CN110318543A - The building construction method that integration pours - Google Patents

The building construction method that integration pours Download PDF

Info

Publication number
CN110318543A
CN110318543A CN201910624887.4A CN201910624887A CN110318543A CN 110318543 A CN110318543 A CN 110318543A CN 201910624887 A CN201910624887 A CN 201910624887A CN 110318543 A CN110318543 A CN 110318543A
Authority
CN
China
Prior art keywords
concrete
building
wall
post
casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910624887.4A
Other languages
Chinese (zh)
Inventor
郭刚
李强
哈智瀚
柴大智
刘辰
武杏蕾
缑栋栋
左亚斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Luqiao Hongsheng Housing Construction And Installation Engineering Co Ltd
Original Assignee
Gansu Luqiao Hongsheng Housing Construction And Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu Luqiao Hongsheng Housing Construction And Installation Engineering Co Ltd filed Critical Gansu Luqiao Hongsheng Housing Construction And Installation Engineering Co Ltd
Priority to CN201910624887.4A priority Critical patent/CN110318543A/en
Publication of CN110318543A publication Critical patent/CN110318543A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Abstract

The present invention relates to the technical fields of housing construction, disclose the building construction method that integration pours, specific steps include the following: S1: basement process: floating sand and mud in place cleaning, mechanical excavation, smooth is carried out with excavator, loading machine, when to apart from designed elevation 250-300m, it is manually smooth again and be compacted with road roller, to casting concrete;S2: casting concrete: after casting of concrete in mass, moisturizing, temperature control measure are used in Ying 10-12h, the table temperature difference should not exceed 25 DEG C in concrete, and concreting body surface face and atmosphere temperature-difference should not exceed 20 DEG C.The present invention is provided with raft board post poured band, open drain, external wall construction post-cast strip, floor slab back casting band and beams of concrete post-cast strip, further enhance the integral waterproofing effect of building, in addition full cast-in-situ steel reinforced concrete shear wall structure is used, main building uses flat raft foundation, supporting course is gravel layer, reach good anti seismic efficiency, improves the safety of building.

Description

The building construction method that integration pours
Technical field
The invention patent relates to the technical field of housing construction, the building poured in particular to integration is applied Work method.
Background technique
The construction method in existing residential house mainly includes construction method based on reinforced concrete structure and is based on The construction method of steel construction.In the construction method based on reinforced concrete structure, generally construct first after the completion of building foundation Then frame structure fills brick in the frame, and in the interior lateral surface of brick wall one layer of cement of construction.
Its major defect is:
The first, construction program is complicated, and the amount of labour is big, long in time limit, generates a large amount of building wastes, and since scene is applied Work amount is difficult to realize stringent quality control greatly.
The second, the concrete of whole building body is implemented to be poured respectively in different construction parts, independent mutually after pouring, it is difficult to Ensure the integral strength of building, anti-seismic performance, sealing performance etc. are unsatisfactory.
Need room isolation, decorating inner and external walls and isothermal holding after third, main body construction, house construction period compared with Long, construction cost further increases.
The present invention provides a kind of building construction method that integration pours, can high efficiency complete housing construction, and And the shock resistance and sealing performance of the building after completing are much better than the prior art.
Summary of the invention
The purpose of the present invention is to provide the building construction methods that integration pours, by preparing before constructing, pouring House is carried out integrated pouring construction by process, maintenance processes and construction post-processing step, which compares traditional construction The method duration can shorten one month, improve construction quality and efficiency, save a large amount of formwork cost, it is intended to solve existing skill The concrete of whole building body is implemented to be poured respectively in different construction parts in art, independent mutually after pouring, it is difficult to ensure to build The integral strength of object, the unsatisfactory problem such as anti-seismic performance, sealing performance.
The invention is realized in this way the building construction method that integration pours, specific steps include the following:
S1: basement process: floating sand and mud in place cleaning carry out mechanical excavation, smooth with excavator, loading machine, When to apart from designed elevation 250-300m, then it is manually smooth and be compacted with road roller, to casting concrete;
S2: after casting of concrete in mass, moisturizing, temperature control measure, concrete casting concrete: are used in Ying 10-12h In the table temperature difference should not exceed 25 DEG C, concreting body surface face and atmosphere temperature-difference should not exceed 20 DEG C, and to concreting Body is to curing time in 14-20d;
S3: the processing of raft board post poured band: multiple raft board post poured bands are uniformly arranged on ground, raft board post poured band bottom end is set Bottom cushion is set, makes to form good separating effect, baseplate reinforcing bar is set on the bottom cushion, the baseplate reinforcing bar top Raft board post poured band top and lower part are provided with compensation reinforcing bar one, are provided with steel plate water stopper between two compensation reinforcing bars one One, the steel plate water stopper is first is that prevent the penetrating on raft board post poured band of underground water;
S4: open drain processing: respectively opening up a gutter in ground two sides, guarantees that draining is unobstructed, when the gutter It is made using raft slab muscle, and the depth that gutter is arranged, convenient for draining, is in addition stitched in outer Retaining wall in 200-250mm It is inserted into steel plate for sealing water in outer wall of basement body, rainwater is avoided to impregnate ground, will receive outer wall of basement body not with construction bottom plate Rainwater impregnates;
S5: the processing of external wall construction post-cast strip: building model is built, the bottom of exterior wall is provided with the horizontal steel of wall Muscle, compensation reinforcing bar two, two compensation reinforcing bars two opposite one are respectively set in two sides above and below the exterior wall above wall horizontal reinforcement Being horizontally disposed on the exterior wall of side has multiple steel plate water stoppers two, and the steel plate water stopper two avoids the rainwater of exterior wall outer wall from seeping Enter inside;
S6: floor slab back casting tape handling: after the completion of external wall construction, top surface carries out the fixed filling building of installation of template and support 800-1000mm is arranged in board post poured band, floor slab back casting bandwidth, the beams of concrete at floor slab back casting band respectively with building top bars, building Lower layer's reinforcing bar does not turn off.
S7: the processing of beams of concrete post-cast strip: beams of concrete post-cast strip is set in the two sides of floor slab back casting band, keeps former design strong It is closely knit that degree grade proposes higher leveled concreting, and carries out surface covering curing, before the casting concrete of beams of concrete post-cast strip Surface should be cleaned out, and arrange to concrete beam reinforcing, that is, complete pouring for integrated building house.
Further, the building setting is rectangular, and using full cast-in-situ steel reinforced concrete shear wall structure, main building is adopted With flat raft foundation, supporting course is gravel layer.
Further, in S3, when the raft board post poured band is constructed, Bottom Board Steel is ensured by setting supporting steel bar measure Muscle, two compensation reinforcing bar one position.
Further, before the casting concrete of beams of concrete post-cast strip, the template of both side plate and support must not be removed, with Accelerate to form after beams of concrete post-cast strip pours.
Further, in S2 before casting concrete, concrete preparation need to be first carried out, the concrete preparation is using receipts The cement of diminution, and take measures suitably to reduce cement consumption, should reduce to the greatest extent sandstone aggregate in concrete raw material containing mud Amount, coarse-fine aggregate clay content control within 2%.
Further, when concreting, reinforcement should be taken to vibrate, conserve and moist keeping measures concrete, it is appropriate to increase Curing time, must not shift to an earlier date demoulding, and concrete ambient relative humidity reaches 80-90%.
Further, before concrete setting, to prevent concrete surface from plasticity shrinking joint occur and because surface is quickly lost Desciccation crack caused by water should be smeared pressure 2~3 times using wooden float before concrete initial set.
Further, in S5, the side of the wall horizontal reinforcement is provided with one layer of waterproof roll, the waterproof roll The wall protective layer for protecting exterior wall is arranged in the side of material.
Further, the floor slab back casting band and beams of concrete post-cast strip are in construction, upstairs layer reinforcing bar and downstairs layer Between the reinforcing bar and top of concrete beam reinforcing is provided with steel wire, and concreting is on steel wire top.
Further, in S7, the upper middle side part of the concrete beam reinforcing is provided with Vierendeel girder, the Vierendeel girder it is upper Portion is poured for compensating the compensating concrete shunk.
Compared with prior art, the building construction method that integration provided by the invention pours, has following advantages:
1, house is carried out by integration by preparation, casting process, maintenance processes and construction post-processing step before constructing Pouring construction, the construction method can shorten one month than the conventional construction method duration, improve construction quality and efficiency, save A large amount of formwork cost, largely reduces construction cost, and there is preferable techno-economic effect and higher popularization to answer With value;
2, provided with being poured after raft board post poured band, open drain, external wall construction post-cast strip, floor slab back casting band and beams of concrete Band further enhances the integral waterproofing effect of building, in addition uses full cast-in-situ steel reinforced concrete shear wall structure, and main building uses Flat raft foundation, supporting course are gravel layer, have reached good anti seismic efficiency, improve the safety of building.
Detailed description of the invention
Fig. 1 is the structural representation for building construction method China and foreign countries' Retaining wall seam that integration provided by the invention pours Figure;
Fig. 2 is the structural schematic diagram of open drain in building construction method that integration provided by the invention pours;
Fig. 3 is the structural representation of floor slab back casting band in building construction method that integration provided by the invention pours Figure;
Fig. 4 is the structural representation of raft board post poured band in building construction method that integration provided by the invention pours Figure;
Fig. 5 is the structural representation of post-pouring belt of outer wall in building construction method that integration provided by the invention pours Figure;
Fig. 6 is that the structure of beams of concrete post-cast strip in building construction method that integration provided by the invention pours is shown It is intended to.
In figure: 1- outer wall of basement body, 2- construct bottom plate, 3- steel plate for sealing water, 4- raft slab muscle, 5- beams of concrete, the building 6- Layer reinforcing bar, 8- steel wire, 9- baseplate reinforcing bar, 10- compensation reinforcing bar one, 11- bottom cushion, 12- reinforcing bar stop downstairs by top bars, 7- Water band one, 13- compensation reinforcing bar two, 14- reinforcing bar waterstop two, 15- wall horizontal reinforcement, 16- waterproof roll, the protection of 17- wall Compensating concrete is poured after layer, 18- Vierendeel girder, 19- concrete beam reinforcing, 20-.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.
Realization of the invention is described in detail below in conjunction with specific embodiment.
The same or similar label correspond to the same or similar components in the attached drawing of the present embodiment;In description of the invention In, it is to be understood that if there is the orientation or positional relationship of the instructions such as term " on ", "lower", "left", "right" for based on attached drawing institute The orientation or positional relationship shown, is merely for convenience of description of the present invention and simplification of the description, rather than the dress of indication or suggestion meaning It sets or element must have a particular orientation, be constructed and operated in a specific orientation, therefore describe the use of positional relationship in attached drawing Language only for illustration, should not be understood as the limitation to this patent, for the ordinary skill in the art, can be with The concrete meaning of above-mentioned term is understood as the case may be.
Embodiment 1
Referring to Fig.1 shown in -6, the building construction method that pours of integration, specific steps include the following:
S1: basement process: floating sand and mud in place cleaning carry out mechanical excavation, smooth with excavator, loading machine, When to apart from designed elevation 250m, then it is manually smooth and be compacted with road roller, to casting concrete;
S2: casting concrete: after casting of concrete in mass, using moisturizing, temperature control measure in Ying 10h, in concrete The table temperature difference should not exceed 25 DEG C, and concreting body surface face and atmosphere temperature-difference should not exceed 20 DEG C, and to concreting body To curing time in 14d;
S3: the processing of raft board post poured band: multiple raft board post poured bands are uniformly arranged on ground, raft board post poured band bottom end is set Bottom cushion 11 is set, makes to form good separating effect, baseplate reinforcing bar 9, the baseplate reinforcing bar 9 is set on the bottom cushion 11 The raft board post poured band top and lower part on top are provided with compensation reinforcing bar 1, are provided between two compensation reinforcing bars 1 Steel plate water stopper 1, the steel plate water stopper 1 are to prevent the penetrating on raft board post poured band of underground water;
S4: open drain processing: respectively opening up a gutter in ground two sides, guarantees that draining is unobstructed, when the gutter It is made using raft slab muscle 4, and the depth that gutter is arranged is convenient for draining, in addition in the underground of outer Retaining wall seam in 200mm It is inserted into steel plate for sealing water 3 in outdoor wall 1, rainwater is avoided to impregnate ground, will receive outer wall of basement body 1 not with construction bottom plate 2 Rainwater impregnates;
S5: the processing of external wall construction post-cast strip: building model is built, the bottom of exterior wall is provided with wall horizontal reinforcement 15, compensation reinforcing bar 2 13, two compensation reinforcing bars 2 13 are respectively set in two sides above and below the exterior wall above wall horizontal reinforcement 15 Being horizontally disposed on the exterior wall of opposite side has multiple steel plate water stoppers 2 14, and the steel plate water stopper 14 2 avoids outside exterior wall The rainwater of wall penetrates into internal;
S6: floor slab back casting tape handling: after the completion of external wall construction, top surface carries out the fixed filling building of installation of template and support 800mm is arranged in board post poured band, floor slab back casting bandwidth, the beams of concrete 5 at floor slab back casting band respectively with building top bars 6, downstairs Layer reinforcing bar 7 does not turn off.
