CN110374263A - Integrated cushion block - Google Patents
Integrated cushion block Download PDFInfo
- Publication number
- CN110374263A CN110374263A CN201910481771.XA CN201910481771A CN110374263A CN 110374263 A CN110374263 A CN 110374263A CN 201910481771 A CN201910481771 A CN 201910481771A CN 110374263 A CN110374263 A CN 110374263A
- Authority
- CN
- China
- Prior art keywords
- groove
- cushion block
- connecting rod
- distance
- diameter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000002146 bilateral effect Effects 0.000 claims description 3
- 210000003205 muscle Anatomy 0.000 abstract description 42
- 125000006850 spacer group Chemical group 0.000 abstract description 4
- 239000010410 layer Substances 0.000 description 36
- 229910000831 Steel Inorganic materials 0.000 description 14
- 239000010959 steel Substances 0.000 description 14
- 238000010276 construction Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 4
- 238000009408 flooring Methods 0.000 description 4
- 230000015572 biosynthetic process Effects 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 239000011449 brick Substances 0.000 description 1
- RKTYLMNFRDHKIL-UHFFFAOYSA-N copper;5,10,15,20-tetraphenylporphyrin-22,24-diide Chemical compound [Cu+2].C1=CC(C(=C2C=CC([N-]2)=C(C=2C=CC=CC=2)C=2C=CC(N=2)=C(C=2C=CC=CC=2)C2=CC=C3[N-]2)C=2C=CC=CC=2)=NC1=C3C1=CC=CC=C1 RKTYLMNFRDHKIL-UHFFFAOYSA-N 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000011241 protective layer Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/16—Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Vibration Prevention Devices (AREA)
Abstract
The present invention relates to a kind of integrated cushion blocks, second connecting rod and several cushion blocks including first connecting rod, connection first connecting rod;The middle part of cushion block is equipped with connecting hole, and cushion block is equipped with the first groove and the second groove, and the bottom of the first groove is H1 at a distance of the distance of connecting hole central axis, and the bottom of the second groove is H2 at a distance of the distance of connecting hole central axis, and H1 is more than or less than H2;Part cushion block is installed on first connecting rod by connecting hole, and after cushion block is installed on first connecting rod, the direction of the first groove is in the same direction and perpendicular to plane where first connecting rod and second connecting rod;Another part cushion block is installed on second connecting rod by connecting hole, and after cushion block is installed on second connecting rod, the direction of the second groove is in the same direction and perpendicular to plane where first connecting rod and second connecting rod.Several cushion blocks are formed into an organic whole, whole load-bearing capacity is improved, and the upper layer bottom muscle of spacer bar net and lower layer's bottom muscle, reinforced mesh can be overally supported simultaneously, is not easy to damage by pressure.
Description
Technical field
The present invention relates to building product technical fields, more particularly to integrated cushion block.
Background technique
Cushion block is called cushion block of concrete bar protective layer, is in brick mix structure and in frame structure, be placed on reinforcing bar and template it
Between, fixed steel bars position, the effect being corroded to prevent reinforcing steel bars exposed is to solve the fixed common method of reinforcing bar.
There is steel mesh upper layer bottom muscle and lower layer's bottom muscle, upper layer bottom muscle to be staggered connection with lower layer's bottom muscle, current cushion block
Generally individually support, the ability of bearing load is poor, and only erects to the bottom muscle of steel mesh lower layer, and upper layer bottom muscle is then
Vacantly, cause to be easy to be damaged by pressure by flooring mesh sheet, seriously affect the pouring quality of flooring.
Summary of the invention
Based on this, it is necessary in view of the above-mentioned problems, a kind of integrated cushion block is provided, several cushion blocks formation one is organically whole
Body, improves whole load-bearing capacity, and can spacer bar net simultaneously upper layer bottom muscle and lower layer's bottom muscle, reinforced mesh obtains
Integrated support, is not easy to damage by pressure.
