CN110344293A - Steel rail welding line measures grinding device - Google Patents

Steel rail welding line measures grinding device Download PDF

Info

Publication number
CN110344293A
CN110344293A CN201910768750.6A CN201910768750A CN110344293A CN 110344293 A CN110344293 A CN 110344293A CN 201910768750 A CN201910768750 A CN 201910768750A CN 110344293 A CN110344293 A CN 110344293A
Authority
CN
China
Prior art keywords
grinding
connect
actuator
mounting base
steel rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910768750.6A
Other languages
Chinese (zh)
Inventor
陈伟国
袁泰北
邹良甫
冯伟
曹登高
郭仕柒
高成钢
周文才
李良栋
袁巍
张小路
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Guangzhou Group Co Ltd
Guangzhou Public Works Overhaul Section of China Railway Guangzhou Group Co Ltd
Original Assignee
China Railway Guangzhou Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Guangzhou Group Co Ltd filed Critical China Railway Guangzhou Group Co Ltd
Priority to CN201910768750.6A priority Critical patent/CN110344293A/en
Publication of CN110344293A publication Critical patent/CN110344293A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B31/00Working rails, sleepers, baseplates, or the like, in or on the line; Machines, tools, or auxiliary devices specially designed therefor
    • E01B31/02Working rail or other metal track components on the spot
    • E01B31/12Removing metal from rails, rail joints, or baseplates, e.g. for deburring welds, reconditioning worn rails
    • E01B31/17Removing metal from rails, rail joints, or baseplates, e.g. for deburring welds, reconditioning worn rails by grinding

Abstract

The invention discloses a kind of steel rail welding lines to measure grinding device comprising master controller, height adjustment mechanism and grinding head, height adjustment mechanism and master controller are electrically connected;Grinding head includes mounting base, actuator, grinding tool and measurement component, mounting base is connect with height adjustment mechanism, mounting base offers mounting hole, and actuator wears mounting hole and connect with mounting base, and grinding tool is connect with actuator, measurement component is connect with mounting base, measuring component includes positioning case and infrared range-measurement system, and positioning case is connect with mounting base, and infrared range-measurement system is set to the inner cavity of positioning case, infrared range-measurement system and master controller are electrically connected, and infrared range-measurement system is used to measure the overlap height on rail.Above-mentioned steel rail welding line measures grinding device, is measured by infrared range-measurement system to overlap height, so that master controller adjusts the height of grinding head, to realize the adjusting to steel rail grinding depth, improves the grinding effect of rail, ensure that the safety traffic of train.

