CN110359649A - 一种大跨度无支撑钢结构旋转楼梯预应力施工工艺 - Google Patents

一种大跨度无支撑钢结构旋转楼梯预应力施工工艺 Download PDF

Info

Publication number
CN110359649A
CN110359649A CN201810251913.9A CN201810251913A CN110359649A CN 110359649 A CN110359649 A CN 110359649A CN 201810251913 A CN201810251913 A CN 201810251913A CN 110359649 A CN110359649 A CN 110359649A
Authority
CN
China
Prior art keywords
steel
girder steel
weld
plate
large span
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810251913.9A
Other languages
English (en)
Other versions
CN110359649B (zh
Inventor
李朝晖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuji Bihan Precision Machinery Technology Co.,Ltd.
Original Assignee
ZHUJI BIHAN FINE MOLDING CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHUJI BIHAN FINE MOLDING CO Ltd filed Critical ZHUJI BIHAN FINE MOLDING CO Ltd
Priority to CN201810251913.9A priority Critical patent/CN110359649B/zh
Publication of CN110359649A publication Critical patent/CN110359649A/zh
Application granted granted Critical
Publication of CN110359649B publication Critical patent/CN110359649B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/02Stairways; Layouts thereof
    • E04F11/022Stairways; Layouts thereof characterised by the supporting structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing

Abstract

一种大跨度无支撑钢结构旋转楼梯预应力施工工艺,具体方法如下,先做好预制构件,在地面上精细放样后构筑基础;将基础钢板用螺栓锚固于地板上;在钢板基础和上一层承重梁之间架设内圈钢梁,焊接加固后直接焊上预制好的踢脚板和踏步板,接着开始多段外圈钢梁预应力拼装,分别从上下两端向中间施工,加载稳定后与相对应的踢脚板和踏步板焊接加固,焊接下一段钢梁时先对齐平缝,在上面绑焊工艺钢板一块作预连接,然后满焊加固,拆掉工艺绑板,与对应的踢脚板和踏步板焊接加固;直到钢梁中心接缝处停止;整体焊接完成后应配合装修进程分几次对外圈钢梁逐步卸荷。本发明极大提高了外侧钢梁的承载能力,兼顾美观的同时几乎不增加用钢量。