A kind of integrated cushion block, second connecting rod and several cushion blocks including first connecting rod, connection first connecting rod;The middle part of cushion block
Equipped with connecting hole, cushion block is equipped with the first groove and the second groove, and the bottom of the first groove is at a distance of the distance of connecting hole central axis
H1, the bottom of the second groove are H2 at a distance of the distance of connecting hole central axis, and H1 is more than or less than H2;Part cushion block passes through connecting hole
It is installed on first connecting rod, after cushion block is installed on first connecting rod, the direction of the first groove connects in the same direction and perpendicular to first
Plane where bar and second connecting rod;Another part cushion block is installed on second connecting rod by connecting hole, and cushion block is installed on the second company
After on bar, the direction of the second groove is in the same direction and perpendicular to plane where first connecting rod and second connecting rod.
Above-mentioned integrated cushion block, part cushion block are movably installed on first connecting rod, form linear array, similarly, another portion
Divide cushion block to be movably installed on second connecting rod, linear array is formed, for example, the first of all cushion blocks being installed on first connecting rod
Groove upward, the second groove for being installed on all cushion blocks on second connecting rod upward, the first groove being installed on first connecting rod
Bottom there is difference in height with the bottom of the second groove being installed on second connecting rod, upper layer bottom muscle and lower layer bottom with steel mesh
The difference in height of muscle is corresponding, and the first groove is for erecting upper layer bottom muscle, and the second groove is for erecting lower layer's bottom muscle, while spacer bar
The upper layer bottom muscle and lower layer's bottom muscle of net, overally support reinforced mesh, are not easy to collapse, strengthen the pouring structure of flooring;
First connecting rod and second connecting rod have good support to cushion block to several cushion blocks, and several cushion blocks formation one is organically whole
Body improves whole load-bearing capacity, and cushion block has the support of first connecting rod or second connecting rod, and height is consistent, as long as searching out
The position of first cushion block, other cushion blocks being mounted on first connecting rod or second connecting rod can adjust predeterminated position quickly,
It is easy to adjust, does not need multiple cushion blocks and measure arrangement respectively, save the construction time.
The first connecting rod and two parallel intervals that cushion block includes the setting of two parallel intervals are integrated in one of the embodiments,
The second connecting rod of setting, two first connecting rods and two second connecting rods are interconnected to form a quadrangle.
The diameter of the first groove is identical as the diameter of the second groove in one of the embodiments,.
The diameter of the first groove is different with the diameter of the second groove in one of the embodiments,.
Cushion block is in square in one of the embodiments, and the first groove and the second groove are located at cushion block wherein
Both sides.
Cushion block is additionally provided with third groove and the 4th groove in one of the embodiments,.
The bottom of third groove is equal to H1 at a distance of the distance of connecting hole central axis in one of the embodiments, and the 4th is recessed
The bottom of slot is equal to H2 at a distance of the distance of connecting hole central axis.
The diameter of the 4th groove is identical as the diameter of the first groove in one of the embodiments,;4th groove and first
Groove is in be disposed adjacent.
The diameter of third groove is identical as the diameter of the second groove in one of the embodiments,;Third groove and second
Groove is in be disposed adjacent.
Integrating cushion block in one of the embodiments, further includes connector, and the both ends of connector are separately connected first connecting rod
With second connecting rod;Connector is L-type bilateral.
Detailed description of the invention
Fig. 1 is the schematic diagram of a preferred embodiment of the integrated cushion block of the present invention;
Fig. 2 is the schematic diagram for the cushion block that Fig. 1 is integrated in cushion block;
Fig. 3 is the schematic diagram for the connector that Fig. 1 is integrated in cushion block;
Fig. 4 is the application schematic diagram that Fig. 1 integrates cushion block.
Description of symbols:
20-first connecting rods;30-second connecting rods;40-cushion blocks, 41-connecting holes, the 42-the first groove, 43-the second is recessed
Slot, 44-third grooves, the 45-the four groove;50-connectors;100-integrated cushion blocks;500-steel meshes, 501-upper layer bottoms
Muscle, 502-lower layer's bottom muscle.
Specific embodiment
It to facilitate the understanding of the present invention, below will be to invention is more fully described.But the present invention can be to be permitted
Mostly different form is realized, however it is not limited to embodiment described herein.On the contrary, purpose of providing these embodiments is makes
It is more thorough and comprehensive to the understanding of the disclosure.
Unless otherwise defined, all technical and scientific terms used herein and belong to technical field of the invention
The normally understood meaning of technical staff is identical.Term as used herein in the specification of the present invention is intended merely to description tool
The purpose of the embodiment of body, it is not intended that in the limitation present invention.
It is a preferred embodiment of the present invention integrated cushion block 100 referring to FIG. 1 to FIG. 4, is mainly used for cableway net
500, upper layer bottom muscle 501 and lower layer's bottom muscle 502 can be supported simultaneously, strengthen building pouring structure.Integrated cushion block 100 includes first
Connecting rod 20, the second connecting rod 30 and several cushion blocks 40 for connecting first connecting rod 20, part cushion block 40 are installed on first connecting rod 20, separately
A part of cushion block 40 is installed on second connecting rod 30.
As shown in Figure 1, connecting between first connecting rod 20 and second connecting rod 30 in predetermined angle, first connecting rod 20 and second connects
The connection angle of bar 30 can be adjusted according to the upper layer bottom muscle 501 of steel mesh 500 and the intersecting angle of lower layer bottom muscle 502.Compared with
Excellently, the connection angle of first connecting rod 20 and second connecting rod 30 is 90 °, is suitable for common steel mesh 500.
As indicated with 2, the middle part of cushion block 40 is equipped with connecting hole 41, and cushion block 40 is equipped with the first groove 42 and the second groove 43, the
The bottom of one groove 42 is H1 at a distance of the distance of 41 central axis of connecting hole, and the bottom of the second groove 43 is at a distance of 41 central axis of connecting hole
Distance be H2, H1 be greater than H2.Part cushion block 40 is installed on first connecting rod 20 by connecting hole 41, and cushion block 40 is installed on first
After on connecting rod 20, the direction of the first groove 42 is in the same direction and perpendicular to 30 place plane of first connecting rod 20 and second connecting rod;Separately
A part of cushion block 40 is installed on second connecting rod 30 by connecting hole 41, after cushion block 40 is installed on second connecting rod 30, second
The direction of groove 43 is in the same direction and perpendicular to 30 place plane of first connecting rod 20 and second connecting rod.In one implementation state, installation
In all cushion blocks on first connecting rod 20 the first groove 42 upward, be installed on second of all cushion blocks 40 on second connecting rod 30
Groove 43 is upward.The bottom for the first groove 42 being installed on first connecting rod 20 and the second groove being installed on second connecting rod 30
The difference of 43 bottom formation difference in height, H1 and H2 are more than or equal to the height at the center upper layer Di Jin501 and 502 center of lower layer bottom muscle
Difference, then the first groove 42 can place upper layer bottom muscle 501, and the second groove 43 can place lower layer's bottom muscle 502, while spacer bar net
500 upper layer bottom muscle 501 and lower layer's bottom muscle 502.
The diameter of first groove 42 can be identical or different with the diameter of the second groove 43.When the first groove 42 diameter with
When the diameter of second groove 43 is identical, the steel mesh of upper layer bottom muscle 501 and lower layer's bottom muscle 502 with same diameter can be erected
500.When the diameter of the first groove 42 is different with the diameter of the second groove 43, the upper layer bottom muscle with different-diameter can be erected
501 and lower layer's bottom muscle 502 steel mesh 500.
In one embodiment, cushion block 40 is additionally provided with third groove 44 and the 4th groove 45, can reduce cushion block 40 weight and
Material is saved, convenient for construction.
In one embodiment, the bottom of third groove 44 is equal to H1 at a distance of the distance of 41 central axis of connecting hole, then third is recessed
Slot 44 can place with the mutually level bottom muscle of the first groove 42, identical requirement for height can be corresponded to, place the bottom of different-diameter
Muscle, or can correspond to identical requirement for height, places the bottom muscle of different-diameter, when replacement, need to only reverse cushion block 40, replacement first
The position of groove 42 and third groove 44 can realize replacement, make the integrated more flexible convenience of cushion block 100.
In one embodiment, the diameter of third groove 44 is identical as the diameter of the second groove 43, can correspond to different height
It is required that placing the bottom muscle of same diameter.More preferably, third groove 44 is in be disposed adjacent with the second groove 43, it is easier to it distinguishes, and
And the groove with difference in height can be adjusted to without reversing too wide-angle.
In one embodiment, the bottom of the 4th groove 45 is equal to H2, the 4th groove at a distance of the distance of 41 central axis of connecting hole
45 can place and similarly when replacement, need to only reverse cushion block 40, replacement second is recessed with the mutually level bottom muscle of the second groove 43
The position of slot 43 and the 4th groove 45.
In one embodiment, the diameter of the 4th groove 45 is identical as the diameter of the first groove 42.More preferably, the 4th groove 45
It is in be disposed adjacent with the first groove 42.
So when cushion block 40 is equipped with the first groove 42, the second groove 43, third groove 44 and four grooves 45 simultaneously,
It can be taken according to the upper layer bottom muscle 501 in steel mesh 500 with the difference in height of lower layer bottom muscle 502 and the diameter selection respective slot of the two
With use, to realize firm erection steel mesh 500.
In one embodiment, cushion block 40 is in square, and the opening of the first groove 42 and the second groove 43 is located at cushion block
40 wherein both sides.More preferably, the first groove 42, the second groove 43, third groove 44 and the 4th groove 45 are sequentially distributed cushion block
The construction time is saved convenient for identification replacement in 40 four sides.The section of cushion block 40 is square, i.e., cushion block 40 is tetragonal body, often
A corner all has angle, roll cushion block 40 will not arbitrarily, more firm to the fixation of steel mesh 500.
In one embodiment, the quantity of first connecting rod 20 is two, and two first connecting rods 20 are in spaced and parallel setting, second connecting rod
30 quantity is two, and two second connecting rods 30 are in spaced and parallel setting;The both ends of second connecting rod 30 are separately connected two first connecting rods 20,
Quadrangle is collectively formed after connecting with two second connecting rods 30 in two first connecting rods 20.Multiple pads are mounted on two first connecting rods 20
Block 40, the groove of the cushion block 40 on two first connecting rods 20 is towards identical;Multiple cushion blocks are mounted on two second connecting rods 30
40, the groove of the cushion block 40 on two second connecting rods 30 is towards identical.As multiple cushion blocks 40 of two first connecting rods 20 select
First groove 42 upward, that is, selects the first groove 42 to erect upper layer bottom muscle 501, and multiple cushion blocks 40 of two second connecting rods 30 select
It selects the second groove 43 upward, that is, the second groove 43 is selected to erect lower layer bottom muscle 502, realize and many places of steel mesh 500 are supported, more
Add securely.When needing replacing the groove of different size, the cushion block 40 of respective link, replacement to suitable height and diameter are rotated
Groove;When needing to adjust adjacent the distance between two cushion blocks 40, by cushion block 40 along first connecting rod 20 or second
The extending direction of connecting rod 30 is mobile, does not need multiple cushion blocks 40 and measures arrangement respectively, saves the construction time.
In one embodiment, integrating cushion block 100 further includes connector 50, and the both ends of connector 50 are separately connected first connecting rod
20 with second connecting rod 30.More preferably, connector 50 is L-type bilateral, respectively by the end insertion connector 50 of first connecting rod 20
A wherein channel, another channel of the end insertion connector 50 of second connecting rod 30, can complete to connect, easy to operate, save
Activity duration.
Several cushion blocks 40 are formed an organic whole by above-mentioned integrated cushion block 100, first connecting rod 20 and second connecting rod 30,
Can simultaneously cableway net 500 upper layer bottom muscle 501 and lower layer's bottom muscle 502, make steel mesh 500 to be overally supported, be not easy
It collapses, strengthens the pouring structure of flooring, improve whole load-bearing capacity, be not easy to damage by pressure, and cushion block 40 has first connecting rod 20
Or the support of second connecting rod 30, height is consistent, as long as searching out the position of first cushion block 40, is mounted on first connecting rod 20 or the
Other cushion blocks 40 on two connecting rods 30 can adjust predeterminated position quickly, be easy to adjust, do not need multiple cushion blocks 40 and survey respectively
Amount arrangement, saves the construction time.
Each technical characteristic of embodiment described above can be combined arbitrarily, for simplicity of description, not to above-mentioned reality
It applies all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited
In contradiction, all should be considered as described in this specification.
One embodiment of the present invention above described embodiment only expresses, the description thereof is more specific and detailed, but simultaneously
It cannot therefore be construed as limiting the scope of the patent.It should be pointed out that coming for those of ordinary skill in the art
It says, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to protection of the invention
Range.Therefore, the scope of protection of the patent of the invention shall be subject to the appended claims.