Description

Steel rail welding line measures grinding device
Technical field
The present invention relates to technical fields of mechanical processing, measure grinding device more particularly to a kind of steel rail welding line.
Background technique
The rail full-length of steel mill's production is 25 meters or 100 meters, the rail transporting of full-length to rail welding base Afterwards, rail welding is linked to be 500 meters of long gapless rails, then transports and is laid in railway line, when railway line scene is laid with 500 meters of gapless lines are successively welded with special equipment again and are linked to be all fronts gapless rail, mechanical connect all is not present in any position of rail The slit connect, when train operation, are very steady.Rail forms weld seam, weldering when welding with welding the base of the rail at every two rail weldings Seam thickness is higher than Rail Surface and forms the overlap for protruding from Rail Surface, and overlap must polish off, form smooth weld seam, make to weld Seam and weld seam or so rail are all smooth excessive, and smoothly excessively must also reach Technical specifications requirement could form qualified weldering Seam, can just make that train operation is steady, operational safety.
However, traditional rail grinding machine for grinding rails when polishing rail section, mainly passes through the polishing time of setting device Or scheduled grinding depth eliminates the overlap of commissure, due to the height of overlap and uneven, is filled using traditional steel rail grinding Setting treated, easily there is polishing excessively in commissure, causes weld seam to be ground and loses, weld seam is unqualified, needs to do over again whole 500 meters long The welding and polishing of rail cause greatly to waste;Or there is polishing amount deficiency, commissure still remains a large amount of overlaps, needs more Secondary polishing, reduces production efficiency.
Summary of the invention
Based on this, it is necessary to for the technical problem of grinding effect difference, provide a kind of steel rail welding line measurement grinding device.
A kind of steel rail welding line measurement grinding device, it includes master controller, height adjustment which, which measures grinding device, Mechanism and grinding head, height adjustment mechanism are electrically connected with master controller and are fixedly connected with outside;Grinding head include mounting base, Actuator, grinding tool and measurement component, mounting base are connect with height adjustment mechanism, and mounting base offers mounting hole, and actuator is worn Mounting hole is simultaneously connect with mounting base, and grinding tool is connect with actuator, and grinding tool measures component and mounting base for polishing rail Connection, measurement component includes positioning case and infrared range-measurement system, and positioning case is connect with mounting base, and infrared range-measurement system is set to positioning case Inner cavity, infrared range-measurement system and master controller be electrically connected, and infrared range-measurement system is used to measure the overlap height on rail.
Mounting base includes fixed plate and limited block in one of the embodiments, and fixed plate is connect with height adjustment mechanism, Limited block is connect with fixed plate, and fixed plate offers a semicircle through slot, and limited block offers another semicircle through slot, two semicircular Shape through slot is connected to and constitutes mounting hole.
Actuator is double end spindle motor in one of the embodiments, and the quantity of grinding tool is two, a grinding tool and double end One end of spindle motor connects, and another grinding tool is connect with the other end of double end spindle motor.
Grinding head further includes protecting crust in one of the embodiments, and protecting crust wears actuator and surrounds grinding tool, protection Shell offers polishing notch, and polishing notch corresponds to rail.
Grinding head further includes actuator shell in one of the embodiments, actuator shell coat actuator and with peace Seat connection is filled, guide groove is offered in actuator shell, the setting of guide groove spiral surrounding actuator, guide groove is for being passed through cooling water.
Grinding head further includes cold water pipe in one of the embodiments, and cold water pipe is installed on the inner cavity of actuator shell simultaneously Spiral surrounding actuator.
Grinding head further includes bobbin winder bracket in one of the embodiments, and bobbin winder bracket is connect with mounting base, and bobbin winder bracket offers Several through-holes, through-hole is for wearing cold water pipe and all kinds of cables.
Grinding head further includes grinding tool fixing piece in one of the embodiments, and grinding tool has turn hole, and grinding tool fixing piece is worn Turn hole is simultaneously connect with grinding tool and actuator respectively.
Positioning case includes container and dodge gate in one of the embodiments, and infrared range-measurement system is set to container, is held It sets box and offers opening, the edge connection of dodge gate and opening.
Measurement component further includes minitype cylinder in one of the embodiments, and minitype cylinder is set to container, miniature gas For being connected to external compression air pump, the output end of minitype cylinder is connect the input terminal of cylinder with dodge gate.
Above-mentioned steel rail welding line measures grinding device, by installing infrared range-measurement system in mounting base, when grinding tool stops polishing When, the data information transfer of the overlap that infrared range-measurement system is measured, and will test to the overlap of commissure height to master control Device processed, so that height of the master controller to height adjustment mechanism is adjusted, thus realize the adjusting to steel rail grinding depth, Occur in this way, avoiding the too deep or excessively shallow situation of steel rail grinding depth, the grinding effect of rail is improved, to ensure that fire The safety traffic of vehicle.
Detailed description of the invention
Fig. 1 is the structural schematic diagram that steel rail welding line measures grinding device in one embodiment;
Fig. 2 is the structural schematic diagram of grinding head in one embodiment;
Fig. 3 is the decomposition texture schematic diagram of grinding head in one embodiment;
Fig. 4 is the schematic diagram of the section structure of the actuator shell and actuator positional relationship in one embodiment;
Fig. 5 is the schematic diagram of the section structure of the actuator shell and actuator positional relationship in another embodiment;
Fig. 6 is the structural schematic diagram of positioning case in one embodiment;
Fig. 7 is the decomposition texture schematic diagram of positioning case in one embodiment;
Fig. 8 is the structural schematic diagram of rail clamp in one embodiment.
Specific embodiment
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, with reference to the accompanying drawing to the present invention Specific embodiment be described in detail.Many details are explained in the following description in order to fully understand this hair It is bright.But the invention can be embodied in many other ways as described herein, those skilled in the art can be not Similar improvement is done in the case where violating intension of the present invention, therefore the present invention is not limited by the specific embodiments disclosed below.
Also referring to Fig. 1 to Fig. 3, the present invention provides a kind of steel rail welding lines to measure grinding device 10, the steel rail welding line It measures grinding device 10 and includes master controller 100, height adjustment mechanism 200 and grinding head 300, height adjustment mechanism 200 and master Controller 100 is electrically connected and is fixedly connected with outside.Grinding head 300 include mounting base 310, actuator 320, grinding tool 330 and Component 340 is measured, mounting base 310 is connect with height adjustment mechanism 200, and mounting base 310 offers mounting hole 311, actuator 320 It wears mounting hole 311 and is connect with mounting base 310, grinding tool 330 is connect with actuator 320, and grinding tool 330 is for playing rail Mill, measurement component 340 are connect with mounting base 310, and measurement component 340 includes positioning case 341 and infrared range-measurement system 342, positioning case 341 connect with mounting base 310, and infrared range-measurement system 342 is set to the inner cavity of positioning case 341, infrared range-measurement system 342 and master controller 100 are electrically connected, and infrared range-measurement system 342 is used to measure the overlap height on rail.
Above-mentioned steel rail welding line measures grinding device 10, by installing infrared range-measurement system 342 in mounting base 310, works as grinding tool When 330 stopping polishing, the data for the overlap that infrared range-measurement system 342 is measured to the overlap height of commissure, and be will test Information is transferred to master controller 100, so that height of the master controller 100 to height adjustment mechanism 200 is adjusted, thus real Now to the adjusting of steel rail grinding depth, occurs in this way, avoiding the too deep or excessively shallow situation of steel rail grinding depth, improve rail Grinding effect, to ensure that the safety traffic of train.
The working principle of above-mentioned steel rail welding line measurement grinding device are as follows: actuator 320 connects under the action of master controller 100 High speed rotation behind energization source, and the grinding tool 330 being attached thereto is driven quickly to rotate, at the same time, master controller 100 is adjusted to height It saves mechanism 200 and issues instruction, control height adjustment mechanism 200 is acted with predetermined path of movement.That is, height adjustment mechanism 200 drive grinding heads 300 move closer to the overlap position of commissure, and are polished with scheduled grinding depth overlap, such as This, the grinding tool 330 of rotation contacts with the overlap of commissure and generates shearing force to overlap, so that overlap is broken, to eliminate weldering The polishing to rail is realized in overlap at seam.After polishing operation of rail, work of the infrared range-measurement system 342 in master controller 100 Infrared light is issued with lower starting, and to rail, infrared light reflects after reaching overlap position, and the infrared light of reflection is returned along original road It is back to infrared range-measurement system 342 and is received by infrared range-measurement system 342.Infrared range-measurement system 342 detects infrared light and connects from reflection is issued to The time difference of receipts, and the information is transferred to master controller 100, it is timely according to the spread speed of infrared light by master controller 100 Between information carry out operation, to obtain each position of overlap to the distance of infrared range-measurement system 342, and then extrapolate the height of remaining overlap Degree, subsequent master controller 100 control height adjustment mechanism 200 according to the elevation information of remaining overlap again and act, and adjust height Saving mechanism 200 drives grinding head 300 to carry out secondary polishing to rail, until completely removing the overlap on rail.It is to be understood that Cooperate the feedback tune, it can be achieved that steel rail grinding operation by master controller 100, height adjustment mechanism 200 and grinding head 300 Section, to improve the efficiency of steel rail grinding operation and promote grinding effect.
Master controller 100 is acted for controlling height adjustment mechanism 200 and grinding head 300, to realize 300 height of grinding head Adjusting and grinding tool 330 quick rotation, in addition, master controller 100 is also used to control the movement of infrared range-measurement system 342, thus real Now to the measurement of overlap height.In one embodiment, steel rail welding line measurement grinding device further includes power distribution cabinet, and master controller 100 is received It is dissolved in power distribution cabinet, prevents other staff from accidentally touching master controller 100, to guarantee being normally carried out for steel rail grinding operation.
Height adjustment mechanism 200 carries out installation positioning to grinding head 300, in addition, height is adjusted for clamping grinding head 300 Section mechanism 200 adjusts oneself height and horizontal position also under the control of master controller 100, and then drives grinding head 300 close Or far from rail, to realize the polishing operation of rail.In one embodiment, height adjustment mechanism 200 is manipulator.Preferably, high Degree regulating mechanism 200 is six shaft mechanical arms, which is fixed on facility floor, the six shaft mechanicals arm and master controller 100 be electrically connected and its end connect with grinding head 300.During the polishing operation of rail, master controller 100 controls six axis Each axis of mechanical arm moves, the spatial position of each common end for adjusting six shaft mechanical arms of axis cooperation, to realize to grinding head The adjustment of 300 positions and grinding head 300 to steel rail grinding depth.
Grinding head 300, to improve the flatness of Rail Surface, reduces rail pair for polishing the overlap of commissure The frictional force of train wheel rim to extend the service life of train wheel rim, and ensures the safety traffic of train.Please refer to Fig. 1, figure 2 and Fig. 3, mounting base 310 are connect with height adjustment mechanism 200, it is preferred that the end of height adjustment mechanism 200 has connector 210, mounting base 310 is spirally connected with connector 210.In this way, unclamping mounting base when steel rail welding line measurement grinding device breaks down Screw between 310 and connector 210 can remove grinding head 300, in favor of grinding head from height adjustment mechanism 200 The progress of 300 upkeep operations.In one embodiment, mounting base 310 includes fixed plate 312 and limited block 313, fixed plate 312 and height It spends regulating mechanism 200 to connect, it is preferred that fixed plate 312 is spirally connected with connector 210.Limited block 313 and fixed plate 312 are detachable Connection, it is preferred that limited block 313 is spirally connected with fixed plate 312.Fixed plate 312 offers a semicircle through slot, limited block 313 Another semicircle through slot is offered, two halves circle through slot is connected to and constitutes mounting hole 311.By making limited block 313 and fixed plate 312 dismountable connections can use lower position block 313, replace to actuator 320 when actuator 320, which damages, to fail, and drop The low difficulty of device maintenance activity, improves maintenance efficiency.In one embodiment, there are two limited blocks for the setting of mounting base 310 313, fixed plate 312 is U-shaped structure, and the both ends of fixed plate 312 respectively offer a semicircle through slot, one end of fixed plate 312 with The connection of one limited block 313, the semicircle through slot of the one of fixed plate 312 are connected to the semicircle through slot of the limited block 313 and constitute one Mounting hole 311, the other end of fixed plate 312 are connect with another limited block 313, another semicircle through slot and this of fixed plate 312 The semicircle through slot of limited block 313 is connected to and constitutes another mounting hole 311.In this way, one end of actuator 320 wears a mounting hole 311 and connect with one end of mounting base 310, the other end of actuator 320 wear another mounting hole 311 and with mounting base 310 Other end connection, in this way, holding power suffered by each section is more uniform on actuator 320, actuator 320 in mounting base 310 not It easily shakes, to improve the stability that actuator 320 is connect with mounting base 310.
Actuator 320 is used for the high speed rotation under the control of master controller 100, and grinding tool 330 is driven to rotate, with realization pair The polishing of rail.Referring to Fig. 3, actuator 320 is double end spindle motor in an embodiment, the quantity of grinding tool 330 is two, One grinding tool 330 is connect with one end of double end spindle motor, and another grinding tool 330 is connect with the other end of double end spindle motor.It can be with It is interpreted as, two grinding tools 330 of grinding head 300 rotate synchronously under the driving of double end spindle motor, and simultaneously to commissure Overlap is polished, in this way, the area for the overlap that can be polished in 300 unit time of grinding head greatly increases, to improve steel The grinding efficiency of rail weld measurement grinding device.
In one embodiment, grinding head 300 further includes grinding tool fixing piece 350, and grinding tool 330 has turn hole 331, grinding tool fixing piece 350 wear turn hole 331 and connect respectively with grinding tool 330 and actuator 320.By the way that grinding tool fixing piece 350 is arranged, grinding tool can be improved 330 stability connecting with actuator 320, prevent grinding tool 330 from sliding from actuator 320, and then injure operating personnel or factory by a crashing object Equipment in room, to guarantee the safety of steel rail grinding operation.In one embodiment, grinding head 300 further includes protecting crust 360, is prevented Protective case 360 is arranged in actuator 320 and surrounds grinding tool 330, and protecting crust 360 offers polishing notch 361, and polishing notch 361 is right Answer rail.During the polishing operation of rail, height adjustment mechanism 200 drives grinding head 300 to move, and makes protecting crust 360 Polishing notch 361 be aligned commissure overlap, so that grinding tool 330 is contacted with overlap, and then polish overlap.Pass through Protecting crust 360 is set, can prevent operating personnel from accidentally touching grinding tool 330 or external equipment shock grinding tool 330, guarantee the people of operating personnel Body safety and property safety, to further increase the safety of steel rail grinding operation.
Referring to Fig. 4, grinding head 300 further includes actuator shell 370 in an embodiment, the cladding of actuator shell 370 is driven Moving part 320 is simultaneously connect with mounting base 310, and guide groove 371,371 spiral surrounding actuator of guide groove are offered in actuator shell 370 320 settings, guide groove 371 is for being passed through cooling water.In the operation process of actuator 320, cooling is continually fed into guide groove 371 Water, in this way, 320 continuous running of actuator is sent out thermogenetic, heat, which will generate heat with cooling water, exchanges, it can be understood as, driving The temperature of part 320 is gradually reduced, and the temperature of cooling water slowly increases, and the cooling water of heating is exported by the output end of guide groove 371, Cool down that is the input terminal of guide groove 371 is endlessly passed through cooling water to actuator 320, prevents 320 mistake of actuator Heat causes its internal wiring ablation, to guarantee the normal use of actuator 320, and then extends the service life of actuator 320, drop The use cost of low steel rail welding line measurement grinding device.In addition, can be increased by the way that 371 spiral surrounding actuator 320 of guide groove is arranged The heat exchange area of big cooling water and actuator 320, to accelerate the exchange rate of cooling water Yu actuator 320, Jin Erti Rise the cooling efficiency of actuator 320.Referring to Fig. 5, grinding head 300 further includes cold water pipe 380, cold water pipe 380 in an embodiment It is installed on the inner cavity of actuator shell 370 and spiral surrounding actuator 320.Preferably, cold water pipe 380 is fixed on drive by bail Moving part shell 370.Cold water pipe 380 is for being continually fed into cooling water, to realize the cooling to actuator 320.By the way that cold water is arranged Pipe 380 can reduce erosion of the cooling water to guide groove 371, and when 380 broken invalid of cold water pipe, can be by cold water pipe 380 from driving It removes on part shell 370 and is individually replaced, without replacing entire actuator shell 370, advantageously reduce steel rail welding line survey Measure the use cost of grinding device.
In one embodiment, grinding head 300 further includes bobbin winder bracket 390, and bobbin winder bracket 390 is connect with mounting base 310, bobbin winder bracket 390 offer several through-holes 391, and through-hole 391 is for wearing cold water pipe 380 and all kinds of cables.It is cold by the way that bobbin winder bracket 390 is arranged Water pipe 380 wears the through-hole 391 of bobbin winder bracket 390 with all kinds of cables respectively and connect with outer tank or master controller 100, this Sample, each route beam are not easy solderless wrapped connection on height adjustment mechanism 200 at one, are conducive to the progress with line maintenance operation.Equally , in steel rail grinding operation process, operating personnel is not easy accidentally short cable or water route, and the stable connection between each component guarantees Effective progress of steel rail grinding operation.
Positioning case 341 is for installing infrared range-measurement system 342, to realize that infrared range-measurement system 342 is determined in mounting base 310 Position.Also referring to Fig. 3, Fig. 6 and Fig. 7, in an embodiment, positioning case 341 includes container 341a and dodge gate 341b, infrared Rangefinder 342 is set to container 341a, and container 341a offers the edge of opening 341c, dodge gate 341b and opening 341c Dismountable connection.Preferably, dodge gate 341b with opening 341c edge hinge connect, dodge gate 341b for unlatching or It is closed opening 341c.When opening 341c is opened, the infrared ray that infrared range-measurement system 342 generates can carry out ranging to overlap.It is logical Setting dodge gate 341b is crossed, infrared range-measurement system 342 can be protected, prevent the overlap generated in steel rail grinding operation process broken Bits splash down on infrared range-measurement system 342, in turn result in the damage of infrared range-measurement system 342.During the polishing operation of rail, activity Door 341b and the edge of opening 341c abut against, at this point, infrared range-measurement system 342 is encapsulated in container 341a and dodge gate 341b In the closed area of composition, hurt infrared range-measurement system 342 to prevent overlap clast from splashing.After steel rail grinding operation, opening activity Door 341b, infrared range-measurement system 342 excite infrared light under the control of master controller 100, which is opened by container 341a's Mouth 341c is pierced by, to realize the measurement to the overlap height of commissure.
In one embodiment, measurement component 340 further includes minitype cylinder 343, and minitype cylinder 343 is set to container 341a, For being connected to external compression air pump, the output end and dodge gate 341b of minitype cylinder 343 connect the input terminal of minitype cylinder 343 It connects.After polishing operation of rail, master controller 100 controls actuator 320 and shuts down, while controlling minitype cylinder 343 air inlets, in this way, the input terminal of minitype cylinder 343 by external compression air pump access compressed air, with compressed air be passed through it is micro- The cylinder barrel of type cylinder 343, the gas pressure intensity in cylinder barrel are gradually increased, and compressed air is by the piston and piston to minitype cylinder 343 Bar generates thrust, so that the piston and piston rod of minitype cylinder 343 are gradually distance from the input terminal of cylinder barrel, in other words, piston rod will Dodge gate 341b is pushed, rotates dodge gate 341b centered on connecting portion of the dodge gate 341b with container 341a, to disappear Except the blocking of the dodge gate 341b infrared light issued to infrared range-measurement system 342, guarantee survey of the infrared range-measurement system 342 to overlap height Measure effective progress of operation.After master controller 100 receives the temporal information that infrared range-measurement system 342 transmits, master controller 100 is controlled Minitype cylinder 343 is deflated, in this way, the compressed air in cylinder barrel is discharged by the input terminal of minitype cylinder 343, the gas pressure in cylinder barrel It gradually decreases by force, that is to say, that compressed air is gradually reduced the thrust of piston and piston rod, when the air pressure in cylinder barrel is lower than ring When the air pressure of border, piston drives piston rod and dodge gate under the action of negative pressure gradually to the input end motion of minitype cylinder 343 341b resets, until the edge of the opening 341c of dodge gate 341b and container 341a abuts against, again to infrared range-measurement system 342 It is packaged protection.
It should be noted that steel rail welding line measurement grinding device further includes rail clamp 400, rail clamp 400 is for pressing from both sides Rail to be polished is held, and treats rail grinding and is positioned.Rail clamp 400 is set under the side of height adjustment mechanism 200 Side, in order to which the grinding tool 330 on the grinding head 300 that is mounted on height adjustment mechanism 200 is directed at the weld seam of rail, to realize Accurate polishing to overlap.Referring again to Fig. 8, in an embodiment, rail clamp 400 includes mounting rack 410, support base 420, oil Cylinder 430 and grip block 440, support base 420 are set on mounting rack 410, and there are two locating part 421, oil cylinders for the tool of support base 420 430 connect with a locating part 421, and the output end of oil cylinder 430 is connect with grip block 440, grip block 440 and another locating part There is grasping part 450, for grasping part 450 for accommodating to rail grinding, grip block 440 and support base 420 are common between 421 For clamping to rail grinding.In the installation process of rail, external oil pump station accesses liquid to oil cylinder 430, in this way, liquid exists The piston that oil cylinder 430 will be pushed in the cylinder barrel of oil cylinder 430, correspondingly, the piston rod of oil cylinder 430 will be into one under the drive of piston Step pushes grip block 440, abuts against grip block 440 with the edge to rail grinding being contained in grasping part 450, with Grip block 440 to the continuous close of rail grinding, to rail grinding respectively with the inner surface of support base 420 and grip block 440 It abuts against, and is limited in grasping part 450 under the constraint of the two, to realize that the clamping to rail grinding is fixed.One is real It applies in example, it further includes disposal box that steel rail welding line, which measures grinding device, and disposal box is set to the lower section to rail grinding, is used to hold The overlap waste material generated during steel rail grinding is connect, the waste material for preventing overlap polishing from generating is spread in workshop, to reduce overlap Injury of the waste material to operating personnel.
Each technical characteristic of embodiment described above can be combined arbitrarily, for simplicity of description, not to above-mentioned reality It applies all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, all should be considered as described in this specification.
The embodiments described above only express several embodiments of the present invention, and the description thereof is more specific and detailed, but simultaneously It cannot therefore be construed as limiting the scope of the patent.It should be pointed out that coming for those of ordinary skill in the art It says, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to protection of the invention Range.Therefore, the scope of protection of the patent of the invention shall be subject to the appended claims.

Claims (10)

1. a kind of steel rail welding line measures grinding device, which is characterized in that including master controller, height adjustment mechanism and grinding head,
The height adjustment mechanism is electrically connected with the master controller and is fixedly connected with outside;
The grinding head includes mounting base, actuator, grinding tool and measurement component, and the mounting base and the height adjustment mechanism connect It connects, the mounting base offers mounting hole, and the actuator wears the mounting hole and connect with the mounting base, the grinding tool It is connect with the actuator, for polishing rail, the measurement component is connect the grinding tool with the mounting base, described Measuring component includes positioning case and infrared range-measurement system, and the positioning case is connect with the mounting base, the infrared range-measurement system setting In the inner cavity of the positioning case, the infrared range-measurement system and the master controller are electrically connected, and the infrared range-measurement system is for surveying Measure the overlap height on the rail.
2. steel rail welding line according to claim 1 measures grinding device, which is characterized in that the mounting base includes fixed plate And limited block, the fixed plate are connect with the height adjustment mechanism, the limited block is connect with the fixed plate, the fixation Plate offers a semicircle through slot, and the limited block offers another semicircle through slot, the two semicircle through slot connections and structure At the mounting hole.
3. steel rail welding line according to claim 1 measures grinding device, which is characterized in that the actuator is double end main shaft Motor, the quantity of the grinding tool are two, and a grinding tool is connect with one end of the double end spindle motor, another grinding tool It is connect with the other end of the double end spindle motor.
4. steel rail welding line according to claim 1 measures grinding device, which is characterized in that the grinding head further includes protection Shell, the protecting crust wear the actuator and surround the grinding tool, and the protecting crust offers polishing notch, the polishing slot The corresponding rail of mouth.
5. steel rail welding line according to claim 1 measures grinding device, which is characterized in that the grinding head further includes driving Part shell, the actuator shell coat the actuator and connect with the mounting base, offer in the actuator shell Guide groove, the setting of actuator described in the guide groove spiral surrounding, the guide groove is for being passed through cooling water.
6. steel rail welding line according to claim 5 measures grinding device, which is characterized in that the grinding head further includes cold water Pipe, the cold water pipe are installed on actuator described in the inner cavity of the actuator shell and spiral surrounding.
7. steel rail welding line according to claim 6 measures grinding device, which is characterized in that the grinding head further includes coiling Frame, the bobbin winder bracket are connect with the mounting base, and the bobbin winder bracket offers several through-holes, and the through-hole is described cold for wearing Water pipe and all kinds of cables.
8. steel rail welding line according to claim 1 measures grinding device, which is characterized in that the grinding head further includes grinding tool Fixing piece, the grinding tool have turn hole, the grinding tool fixing piece wear the turn hole and respectively with the grinding tool and the driving Part connection.
9. steel rail welding line according to claim 1 measures grinding device, which is characterized in that the positioning case includes container And dodge gate, the infrared range-measurement system are set to the container, the container offers opening, the dodge gate with it is described The edge of opening connects.
10. steel rail welding line according to claim 9 measures grinding device, which is characterized in that the measurement component further includes Minitype cylinder, the minitype cylinder are set to the container, and the input terminal of the minitype cylinder is used for and external compression air pump Connection, the output end of the minitype cylinder are connect with the dodge gate.
CN201910768750.6A 2019-08-20 2019-08-20 Steel rail welding line measures grinding device Pending CN110344293A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910768750.6A CN110344293A (en) 2019-08-20 2019-08-20 Steel rail welding line measures grinding device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910768750.6A CN110344293A (en) 2019-08-20 2019-08-20 Steel rail welding line measures grinding device

Publications (1)

Publication Number Publication Date
CN110344293A true CN110344293A (en) 2019-10-18

Family

ID=68180818

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910768750.6A Pending CN110344293A (en) 2019-08-20 2019-08-20 Steel rail welding line measures grinding device

Country Status (1)

Country Link
CN (1) CN110344293A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114318975A (en) * 2020-10-11 2022-04-12 华东交通大学 Automatic grinding method for turnout
CN114919000A (en) * 2022-04-12 2022-08-19 苏州钜锋砂带研磨有限公司 Size adjusting method for cutting tool of vertical and horizontal abrasive paper cutting machine

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0002177A1 (en) * 1977-11-28 1979-06-13 Franz Plasser Bahnbaumaschinen-Industriegesellschaft m.b.H. Rail grinding machine for grinding irregularities off the running surface of rails
CN104889865A (en) * 2015-06-10 2015-09-09 长兴捷明机械有限公司 Double-ended grinding machine
CN207189366U (en) * 2017-09-12 2018-04-06 重庆艾斯拉特科技有限公司 A kind of sanding apparatus for handware
CN108481120A (en) * 2018-04-23 2018-09-04 宁波汇智恒动自动化科技有限公司 A kind of flexibility grinding device and flexible polishing system
CN109056434A (en) * 2018-10-19 2018-12-21 上海瑞纽机械股份有限公司 A kind of steel rail welding line milling-grinding equipment
CN208923989U (en) * 2018-11-29 2019-05-31 佛山市金台荟电机有限公司 A kind of double end electric spindle motor of numerical control machining center
CN210712398U (en) * 2019-08-20 2020-06-09 中国铁路广州局集团有限公司广州工务大修段 Steel rail welding seam measuring and polishing device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0002177A1 (en) * 1977-11-28 1979-06-13 Franz Plasser Bahnbaumaschinen-Industriegesellschaft m.b.H. Rail grinding machine for grinding irregularities off the running surface of rails
CN104889865A (en) * 2015-06-10 2015-09-09 长兴捷明机械有限公司 Double-ended grinding machine
CN207189366U (en) * 2017-09-12 2018-04-06 重庆艾斯拉特科技有限公司 A kind of sanding apparatus for handware
CN108481120A (en) * 2018-04-23 2018-09-04 宁波汇智恒动自动化科技有限公司 A kind of flexibility grinding device and flexible polishing system
CN109056434A (en) * 2018-10-19 2018-12-21 上海瑞纽机械股份有限公司 A kind of steel rail welding line milling-grinding equipment
CN208923989U (en) * 2018-11-29 2019-05-31 佛山市金台荟电机有限公司 A kind of double end electric spindle motor of numerical control machining center
CN210712398U (en) * 2019-08-20 2020-06-09 中国铁路广州局集团有限公司广州工务大修段 Steel rail welding seam measuring and polishing device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114318975A (en) * 2020-10-11 2022-04-12 华东交通大学 Automatic grinding method for turnout
CN114919000A (en) * 2022-04-12 2022-08-19 苏州钜锋砂带研磨有限公司 Size adjusting method for cutting tool of vertical and horizontal abrasive paper cutting machine

Similar Documents

Publication Publication Date Title
CN110344293A (en) Steel rail welding line measures grinding device
CN109187249B (en) On-machine vision detection method and detection device for rotary cutter
CN100357055C (en) Agitation friction welding system and corralation agitation friction welding assembly, controller and method
GB2174065A (en) Remotely operable positioning and carrier apparatus
CN103192159A (en) Workstation system with welding robots for radar structural parts
CN104941961A (en) Robot for cleaning metal pipeline by laser light
CN109304604A (en) A kind of locomotive gear hub bolt automatic screwing-down
CN114102410B (en) Full-automatic polishing workstation
CN103741135A (en) Device for remanufacturing metal surface and application method of device
CN210712398U (en) Steel rail welding seam measuring and polishing device
CN111958114A (en) Four-axis optical fiber laser welding equipment
CN105538137A (en) Automatic pipe fitting feeding and grinding device
CN204101513U (en) Contactless hollow-axle ultrasonic flaw-detecting machine
US9899109B2 (en) Treatment apparatus and method for waste steam generator, and installation method of treatment apparatus for waste steam generator
WO2024045598A1 (en) Intelligent submerged arc welding method for stainless-steel composite plate
CN104962906A (en) Power-driven laser field repair system
CN210677455U (en) Mechanical arm for welding metal screw
CN212443745U (en) Four-axis optical fiber laser welding equipment
CN208713091U (en) A kind of numerical-controlled gantry cutting machine with anti-drop function
CN210215546U (en) Laser cladding head
CN105563310A (en) Pipe grinding equipment
CN220056966U (en) High Wen Zhifeng steel pipeline heat treatment device
KR20210112494A (en) ATC Mounted Broaching Machine using Fog Computing
CN105538139A (en) Automatic loading and grinding equipment for pipe fittings
CN205230567U (en) Allow iron plate capotasto laser heat treatment device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination