CN110409822A - A kind of overhanging I-steel hole Embedment Construction technique - Google Patents

A kind of overhanging I-steel hole Embedment Construction technique Download PDF

Info

Publication number
CN110409822A
CN110409822A CN201910585597.3A CN201910585597A CN110409822A CN 110409822 A CN110409822 A CN 110409822A CN 201910585597 A CN201910585597 A CN 201910585597A CN 110409822 A CN110409822 A CN 110409822A
Authority
CN
China
Prior art keywords
overhanging
fitting
steel
shear wall
foam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910585597.3A
Other languages
Chinese (zh)
Inventor
宋立康
马清杰
陈浩
杲晓
程建军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd filed Critical Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority to CN201910585597.3A priority Critical patent/CN110409822A/en
Publication of CN110409822A publication Critical patent/CN110409822A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G15/00Forms or shutterings for making openings, cavities, slits, or channels
    • E04G15/06Forms or shutterings for making openings, cavities, slits, or channels for cavities or channels in walls of floors, e.g. for making chimneys
    • E04G15/061Non-reusable forms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The present invention discloses a kind of overhanging I-steel hole Embedment Construction technique, including foam built-in fitting and dust catcher;The length of the foam built-in fitting is equal to the thickness of shear wall, its cross section is rectangular configuration, the I-shaped channel to match with the cross-sectional structure of overhanging I-steel is provided through on the cross section of the foam built-in fitting, the overhanging I-steel passes through the I-shaped channel of foam built-in fitting;And the following steps are included: 1) the overhanging I-steel hole defaults between floor and shear wall, foam built-in fitting is placed at the cave entrance reservation of shear wall bottom, and foam built-in fitting is fixed on shear wall vertical reinforcement by tied silk, so that foam built-in fitting and shear wall are straight, the overhanging I-steel passes through foam built-in fitting and is embedded at cave entrance reservation in advance;The accurate positioning at the overhanging I-steel hole in construction technology of the present invention, and the foam built-in fitting for overhanging I-steel position cuts simple and convenient, later period sealing hole massless hidden danger.

Description

A kind of overhanging I-steel hole Embedment Construction technique
Technical field
The invention belongs to the operating methods of construction operation, and in particular to a kind of overhanging I-steel hole Embedment Construction work Skill.
Background technique
Tradition overhanging I-steel hole through walls is all to be fixed wooden box before shear wall molding using wooden box is made in advance On shear wall formwork, for the wooden box in course of hardening, concrete is increasing to the extruding force of wooden box, leads to wooden box It removes difficult, it is difficult to reuse;And wooden box dismounting is not clean, later period sealing hole is easy to cause the quality such as hole infiltration hidden Suffer from;Using the pre-buried overhanging I-steel hole of the traditional approach, complex process be easy to cause adverse effect to postorder construction.
Summary of the invention
Goal of the invention: present invention aims in view of the deficiencies of the prior art, providing, a kind of overhanging I-steel hole is pre-buried Construction technology, the present invention are mainly used for pre-buried overhanging I-steel hole in advance.
Technical solution: a kind of overhanging I-steel hole Embedment Construction technique of the present invention, including foam built-in fitting and suction Dirt device;The length of the foam built-in fitting is equal to the thickness of overhanging the worn shear wall of I-steel, and cross section is rectangular configuration, institute State the I-shaped channel for being provided through on the cross section of foam built-in fitting and matching with the cross-sectional structure of overhanging I-steel, institute State the I-shaped channel that overhanging I-steel passes through foam built-in fitting;And the following steps are included:
1) the overhanging I-steel hole defaults between floor and shear wall, and foam built-in fitting is placed in shear wall bottom At cave entrance reservation, and foam built-in fitting is fixed on shear wall vertical reinforcement by tied silk, so that foam built-in fitting and shearing Wall is straight, and shear wall is facilitated to mold, and the overhanging I-steel passes through foam built-in fitting and is embedded at cave entrance reservation in advance;
2) when shear wall molds, square opening, the square opening are opened up on the shear wall formwork that overhanging I-steel wears shear wall position Without particular/special requirement, only needs guiding through overhanging I-steel and cover foam built-in fitting;
3) when the concrete that shear wall formwork pours reaches demoulding condition, the concrete grout in foam built-in fitting surface layer is rejected Block;
4) after being removed after overhanging I-steel use, 2 construction personnel is needed to reject foam built-in fitting, 1 construction Personnel's hand-held cleaners on outrigger, suction port of suction cleaner cover overhanging I-steel hole completely, and another 1 construction personnel is in shear wall It is indoor foam built-in fitting is dug broken, be sucked out by dust catcher, prevent foam beads floating pollution, then carry out overhanging I-steel Sealing hole.
Preferably, the spine support on the shear wall formwork is steel pipe, and the steel pipe is symmetrically set to shear wall Template two sides, connecting hole is respectively symmetrically offered on symmetrically arranged steel pipe, and Screw arbor with nut at both-ends passes through the connection on shear wall formwork Hole, the both ends of the split bolt pass through gasket respectively and shear wall formwork is fastenedly connected by nut.
Preferably, the overhanging I-steel runs through the medium position of foam built-in fitting.
The utility model has the advantages that the present invention constructs to pre-buried overhanging I-steel hole in advance by the construction technology, this is applied Work technique will overhang I-steel and run through foam built-in fitting, and pre-buried be installed on of foam built-in fitting is overhang I-steel hole, this peace Dress method is convenient and efficient, and after the completion of overhanging the shear wall on I-steel hole and pouring, foam built-in fitting and shear wall form one Body, the generation for phenomena such as not will lead to concrete spillage, the hole accurate positioning constructed out by the construction technology overhang I-shaped The foam built-in fitting of steel position cut it is simple and convenient, to later period sealing hole massless hidden danger.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of construction technology of the present invention;
Fig. 2 is the main view of construction technology of the present invention;
Fig. 3 is the top view of construction technology of the present invention;
Fig. 4 is the main view of foam built-in fitting of the present invention;
Fig. 5 is the top view of foam built-in fitting of the present invention.
In figure, 1- foam built-in fitting, 2- overhangs I-steel, 3- shear wall formwork, 4- floor.
Specific embodiment
Technical solution of the present invention is described in detail below by attached drawing, but protection scope of the present invention is not limited to The embodiment.
Embodiment: a kind of overhanging I-steel hole Embedment Construction technique, including foam built-in fitting 1 and dust catcher;The bubble The length of foam built-in fitting 1 is equal to the thickness of overhanging the worn shear wall of I-steel 2, and cross section is rectangular configuration, and the foam is pre- The I-shaped channel to match with the cross-sectional structure of overhanging I-steel 2, the overhanging are provided through on the cross section of embedded part 1 I-steel 2 passes through the I-shaped channel of foam built-in fitting 1, and the overhanging I-steel 2 runs through the medium position of foam built-in fitting 1; And the following steps are included:
1) the overhanging I-steel hole defaults between floor 4 and shear wall, and foam built-in fitting 1 is placed in shear wall bottom Cave entrance reservation at, and foam built-in fitting 1 is fixed on shear wall vertical reinforcement by tied silk so that foam built-in fitting 1 with Shear wall is straight, and shear wall is facilitated to mold, and the overhanging I-steel 2 passes through foam built-in fitting 1 and is embedded at cave entrance reservation in advance;
2) when shear wall molds, square opening, the side are opened up on the shear wall formwork 3 that overhanging I-steel 2 wears shear wall position Mouth only needs guiding through overhanging I-steel 2 and covers foam built-in fitting 1 without particular/special requirement;
3) when the concrete that shear wall formwork 3 pours reaches demoulding condition, the concrete grout in 1 surface layer of foam built-in fitting is rejected Block;
4) it after being removed after overhanging 2 use of I-steel, needs 2 construction personnel to reject foam built-in fitting 1,1 and applies Worker person's hand-held cleaners on outrigger, suction port of suction cleaner cover overhanging I-steel hole completely, and another 1 construction personnel is shearing The interior of wall digs foam built-in fitting 1 broken, is sucked out by dust catcher, prevents foam beads floating pollution, then carries out overhanging work Word steel sealing hole.
Preferably, the spine support on the shear wall formwork 3 is steel pipe, and the steel pipe is symmetrically set to shear wall 3 two sides of template, connecting hole is respectively symmetrically offered on symmetrically arranged steel pipe, and Screw arbor with nut at both-ends passes through the company on shear wall formwork 3 Hole is connect, the both ends of the split bolt pass through gasket and nut respectively and are fastenedly connected shear wall formwork 3.
As described above, must not be explained although the present invention has been indicated and described referring to specific preferred embodiment For the limitation to invention itself.It without prejudice to the spirit and scope of the invention as defined in the appended claims, can be right Various changes can be made in the form and details for it.

Claims (3)

1. a kind of overhanging I-steel hole Embedment Construction technique, which is characterized in that including foam built-in fitting and dust catcher;The bubble The length of foam built-in fitting is equal to the thickness of overhanging the worn shear wall of I-steel, and cross section is rectangular configuration, and the foam is pre-buried The I-shaped channel to match with the cross-sectional structure of overhanging I-steel, the overhanging I-shaped are provided through on the cross section of part Steel passes through the I-shaped channel of foam built-in fitting;And the following steps are included:
1) the overhanging I-steel hole defaults between floor and shear wall, and foam built-in fitting is placed in shear wall bottom At cave entrance reservation, and foam built-in fitting is fixed on shear wall vertical reinforcement by tied silk, so that foam built-in fitting and shearing Wall is straight, and shear wall is facilitated to mold, and the overhanging I-steel passes through foam built-in fitting and is embedded at cave entrance reservation in advance;
2) when shear wall molds, square opening, the square opening are opened up on the shear wall formwork that overhanging I-steel wears shear wall position Without particular/special requirement, only needs guiding through overhanging I-steel and cover foam built-in fitting;
3) when the concrete that shear wall formwork pours reaches demoulding condition, the concrete grout in foam built-in fitting surface layer is rejected Block;
4) after being removed after overhanging I-steel use, 2 construction personnel is needed to reject foam built-in fitting, 1 construction Personnel's hand-held cleaners on outrigger, suction port of suction cleaner cover overhanging I-steel hole completely, and another 1 construction personnel is in shear wall It is indoor foam built-in fitting is dug broken, be sucked out by dust catcher, prevent foam beads floating pollution, then carry out overhanging I-steel Sealing hole.
2. a kind of overhanging I-steel hole Embedment Construction technique according to claim 1, which is characterized in that the shear wall Spine support in template is steel pipe, and the steel pipe is symmetrically set to shear wall formwork two sides, on symmetrically arranged steel pipe Connecting hole is respectively symmetrically offered, Screw arbor with nut at both-ends passes through the connecting hole on shear wall formwork, the both ends difference of the split bolt Shear wall formwork is fastenedly connected by gasket and nut.
3. a kind of overhanging I-steel hole Embedment Construction technique according to claim 1, which is characterized in that the overhanging work Word steel runs through the medium position of foam built-in fitting.
CN201910585597.3A 2019-07-01 2019-07-01 A kind of overhanging I-steel hole Embedment Construction technique Pending CN110409822A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910585597.3A CN110409822A (en) 2019-07-01 2019-07-01 A kind of overhanging I-steel hole Embedment Construction technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910585597.3A CN110409822A (en) 2019-07-01 2019-07-01 A kind of overhanging I-steel hole Embedment Construction technique

Publications (1)

Publication Number Publication Date
CN110409822A true CN110409822A (en) 2019-11-05

Family

ID=68358626

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910585597.3A Pending CN110409822A (en) 2019-07-01 2019-07-01 A kind of overhanging I-steel hole Embedment Construction technique

Country Status (1)

Country Link
CN (1) CN110409822A (en)

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1350764A (en) * 1970-03-04 1974-04-24 Gkn Sankey Ltd Structural members
DE3208374A1 (en) * 1982-03-09 1983-09-15 Frhr. von Gravenreuth Ernst-Ludwig 8000 München Dörr Holding claw for fixing porous building materials
DE202005004697U1 (en) * 2005-03-17 2005-05-25 Biermann, Bettina Wall duct for the passage of mains water, waste water and or heating system pipes through the walls of a building has a wall element whose diameter is matched to an available opening and which is made from compressed plastic foam
CN205046847U (en) * 2015-10-16 2016-02-24 中建四局第一建筑工程有限公司 Pre -buried fixing device of layer I -steel encorbelments
CN105780976A (en) * 2016-03-29 2016-07-20 北京城建北方建设有限责任公司 Compound concrete shear wall structure and concrete pouring method thereof
CN205777512U (en) * 2016-06-29 2016-12-07 郑州市第一建筑工程集团有限公司 Encorbelment I-steel embedded box die device
CN206769180U (en) * 2017-05-22 2017-12-19 中国建筑第七工程局有限公司 A kind of shaped steel hole prefabricated section through walls
CN206815804U (en) * 2017-05-05 2017-12-29 绍兴明煌建材科技有限公司 A kind of new builder's jack girder steel built-in fitting
CN107905383A (en) * 2017-10-23 2018-04-13 中国十七冶集团有限公司 A kind of Long-span Cantilever stay in place form support I-steel built-in fitting and its construction method
CN207296014U (en) * 2017-10-12 2018-05-01 刘伟 A kind of construction exterior rack I-steel pre-buried structure
CN207776403U (en) * 2018-01-15 2018-08-28 湖南中力建筑设备租赁有限公司 The plug-in adjustable cantilever system of tool-type
CN109403466A (en) * 2018-10-25 2019-03-01 中国十七冶集团有限公司 A kind of construction method of eminence reinforced concrete hanging beam diaphragm structure built-in fitting
CN109779237A (en) * 2019-03-08 2019-05-21 中国十七冶集团有限公司 A kind of scaffold overhanging I-steel is in shear wall position construction auxiliary device and construction method

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1350764A (en) * 1970-03-04 1974-04-24 Gkn Sankey Ltd Structural members
DE3208374A1 (en) * 1982-03-09 1983-09-15 Frhr. von Gravenreuth Ernst-Ludwig 8000 München Dörr Holding claw for fixing porous building materials
DE202005004697U1 (en) * 2005-03-17 2005-05-25 Biermann, Bettina Wall duct for the passage of mains water, waste water and or heating system pipes through the walls of a building has a wall element whose diameter is matched to an available opening and which is made from compressed plastic foam
CN205046847U (en) * 2015-10-16 2016-02-24 中建四局第一建筑工程有限公司 Pre -buried fixing device of layer I -steel encorbelments
CN105780976A (en) * 2016-03-29 2016-07-20 北京城建北方建设有限责任公司 Compound concrete shear wall structure and concrete pouring method thereof
CN205777512U (en) * 2016-06-29 2016-12-07 郑州市第一建筑工程集团有限公司 Encorbelment I-steel embedded box die device
CN206815804U (en) * 2017-05-05 2017-12-29 绍兴明煌建材科技有限公司 A kind of new builder's jack girder steel built-in fitting
CN206769180U (en) * 2017-05-22 2017-12-19 中国建筑第七工程局有限公司 A kind of shaped steel hole prefabricated section through walls
CN207296014U (en) * 2017-10-12 2018-05-01 刘伟 A kind of construction exterior rack I-steel pre-buried structure
CN107905383A (en) * 2017-10-23 2018-04-13 中国十七冶集团有限公司 A kind of Long-span Cantilever stay in place form support I-steel built-in fitting and its construction method
CN207776403U (en) * 2018-01-15 2018-08-28 湖南中力建筑设备租赁有限公司 The plug-in adjustable cantilever system of tool-type
CN109403466A (en) * 2018-10-25 2019-03-01 中国十七冶集团有限公司 A kind of construction method of eminence reinforced concrete hanging beam diaphragm structure built-in fitting
CN109779237A (en) * 2019-03-08 2019-05-21 中国十七冶集团有限公司 A kind of scaffold overhanging I-steel is in shear wall position construction auxiliary device and construction method

Similar Documents

Publication Publication Date Title
CN106639319A (en) Rotten root prevention construction method for shear walls, columns and other concrete vertical structures
CN203247600U (en) Equipment foundation bolt preformed hole die
CN104947719A (en) Basement roof post-cast strip hanging support formwork structure and post-cast strip construction method thereof
CN204492187U (en) A kind of for the sealing locating device bottom concrete wall template
CN206374015U (en) Concrete pipe gallery vertical-forming die and system
CN203856202U (en) Simple pullable sizing device of reserved holes
CN207469307U (en) A kind of gang form structure of the inspection shaft cast-in-place construction of town road pipeline
CN110409822A (en) A kind of overhanging I-steel hole Embedment Construction technique
CN203050108U (en) Concrete slab pipe installation reserved hole construction mold
CN104453235B (en) Current conversion station fire wall construction technology
CN112412013A (en) Construction method for plugging reserved hole of structural outer wall
CN105275198B (en) A kind of shear-wall strengthening formwork structure and its construction method
CN208430643U (en) A kind of wall hole plugging device
CN207048314U (en) A kind of shaping type stair wooden model board component
CN205875714U (en) A consolidate fixture for retainer plate beam mold board
CN206815804U (en) A kind of new builder's jack girder steel built-in fitting
CN115256615A (en) Intelligent shower maintenance standard construction system for prefabricated box girder of expressway
CN208981359U (en) The gang form structure of the inspection shaft cast-in-place construction of town road pipeline
CN201254833Y (en) Novel section steel-wood combination door and window hole forming template
CN110118015A (en) The embedding casing methods of aperture on a kind of concrete floor
CN208363593U (en) A kind of novel shear wall formwork positioning back cover tool
CN210562705U (en) Finished post-pouring belt
CN201078097Y (en) Size-sealing member
CN208918276U (en) Simple plugging device for vertical pipeline preformed hole
CN113668529A (en) Construction method for breaking and removing pile head with template based on steel wedge-shaped gap

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191105