Claims (10)
1. a kind of integrated cushion block, which is characterized in that second connecting rod and several pads including first connecting rod, the connection first connecting rod
Block;The middle part of the cushion block is equipped with connecting hole, and the cushion block is equipped with the first groove and the second groove, the bottom of first groove
Distance at a distance of the central axis of the connecting hole is H1, the bottom of second groove at a distance of the connecting hole central axis away from
It is more than or less than the H2 from for H2, the H1;The part cushion block is installed on the first connecting rod by the connecting hole,
After the cushion block is installed on first connecting rod, the direction of the first groove is in the same direction and perpendicular to first connecting rod and second connecting rod institute
In plane;Cushion block described in another part is installed on the second connecting rod by the connecting hole, and the cushion block is installed on second
After on connecting rod, the direction of the second groove is in the same direction and perpendicular to plane where first connecting rod and second connecting rod.
2. integrated cushion block according to claim 1, which is characterized in that the integrated cushion block includes what two parallel intervals were arranged
First connecting rod and the second connecting rod of two parallel intervals setting, two first connecting rods and two second connecting rods are connected with each other shape
At a quadrangle.
3. integrated cushion block according to claim 1, which is characterized in that the diameter of first groove and second groove
Diameter it is identical.
4. integrated cushion block according to claim 1, which is characterized in that the diameter of first groove and second groove
Diameter it is different.
5. integrated cushion block according to claim 1, which is characterized in that the cushion block be in square, first groove with
Second groove is located at the wherein both sides of the cushion block.
6. integrated cushion block according to claim 1, which is characterized in that the cushion block is additionally provided with third groove and the 4th recessed
Slot.
7. integrated cushion block according to claim 6, which is characterized in that the bottom of the third groove is at a distance of the connecting hole
The distance of central axis is equal to the H1, and the bottom of the 4th groove is equal to described at a distance of the distance of the connecting hole central axis
H2。
8. integrated cushion block according to claim 6 or 7, which is characterized in that the diameter and described first of the 4th groove
The diameter of groove is identical;4th groove is in be disposed adjacent with first groove.
9. integrated cushion block according to claim 6 or 7, which is characterized in that the diameter of the third groove and described second
The diameter of groove is identical;The third groove is in be disposed adjacent with second groove.
10. integrated cushion block according to claim 1, which is characterized in that the integrated cushion block further includes connector, the company
The both ends of fitting are separately connected the first connecting rod and the second connecting rod;The connector is L-type bilateral.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910481771.XA CN110374263B (en) | 2019-06-04 | 2019-06-04 | Integrated cushion block |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910481771.XA CN110374263B (en) | 2019-06-04 | 2019-06-04 | Integrated cushion block |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110374263A true CN110374263A (en) | 2019-10-25 |
CN110374263B CN110374263B (en) | 2021-05-18 |
Family
ID=68249661
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910481771.XA Expired - Fee Related CN110374263B (en) | 2019-06-04 | 2019-06-04 | Integrated cushion block |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110374263B (en) |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN200985598Y (en) * | 2006-12-21 | 2007-12-05 | 上海来福建筑技术有限公司 | Concrete protective layer cushion block for reinforced steel bar |
CN201071567Y (en) * | 2007-03-29 | 2008-06-11 | 胥艾丽 | Slurry shaping cushion block for steel bar protection layer |
JP2009174141A (en) * | 2008-01-22 | 2009-08-06 | Japan Life Kk | Spacer with indication |
CN102587588A (en) * | 2012-03-12 | 2012-07-18 | 中天建设集团有限公司 | Multifunctional concrete cushion block |
CN203308003U (en) * | 2013-05-27 | 2013-11-27 | 沂源恒通新型建筑砖有限公司 | Rebar cushion block |
KR20160000817U (en) * | 2015-01-26 | 2016-03-09 | 박찬원 | Spacer combination structure of non-welding deck plate |
CN205531026U (en) * | 2016-01-15 | 2016-08-31 | 王树森 | Basic unit's framework of steel reinforcement lip block |
CN206053144U (en) * | 2016-09-20 | 2017-03-29 | 中建八局第四建设有限公司 | A kind of concrete pad |
CN206512931U (en) * | 2017-01-16 | 2017-09-22 | 中建四局第三建筑工程有限公司 | A kind of working iron railing stool of building floor |
CN109235782A (en) * | 2018-11-20 | 2019-01-18 | 中建二局第建筑工程有限公司 | Support construction and steel frame construction |
-
2019
- 2019-06-04 CN CN201910481771.XA patent/CN110374263B/en not_active Expired - Fee Related
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN200985598Y (en) * | 2006-12-21 | 2007-12-05 | 上海来福建筑技术有限公司 | Concrete protective layer cushion block for reinforced steel bar |
CN201071567Y (en) * | 2007-03-29 | 2008-06-11 | 胥艾丽 | Slurry shaping cushion block for steel bar protection layer |
JP2009174141A (en) * | 2008-01-22 | 2009-08-06 | Japan Life Kk | Spacer with indication |
CN102587588A (en) * | 2012-03-12 | 2012-07-18 | 中天建设集团有限公司 | Multifunctional concrete cushion block |
CN203308003U (en) * | 2013-05-27 | 2013-11-27 | 沂源恒通新型建筑砖有限公司 | Rebar cushion block |
KR20160000817U (en) * | 2015-01-26 | 2016-03-09 | 박찬원 | Spacer combination structure of non-welding deck plate |
CN205531026U (en) * | 2016-01-15 | 2016-08-31 | 王树森 | Basic unit's framework of steel reinforcement lip block |
CN206053144U (en) * | 2016-09-20 | 2017-03-29 | 中建八局第四建设有限公司 | A kind of concrete pad |
CN206512931U (en) * | 2017-01-16 | 2017-09-22 | 中建四局第三建筑工程有限公司 | A kind of working iron railing stool of building floor |
CN109235782A (en) * | 2018-11-20 | 2019-01-18 | 中建二局第建筑工程有限公司 | Support construction and steel frame construction |
Also Published As
Publication number | Publication date |
---|---|
CN110374263B (en) | 2021-05-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11795681B2 (en) | Structural frame for a building and method of constructing the same | |
CN100585104C (en) | Building structure | |
US20190010695A1 (en) | Methods and apparatuses for constructing a concrete structure | |
WO2008151403A1 (en) | Building block system | |
KR100911148B1 (en) | Lightened Coping for bridge | |
CN110374263A (en) | Integrated cushion block | |
CN209457162U (en) | A kind of assembled wallboard connecting joint structure | |
US10487494B1 (en) | Architectural building block system | |
CN214833972U (en) | ALC wallboard | |
CN101250946A (en) | Construction method and construction technique for wide cross section beam formwork supporting system | |
CN213204696U (en) | Narrow-flange I-shaped steel concrete conversion beam | |
CN205153121U (en) | Buckling restrained brace and concrete beam column angle steel anchor connected node | |
CN105155406B (en) | Hollow thin-walled high pier framework cushion cap and bridge | |
CN211898331U (en) | Building concrete pipe pile | |
CN105297891A (en) | Flexing constraint support and concrete beam-column T-shaped steel anchoring and connecting node | |
CN210289183U (en) | Auxiliary device for mounting beam steel bars | |
CN205153120U (en) | Buckling restrained brace and concrete beam column T shaped steel anchor connected node | |
WO2020132266A1 (en) | Methods and apparatuses for constructing a concrete structure | |
CN210482556U (en) | Concrete member | |
CN201695680U (en) | Dismounting-free inner mold for cast-in-situ large-span floors | |
CN210887235U (en) | Prestressed concrete interlocking support pile | |
CN216552445U (en) | Closely concreties built-in fitting | |
RU2288839C1 (en) | Method of manufacture of the lengthy building structures, the lengthy building structure and the column manufactured by this method | |
CN219033999U (en) | Reinforcing and fixing device for horizontal truss | |
CN214738768U (en) | Truss girder with solid web girder section variable in height |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20230621 Address after: Room 103, Building 121, Zone A, East China International Building Materials Center, North Hema Road, Cuozhen Town, Feidong County, Hefei City, Anhui Province, 231602 Patentee after: Anhui HENGCHUANG Construction Engineering Co.,Ltd. Address before: 528300 East Office, No. 11 Junye East Road, Beijiao Town, Shunde District, Foshan City, Guangdong Province Patentee before: GUANGDONG BOZHILIN ROBOT Co.,Ltd. |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210518 |