CN110375113A - Standard module electromechanics pipeline assembly method based on BIM - Google Patents

Standard module electromechanics pipeline assembly method based on BIM Download PDF

Info

Publication number
CN110375113A
CN110375113A CN201910702885.2A CN201910702885A CN110375113A CN 110375113 A CN110375113 A CN 110375113A CN 201910702885 A CN201910702885 A CN 201910702885A CN 110375113 A CN110375113 A CN 110375113A
Authority
CN
China
Prior art keywords
pipeline
standard module
bim
duct section
modulus
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910702885.2A
Other languages
Chinese (zh)
Inventor
李江龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Biyi Mechanical And Electrical Design Consulting Co Ltd
Original Assignee
Beijing Biyi Mechanical And Electrical Design Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Biyi Mechanical And Electrical Design Consulting Co Ltd filed Critical Beijing Biyi Mechanical And Electrical Design Consulting Co Ltd
Priority to CN201910702885.2A priority Critical patent/CN110375113A/en
Publication of CN110375113A publication Critical patent/CN110375113A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/0243Laying or reclaiming pipes on land, e.g. above the ground above ground
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/0243Laying or reclaiming pipes on land, e.g. above the ground above ground
    • F16L1/0246Laying or reclaiming pipes on land, e.g. above the ground above ground at a certain height off the ground
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/17Mechanical parametric or variational design
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2113/00Details relating to the application field
    • G06F2113/14Pipes

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • General Physics & Mathematics (AREA)
  • Mechanical Engineering (AREA)
  • Theoretical Computer Science (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Pipeline Systems (AREA)

Abstract

The present invention discloses the standard module electromechanics pipeline assembly method based on BIM, modular design is carried out using BIM technology, conduit component all in the electromechanical project of building is split into the pipeline section of standard module, duct section with caliber uses identical modulus, it is general mutually, greatly reduce the number of types of pipeline section.It can be in the batch production of factory's realization pipeline section, without being customized to all pipeline sections.The pipe fitting of the standard module of batch production is assembled after transporting to project scene.The present invention compared with prior art the advantages of: factory's lathe automatic cutting and welding, one side machining accuracy and quality greatly improve, and another aspect production efficiency also greatly improves.Using plant produced, site-assembled mode eliminates the environmental pollution and fire safety evaluating hidden danger of construction site.Standard module pipeline section and pipe fitting, pipeline section versatility are reinforced, and the rejection rate of pipeline section production is substantially reduced, while improving the production efficiency of factory, improve the installation effectiveness of erecting bed.

Description

Standard module electromechanics pipeline assembly method based on BIM
Technical field
The present embodiments relate to pipe installation technology fields, and in particular to a kind of standard moduleization based on BIM is electromechanical Pipeline assembly method, particularly suitable for building Heating,Ventilating and Air Conditioning, the Pipe installing field of supply and drain water system, including building gold Belong to, nonmetal pipeline installation, building pipe, refrigerating plant room heats computer room, and boiler room, Air Conditioning Facilities, the fields such as pump house are applied Work installation.
Background technique
BIM is based on 3-dimensional digital technology, by the data information of building, geometric dimension, physical attribute etc. with more The mode of visual pattern is shown, and can represent the relationship of space relative position and function.And standardizing is then to build Perfect Standardization System is found, to promote building industrialization to produce, using the versatility and interchangeability of component accessory come specification life It produces, to obtain more preferably economic benefit.BIM can the more vivid effective guidance standard of mode tell somebody what one's real intentions are, with digital technology Promote standardization.Standardization has then standardized the digitlization modulus of BIM, and the two complements each other, mutually promotes.
In recent years, China's construction market passes through extensive development, and building mechanical & electrical technology is advanced by leaps and bounds, and builds the scale of construction and height Tend to the super scale of construction.Meanwhile construction site is increasingly stringent to requirements such as safe and environment-friendly and construction speeds.Traditional electromechanical tube Road mounting technique is using live unwrapping wire, the technique of measurement, cutting and welding, the disadvantage is that, Contraction in Site amount is very big, scene Including the operations such as pipe cutting and welding, it be easy to cause the pollution environment such as metallic dust and weldering cigarette, the spark that welding cutting generates Bring very big fire hazard.The techniques such as the cutting and welding at scene are all made of artificial manual operations, and working efficiency is low, installation Precision and quality cannot be guaranteed, while the construction period of entire electromechanical project is very long, has been unable to satisfy the actual demand of engineering.
Summary of the invention
For this purpose, the embodiment of the present invention provides a kind of standard module electromechanics pipeline assembly method based on BIM, reduce existing Field construction operation amount eliminates the environmental pollution and fire safety evaluating hidden danger of construction site, improves the production efficiency and installation of factory The installation effectiveness at scene.
To achieve the goals above, the embodiment of the present invention provides the following technical solutions: the standard moduleization based on BIM is electromechanical Pipeline assembly method, comprising the following steps:
1) the standard module design phase: carrying out electromechanical pipeline modulus optimization according to building intercolumniation modulus data, according to Preset pipeline modulus carries out Modular design to project pipe-line system using BIM tool, will during the Modular design The project pipe-line system is divided into the duct section using the pipeline modulus, first carries out the comprehensive arrangement of duct section and eliminates pipeline Section intersection-type collision, then quantity statistics are encoded and carried out to duct section and conduit fittings, output channel material table is simultaneously worked out existing Field instruction for mounting;
2) the order Prefabrication stage: according to the pipeline material table number exported during the Modular design Amount, produces the duct section and conduit fittings of the pipeline modulus on plant produced line, duct section end welding standard flange, and Bolt hole accurate contraposition is carried out to the standard flange, then packs received shipment;
3) scene is according to drawing assembling stage: according to drawing pipe diameter, absolute altitude and position in the in-site installation specification The assembly installation that data carry out suspension and support is set, after suspension and support installation is in place, according to pipeline coded data selection criteria mould Several duct sections and conduit fittings are lifted, successively in place, fixed and connection complete electromechanical pipeline assembly construction.
As the preferred embodiment of the standard module electromechanics pipeline assembly method based on BIM, the standard moduleization design In stage, electromechanical pipeline is separated according to preset pipeline modulus, by adjusting conduit fittings and valve location by all pipelines It is optimized for the duct section of preset pipeline modulus, simultaneously output channel material table is numbered to duct section using BIM software.
As the preferred embodiment of the standard module electromechanics pipeline assembly method based on BIM, the standard moduleization design In stage, preset pipeline modulus include 200mm, 400mm, 500mm, 600mm, 800mm, 1000mm, 1200mm, 1500mm, One of 1800mm, 2000mm, 2500mm, 3000mm, 3500mm, 4000mm, 5000mm and 6000mm or a variety of.
As the preferred embodiment of the standard module electromechanics pipeline assembly method based on BIM, the standard moduleization design In stage, Modular design is carried out to project pipe-line system using Revit tool according to preset pipeline modulus.
As the preferred embodiment of the standard module electromechanics pipeline assembly method based on BIM, the standard moduleization design In stage, allow there are the non-modularization pipeline section of preset quantity carry out error adaptation, using the duct section conduct of non-standard modulus Free terminal reserves the position of free terminal to adjust installation error during installation.
As the preferred embodiment of the standard module electromechanics pipeline assembly method based on BIM, the order Prefabrication It in stage, places an order production in the pipeline material table data on factory's automatic cutting, sealing wire according to output, completes duct section and pipe The production of road attachment, welding flange is to positive flange hole, and duct section to completion and conduit fittings are derusted, at anti-corrosion Reason, packing and transporting to project scene.
As the preferred embodiment of the standard module electromechanics pipeline assembly method based on BIM, the order Prefabrication In stage, packaging received shipment is carried out again after carrying out derusting and preservative treatment to the duct section and conduit fittings in factory.
As the preferred embodiment of the standard module electromechanics pipeline assembly method based on BIM, the scene is filled according to drawing With in the stage, the positioning and peace of pipe-hanger support are carried out according to the in-site installation specification that the standard module design phase is worked out Dress carries out duct section and conduit fittings positioning and assembly, carries out the connection of equipment and pipe fitting.
As the preferred embodiment of the standard module electromechanics pipeline assembly method based on BIM, the scene is filled according to drawing With in the stage, the duct section and conduit fittings are attached with cold, water pump, boiler, air-conditioner set or water treatment facilities.
The embodiment of the present invention has the advantages that, using BIM standardized designs, design accuracy and design efficiency mention significantly Height embodies the Design Thinking of What You See Is What You Get, eliminate in two-dimentional layout design in a model unpredictalbe pipeline collision with Intersect;Standard module duct section and conduit fittings, pipeline section versatility are reinforced, and greatly reduce the rejection rate of pipeline section production, together When also improve the production efficiency of factory, improve the installation effectiveness of erecting bed;The cutting of factory's lathe and welding, on the one hand add Work precision and quality greatly improves, and another aspect production efficiency also greatly improves;Using plant produced, site-assembled mode, Eliminate the environmental pollution and fire safety evaluating hidden danger of construction site.
Detailed description of the invention
It, below will be to embodiment party in order to illustrate more clearly of embodiments of the present invention or technical solution in the prior art Formula or attached drawing needed to be used in the description of the prior art are briefly described.It should be evident that the accompanying drawings in the following description is only It is merely exemplary, it for those of ordinary skill in the art, without creative efforts, can also basis The attached drawing of offer, which is extended, obtains other implementation attached drawings.
Fig. 1 is pipeline mould in the standard module electromechanics pipeline assembly method based on BIM provided in the embodiment of the present invention Number schematic diagram;
Fig. 2 is duct section in the standard module electromechanics pipeline assembly method based on BIM provided in the embodiment of the present invention And conduit fittings application mode schematic diagram;
Fig. 3 is the item of standard module electromechanics pipeline assembly method of the use based on BIM provided in the embodiment of the present invention Mesh overall applicability case schematic diagram;
Fig. 4 is the item of standard module electromechanics pipeline assembly method of the use based on BIM provided in the embodiment of the present invention The schematic three dimensional views of mesh overall applicability case;
Fig. 5 is the item of standard module electromechanics pipeline assembly method of the use based on BIM provided in the embodiment of the present invention The pipeline material table of mesh overall applicability case.
Specific embodiment
Embodiments of the present invention are illustrated by particular specific embodiment below, those skilled in the art can be by this explanation Content disclosed by book is understood other advantages and efficacy of the present invention easily, it is clear that described embodiment is the present invention one Section Example, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art are not doing Every other embodiment obtained under the premise of creative work out, shall fall within the protection scope of the present invention.
Referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4 and Fig. 5, it is electromechanical that the embodiment of the present invention provides a kind of standard moduleization based on BIM Pipeline assembly method, comprising the following steps:
1) the standard module design phase: carrying out electromechanical pipeline modulus optimization according to building intercolumniation modulus data, according to Preset pipeline modulus carries out Modular design to project pipe-line system using BIM tool, will during the Modular design The project pipe-line system is divided into the duct section using the pipeline modulus, first carries out the comprehensive arrangement of duct section and eliminates pipeline Section intersection-type collision, then quantity statistics are encoded and carried out to duct section and conduit fittings, output channel material table is simultaneously worked out existing Field instruction for mounting;
2) the order Prefabrication stage: according to the pipeline material table number exported during the Modular design Amount, produces the duct section and conduit fittings of the pipeline modulus on plant produced line, duct section end welding standard flange, and Bolt hole accurate contraposition is carried out to the standard flange, then packs received shipment;
3) scene is according to drawing assembling stage: according to drawing pipe diameter, absolute altitude and position in the in-site installation specification The assembly installation that data carry out suspension and support is set, after suspension and support installation is in place, according to pipeline coded data selection criteria mould Several duct sections and conduit fittings are lifted, successively in place, fixed and connection complete electromechanical pipeline assembly construction.
Specifically, referring to fig. 2, in the standard module design phase, to electromechanical pipeline according to preset pipeline modulus Separate, all pipelines is optimized for the duct section of preset pipeline modulus by adjusting conduit fittings and valve location, using BIM Duct section is numbered software and output channel material table.In the standard module design phase, preset pipeline modulus Including 200mm, 400mm, 500mm, 600mm, 800mm, 1000mm, 1200mm, 1500mm, 1800mm, 2000mm, 2500mm, One of 3000mm, 3500mm, 4000mm, 5000mm and 6000mm or a variety of.In the standard module design phase, press Modular design is carried out to project pipe-line system using Revit tool according to preset pipeline modulus.The standard moduleization design In stage, allow there are the non-modularization pipeline section of preset quantity carry out error adaptation, using the duct section conduct of non-standard modulus Free terminal reserves the position of free terminal to adjust installation error during installation.
Specifically, Revit is the title of a set of groupware of autodesk, inc..The Revit groupware is to aim at building Information model (BIM) building, building designers can be helped to design, construction and maintenance quality are more preferable, the higher building of efficiency. Revit is provided as a kind of application program, combine AutodeskRevitArchitecture, AutodeskRevitMEP and The function of AutodeskRevitStructure software.The specifically used of Revit is known described in those skilled in the art.
In one embodiment of standard module electromechanics pipeline assembly method based on BIM, the order Prefabrication It in stage, places an order production in the pipeline material table data on factory's automatic cutting, sealing wire according to output, completes duct section and pipe The production of road attachment, welding flange is to positive flange hole, and duct section to completion and conduit fittings are derusted, at anti-corrosion Reason, packing and transporting to project scene.In the order Prefabrication stage, to the duct section and conduit fittings in factory Packaging received shipment is carried out again after carrying out derusting and preservative treatment.
In one embodiment of standard module electromechanics pipeline assembly method based on BIM, the scene is filled according to drawing With in the stage, the positioning and peace of pipe-hanger support are carried out according to the in-site installation specification that the standard module design phase is worked out Dress carries out duct section and conduit fittings positioning and assembly, carries out the connection of equipment and pipe fitting.The scene is filled according to drawing With in the stage, the duct section and conduit fittings are attached with cold, water pump, boiler, air-conditioner set or water treatment facilities.
Referring to Fig. 3, Fig. 4 and Fig. 5, in a practice process based on the technical program:
Preset pipeline modulus series is the integral multiple of 500mm and 500mm, in actual implementation, according to the column of building Spacing modulus rationally determines the standard module of duct section, determines reasonable pipeline modulus, modulus series according to computer room bulk Middle quantity is fewer, then the standardization level of pipe-line system is higher, and pipeline section production is simpler in factory.In general, in view of transport ruler Very little and duct length is limited, and the modular dimension of standard pipe is usually no more than 6000mm.
After the standard module series for the duct section identified project, modularization is carried out to pipe-line system or computer room duct system Design carries out duct section combination using the modulus series of standard, and Fig. 2 gives the tool being combined using standard module duct section Body application mode BIM illustrates, and in Fig. 2,1 represents 500 pipeline section of modulus;2 represent pipeline valve;3 represent 1000 pipeline section of modulus;4 generations The first threeway of table;5 represent 500 pipeline section of modulus;6 represent the second threeway;7 represent 600 pipeline section of modulus;8 represent 1000 pipeline section of modulus; 9 represent third threeway;10 represent 1200 pipeline section of modulus;11 represent elbow;12 represent 1500 pipeline section of modulus;13 represent modulus 200 Pipeline section;14 represent 500 pipeline section of modulus.In the design phase, the position of conduit fittings and valve member should be adjusted, makes every effort to make all pipes Road is prover section, is connect in section of tubing section with equipment, and duct section and conduit fittings junction allow using nonstandard quasi-mode Several pipeline sections, to adjust installation error, during installation, can reserve the position of free terminal, last basis as free terminal The data mart modeling of live actual measurement is installed.
Fig. 3, Fig. 4 are machine room pipeline installation diagram, and the installation position of duct section and conduit fittings is identified in installation diagram It sets, mounting height and the corresponding number of pipeline, Fig. 5 give master die used by each pipe number for Fig. 3 computer room The quantity and dimensional parameters of number duct section, in actual implementation, the Modular design stage can provide Pipe installing specification, explanation The mounting means of clear pipeline in book, suspension and support mode, the tool that installation process uses install order and Installation Considerations. Also the production precision of standard pipe is coped in specification, error, preservative treatment mode, thermal insulation material, insulation thickness does specifically It is bright.After the prover section pipe fitting at packing and transporting to scene is got all the ready, installation is carried out to assembled in situ worker and is told somebody what one's real intentions are, installation instructions Book study and training, content carries out Pipe installing to specifications later.
The pipe that conduit component all in the electromechanical project of building is split into standard module by the embodiment of the present invention is managed together to section The duct section of diameter uses identical modulus, general mutually, greatly reduces the number of types of pipeline section.It can thus be realized in factory The batch production of pipeline section, without being customized to all pipeline sections.The pipe fitting of the standard module of batch production transports existing to project It is assembled after.Using BIM standardized designs, design accuracy and design efficiency are greatly improved, and embody What You See Is What You Get Design Thinking eliminates unpredictalbe pipeline in two-dimentional layout design in a model and collides and intersect;Standard module duct section With conduit fittings, pipeline section versatility is reinforced, and greatly reduces the rejection rate of pipeline section production, while also improving the production effect of factory Rate improves the installation effectiveness of erecting bed;The cutting of factory's lathe and welding, one side machining accuracy and quality greatly improve, Another aspect production efficiency also greatly improves;Using plant produced, site-assembled mode eliminates the environment dirt of construction site Dye and fire safety evaluating hidden danger.
Although above having used general explanation and specific embodiment, the present invention is described in detail, at this On the basis of invention, it can be made some modifications or improvements, this will be apparent to those skilled in the art.Therefore, These modifications or improvements without departing from theon the basis of the spirit of the present invention are fallen within the scope of the claimed invention.

Claims (9)

1. the standard module electromechanics pipeline assembly method based on BIM, which comprises the following steps:
1) the standard module design phase: electromechanical pipeline modulus optimization is carried out according to building intercolumniation modulus data, according to default Pipeline modulus Modular design is carried out to project pipe-line system using BIM tool, will be described during the Modular design Project pipe-line system is divided into the duct section using the pipeline modulus, first carries out the comprehensive arrangement of duct section and eliminates duct section friendship Fork collision, then quantity statistics are encoded and carried out to duct section and conduit fittings, output channel material table simultaneously works out live peace Fill specification;
2) the order Prefabrication stage: the pipeline material table quantity exported in the process according to the Modular design, Produce the duct section and conduit fittings of the pipeline modulus on plant produced line, duct section end welding standard flange, and to institute It states standard flange and carries out bolt hole accurate contraposition, then pack received shipment;
3) scene is according to drawing assembling stage: according to drawing pipe diameter, absolute altitude and positional number in the in-site installation specification According to the assembly installation for carrying out suspension and support, after suspension and support installation is in place, according to pipeline coded data selection criteria modulus Duct section and conduit fittings are lifted, successively in place, fixed and connection complete electromechanical pipeline assembly construction.
2. the standard module electromechanics pipeline assembly method according to claim 1 based on BIM, which is characterized in that described In the standard module design phase, electromechanical pipeline is separated according to preset pipeline modulus, by adjusting conduit fittings and valve All pipelines are optimized for the duct section of preset pipeline modulus by position, and duct section is numbered and is exported using BIM software Pipeline material table.
3. the standard module electromechanics pipeline assembly method according to claim 1 based on BIM, which is characterized in that described In the standard module design phase, preset pipeline modulus include 200mm, 400mm, 500mm, 600mm, 800mm, 1000mm, One in 1200mm, 1500mm, 1800mm, 2000mm, 2500mm, 3000mm, 3500mm, 4000mm, 5000mm and 6000mm Kind is a variety of.
4. the standard module electromechanics pipeline assembly method according to claim 1 based on BIM, which is characterized in that described In the standard module design phase, modularization is carried out to project pipe-line system using Revit tool according to preset pipeline modulus Design.
5. the standard module electromechanics pipeline assembly method according to claim 1 based on BIM, which is characterized in that described In the standard module design phase, allow there are the non-modularization pipeline section of preset quantity carry out error adaptation, using nonstandard quasi-mode Several duct sections, to adjust installation error, reserves the position of free terminal as free terminal during installation.
6. the standard module electromechanics pipeline assembly method according to claim 1 based on BIM, which is characterized in that described In the order Prefabrication stage, place an order production in the pipeline material table data on factory's automatic cutting, sealing wire according to output, Complete the production of duct section and conduit fittings, welding flange to positive flange hole, and duct section to completion and conduit fittings into Row derusting, preservative treatment, packing and transporting to project scene.
7. the standard module electromechanics pipeline assembly method according to claim 1 based on BIM, which is characterized in that described In the order Prefabrication stage, carried out again after carrying out derusting and preservative treatment to the duct section and conduit fittings in factory Pack received shipment.
8. the standard module electromechanics pipeline assembly method according to claim 1 based on BIM, which is characterized in that described Scene carries out pipeline branch according to the in-site installation specification that the standard module design phase is worked out according in drawing assembling stage The positioning and installation of hanger carry out duct section and conduit fittings positioning and assembly, carry out the connection of equipment and pipe fitting.
9. the standard module electromechanics pipeline assembly method according to claim 8 based on BIM, which is characterized in that described Scene is according in drawing assembling stage, the duct section and conduit fittings and cold, water pump, boiler, air-conditioner set or water process Equipment is attached.
CN201910702885.2A 2019-07-31 2019-07-31 Standard module electromechanics pipeline assembly method based on BIM Pending CN110375113A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910702885.2A CN110375113A (en) 2019-07-31 2019-07-31 Standard module electromechanics pipeline assembly method based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910702885.2A CN110375113A (en) 2019-07-31 2019-07-31 Standard module electromechanics pipeline assembly method based on BIM

Publications (1)

Publication Number Publication Date
CN110375113A true CN110375113A (en) 2019-10-25

Family

ID=68257504

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910702885.2A Pending CN110375113A (en) 2019-07-31 2019-07-31 Standard module electromechanics pipeline assembly method based on BIM

Country Status (1)

Country Link
CN (1) CN110375113A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111444571A (en) * 2020-04-19 2020-07-24 北京城建远东建设投资集团有限公司 BIM-based electromechanical air duct flange batch processing and drawing method

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103218492A (en) * 2013-04-16 2013-07-24 上海上安机电设计事务所有限公司 BIM (Building Information Model)-based pipe prefabrication method
CN105046359A (en) * 2015-07-19 2015-11-11 南宁市政工程集团有限公司 BIM (Building Information Modelling) technology based municipal pipeline factory prefabrication and installation method
CN105677978A (en) * 2016-01-08 2016-06-15 中建三局第一建设工程有限责任公司 Horizontal multi-pipe support and prefabricating construction method thereof based on BIM
CN105888317A (en) * 2016-04-19 2016-08-24 中建三局第二建设工程有限责任公司 Central refrigeration machine room modular prefabrication and assembled construction method
CN106677534A (en) * 2016-11-16 2017-05-17 上海建工集团股份有限公司 Assembly integral building electromechanical engineering installation system and method
CN107255356A (en) * 2017-05-18 2017-10-17 中铁隧道勘测设计院有限公司 A kind of subway station air conditioner airduct standardized components design method
CN107542161A (en) * 2017-08-23 2018-01-05 中建八局第建设有限公司 BIDA engineering of integrating technical systems
CN108108510A (en) * 2017-10-27 2018-06-01 广东星层建筑科技股份有限公司 A kind of assembled architecture design method and equipment based on BIM
CN109117510A (en) * 2018-07-16 2019-01-01 同济大学建筑设计研究院(集团)有限公司 A kind of method for prefabricating of the groove-type piping system based on BIM
CN109514188A (en) * 2018-10-23 2019-03-26 筑梦高科建筑有限公司 Electromechanical pipeline and equipment batch production prefabricating and constructing based on BIM
CN109543233A (en) * 2018-10-26 2019-03-29 中交第航务工程局有限公司 A kind of electromechanical pipeline assembly construction method based on BIM technology
CN109614719A (en) * 2018-12-14 2019-04-12 中建二局第建筑工程有限公司 A kind of refrigerating plant room assembly construction method based on BIM technology
CN109812637A (en) * 2019-03-11 2019-05-28 四川省第六建筑有限公司 A kind of concrete pump pipe connection and the concrete pump pipe structure based on the device

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103218492A (en) * 2013-04-16 2013-07-24 上海上安机电设计事务所有限公司 BIM (Building Information Model)-based pipe prefabrication method
CN105046359A (en) * 2015-07-19 2015-11-11 南宁市政工程集团有限公司 BIM (Building Information Modelling) technology based municipal pipeline factory prefabrication and installation method
CN105677978A (en) * 2016-01-08 2016-06-15 中建三局第一建设工程有限责任公司 Horizontal multi-pipe support and prefabricating construction method thereof based on BIM
CN105888317A (en) * 2016-04-19 2016-08-24 中建三局第二建设工程有限责任公司 Central refrigeration machine room modular prefabrication and assembled construction method
CN106677534A (en) * 2016-11-16 2017-05-17 上海建工集团股份有限公司 Assembly integral building electromechanical engineering installation system and method
CN107255356A (en) * 2017-05-18 2017-10-17 中铁隧道勘测设计院有限公司 A kind of subway station air conditioner airduct standardized components design method
CN107542161A (en) * 2017-08-23 2018-01-05 中建八局第建设有限公司 BIDA engineering of integrating technical systems
CN108108510A (en) * 2017-10-27 2018-06-01 广东星层建筑科技股份有限公司 A kind of assembled architecture design method and equipment based on BIM
CN109117510A (en) * 2018-07-16 2019-01-01 同济大学建筑设计研究院(集团)有限公司 A kind of method for prefabricating of the groove-type piping system based on BIM
CN109514188A (en) * 2018-10-23 2019-03-26 筑梦高科建筑有限公司 Electromechanical pipeline and equipment batch production prefabricating and constructing based on BIM
CN109543233A (en) * 2018-10-26 2019-03-29 中交第航务工程局有限公司 A kind of electromechanical pipeline assembly construction method based on BIM technology
CN109614719A (en) * 2018-12-14 2019-04-12 中建二局第建筑工程有限公司 A kind of refrigerating plant room assembly construction method based on BIM technology
CN109812637A (en) * 2019-03-11 2019-05-28 四川省第六建筑有限公司 A kind of concrete pump pipe connection and the concrete pump pipe structure based on the device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
上海市城市建设工程学校: "《装配式混凝土建筑结构设计》", 31 December 2016 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111444571A (en) * 2020-04-19 2020-07-24 北京城建远东建设投资集团有限公司 BIM-based electromechanical air duct flange batch processing and drawing method
CN111444571B (en) * 2020-04-19 2023-02-21 北京城建远东建设投资集团有限公司 BIM-based electromechanical air duct flange batch processing and drawing method

Similar Documents

Publication Publication Date Title
CN106989211B (en) Assembled architecture pipeline hanger system installation method based on BIM
CN105677978A (en) Horizontal multi-pipe support and prefabricating construction method thereof based on BIM
CN102644814B (en) Large-diameter variable-diameter pipe joint and manufacturing method thereof
CN104470676A (en) Apparatus and method for connecting air cooled condenser heat exchanger coils to steam distribution manifold
CN110566720A (en) construction method of arc corridor pipeline
CN109514188A (en) Electromechanical pipeline and equipment batch production prefabricating and constructing based on BIM
CN116383953B (en) Assembled plate change module manufacturing and material economy optimization system and method
CN110375113A (en) Standard module electromechanics pipeline assembly method based on BIM
CN107218739A (en) A kind of refrigerating plant room based on the integrated races of BIM
CN116090267A (en) Assembled refrigerator module manufacturing and labor economy optimization system and method
CN102426620A (en) High-pressure and ultrahigh-pressure hydraulic pipeline 3D (Three-Dimensional) preassembly and plant prefabrication construction method
CN101664776A (en) Method for bending large-diameter arc pipe in site and large-diameter arc pipe fixing device
CN102620064B (en) Full steel framework enhanced plug type composite pipe
CN202270845U (en) Pre-embedded pipeline type fusion casting die
CN202532039U (en) Enhanced bidirectional bell and spigot composite pipe based on steel skeleton
CN101303102A (en) Factory producing pipe system and production assembling method thereof
CN204628800U (en) The butt joint of super large caliber steel-plastic composite pipe site operation
CN105157085A (en) Heating and ventilation pipeline segmentation method
CN209211649U (en) A kind of pre-buried anchor ear casing
CN108179898B (en) Automatic station type manual composite material laying workshop
CN110968932A (en) Metal air duct product production management system based on BIM
CN205935797U (en) Box whole computer lab integrates
CN213900731U (en) Integrated pipeline block valve chamber
CN112747172B (en) Method for laying pipeline
CN204942777U (en) Seamless ventilation duct

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191025