Description

一种大跨度无支撑钢结构旋转楼梯预应力施工工艺
技术领域
本发明涉及一种大跨度无支撑钢结构旋转楼梯预应力施工工艺。
背景技术
现在建筑当中采用旋转楼梯及椭圆旋转楼梯越来越多,其中钢结构梯又以相对的轻质高强,施工便捷,精度易于把握而倍受青睐,然而旋转楼梯外侧钢梁通常长度很长,架设后会在中间附近区域产生较大挠度,无论用何种材料,在不加支撑的情况下有效载荷始终不高,做各种支撑又会破坏旋转楼梯凌空而起这个最大的美感,用传统方法设计无支撑大跨度旋转楼梯需要大幅提高钢材用量,并非明智的选择。
发明内容
本发明就是为了解决提供一种可提高外侧钢梁的承载能力的大跨度无支撑钢结构旋转楼梯预应力施工工艺技术问题。
为解决上述技术问题,本发明一种大跨度无支撑钢结构旋转楼梯预应力施工工艺的技术解决方案为:
所述大跨度无支撑钢结构旋转楼梯包括以下步骤:
步骤一:先做好预制构件,在地面上精细放样后构筑基础;
步骤二:将基础钢板用螺栓锚固于地板上;
步骤三:在钢板基础和上一层承重梁之间架设内圈钢梁,焊接加固后直接焊上预制好的踢脚板和踏步板,
步骤四:全部踢脚板和踏步板焊接加固完以后,开始多段外圈钢梁预应力拼装,分别从上下两端向中间施工,焊接好第一段钢梁后即在其外侧加挂重物,重量为其将要承受在其上方到钢梁中心点为止所有构件总重量再加目标承载力;
步骤五:加载稳定后与相对应的踢脚板和踏步板焊接加固,焊接下一段钢梁时先对齐平缝,在上面绑焊工艺钢板一块作预连接,然后通过在下口缝隙处垫薄钢片迫使构件产生上翘;通过调整缝隙使得其在该载荷下符合图纸的高度要求,然后满焊加固,拆掉工艺绑板,与对应的踢脚板和踏步板焊接加固;
步骤六:重复步骤五,直到钢梁中心接缝处停止;
步骤七:整体焊接完成后应配合装修进程分几次对外圈钢梁逐步卸荷。
所述步骤二完成后,在楼下对基础楼板进行支撑,再进行步骤三,待步骤七完成后将支撑物进行拆除。
所述步骤三焊接时可在外端加钢管支撑以控制水平度。
本发明可以达到的技术效果是:本发明整体焊接完成后应配合装修进程分几次对外圈钢梁逐步卸荷,卸荷后外圈钢梁的回弹力对踢脚板和踏步板产生举升力矩,又因为内侧钢梁的牵制而处于矛盾平衡,极大提高了外侧钢梁的承载能力,兼顾美观的同时几乎不增加用钢量,可谓一具多得。
附图说明
下面结合附图和具体实施方式对本发明作进一步详细的说明:
图1是本发明一种大跨度无支撑钢结构旋转楼梯的俯视图;
图2是本发明一种大跨度无支撑钢结构旋转楼梯的主视图;
图3是本发明钢板基础图。
具体实施方式
下面结合附图对本发明作进一步详细的阐述。
参阅图1至图3。
本工艺方法对外圈钢梁施加预应力,具体方法如下:如图所示,椭圆旋转楼梯外圈梁展开长度达到了17米,钢梁设计为多箱体拼接,先做好预制构件,在地面上精细放样后构筑基础,因为楼梯自重及上面的正常载荷沿弧形梁螺旋方向传递而产生的水平分力可以使得楼梯基础位移而消除预应力,所以将基础钢板用螺栓锚固于地板上,适当加大基础钢板面积可有效分散对楼板产生的压力,在必要时要在楼下对基础楼板进行支撑,待施工结束后拆除,先在钢板基础和上一层承重梁之间架设内圈钢梁,焊接加固后直接焊上预制好的踢脚板和踏步板,适当加高加厚踢脚板将有助于预应力释放后的力矩传递,具体焊接时可在外端加钢管支撑以控制水平度,全部踢脚板和踏步板焊接加固完以后,开始多段外圈钢梁预应力拼装,分别从上下两端向中间施工,焊接好第一段钢梁后即在其外侧加挂重物,重量为其将要承受在其上方到钢梁中心点为止所有构件总重量再加目标承载力,通过计算可以轻易得到,加载稳定后与相对应的踢脚板和踏步板焊接加固,焊接下一段钢梁时先对对齐平缝,在上面绑焊工艺钢板一块作预连接,然后通过在下口缝隙处垫薄钢片迫使构件产生上翘,然后加载经过计算的重量,同时在第一段减去该重量,通过调整缝隙使得其在该载荷下符合图纸的高度要求,然后满焊加固,拆掉工艺绑板,与对应的踢脚板和踏步板焊接加固,下一步以此类推,直到钢梁中心接缝处停止,上半段钢梁由上向下施工,预应力为对上层承重梁的下拉力,其他方法步骤均相同,整体焊接完成后应配合装修进程分几次对外圈钢梁逐步卸荷,卸荷后外圈钢梁的回弹力对踢脚板和踏步板产生举升力矩,又因为内侧钢梁的牵制而处于矛盾平衡,极大提高了外侧钢梁的承载能力,兼顾美观的同时几乎不增加用钢量,可谓一具多得。

Claims (3)

1.一种大跨度无支撑钢结构旋转楼梯预应力施工工艺,其特征在于,所述大跨度无支撑钢结构旋转楼梯包括以下步骤:
步骤一:先做好预制构件,在地面上精细放样后构筑基础;
步骤二:将基础钢板用螺栓锚固于地板上;
步骤三:在钢板基础和上一层承重梁之间架设内圈钢梁,焊接加固后直接焊上预制好的踢脚板和踏步板,
步骤四:全部踢脚板和踏步板焊接加固完以后,开始多段外圈钢梁预应力拼装,分别从上下两端向中间施工,焊接好第一段钢梁后即在其外侧加挂重物,重量为其将要承受在其上方到钢梁中心点为止所有构件总重量再加目标承载力;
步骤五:加载稳定后与相对应的踢脚板和踏步板焊接加固,焊接下一段钢梁时先对齐平缝,在上面绑焊工艺钢板一块作预连接,然后通过在下口缝隙处垫薄钢片迫使构件产生上翘;通过调整缝隙使得其在该载荷下符合图纸的高度要求,然后满焊加固,拆掉工艺绑板,与对应的踢脚板和踏步板焊接加固;
步骤六:重复步骤五,直到钢梁中心接缝处停止;
步骤七:整体焊接完成后应配合装修进程分几次对外圈钢梁逐步卸荷。
2.根据权利要求1所述的一种大跨度无支撑钢结构旋转楼梯预应力施工工艺,其特征在于:所述步骤二完成后,在楼下对基础楼板进行支撑,再进行步骤三,待步骤七完成后将支撑物进行拆除。
3.根据权利要求1所述的一种大跨度无支撑钢结构旋转楼梯预应力施工工艺,其特征在于:所述步骤三焊接时可在外端加钢管支撑以控制水平度。
CN201810251913.9A 2018-03-26 2018-03-26 一种大跨度无支撑钢结构旋转楼梯预应力施工工艺 Active CN110359649B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810251913.9A CN110359649B (zh) 2018-03-26 2018-03-26 一种大跨度无支撑钢结构旋转楼梯预应力施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810251913.9A CN110359649B (zh) 2018-03-26 2018-03-26 一种大跨度无支撑钢结构旋转楼梯预应力施工工艺

Publications (2)

Publication Number Publication Date
CN110359649A true CN110359649A (zh) 2019-10-22
CN110359649B CN110359649B (zh) 2021-08-06

Family

ID=68212077

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810251913.9A Active CN110359649B (zh) 2018-03-26 2018-03-26 一种大跨度无支撑钢结构旋转楼梯预应力施工工艺

Country Status (1)

Country Link
CN (1) CN110359649B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112031298A (zh) * 2020-09-01 2020-12-04 湖北工业大学 一种钢筋混凝土楼梯抗震加固结构

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB786955A (en) * 1954-03-04 1957-11-27 Costain Concrete Company Ltd Improvements in or relating to pre-stressed concrete members
US4413460A (en) * 1979-03-01 1983-11-08 Horst Gerlach Method of assembling a spiral stair case
CN202416744U (zh) * 2011-12-31 2012-09-05 苏州工业园区设计研究院股份有限公司 大跨预应力交叉弦支钢楼梯
CN103659182A (zh) * 2013-12-03 2014-03-26 中建钢构江苏有限公司 弯扭箱型梁360°旋转楼梯的制作方法
CN104264920A (zh) * 2014-09-09 2015-01-07 中国建筑第八工程局有限公司 超高大曲率圆形螺旋清水楼梯的施工方法
CN205712823U (zh) * 2016-06-07 2016-11-23 三能集成房屋股份有限公司 预应力装配式楼梯
CN107237461A (zh) * 2017-07-17 2017-10-10 深圳市建艺装饰集团股份有限公司 一种全悬空旋转钢结构楼梯结构及施工方法

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB786955A (en) * 1954-03-04 1957-11-27 Costain Concrete Company Ltd Improvements in or relating to pre-stressed concrete members
US4413460A (en) * 1979-03-01 1983-11-08 Horst Gerlach Method of assembling a spiral stair case
CN202416744U (zh) * 2011-12-31 2012-09-05 苏州工业园区设计研究院股份有限公司 大跨预应力交叉弦支钢楼梯
CN103659182A (zh) * 2013-12-03 2014-03-26 中建钢构江苏有限公司 弯扭箱型梁360°旋转楼梯的制作方法
CN104264920A (zh) * 2014-09-09 2015-01-07 中国建筑第八工程局有限公司 超高大曲率圆形螺旋清水楼梯的施工方法
CN205712823U (zh) * 2016-06-07 2016-11-23 三能集成房屋股份有限公司 预应力装配式楼梯
CN107237461A (zh) * 2017-07-17 2017-10-10 深圳市建艺装饰集团股份有限公司 一种全悬空旋转钢结构楼梯结构及施工方法

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112031298A (zh) * 2020-09-01 2020-12-04 湖北工业大学 一种钢筋混凝土楼梯抗震加固结构
CN112031298B (zh) * 2020-09-01 2022-02-08 湖北工业大学 一种钢筋混凝土楼梯抗震加固结构

Also Published As

Publication number Publication date
CN110359649B (zh) 2021-08-06

Similar Documents

Publication Publication Date Title
US11149390B2 (en) Prefabricated, prestressed bridge module
CN101538831B (zh) 简支梁转换为连续梁的后浇隐盖梁施工工法
KR20010078870A (ko) 프리스트레스트 복합 트러스 보의 개발 및 제작공법
CN100447338C (zh) 软土地基多孔双悬臂拱形桥结构及其施工方法
CN101440598B (zh) 钢箱-砼组合箱板拱结构及其施工方法
CN106812229A (zh) 组合约束双钢板混凝土剪力墙及其施工方法
CN201794214U (zh) 一种带有空腔的预制梁
CN104929381A (zh) 钢支托无粘结钢绞线下撑式预应力加固楼板的方法
CN110359649A (zh) 一种大跨度无支撑钢结构旋转楼梯预应力施工工艺
KR101337185B1 (ko) 보강 콘크리트에 의해 보강된 하이브리드 교량의 시공방법 및 그 구조체
CN201254731Y (zh) 一种钢十字梁式可拆卸塔基
CN202466844U (zh) 钢管混凝土柱与型钢混凝土梁顶层节点连接结构
CN106758839A (zh) 一种墩顶现浇节段施工的支架体系及其安装方法
CN210597882U (zh) 一种格构式钢骨混凝土组合柱梁柱节点
CN205369295U (zh) 基础预制预应力梁板式风力发电塔基础
CN201071515Y (zh) 组合式斜拉柱伞反力装置
CN215211508U (zh) 一种混凝土柱和钢柱的连接节点
JPH02136445A (ja) スーパーフレームを含む構造物の構築方法
KR102107666B1 (ko) 장스팬 합성보 및 이를 이용한 장스팬 구조 시공 방법
JP2004019306A (ja) 塔状建造物及びその構築方法
CN110565600A (zh) 一种长隧洞衬砌施工方法
CN101230673A (zh) 一种砼楼盖用结构承力式叠合构件
CN101230664A (zh) 一种承力式底板构件
CN214272589U (zh) 一种内置填充预制球及钢筋桁架的楼承板
CN211037415U (zh) 一种剪力墙的转换支承结构

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220720

Address after: 311800 no.713-3, Jiefang Road, Diankou Town, Zhuji City, Shaoxing City, Zhejiang Province

Patentee after: Zhuji Bihan Precision Machinery Technology Co.,Ltd.

Address before: 311800 no.713 Jiefang Road, Diankou Town, Zhuji City, Shaoxing City, Zhejiang Province

Patentee before: ZHUJI BIHAN PRECISION MOULDING CO.,LTD.

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A prestressed construction technology of large-span unsupported steel structure rotating stairs

Effective date of registration: 20220719

Granted publication date: 20210806

Pledgee: Zhejiang Zhuji Rural Commercial Bank Co.,Ltd. Meichi sub branch

Pledgor: Zhuji Bihan Precision Machinery Technology Co.,Ltd.

Registration number: Y2022980010767