN 110410095B
Authority
CN
China
Prior art keywords
tunnel
flat
tbm
main
line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910759749.7A
Other languages
Chinese (zh)
Other versions
CN110410095A (en
Inventor
王亚锋
马亮
胡新朋
陈阳
李增
曹耀祖
刘强
李福才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Co Ltd CRTG
China Railway Tunnel Stock Co Ltd
Original Assignee
China Railway Tunnel Group Co Ltd CRTG
China Railway Tunnel Stock Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Co Ltd CRTG, China Railway Tunnel Stock Co Ltd filed Critical China Railway Tunnel Group Co Ltd CRTG
Priority to CN201910759749.7A priority Critical patent/CN110410095B/en
Publication of CN110410095A publication Critical patent/CN110410095A/en
Application granted granted Critical
Publication of CN110410095B publication Critical patent/CN110410095B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G35/00Mechanical conveyors not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

A material residue soil transportation method for TBM tunnel construction is disclosed, wherein the tunnel comprises a main tunnel, a flat tunnel and an auxiliary channel for communicating the main tunnel with the flat tunnel, the flat tunnel comprises a small TBM machine entering section and a small TBM machine digging section, a temporary transportation line with double tracks is arranged at the small TBM machine entering section, and three flat transportation lines with four tracks are arranged at the small TBM machine digging section; arranging a muck conveyer belt and two main tunnel conveying lines of four tracks in a main tunnel; after the tail of the large TBM machine passes through an auxiliary channel and a horizontal guide conveying line can be connected with a main hole conveying line through the auxiliary channel, arranging a horizontal guide conveying line extension line connected with the main hole conveying line in the auxiliary channel; during the process of expanding and excavating the flat tunnel, the flat transport line is connected with the main tunnel transport line through an auxiliary channel in front of the expanding and excavating operation surface of the flat tunnel, and then the flat tunnel is expanded and excavated by adopting a drilling and blasting method. The method is matched with the construction process, and the material and residue soil transportation is matched with the excavation progress.

Description

Material residue soil transportation method for tunnel construction of Tunnel Boring Machine (TBM)
Technical Field
The invention relates to the technical field of tunnel construction, in particular to a method for transporting material dregs for tunnel boring construction of a Tunnel Boring Machine (TBM).
Background
The materials required by the construction of the TBM tunnel comprise construction materials and equipment, and can uninterruptedly produce muck in the excavation process of the TBM tunnel, so that the muck needs to be timely conveyed out of the tunnel.
Disclosure of Invention
The invention provides a material residue soil transportation method for TBM tunnel construction, which aims to solve the technical problems that the excavation progress of a TBM tunnel is not matched with residue soil transportation, and mutual interference among a plurality of working faces and working procedures is large.
In order to solve the technical problems, the invention adopts the following technical scheme:
designing a material residue soil transportation method for tunnel construction of a TBM (tunnel boring machine), wherein the tunnel comprises a main tunnel, a flat tunnel and an auxiliary channel, and the auxiliary channel is used for communicating the main tunnel and the flat tunnel; the method comprises the following steps:
step 1, after a small TBM machine starts operation conditions, continuously excavating a flat tunnel by using the small TBM machine, arranging a double track capable of forming a temporary transportation line at an entrance section of the small TBM machine of the flat tunnel, and arranging four tracks capable of forming three flat transportation lines at an excavation section of the small TBM machine of the flat tunnel;
step 2, after the main tunnel has the starting operation conditions of the large TBM, continuously digging the main tunnel by using the large TBM, and arranging a residue soil conveyer belt and four tracks capable of forming two main tunnel conveying lines on the main tunnel;
step 3, after the tail of the large TBM machine passes through an auxiliary channel and a horizontal guide conveying line can be connected with a main hole conveying line through the auxiliary channel, arranging a horizontal guide conveying line extension line in the auxiliary channel so as to enable the horizontal guide conveying line to be connected with the main hole conveying line;
and 4, during the process of expanding and excavating the flat tunnel, connecting the flat tunnel transportation line with the main tunnel transportation line through an auxiliary channel in front of the expanding and excavating operation surface of the flat tunnel, and then expanding and excavating the flat tunnel by adopting a drilling and blasting method.
And 3, performing excavation operation on the large TBM machine for excavating the main tunnel and the small TBM machine for excavating the flat tunnel.
Preferably, the step 3 further comprises a step 3a, the main tunnel and the flat tunnel pass through a fault crushing zone, the small TBM machine stops working before reaching the fault crushing zone of the flat tunnel, a bypass pit bypassing the small TBM machine is constructed by adopting a drilling and blasting method and reaches the front of the fault crushing zone of the flat tunnel, and a double track capable of forming a bypass pit conveying line is arranged in the bypass pit; and processing the fault broken belt area of the flat tunnel passing by the drilling and blasting method, reinforcing, and continuously excavating the flat tunnel after the small TBM machine passes through the fault broken belt area of the flat tunnel passing by step.
Further, the step 3 further comprises a step 3b, the roundabout pilot tunnel passes through the main tunnel, after the fault crushing zone area where the main tunnel passes is excavated by adopting a drilling and blasting method, a tunnel face lining which enables the large TBM to pass through in a stepping mode is constructed in the fault crushing zone area where the main tunnel passes.
Preferably, the excavation diameter of the small TBM is 6.36m, the excavation diameter of the large TBM is 9m, and the track spacing of the four tracks forming the two main tunnel transportation lines is 970mm +1100mm +970 mm; the track pitch of the four tracks forming the three flat guide conveying lines is 970mm +970mm +970 mm.
Compared with the prior art, the invention has the beneficial effects that:
(1) the main tunnel is formed by one-time excavation through a large TBM machine, the excavation progress is slow, the slag amount is large, and therefore a slag conveyer belt is adopted to convey slag; the flat tunnel is excavated by the small TBM machine in advance and then expanded by a drilling and blasting method, and the small TBM machine has the advantages of high excavation speed and less slag discharge, so that the flat tunnel is more suitable for rail transportation.
(2) The horizontal tunnel adopts small-size TBM machine light in weight, and the excavation progress is fast, and geological adaptability is higher than large-scale TBM machine, can carry out advanced detection to the stratum to handling the broken area of fault that the horizontal tunnel passed through, the broken area of fault that the positive tunnel passed through as early as possible, reducing construction risk and collapse risk, the indirect emergence probability that reduces the circumstances that the slag output that the collapse caused increases.
(3) The four-track anti-blocking effect of the three flat guide conveying lines is good, any two adjacent tracks of the three flat guide conveying lines can form the conveying lines, and the three flat guide conveying lines are suitable for geological environments with poor geological stability.
(4) The track pitch of the four tracks forming the two main hole transportation lines is 970mm +1100mm +970mm, the safety boundary of the four tracks is 550mm outside the tracks, and two rows of rail cars can pass through the four tracks in parallel.
Drawings
FIG. 1 is a diagram of the construction range of a tunnel.
FIG. 2 is a schematic plane view of a rail-bound transportation rail for constructing the construction section in FIG. 1 by using step 1 of the material residue soil transportation method for TBM tunnel construction of the present invention.
Fig. 3 is a schematic view of a cross-sectional arrangement of rails of a main tunnel for tunnel construction in fig. 1.
Fig. 4 is a schematic view of a cross-sectional track layout of the flat tunnel of the tunnel construction of fig. 1.
FIG. 5 is a schematic plane view of a rail-bound transportation rail for constructing the construction section in FIG. 1 by using step 2 of the material residue soil transportation method for TBM tunnel construction of the present invention.
FIG. 6 is a schematic plane view of a rail-bound transportation rail for constructing the construction section in FIG. 1 in step 3 of the material residue soil transportation method for TBM tunnel construction of the present invention.
Fig. 7 is a schematic plane view of a rail-bound transportation track for constructing the construction section in fig. 1 by using the steps 3a and 3b of the material residue soil transportation method for TBM tunnel construction of the present invention.
In the figure, 1-a flat tunnel, 11-a flat tunnel drilling and blasting method excavation section, 111-a flat tunnel small TBM machine starting section, 12-a flat tunnel small TBM machine excavation section, 121-a flat tunnel running fault breaking zone, 13-a flat tunnel expanding excavation section, 2-a main tunnel, 21-a main tunnel drilling and blasting method excavation section, 211-a main tunnel large TBM machine starting section, 22-a main tunnel large TBM machine excavation section, 221-a main tunnel running fault breaking zone, 3-an auxiliary channel, 31-an auxiliary channel, 32-an auxiliary channel, 33-an auxiliary channel, 3 n-an auxiliary channel, 41-a flat tunnel outlet section transportation line, 411-a steel rail, 412-a steel rail, 421-a flat tunnel small TBM machine excavation section transportation line, 4211-a steel rail, 4212-a steel rail, 422# -small TBM machine digging section conveying line of a flat tunnel, 4221-steel rail, 4222-steel rail, 45-fresh air pipe, 51# -main tunnel material conveying line, 511-steel rail, 512-steel rail, 52# -main tunnel material conveying line, 521-steel rail, 522-steel rail, 53# -avoidance line, 54-main tunnel slag conveying belt, 55-fresh air pipe, 6-circuitous guide pit, 441-rail, 442-rail, 91-small TBM machine and 92-large TBM machine.
Detailed Description
The following examples are intended to illustrate the present invention in detail and should not be construed as limiting the scope of the present invention in any way.
A certain tunnel is used for founding the railway transportation tunnel, and its design standard possesses I line tunnel and II line tunnels, and the design section of I line tunnel and II line tunnels is 9m, and I line tunnel and II line tunnels are provided with the flat tunnel that leads that is used for connecting the station through many auxiliary passage intercommunications, in the end department of II line tunnels. The I-line tunnel and the II-line tunnel both pass through the geological fault zone.
In fig. 1-7, rails 411, 412 form a transportation line 41# at the exit section of the tunnel. The steel rail 4211, the steel rail 4212, the steel rail 4221 and the steel rail 4222 form a three-line four-track of the flat tunnel, namely four tracks capable of forming three flat guide transportation lines, a flat guide tunnel small TBM machine excavation section transportation line 421# formed by the steel rail 4211 and the steel rail 4212, a flat guide tunnel small TBM machine excavation section transportation line 422# formed by the steel rail 4221 and the steel rail 4222 are drawn in a simplified drawing form in fig. 2, 3 and 5, but the flat guide tunnel small TBM machine excavation section transportation line formed by the steel rail 4212 and the steel rail 4221 is not shown. Rails 511, 512, 521 and 522 form a double-track four-track tunnel, i.e., a four-track tunnel capable of forming two tunnel transportation lines.
Example 1: the utility model provides a material dregs transportation method is used in TBM tunnel construction, the tunnel includes I line tunnel, II line tunnels and many auxiliary channel 3 that communicate I line tunnel and II line tunnels, wherein, adopt large-scale TBM machine 92 one shot forming to excavate the main tunnel 2 that is used for forming I line tunnel, adopt small-size TBM machine 91 to excavate the flat tunnel 1 that is used for forming II line tunnels, it is little to utilize small-size TBM machine 91 to excavate the section, the advantage of the excavation progress is fast is surveyed the disconnected regional of geology in advance, consolidate the back of handling, make large-scale TBM machine 92 can step-by-step geological fault region through main tunnel 2 to large-scale TBM machine 92 excavates the main tunnel. In this embodiment, the large TBM machine 92 is a shield machine with a cross-sectional diameter of 9m, and the small TBM machine 91 is a shield machine with a cross-sectional diameter of 6.36 m. Based on the difference of the section diameters of the large TBM and the small TBM, the slag output amount of the large TBM is different, and after the flat tunnel is excavated by the small TBM, the flat tunnel needs to be expanded and excavated at the later stage, so that the required supporting materials are less.
When the small TBM 91 and the large TBM 92 are used for operation, the flat tunnel 1 and the main tunnel 2 need to have TBM starting operation conditions, so that firstly, a drilling and blasting method is adopted to excavate the end head of the flat tunnel, the end head of the main tunnel and an auxiliary channel in an end head area, so that the flat tunnel has the small TBM starting operation conditions, and the main tunnel has the large TBM starting operation conditions. Specifically, the areas indicated by the dark gray areas in fig. 1 (the horizontal tunnel drilling and blasting excavation section 11, the main tunnel drilling and blasting excavation section 21, the auxiliary passage 31, and the auxiliary passage 32) are indicated by the light gray areas in fig. 1 as the shield excavation sections of the TBM machine (the horizontal tunnel small TBM machine excavation section 12, the main tunnel large TBM machine excavation section 22, which include the fracture zone 121 where the horizontal tunnel passes through and the fracture zone 221 where the main tunnel passes through)
The method comprises the following steps:
step 1, after a small TBM machine starts operation conditions, continuously excavating a flat tunnel by using the small TBM machine, arranging a double track capable of forming a temporary transportation line at an entrance section of the small TBM machine of the flat tunnel, and arranging four tracks capable of forming three flat transportation lines at an excavation section of the small TBM machine of the flat tunnel; the four-track anti-blocking effect of the three flat guide conveying lines is good, any two adjacent tracks can form the conveying lines, and the three flat guide conveying lines are suitable for geological environments with poor geological stability. In this embodiment, the track pitch of the four tracks forming the three flat conductive transport lines is 970mm +970mm +970 mm. The slag soil outward transportation and the construction material inward transportation of the horizontal tunnel pass through a transportation train on a horizontal transportation line; before the tail of the large TBM machine crosses the auxiliary channel, the flat guide transport line cannot transport muck and construction materials through the main tunnel transport line and the auxiliary channel, so that the muck and the construction materials need to be transported by means of a temporary transport line.
Step 2, after the main tunnel has the starting operation conditions of the large TBM, continuously digging the main tunnel by using the large TBM, and arranging a residue soil conveyer belt and four tracks capable of forming two main tunnel conveying lines on the main tunnel; in this embodiment, the track pitch of the four tracks forming the two main hole transportation lines is 970mm +1100mm +970mm, and the safety boundary thereof is 550mm outside the tracks, so that two rows of rail cars can pass through in parallel. The main tunnel excavation section is large, the slag discharge amount is large, the adoption of the slag conveyer belt is more economical, and the transport capacity occupation of the main tunnel transport line can be saved.
Step 3, after the tail of the large TBM machine passes through an auxiliary channel and a horizontal guide conveying line can be connected with a main hole conveying line through the auxiliary channel, arranging a horizontal guide conveying line extension line in the auxiliary channel so as to enable the horizontal guide conveying line to be connected with the main hole conveying line; the mode that the transportation line is linked up with the transportation line of main tunnel is through the connection of railway switch. In the period, the temporary transport line in the entering section of the small TBM can be detached, and railway turnouts can be arranged at the temporary transport line, so that the flat-guide transport line and the extension line of the flat-guide transport line are conveniently connected. In this step, the large TBM machine for excavating the main tunnel and the small TBM machine for excavating the flat tunnel are both subjected to excavation work. After the flat guide conveying line is connected with the main tunnel conveying line, the construction materials and the muck can be conveniently loaded and unloaded in a near field.
And 3a, stopping the small TBM when the small TBM reaches the front of the fault broken belt area where the flat tunnel passes, constructing and manufacturing a circuitous pilot tunnel bypassing the small TBM by adopting a drilling and blasting method, so that the circuitous pilot tunnel reaches the front of the first fault broken belt area where the flat tunnel passes through by the circuitous pilot tunnel, arranging a double track capable of forming a circuitous pilot tunnel conveying line in the circuitous pilot tunnel, wherein the circuitous pilot tunnel conveying line is used as a running track of a transport train, treating the fault broken belt area where the flat tunnel passes through by the drilling and blasting method, and reinforcing, and continuously excavating the flat tunnel after the small TBM passes through the fault broken belt area where the flat tunnel passes by in a stepping manner.
And 3b, the roundabout pilot tunnel passes through the main hole, after a fault broken belt area passing through the main hole is excavated by a drilling and blasting method, a hole surface lining capable of enabling the large TBM to pass through in a stepping mode is constructed in the fault broken belt area passing through the main hole. The small TBM machine is adopted to carry out advanced detection and excavation treatment on the geological fault area, and the passing difficulty of the large TBM machine can be reduced.
And 4, during the process of expanding and excavating the flat tunnel, connecting the flat transport line with the main tunnel transport line through an auxiliary channel in front of the expanding and excavating operation surface of the flat tunnel, removing facilities in the flat tunnel which influence the expanding and excavating operation, and then expanding and excavating the flat tunnel by adopting a drilling and blasting method. By means of the auxiliary channel and the main tunnel conveying line, the conveying of the muck and the construction materials on the working face of the small TBM machine can be maintained while the expanding and digging operation of the flat tunnel is not influenced.
In the foregoing steps 1-3, in order to facilitate the operation of the train, a temporary stop line may be added at a position required by the level guidance transportation line or the main tunnel transportation line.
While the present invention has been described in detail with reference to the drawings and the embodiments, those skilled in the art will understand that various specific parameters in the above embodiments can be changed without departing from the spirit of the present invention, and a plurality of specific embodiments are formed, which are common variation ranges of the present invention, and will not be described in detail herein.

Claims (2)

1. A material residue soil transportation method for TBM tunnel construction is characterized in that the tunnel comprises a main tunnel, a flat tunnel and an auxiliary channel, wherein the auxiliary channel is used for communicating the main tunnel and the flat tunnel; the method comprises the following steps:
step 1, after a small TBM machine starts operation conditions, continuously excavating a flat tunnel by using the small TBM machine, arranging a double track capable of forming a temporary transportation line at an entrance section of the small TBM machine of the flat tunnel, and arranging four tracks capable of forming three flat transportation lines at an excavation section of the small TBM machine of the flat tunnel;
step 2, after the main tunnel has the starting operation conditions of the large TBM, continuously digging the main tunnel by using the large TBM, and arranging a residue soil conveyer belt and four tracks capable of forming two main tunnel conveying lines on the main tunnel;
step 3, after the tail of the large TBM machine passes through an auxiliary channel and a horizontal guide conveying line can be connected with a main hole conveying line through the auxiliary channel, arranging a horizontal guide conveying line extension line in the auxiliary channel so as to enable the horizontal guide conveying line to be connected with the main hole conveying line;
the small TBM machine stops, a circuitous pilot tunnel bypassing the small TBM machine is constructed and manufactured by adopting a drilling and blasting method so as to reach the front of the fault crushing zone area where the parallel tunnel passes, and a double track capable of forming a circuitous pilot tunnel conveying line is arranged in the circuitous pilot tunnel; processing the fault broken belt area passing through the flat tunnel by a drilling and blasting method and reinforcing the fault broken belt area, and continuously excavating the flat tunnel after the small TBM machine passes through the fault broken belt area passing through the flat tunnel in a stepping manner;
the step 3 also comprises a step 3b, the roundabout pilot tunnel passes through the main tunnel, after a fault broken belt area where the main tunnel passes is excavated by adopting a drilling and blasting method, a tunnel face lining which can enable a large TBM (tunnel boring machine) to pass by in a stepping mode is constructed in the fault broken belt area where the main tunnel passes;
step 4, during the tunnel expanding and excavating process, connecting a flat guide conveying line with a main tunnel conveying line through an auxiliary channel in front of the tunnel expanding and excavating operation surface of the flat guide tunnel, and then expanding and excavating the flat guide tunnel by adopting a drilling and blasting method;
and in the step 3, carrying out excavation operation on the large TBM machine for excavating the main tunnel and the small TBM machine for excavating the flat tunnel.
2. The method for transporting the material dregs for the tunnel construction of the TBM as claimed in claim 1, wherein the excavation diameter of the small TBM is 6.36m, the excavation diameter of the large TBM is 9m, and the track pitch of the four tracks forming the two main tunnel transportation lines is 970mm +1100mm +970 mm; the track pitch of the four tracks forming the three flat guide conveying lines is 970mm +970mm +970 mm.
CN201910759749.7A 2019-08-16 2019-08-16 Material residue soil transportation method for tunnel construction of Tunnel Boring Machine (TBM) Active CN110410095B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910759749.7A CN110410095B (en) 2019-08-16 2019-08-16 Material residue soil transportation method for tunnel construction of Tunnel Boring Machine (TBM)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910759749.7A CN110410095B (en) 2019-08-16 2019-08-16 Material residue soil transportation method for tunnel construction of Tunnel Boring Machine (TBM)

Publications (2)

Publication Number Publication Date
CN110410095A CN110410095A (en) 2019-11-05
CN110410095B true CN110410095B (en) 2021-10-08

Family

ID=68367597

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910759749.7A Active CN110410095B (en) 2019-08-16 2019-08-16 Material residue soil transportation method for tunnel construction of Tunnel Boring Machine (TBM)

Country Status (1)

Country Link
CN (1) CN110410095B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112502721B (en) * 2020-12-08 2022-03-25 中铁隧道局集团有限公司 Arc-shaped bifurcation stepping construction method for positioning double TBMs based on double-line separate repair
CN114109400A (en) * 2021-12-03 2022-03-01 中铁隧道局集团有限公司 TBM (Tunnel boring machine) escaping processing method in tunnel construction and construction structure
CN114233309B (en) * 2021-12-17 2023-11-03 新疆额尔齐斯河流域开发工程建设管理局 TBM construction method for one-hole double-machine in ultra-long-distance tunnel

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101220746A (en) * 2008-02-01 2008-07-16 中铁十三局集团有限公司 TBM pilot tunnel expansion digging method for 20km double-line double-cavity ultra-long tunnel construction
CN107355226A (en) * 2017-08-23 2017-11-17 中国电建集团成都勘测设计研究院有限公司 TBM construction tunnel fault belts hole section processing structure
CN207111096U (en) * 2017-08-23 2018-03-16 中国电建集团成都勘测设计研究院有限公司 TBM construction tunnel fault belts hole section processing structure
CN207161090U (en) * 2017-05-03 2018-03-30 中国水利水电第十三工程局有限公司 Shipping unit outside a kind of shield section service channel dregs
CN108049886A (en) * 2018-01-12 2018-05-18 中铁上海工程局集团有限公司 Shield method service channel slag-tapping system
CN109403986A (en) * 2017-08-16 2019-03-01 中铁二院工程集团有限责任公司 The synchronous enlarging of the parallel heading of TBM tunneling construction is the construction method of double line tunnel
CN109458190A (en) * 2018-10-25 2019-03-12 中铁二十二局集团轨道工程有限公司 It is a kind of to turn over slag construction method and its application in TBM construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101220746A (en) * 2008-02-01 2008-07-16 中铁十三局集团有限公司 TBM pilot tunnel expansion digging method for 20km double-line double-cavity ultra-long tunnel construction
CN207161090U (en) * 2017-05-03 2018-03-30 中国水利水电第十三工程局有限公司 Shipping unit outside a kind of shield section service channel dregs
CN109403986A (en) * 2017-08-16 2019-03-01 中铁二院工程集团有限责任公司 The synchronous enlarging of the parallel heading of TBM tunneling construction is the construction method of double line tunnel
CN107355226A (en) * 2017-08-23 2017-11-17 中国电建集团成都勘测设计研究院有限公司 TBM construction tunnel fault belts hole section processing structure
CN207111096U (en) * 2017-08-23 2018-03-16 中国电建集团成都勘测设计研究院有限公司 TBM construction tunnel fault belts hole section processing structure
CN108049886A (en) * 2018-01-12 2018-05-18 中铁上海工程局集团有限公司 Shield method service channel slag-tapping system
CN109458190A (en) * 2018-10-25 2019-03-12 中铁二十二局集团轨道工程有限公司 It is a kind of to turn over slag construction method and its application in TBM construction

Also Published As

Publication number Publication date
CN110410095A (en) 2019-11-05

Similar Documents

Publication Publication Date Title
CN110410095B (en) Material residue soil transportation method for tunnel construction of Tunnel Boring Machine (TBM)
CN107725053B (en) Lane is reserved for one's own use without pillar mining method in exploiting field suitable for gently inclined seam
US20130106165A1 (en) Underground mining
CN111335894B (en) Horizontal subsection small short wall fully mechanized caving mining method for steep thick coal seam
US20030168903A1 (en) Mining method
AU2003297759B2 (en) Mining system
CN103485786A (en) Steeply inclined coal seam strike long-wall mechanization mining method
CN108049886B (en) Slag discharging system of shield method connecting channel
CN111322073A (en) Combined mine exploitation system based on vertical shaft and adhesive tape inclined shaft
US11746654B2 (en) Kind of no-pillar and gob-side entry retaining mining and construction method without the mining area division
US6796616B2 (en) Mining system
CN114427463B (en) Deep deposit downward approach type plate area partition unloading layering advanced pressure relief stoping method
AU2009212092B2 (en) A method and an apparatus for mining a material in an underground environment
CN101302932A (en) Method for underground chamber digging and laneway opening digging
CN102787845B (en) Segmented construction method of extra-long tunnels by adopting development machines to construct inclined shafts and headings first
CN100529328C (en) Mining producing method for synchronous excavation and mining drift multiplying
CN107218077B (en) Rock gangway multimode combines cash technique out
CN111550246B (en) Novel caving mining method for steeply-inclined crushed ultra-thick stone coal type vanadium ore
CN118128536A (en) Coal seam mining method capable of preventing impact ground pressure through rock roadway arrangement
CN113803070B (en) Horizontal sectional coordination mining method for steep short-distance super-thick coal group
CN113153301B (en) Horizontal sectional mechanized caving coal mining method for steeply inclined coal seam
CN110454187B (en) Roadway arrangement method for improving coal resource extraction rate of footrill exploitation mine
CN117345235A (en) Sectional rock drilling stage ore-discharging subsequent filling mining method for stage first mining disc area
CN117145472A (en) Mining system and mining method for steeply inclined coal seam
CN112211636A (en) Comprehensive mechanized coal mining method for irregular block sections

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant