CN110348901A - A kind of project cost amending method and system - Google Patents
A kind of project cost amending method and system Download PDFInfo
- Publication number
- CN110348901A CN110348901A CN201910596456.1A CN201910596456A CN110348901A CN 110348901 A CN110348901 A CN 110348901A CN 201910596456 A CN201910596456 A CN 201910596456A CN 110348901 A CN110348901 A CN 110348901A
- Authority
- CN
- China
- Prior art keywords
- data
- price
- project cost
- change
- engineering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q30/00—Commerce
- G06Q30/02—Marketing; Price estimation or determination; Fundraising
- G06Q30/0283—Price estimation or determination
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q30/00—Commerce
- G06Q30/06—Buying, selling or leasing transactions
- G06Q30/08—Auctions
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Abstract
The present invention relates to the technical fields of project cost, more particularly, to a kind of project cost amending method and system, project cost amending method includes: S10: if getting price change message, price change material mark and change price data are obtained from the price change message;S20: engineering material tables of data is matched from project file data using preset project cost template, the engineering material tables of data includes engineering material mark;S30: matching inquiry is carried out in the engineering material tables of data one by one using the price change material mark, and matching inquiry successful engineering material mark is marked, obtains material mark to be changed;S40: the original prices data of the material mark to be changed are obtained, the original prices data are changed according to the change price data, obtain price adjustment result.The present invention, which has the effect of being promoted, modifies efficiency to project cost.
Description
Technical field
The present invention relates to the technical fields of project cost, more particularly, to a kind of project cost amending method and system.
Background technique
Currently, bidding can be carried out to unit in charge of construction before carrying out for each architectural engineering, it is each in bidding
Unit in charge of construction can to the engineering carry out project cost assessment, and then by the project cost when, be by for staff according to
The information of owner's offer and the work for oneself carrying out cost calculating to the engineering of undertaking to the information that site inspection obtains.
With the fluctuation of price, after obtaining the file of project cost, finally obtained cost can be with object after being possible to
The fluctuation of valence and generate variation, therefore will lead to the accuracy for reducing the cost of entire engineering, if to needing according to the price
Fluctuation modifies to the content of project cost when adjusting, and staff needs to position price change in the file of project cost
Material, and carry out the adjustment of price, cumbersome, accordingly, there exist rooms for improvement.
Summary of the invention
The object of the present invention is to provide a kind of promoted to modify a kind of project cost modification side of efficiency to project cost
Method and system.
Foregoing invention purpose one of the invention has the technical scheme that
A kind of project cost amending method, the project cost amending method include:
S10: if getting price change message, price change material mark and change are obtained from the price change message
Price data;
S20: engineering material tables of data, the engineering material are matched from project file data using preset project cost template
Material tables of data includes engineering material mark;
S30: carrying out matching inquiry using the price change material mark in the engineering material tables of data one by one, and to
Engineering material mark with successful inquiring is marked, and obtains material mark to be changed;
S40: the original prices data of the material mark to be changed are obtained, according to the change price data to the original valence
Lattice data change, and obtain price adjustment result.
By using above-mentioned technical proposal, the project cost template is pre-set, can be disappeared getting price change
After breath, the engineering material data in the project file data are matched from the more parts of project file data that need to modify immediately
Table, and then improve the efficiency that data are obtained from project file data;By the price change material mark in price change message
Knowledge matches material mark to be changed in engineering material tables of data, original prices that can in time to the material mark to be changed
Data change, and improve to obtain the efficiency of price adjustment result.
The present invention is further arranged to: step S20 includes:
S21: history engineering protocol is obtained;
S22: material category information is obtained, matches material information from the history engineering protocol;
S23: classified according to the material category information to the material information, obtain material category data;
S24: the material category data are formed into the project cost template.
It can be from history engineering side by obtaining passing history engineering protocol by using above-mentioned technical proposal
It obtains passing data in case data to be arranged, by the material category information of engineering, from history engineering protocol
Material information is matched, and is classified according to material category information to the material information, each material category can be obtained
The corresponding material category data of information, and then the project cost template can be made up of the material category data, and then can
When carrying out new project cost, using the project cost template, Auto-matching goes out from the arrangement and method for construction of the new project cost
Required material and corresponding quantity, improve summarizing to the material in arrangement and method for construction, improve change or modification work
The efficiency of journey cost data.
The present invention is further arranged to: step S22 includes:
S221: corresponding engineering material information is obtained from each material category information;
S222: using each engineering material information as matched character string, using the matched character string in the history work
It is matched in journey protocol.
By using above-mentioned technical proposal, using the engineering material information in category work information as matched character string, energy
It is enough that the material used in passing project cost scheme is matched in history engineering protocol, with history engineering side
The increase of the amount of case data so that obtained material information is more perfect, and then enables to project cost template service efficiency to increase
Add.
The present invention is further arranged to: step S24 includes:
S241: according to the material category data, project cost frame is constructed;
S242: after the project cost template is written in the corresponding engineering material information of the material category data, institute is obtained
State project cost template.
By using above-mentioned technical proposal, project cost frame is constructed previously according to material information, can be somebody's turn to do convenient for composition
When project cost template, material category information is inserted in the project cost frame according to the content in project cost frame, from
And the efficiency for obtaining project cost template is promoted, and then be able to ascend change or modify the efficiency of Construction Cost Data.
The present invention is further arranged to: step S40 includes:
S41: if the change price data is amount of change data, the amount of change data and original prices data being summed,
Obtain the price adjustment result;
S42: if the change price data is new price data, the original prices data are substituted for the new price number
According to.
By using above-mentioned technical proposal, the case where according to change price data, original prices data are adjusted respectively
It is whole, it can guarantee the accuracy of price adjustment result adjusted.
Foregoing invention purpose two of the invention has the technical scheme that
A kind of project cost modification system, the project cost modification system include:
Message capturing module is changed, if obtaining price from the price change message for getting price change message
Change material mark and change price data;
Data match module, for matching engineering material data from project file data using preset project cost template
Table, the engineering material tables of data include engineering material mark;
Mark module is looked into for being carried out matching in the engineering material tables of data one by one using the price change material mark
It askes, and matching inquiry successful engineering material mark is marked, obtain material mark to be changed;
Price adjustment module, for obtaining the original prices data of the material mark to be changed, according to the change price number
It is changed according to the original prices data, obtains price adjustment result.
By using above-mentioned technical proposal, the project cost template is pre-set, can be disappeared getting price change
After breath, the engineering material data in the project file data are matched from the more parts of project file data that need to modify immediately
Table, and then improve the efficiency that data are obtained from project file data;By the price change material mark in price change message
Knowledge matches material mark to be changed in engineering material tables of data, original prices that can in time to the material mark to be changed
Data change, and improve to obtain the efficiency of price adjustment result.
In conclusion advantageous effects of the invention are as follows:
1. pre-setting the project cost template, can need to carry out from more parts immediately after getting price change message
The engineering material tables of data in the project file data is matched in modification project file data, and then is improved from project file
The efficiency of data is obtained in data;
2. the price change material mark in price change message is matched material mark to be changed in engineering material tables of data
Know, can the original prices data in time to the material mark to be changed change, improve to obtain price adjustment result
Efficiency;
3. by obtaining passing history engineering protocol, can be obtained from history engineering protocol passing data into
Row arranges, by matching material information from history engineering protocol, and according to material in the material category information of engineering
Information classifies to the material information, can obtain the corresponding material category data of each material category information, into
And the project cost template can be made up of the material category data, and then can use when carrying out new project cost
Project cost template Auto-matching from the arrangement and method for construction of the new project cost goes out required material and corresponding number
Amount, improves summarizing to the material in arrangement and method for construction, improves change or modifies the efficiency of Construction Cost Data.
Detailed description of the invention
Fig. 1 is a flow chart of project cost amending method in one embodiment of the invention;
Fig. 2 is the implementation flow chart of step S20 in project cost amending method in one embodiment of the invention;
Fig. 3 is the implementation flow chart of step S22 in project cost amending method in one embodiment of the invention;
Fig. 4 is the implementation flow chart of step S24 in project cost amending method in one embodiment of the invention;
Fig. 5 is the implementation flow chart of step S40 in project cost amending method in one embodiment of the invention;
Fig. 6 is a functional block diagram of project cost modification system in one embodiment of the invention.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
Embodiment one:
In one embodiment, as shown in Figure 1, specifically comprising the following steps: the invention discloses a kind of project cost amending method
S10: if getting price change message, price change material mark and change price are obtained from price change message
Data.
In the present embodiment, price change message refers to the changed message of the price of construction material.Change material mark
Know the title for referring to the material for referring to price change.Change price data refers to that the changed material of the price is corresponding
The data of price change.The change price data can be the specific number after price change, be also possible to the width of price change
Degree.
Specifically, after getting price change message, price change material mark is obtained from the price change message
With change price data.
S20: engineering material tables of data, engineering material are matched from project file data using preset project cost template
Material tables of data includes engineering material mark.
In the present embodiment, project cost template, which refers to, pre-sets, and the arrangement and method for construction is matched in arrangement and method for construction
The template of used material.Project file data refer to the file submitted a tender.Engineering material tables of data refers to record
There is the data form of material used in the project file data.Engineering material mark refers to specifically used in the project file
The mark of material.
Specifically, matched in project file data using project cost template, if can successful match, illustrate
The data allotted are material specifically used in the project file data.Further, after the completion of matching, by successful match
Character string is identified as the engineering material, and then the engineering material is identified one data form of write-in, obtains engineering material data
Table.
S30: matching inquiry is carried out in engineering material tables of data one by one using price change material mark, and matching is looked into
It askes successful engineering material mark to be marked, obtains material mark to be changed.
In the present embodiment, material mark to be changed, which refers to, needs the price to the material in engineering material data to become
Mark more.
Specifically, each price change material mark is subjected to matching inquiry in engineering material tables of data, if can
With successful inquiring, then there are the prices of engineering material mark to be changed in engineering material tables of data for explanation, and use pair
The character string answered is to being marked, and further, matches and looks into engineering material tables of data in all price change material marks
After inquiry, it regard the engineering material mark of label as material mark to be changed.
S40: obtaining the original prices data of material mark to be changed, according to change price data to original prices data into
Row change, obtains price adjustment result.
In the present embodiment, original prices information refers to the original unit price of material mark to be changed before changing.Price adjustment
As a result refer to the result after original prices data are adjusted.
Specifically, original prices data are adjusted using change price data corresponding with price sign to be changed,
Obtain the price adjustment result of the price sign to be changed.
In the present embodiment, the project cost template is pre-set, it can be after getting price change message, immediately
The engineering material tables of data in the project file data, Jin Erti are matched from the more parts of project file data that need to modify
The efficiency that data are obtained from project file data is risen;By the price change material mark in price change message in engineering material
Material tables of data in match material mark to be changed, can the original prices data in time to the material mark to be changed become
More, it improves to obtain the efficiency of price adjustment result.
In one embodiment, as shown in Fig. 2, in step S20, project cost template is set using following steps:
S21: history engineering protocol is obtained.
In the present embodiment, history engineering protocol referred within the past period, such as half a year, 1 year or three
Year etc., the file for the arrangement and method for construction that unit in charge of construction submits a tender.
Specifically, from the database for being stored with history engineering protocol, the history engineering protocol is obtained.It is preferred that
Ground can classify to history engineering protocol, obtain according to type of construction, such as construction, railway, water conservancy or highway etc.
To the history protocol of the construction of every one kind.
S22: material category information is obtained, matches material information from history engineering protocol.
In the present embodiment, material category information refers in every a kind of construction, required engineering material type
Information.Material information refers in each material category information, specific engineering material.For example, if the material category information is
Fastener, the material information can be nail, screw, bolt or screw etc..
Specifically, by pre-setting the material category information, the material category information and each material category letter
Breath is those skilled in the art's common used material, can summarize and summarize previously according to those skilled in the art's daily experience, obtain
To material information material category information corresponding with the material information.
Further, the data planted one by one in material category information are matched in history engineering protocol, if having
Data Matching success, then illustrate that the corresponding material of the data is the material that the history engineering protocol uses, then to the material
It is marked.After matching, using the material of label as the material information.
S23: classifying to material information according to material category information, obtains material category data.
In the present embodiment, material category data refer to that history is the type of used material in arrangement and method for construction.It can manage
Solution, in material category data and material category information, the content of material category is identical, but since material category data are specific
Applied to the construction of a certain type, therefore the number of species in material category data are than the quantity of the type in material category information
Lack.
Specifically, when matching the material information, the corresponding material category information of the material information is marked, example
Such as, material information A1 is matched from type A, then type A is marked, and another character is used to material information A1
String is marked, and further, all material information uses matched from type A character string identical with A1 is marked
Note.And the material information used matched from type B is marked using not A1 different character string.
Further, when classifying according to material category information to material information, the material of same string token is obtained
Expect information, and is marked using corresponding material category information, and then obtain the material category data.
S24: material category data are formed into project cost template.
In the present embodiment, project cost template refers in new arrangement and method for construction, obtaining institute in the arrangement and method for construction
The template of all engineering material and corresponding quantity that use.
Specifically, the material category data that above-mentioned steps obtain are formed into the project cost template, so that using should
Project cost template is matched in the arrangement and method for construction of corresponding type, can match the work used in the arrangement and method for construction
Journey material and corresponding quantity.
In one embodiment, as shown in figure 3, in step S22, that is, material category information is obtained, from history engineering scheme
Material information is matched in data, is specifically comprised the following steps:
S221: corresponding engineering material information is obtained from each material category information.
In the present embodiment, engineering material information refers to the information of the specific material in material category information.
Specifically, corresponding engineering material information is obtained from each material category information.
S222: using each engineering material information as matched character string, using matched character string in history engineering scheme number
It is matched in.
In the present embodiment, matched character string refers to carries out matched character string in history engineering protocol.
Specifically, the length of the engineering material information is calculated by calling length function in matching, and by the length
Engineering material information as matched character string.
Further, then by length function it is obtained in history engineering protocol identical as matched character string length
Character string, as compare character string.
Further, the comparison character string is compared with the matched character string using simple algorithm.Specific method is such as
Under: it is matched since matched character string character corresponding with first position of character string is compared, if matched character string and comparison
The first character of character string is identical, then start to matched character string with compare the corresponding character in next position of character string into
Row matching.If during this is matched, matched character string character match knot corresponding with any one position of character string is compared
Fruit is not identical, then judges that the matched character string and comparison character string be not identical, and terminate the matching operation.If detecting matching word
Symbol string character corresponding with comparison the last one position of character string is identical, then judges the matched character string and compare character string phase
Together, and terminate the matching operation.
In one embodiment, as described in Figure 4, in step 24, i.e., material category data are formed into project cost template, tool
Body includes the following steps:
S241: according to material category data, project cost frame is constructed.
In the present embodiment, project cost frame refers to the data form for obtaining data.
Specifically, data form is written into material category data one by one, it is unique right being used to each material category data
After the character string answered is marked, using the data form as the project cost frame.
S242: it after by the corresponding engineering material information write-in project cost frame of material category data, obtains engineering and makes
Valence template.
It specifically, will be same after being marked in engineering material information using the character string of affiliated material category data
The engineering material information extraction of one label in corresponding category work information, and then obtains the engineering into project cost frame
Cost template.
In one embodiment, as shown in figure 5, in step s 40, that is, obtaining the original prices number of material mark to be changed
According to, according to change price data original prices data are changed, obtain price adjustment as a result, specifically comprising the following steps:
S41: if change price data is amount of change data, amount of change data and original prices data is summed, price is obtained
Adjust result.
In the present embodiment, amount of change data refer to the amplitude for being changed to change of the price of construction material.If the change
Measuring data is to appreciate, then the amount of change data are positive number, if the amount of change data are price reduction, which is negative.
Specifically, amount of change data and original prices data are directly summed, and then obtains price adjustment result.
S42: if change price data is new price data, original prices data are substituted for new price data.
In the present embodiment, new price data refers to the specific price data after price change.
Specifically, if change price data is new price data, original prices data are substituted for new price data, into
And obtain price adjustment result.
It should be understood that the size of the serial number of each step is not meant that the order of the execution order in above-described embodiment, each process
Execution sequence should be determined by its function and internal logic, the implementation process without coping with the embodiment of the present invention constitutes any limit
It is fixed.
Embodiment two:
In one embodiment, a kind of project cost modification system is provided, which modifies work in system and above-described embodiment
Journey cost amending method corresponds.As shown in fig. 6, project cost modification system includes change message capturing module 10, number
According to matching module 20, mark module 30 and price adjustment module 40.Detailed description are as follows for each functional module:
Message capturing module 10 is changed, if obtaining price for getting price change message from price change message and becoming
More material mark and change price data;
Data match module 20, for matching engineering material number from project file data using preset project cost template
According to table, engineering material tables of data includes engineering material mark;
Mark module 30, for using price change material mark to carry out matching inquiry in engineering material tables of data one by one, and
Matching inquiry successful engineering material mark is marked, material mark to be changed is obtained;
Price adjustment module 40, for obtaining the original prices data of material mark to be changed, according to change price data to original
Beginning price data changes, and obtains price adjustment result.
Preferably, data match module module 20 includes:
Acquisition submodule 21, for obtaining history engineering protocol;
Matched sub-block 22 matches material information from history engineering protocol for obtaining material category information;
Classification submodule 23 obtains material category data for classifying according to material category information to material information;
Template construct submodule 24, for material category data to be formed project cost template.
Preferably, matched sub-block 22 includes:
Material information acquiring unit 221, for obtaining corresponding engineering material information from each material category information;
Matching unit 222 is used for using each engineering material information as matched character string, using matched character string in history engineering
It is matched in protocol.
Preferably, template construct submodule 24 includes:
Frame builds unit 241, for constructing project cost frame according to material category data;
Template construct unit is used for 242 after by the corresponding engineering material information write-in project cost frame of material category data,
Obtain project cost template.
Preferably, price adjustment module 40 includes:
The first adjustment submodule 41, if being amount of change data for changing price data, by amount of change data and original prices
Data summation, obtains price adjustment result;
Original prices data are substituted for newly by second adjustment submodule 42 if being new price data for changing price data
Price data.
Specific about project cost modification system limits the limit that may refer to above for project cost amending method
Fixed, details are not described herein.Modules in above-mentioned project cost modification system can fully or partially through software, hardware and its
Combination is to realize.Above-mentioned each module can be embedded in the form of hardware or independently of in the processor in computer equipment, can also be with
It is stored in the memory in computer equipment in a software form, in order to which processor calls the above modules of execution corresponding
Operation.
Claims (10)
1. a kind of project cost amending method, which is characterized in that the project cost amending method includes:
S10: if getting price change message, price change material mark and change are obtained from the price change message
Price data;
S20: engineering material tables of data, the engineering material are matched from project file data using preset project cost template
Material tables of data includes engineering material mark;
S30: carrying out matching inquiry using the price change material mark in the engineering material tables of data one by one, and to
Engineering material mark with successful inquiring is marked, and obtains material mark to be changed;
S40: the original prices data of the material mark to be changed are obtained, according to the change price data to the original valence
Lattice data change, and obtain price adjustment result.
2. project cost amending method as described in claim 1, which is characterized in that step S20 includes:
S21: history engineering protocol is obtained;
S22: material category information is obtained, matches material information from the history engineering protocol;
S23: classified according to the material category information to the material information, obtain material category data;
S24: the material category data are formed into the project cost template.
3. project cost amending method as claimed in claim 2, which is characterized in that step S22 includes:
S221: corresponding engineering material information is obtained from each material category information;
S222: using each engineering material information as matched character string, using the matched character string in the history work
It is matched in journey protocol.
4. project cost amending method as claimed in claim 2, which is characterized in that step S24 includes:
S241: according to the material category data, project cost frame is constructed;
S242: after the project cost template is written in the corresponding engineering material information of the material category data, institute is obtained
State project cost template.
5. project cost amending method as described in claim 1, which is characterized in that step S40 includes:
S41: if the change price data is amount of change data, the amount of change data and original prices data being summed,
Obtain the price adjustment result;
S42: if the change price data is new price data, the original prices data are substituted for the new price number
According to.
6. a kind of project cost modifies system, which is characterized in that the project cost modifies system and includes:
Message capturing module is changed, if obtaining price from the price change message for getting price change message
Change material mark and change price data;
Data match module, for matching engineering material data from project file data using preset project cost template
Table, the engineering material tables of data include engineering material mark;
Mark module is looked into for being carried out matching in the engineering material tables of data one by one using the price change material mark
It askes, and matching inquiry successful engineering material mark is marked, obtain material mark to be changed;
Price adjustment module, for obtaining the original prices data of the material mark to be changed, according to the change price number
It is changed according to the original prices data, obtains price adjustment result.
7. project cost as claimed in claim 6 modifies system, which is characterized in that the data match module module includes:
Acquisition submodule, for obtaining history engineering protocol;
Matched sub-block matches material information from the history engineering protocol for obtaining material category information;
Classification submodule obtains material category number for classifying according to the material category information to the material information
According to;
Template construct submodule, for the material category data to be formed project cost template.
8. project cost as claimed in claim 7 modifies system, which is characterized in that the matched sub-block includes:
Material information acquiring unit, for obtaining corresponding engineering material information from each material category information;
Matching unit is used for using each engineering material information as matched character string, using the matched character string in institute
It states and is matched in history engineering protocol.
9. project cost as claimed in claim 7 modifies system, which is characterized in that the template construct submodule includes:
Frame builds unit, for constructing project cost frame according to the material category data;
Template construct unit, for the project cost frame to be written in the corresponding engineering material information of the material category data
After frame, the project cost template is obtained.
10. project cost as claimed in claim 6 modifies system, which is characterized in that the price adjustment module includes:
The first adjustment submodule, if being amount of change data for the change price data, by the amount of change data and original
The summation of beginning price data, obtains the price adjustment result;
Second adjustment submodule replaces the original prices data if being new price data for the change price data
Change the new price data into.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910596456.1A CN110348901B (en) | 2019-07-03 | 2019-07-03 | Engineering cost modification method and system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910596456.1A CN110348901B (en) | 2019-07-03 | 2019-07-03 | Engineering cost modification method and system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110348901A true CN110348901A (en) | 2019-10-18 |
CN110348901B CN110348901B (en) | 2023-05-02 |
Family
ID=68178173
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910596456.1A Active CN110348901B (en) | 2019-07-03 | 2019-07-03 | Engineering cost modification method and system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110348901B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111724280A (en) * | 2020-06-17 | 2020-09-29 | 广州广日电梯工业有限公司 | Elevator contract change quotation method, system, electronic equipment and storage medium |
CN112767040A (en) * | 2021-01-26 | 2021-05-07 | 广联达科技股份有限公司 | Method and device for generating project pricing file, computer equipment and storage medium |
CN113095922A (en) * | 2021-05-10 | 2021-07-09 | 广东明正项目管理有限公司 | Engineering quota pricing method and system |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108256964A (en) * | 2018-01-10 | 2018-07-06 | 杭州纳戒科技有限公司 | Management method, device and the server of automatic vending box for material circulation |
CN108364193A (en) * | 2018-01-25 | 2018-08-03 | 广州建衡工程咨询有限公司 | A kind of construction project cost auditing method and system |
CN109615419A (en) * | 2018-11-27 | 2019-04-12 | 建经投资咨询有限公司 | A kind of method for building up, device, equipment and the storage medium of project cost template |
CN109886647A (en) * | 2019-01-29 | 2019-06-14 | 广东华伦招标有限公司 | Procurement business managing functional module method, apparatus, equipment and storage medium |
CN109993406A (en) * | 2019-02-28 | 2019-07-09 | 深圳市元征科技股份有限公司 | A kind of information processing method and device |
-
2019
- 2019-07-03 CN CN201910596456.1A patent/CN110348901B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108256964A (en) * | 2018-01-10 | 2018-07-06 | 杭州纳戒科技有限公司 | Management method, device and the server of automatic vending box for material circulation |
CN108364193A (en) * | 2018-01-25 | 2018-08-03 | 广州建衡工程咨询有限公司 | A kind of construction project cost auditing method and system |
CN109615419A (en) * | 2018-11-27 | 2019-04-12 | 建经投资咨询有限公司 | A kind of method for building up, device, equipment and the storage medium of project cost template |
CN109886647A (en) * | 2019-01-29 | 2019-06-14 | 广东华伦招标有限公司 | Procurement business managing functional module method, apparatus, equipment and storage medium |
CN109993406A (en) * | 2019-02-28 | 2019-07-09 | 深圳市元征科技股份有限公司 | A kind of information processing method and device |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111724280A (en) * | 2020-06-17 | 2020-09-29 | 广州广日电梯工业有限公司 | Elevator contract change quotation method, system, electronic equipment and storage medium |
CN111724280B (en) * | 2020-06-17 | 2024-03-26 | 广州广日电梯工业有限公司 | Elevator contract changing quotation method, system, electronic equipment and storage medium |
CN112767040A (en) * | 2021-01-26 | 2021-05-07 | 广联达科技股份有限公司 | Method and device for generating project pricing file, computer equipment and storage medium |
CN113095922A (en) * | 2021-05-10 | 2021-07-09 | 广东明正项目管理有限公司 | Engineering quota pricing method and system |
Also Published As
Publication number | Publication date |
---|---|
CN110348901B (en) | 2023-05-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110348901A (en) | A kind of project cost amending method and system | |
CN106649223A (en) | Financial report automatic generation method based on natural language processing | |
WO2022142116A1 (en) | Method and apparatus for processing document, and electronic device and storage medium | |
CN110175909A (en) | A kind of enterprise's incidence relation determines method and system | |
CN102024024A (en) | Method and device for constructing address database | |
CN110347988B (en) | Template building method and system for engineering supervision | |
CN110929797A (en) | Personnel capacity quantitative evaluation method | |
CN106919373A (en) | A kind of program code method for evaluating quality | |
CN112634056A (en) | Method, equipment and storage medium for rapidly calculating and updating enterprise share right structure | |
CN109299785A (en) | Method and device for realizing machine learning model | |
CN106294498A (en) | A kind of data processing method and equipment | |
CN107220246B (en) | Business object analysis method and device | |
CN112419124B (en) | Method and device for quickly identifying low-efficiency industrial land and storage medium thereof | |
CN114330318A (en) | Method and device for recognizing Chinese fine-grained entities in financial field | |
Konarasinghe | Decomposition Techniques on Forecasting Tourist Arrivals from Western European Countries to Sri Lanka | |
CN110347686A (en) | Record the method and system of engineering drawing modification information | |
CN116468580A (en) | Human resource training service system and method | |
CN109472541A (en) | A kind of Design of Workflow method suitable for enterprise-level OA | |
CN108920134A (en) | The method and device of Design of automatic generation document | |
CN110322225A (en) | A kind of method for building up and system of project cost template | |
CN114064615A (en) | Data operation and maintenance system and method | |
CN113420876A (en) | Real-time operation data processing method, device and equipment based on unsupervised learning | |
CN109102178A (en) | A kind of electric power enterprise Valuation Method, device and equipment | |
CN111783391A (en) | Online artificial text marking system and method | |
Kowang et al. | Takt time analysis in Lean Six Sigma: From conventional to integration |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |