CN110396987A - A kind of willow row's bank protection structure administered for erosion groove - Google Patents

A kind of willow row's bank protection structure administered for erosion groove Download PDF

Info

Publication number
CN110396987A
CN110396987A CN201910758799.3A CN201910758799A CN110396987A CN 110396987 A CN110396987 A CN 110396987A CN 201910758799 A CN201910758799 A CN 201910758799A CN 110396987 A CN110396987 A CN 110396987A
Authority
CN
China
Prior art keywords
willow
stakes
stake
withies
rows
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201910758799.3A
Other languages
Chinese (zh)
Inventor
王小明
戴芝梅
王莉
赵健
赵颖
尚佰晓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910758799.3A priority Critical patent/CN110396987A/en
Publication of CN110396987A publication Critical patent/CN110396987A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

A kind of willow row's bank protection structure administered for erosion groove, including multiple willow stakes, multiple transverse direction withies, multiple longitudinal direction willow tips and iron wire, its main points is according to surveying setting-out, determine pile anchoring position, multiple willow stakes are respectively that two rows of fixations are embedded on pile anchoring position, ' 8 ' fonts are pressed by iron wire respectively between two rows of multiple willows stakes to be fastened connection, multiple transverse direction withies are laterally laid with respectively to be set between multiple willow stakes lower part, multiple transverse direction withies pass through iron wire respectively and are fixedly connected with multiple willow stakes, multiple longitudinal direction willow tips are longitudinally arranged above and below setting between two rows of multiple willow stakes respectively, and it is fixedly connected respectively with multiple willow stakes by iron wire, it is respectively arranged between two rows of multiple willow stakes and between the stake of multiple willows and ditch bank and bankets.The present invention has many advantages, such as low cost, easily constructs, is profitable on ecology, be suitable for narrow type erosion groove shore protection and administer compared with traditional gabion shore protection.

Description

A kind of willow row's bank protection structure administered for erosion groove
Technical field
The present invention relates to soil erosion erosion grooves to administer field, especially a kind of willow row administered for sloping upland erosion groove Bank protection method.
Background technique
Black soil region sloping upland hypsography is big, the gradient is slow, slope surface is long, soil resistance to corrosion is poor, rainfall is concentrated, the ground of dispersion Table runoff forms the water flow of fixed route since the influence of topography is gradually concentrated, and lumped scour earth's surface, takes away soil at incision ground, Erosion groove is ultimately formed, and as fixed water channel, slope runoff is discharged.Erosion groove early development, two sides bank slope is steeper, in water flow Under Scouring Condition, the continuous incision of bottom of trench, ditch bank, which are collapsed, to be expanded to two sides rapidly, and the soil body carries defeated shifting, erosion quantity with runoff Greater than siltation volume, is formed under a large amount of silts and let out.Erosion groove harm is huge, on the one hand destroys arable land, grain drop in production, on the other hand broken Bad ecological environment, siltation downstream river course.Therefore, erosion groove soil erosion problem is only resolved, can just protect farmland, protect life State environment, and then avoid the generation of related natural calamity.
The water-and-soil conservation measures of existing RBS in channel direction is mainly check dam, however is not suitable for shallow narrow water channel erosion groove.Reference The method of river regulation, the main method for administering water channel erosion groove at this stage are to build gabion wall along riverbank two sides, are prevented according to this Sealing stream washes away bank slope.However the investment of gabion shore protection is high, ecological benefits are poor, most importantly gabion shore protection land occupation is more, single Wide 0.8 ~ the 1.0m in side, bilateral shore protection need to take up an area wide 1.6 ~ 2.0m, be not suitable for implementing in narrow type erosion groove, especially furrow width is less than The channel of 2m.
In consideration of it, we develop, a kind of investment is small, protection effect is firm, the service life is long, the good erosion groove of ecological benefits The willow of improvement arranges shore protection technology, and proposes this application.
Summary of the invention
Regarding the issue above, the present invention provides a kind of willow administered for erosion groove arranges bank protection structure, it is intended to Ecological benefit of soil and water conservation is given full play to while administering erosion groove.Traditional gabion shore protection be by the way of building gabion wall, Prevent bank slope caused by acting on because of current scour from collapsing with this.Given this principle, the present invention replace tradition using willow stake " reinforcement walls " The gabion engineering of shore protection.
The technical solution adopted by the present invention is that:
A kind of willow administered for erosion groove arranges bank protection structure, including the stake of multiple willows, multiple lateral withies, multiple longitudinal willow tips and Iron wire, main points are to determine pile anchoring position according to surveying setting-out, and multiple willow stakes are respectively that two rows of fixations are embedded in pile anchoring position On, it is fastened connection by iron wire by ' 8 ' fonts respectively between two rows of multiple willows stakes, the lateral layings respectively of multiple transverse direction withies It sets between multiple willow stakes lower part, multiple transverse direction withies pass through iron wire respectively and are fixedly connected with multiple willow stakes, multiple longitudinal direction willow tips It is longitudinal respectively to be arranged above and below setting between two rows of multiple willow stakes, and be fixedly connected respectively with multiple willow stakes by iron wire, two It arranges between multiple willow stakes and is respectively arranged between the stake of multiple willows and ditch bank and banketed.
The used stake of multiple willows, multiple withies and multiple all live standing trees of the willow tip, the long 1.0 ~ 1.2m of multiple willow stakes, diameter 5 ~ 8cm, the long 90cm of multiple withies, diameter 2cm or so.
Multiple willows stake buried depth degree is 0.5m, two rows of willow stake spacing 0.2m;Multiple transverse direction withies are inserted into wall 30cm It is deep;Every layer of multiple longitudinal direction willow tips spread willow 3-5 layers with a thickness of 10cm.
Described multiple willows stake is in order to guarantee that truncheon survives, it is noted that truncheon perpendicular to horizontal plane, is sure not to scratch when plant Crust protects bud eye, guarantees that bud eye direction is upward;Multiple willow stake top cut aways, paint red paint, prevent moisture from evaporating.
Beneficial effect after the present invention is implemented is: two rows willow pile holder living willow fascine living forms a protecting wall.After spring, The willow tip and willow stake growth, branch form a firm protection body after intersecting, prevent ditch bank from expanding;The withy germinating growth of horizontal paving goes out New branch can laterally block water, slow down water velocity, prevent gullying;Ecological benefits are quick, effect is obvious.
Detailed description of the invention
Fig. 1 is a kind of example structure schematic diagram of the invention.
Fig. 2 is a kind of top view of embodiment of the invention.
Fig. 3 is a kind of side view of embodiment of the invention.
Specific embodiment
A kind of willow row's bank protection structure administered for erosion groove, including multiple willows stake 2, multiple lateral withies 3, multiple longitudinal directions The willow tip 4 and iron wire 6, main points are to determine pile anchoring position 1 according to surveying setting-out, and multiple willow stakes 2 are respectively that two rows of fixations are embedded in On pile anchoring position 1, it is fastened connection by iron wire 6 by ' 8 ' fonts respectively between two rows of multiple willows stakes 2, multiple lateral withies 3 It is laterally laid with and is set between 2 lower parts of multiple willow stakes respectively, multiple lateral withies 3 pass through iron wire 6 and the fixed company of multiple willows stake 2 respectively Connect, multiple longitudinal direction willow tips 4 are longitudinal respectively to be arranged above and below setting between two rows of multiple willows stakes 2, and by iron wire 6 respectively with it is multiple Willow stake 2 is fixedly connected, and is respectively arranged between two rows of multiple willows stakes 2 and between multiple willows stake 2 and ditch bank and is banketed 5.
Below it is the technical pattern scheme operated in detailed examples:
1, it cuts slope shaping: carrying out cutting slope shaping before channel regulation.The purpose for cutting slope shaping is in order to which measures can be more preferable Be arranged in erosion groove, while cutting slope shaping also for the earthwork for public use is reduced, each erosion groove improvement made to reach earthwork balance. Cutting slope object is high gradient slope and the side slope there are security risk, is constructed for convenience, and it is appropriate that stable side slope need to only be carried out Finishing, the side slope for not influencing construction will be without cutting slope;
Original shrub or arbor should be retained when cutting slope, cutting slope angle is 35 ~ 45o.Surface soil should concentrate stacking, do for next procedure Prepare.
2, pile anchoring: according to ditch depth size, willow row's shore protection divides two ways, i.e., high stake willow row and stump willow row, channel upstream Selection stump willow of the ditch depth less than 0.5m is arranged, and selection height stake willow of the middle and lower reaches ditch depth greater than 0.5m is arranged.After Slope Treatment is good, measurement Unwrapping wire determines pile anchoring position 1.Multiple 2 two rows of willows stake, array pitch 0.2m, pilespacing 0.5m are squeezed into groove bottom line along the slope slope Hou Gou is cut. The live standing tree that multiple willow stakes 2 select growth ability strong, the long 1.0m of the high long 1.2m(dwarf willow stake of willow stake), 5 ~ 8cm of diameter, piling is buried 50cm;
Soil property harder place in Project Areas causes unnecessary damage to multiple willow stakes 2 when pile anchoring in order to prevent, with works such as crooked chisels Tool pile anchoring again after needing to punch in advance at pile anchoring.Multiple willow stakes 2 are made use of momentum with curved, smooth to connect, and make water flow according to original waterline It smoothly passes.
3, it spreads withy (tip): such as attached drawing 3, being laid with multiple lateral withies 3, lateral 3 diameter 2cm of withy, length along ditch bottom horizontal 90cm or so, length is not less than 30cm to microcephaly outside, after major part insertion willow row's wall.It is laid between multiple willow stakes 2 by root, it is multiple Lateral 3 microcephaly of withy is close to bottom of trench soil, and is directed toward ditch center line.Under conditions of spring moisture condition is sufficient, multiple transverse directions Withy 3 can then germinate, and the new branch grown can laterally block water, and slow down water velocity, prevent and treat gulley bottom;
(being vertical along ditch direction) is indulged on the inside of willow row to one layer of paving longitudinal willow tip 4, about 10cm is thick, and high stake willow row paving 50cm high is (short Stake willow row's paving 30cm high), the biennial willow tip that multiple longitudinal direction willow tips 4 should select growing power strong, if multiple longitudinal direction 4 branches of Liu Shao 8# iron wire 6 is relatively mostly used to bind securely, guarantee is banketed and 5 cannot be squeezed out from 4 gap of the willow tip.After multiple longitudinal willow tips 4 are laid with, Front two rows willow stake 2 should be bound together with 8# iron wire 6, be fastened using ' 8 ' words;Prevent front-seat multiple willow stakes 2 inwardly Inclination.
4, it bankets: after the completion of multiple longitudinal direction willow tips 4 are laid with, in 2 rear portion backfills 5 of multiple willow stakes, and being compacted, top covering 10cm topsoil, 2 exposed 20cm of multiple willow stakes or so.2 top cut aways of multiple willow stakes, paint red paint, prevent moisture from evaporating. Heel row willow row's rear side fill compaction, guarantees the stability of entire willow row wall;
The multiple willow stakes 2 of the next spring and multiple longitudinal 4 survival rates of the willow tip are up to 95% or more, and sufficient into rainy season moisture, growth adds Speed, protection effect are significant;
In order to guarantee that multiple willows 2 truncheons of stake survive, it is noted that truncheon perpendicular to horizontal plane, is sure not to scratch crust, protection when plant Good bud eye guarantees that direction is upward.Suitable in spring and autumn construction, this season interior raceway groove non-water flow, convenient for construction.But at this time Soil moisture content is poor, needs suitably to water.
5, spring is managed and protected: first spring after engineering construction, waters to the dry channel segments of soil layer, it is ensured that The survival rate of multiple willow stakes 2 and multiple lateral withies 3.It needs to cut multiple willows 2 tie wires 6 of stake to grow fine before summer has set in, It prevents iron wire 6 from tying tight willow stake 2, multiple willows stake 2 is hindered to grow.The current year survival rate of multiple willow stakes 2 and multiple longitudinal willow tips 4 should not Less than 80%, and there cannot be two or more continuous dry stakes, front two rows willow stake 2 will at least survive one.It is wanted for being not achieved The willow row asked should carry out changing stake in spring.
Effect analysis: showing according to project investigation result is implemented, and willow arranges shore protection plant survival rate up to 98%, and individual water flows are big Position have a phenomenon of destroying by rush of water, storage rate is up to 99%.It is tentatively monitored, in addition to damaging position, channel two sides are existing without collapsing and destroying by rush of water As willow row's protection effect is obvious, and the multiple lateral withies 3 of bottom of trench, which slow down, washes away bottom of trench.The gabion implemented with other channels Shore protection is compared, and willow row's shore protection of the invention reduces cost of investment because the material prices such as willow stake 2, wicker are cheap compared with building stones.Willow row Shore protection cross dimensions is small, compared with gabion shore protection land occupation width reduce 60%, and with it is curved make use of momentum, construct it is more flexible, reduce construction make Industry face.Since the willow speed of growth is very fast, trunk is thicker, and trunk new life is thick with leaves, and root system constantly grows extension, protection effect Enhance year by year, ecological benefits are obvious.
1 gabion shore protection of table and willow arrange shore protection contrast table
Survival rate/storage rate (%) It invests (member/m) Construction difficulty or ease Take up an area wide (m) Ecological benefits
Gabion shore protection -/100 450 It is difficult 0.8 Nothing
Willow arranges shore protection 98/99 240 Easily 0.3 It is good

Claims (4)

1. a kind of willow administered for erosion groove arranges bank protection structure, including it is multiple willows stake (2), multiple lateral withies (3), multiple vertical To the willow tip (4) and iron wire (6), it is characterized in that being determined pile anchoring position (1) according to surveying setting-out, multiple willow stakes (2) are respectively two rows Fixation is embedded on pile anchoring position (1), is pressed ' 8 ' fonts by iron wire (6) respectively between two rows of multiple willows stakes (2) and is fastened company It connects, multiple transverse direction withies (3) are laterally laid with respectively sets between multiple willow stakes (2) lower part, and multiple transverse direction withies (3) pass through respectively Iron wire (6) is fixedly connected with multiple willow stakes (2), and longitudinal be arranged above and below is arranged in two rows of multiple willows multiple longitudinal direction willow tips (4) respectively Between stake (2), and it is fixedly connected respectively with multiple willow stakes (2) by iron wire (6), it is between two rows of multiple willow stakes (2) and multiple Banket (5) are respectively arranged between willow stake (2) and ditch bank.
2. a kind of willow administered for erosion groove according to claim 1 arranges bank protection structure, it is characterised in that used is more A willow stake (2), multiple withies (3) and multiple willow tips (4) all live standing trees, 1.0 ~ 1.2m of multiple willow stake (2) length, diameter 5 ~ 8cm, the long 90cm of multiple withies (3), diameter 2cm or so.
3. a kind of willow administered for erosion groove according to claim 1 arranges bank protection structure, it is characterised in that described is more A willow stake (2) buried depth degree is 0.5m, two rows of willow stake (2) spacing 0.2m;It is deep that multiple transverse direction withies (3) are inserted into wall 30cm;It is multiple Every layer of longitudinal willow tip (4) with a thickness of 10cm, spreads willow 3-5 layers.
4. a kind of willow administered for erosion groove according to claim 1 arranges bank protection structure, it is characterised in that in order to guarantee Multiple willows stake (2) truncheons survive, it is noted that truncheon perpendicular to horizontal plane, is sure not to scratch crust when plant, protect bud eye, guarantee Bud eye direction is upward;Multiple willow stake (2) top cut aways, paint red paint, prevent moisture from evaporating.
CN201910758799.3A 2019-08-16 2019-08-16 A kind of willow row's bank protection structure administered for erosion groove Withdrawn CN110396987A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910758799.3A CN110396987A (en) 2019-08-16 2019-08-16 A kind of willow row's bank protection structure administered for erosion groove

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910758799.3A CN110396987A (en) 2019-08-16 2019-08-16 A kind of willow row's bank protection structure administered for erosion groove

Publications (1)

Publication Number Publication Date
CN110396987A true CN110396987A (en) 2019-11-01

Family

ID=68328522

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910758799.3A Withdrawn CN110396987A (en) 2019-08-16 2019-08-16 A kind of willow row's bank protection structure administered for erosion groove

Country Status (1)

Country Link
CN (1) CN110396987A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112726494A (en) * 2020-12-28 2021-04-30 中水北方勘测设计研究有限责任公司 Channel treatment method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010100347A (en) * 2000-05-01 2001-11-14 임철수 Bank protecting structure in stream corridor and its construction
KR200268853Y1 (en) * 2001-12-10 2002-03-18 주식회사 우일 이알에스 Bank protection vegetation zone at the low-water channel of river
CN102505700A (en) * 2011-11-23 2012-06-20 中国神华能源股份有限公司 Willow rod anchoring side slope protection method for loess area
CN103015397A (en) * 2012-12-26 2013-04-03 若尔盖县综合林场 Salix paraqplesia sand-protecting barrier for high and cold desert areas and setting method for Salix paraqplesia sand-protecting barrier
CN210561988U (en) * 2019-08-16 2020-05-19 王小明 A willow row revetment structure for erosion gully is administered

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010100347A (en) * 2000-05-01 2001-11-14 임철수 Bank protecting structure in stream corridor and its construction
KR200268853Y1 (en) * 2001-12-10 2002-03-18 주식회사 우일 이알에스 Bank protection vegetation zone at the low-water channel of river
CN102505700A (en) * 2011-11-23 2012-06-20 中国神华能源股份有限公司 Willow rod anchoring side slope protection method for loess area
CN103015397A (en) * 2012-12-26 2013-04-03 若尔盖县综合林场 Salix paraqplesia sand-protecting barrier for high and cold desert areas and setting method for Salix paraqplesia sand-protecting barrier
CN210561988U (en) * 2019-08-16 2020-05-19 王小明 A willow row revetment structure for erosion gully is administered

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李影等: "柳树在河流防护工程中的应用", 《黑龙江水利科技》, pages 118 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112726494A (en) * 2020-12-28 2021-04-30 中水北方勘测设计研究有限责任公司 Channel treatment method

Similar Documents

Publication Publication Date Title
CN103898870B (en) A kind of gabion net Ecotypic Stone Mesh-box river course slope protection construction method
CN104805845B (en) A kind of flexible bank protecting method of feldspathic sandstone natural slope
CN108130888B (en) Soft ecological bank protection structure and construction method thereof
CN102322066A (en) Three-in-one slope collapse managing method employing slope management, slope lowering and slope stabilization
CN104762923B (en) The soil-plant of agricultural watershed Riparian Zone side slope-Biostatic method
CN108708350B (en) Ecological slope protection structure and construction method thereof
CN110593281A (en) High-steep rock slope ecological protection system and construction method thereof
CN103362135B (en) Fang Beng hilllock, protect water and soil net grass bank protection
CN105075792A (en) Earth-rock mountain region low-interference artificial afforestation and soil preparation method
CN109258211A (en) One kind being used for river and lake boundary falling zone protection against erosion modernization system and laying method
CN104294830A (en) Side slope ecological protection and recovery method and arrangement structure
CN107165176A (en) A kind of method for strengthening the native check dam in the slope collapse exit or entrance of a clitch or check dam sediment trapping retaining
CN109610404B (en) Mud-sand separation and blocking method for debris flow gully and application thereof
CN107409954A (en) A kind of irrigation rig
CN206267161U (en) A kind of three-dimension vegetative net slope protection construction structure suitable for soil-slope
CN110396987A (en) A kind of willow row's bank protection structure administered for erosion groove
CN211849496U (en) High steep rock slope ecological protection system
CN108643118A (en) A kind of staged ecological bank protection structure
CN210561988U (en) A willow row revetment structure for erosion gully is administered
CN103650694A (en) Erosion gully reclamation technology
CN208039181U (en) A kind of small watershed river water comprehensive treatment system
KR101074565B1 (en) Method for green planting a slope by jute-net and pulp
CN114086507A (en) Ecological revetment process with high water and soil retention
Srivastava et al. Suitability of soil and water conservation measures for watershed management using geographical information system
Singh Gully erosion and its control

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20191101