S7: the processing of beams of concrete post-cast strip: beams of concrete post-cast strip is set in the two sides of floor slab back casting band, keeps former design strong It is closely knit that degree grade proposes higher leveled concreting, and carries out surface covering curing, before the casting concrete of beams of concrete post-cast strip Surface should be cleaned out, and arrange to concrete beam reinforcing 19, that is, complete pouring for integrated building house.
When concreting, reinforcement should be taken to vibrate, conserve and moist keeping measures concrete, suitably increase curing time, Demoulding must not be shifted to an earlier date, concrete ambient relative humidity reaches 80%.
Before concrete setting, to prevent concrete surface from plasticity shrinking joint occur and because doing caused by the quick dehydration in surface Draw is stitched, and pressure should be smeared using wooden float 2 times before concrete initial set.
The side of the wall horizontal reinforcement 15 is provided with one layer of waterproof roll 16, the side of the waterproof roll 16 is set Set the wall protective layer 17 for protecting exterior wall.
The floor slab back casting band and beams of concrete post-cast strip are in construction, upstairs layer reinforcing bar 6 and downstairs between layer reinforcing bar 7 And the top of concrete beam reinforcing is provided with steel wire 8, concreting is on 8 top of steel wire.
In S7, the upper middle side part of the concrete beam reinforcing 19 is provided with Vierendeel girder 18, the top of the Vierendeel girder 18 It pours for compensating the compensating concrete 20 shunk.
Embodiment 2
Referring to Fig.1 shown in -6, the building construction method that pours of integration, specific steps include the following:
S1: basement process: floating sand and mud in place cleaning carry out mechanical excavation, smooth with excavator, loading machine, When to apart from designed elevation 280m, then it is manually smooth and be compacted with road roller, to casting concrete;
S2: casting concrete: after casting of concrete in mass, using moisturizing, temperature control measure in Ying 11h, in concrete The table temperature difference should not exceed 25 DEG C, and concreting body surface face and atmosphere temperature-difference should not exceed 20 DEG C, and to concreting body To curing time in 16d;
S3: the processing of raft board post poured band: multiple raft board post poured bands are uniformly arranged on ground, raft board post poured band bottom end is set Bottom cushion 11 is set, makes to form good separating effect, baseplate reinforcing bar 9, the baseplate reinforcing bar 9 is set on the bottom cushion 11 The raft board post poured band top and lower part on top are provided with compensation reinforcing bar 1, are provided between two compensation reinforcing bars 1 Steel plate water stopper 1, the steel plate water stopper 1 are to prevent the penetrating on raft board post poured band of underground water;
S4: open drain processing: respectively opening up a gutter in ground two sides, guarantees that draining is unobstructed, when the gutter It is made using raft slab muscle 4, and the depth that gutter is arranged is convenient for draining, in addition in the underground of outer Retaining wall seam in 230mm It is inserted into steel plate for sealing water 3 in outdoor wall 1, rainwater is avoided to impregnate ground, will receive outer wall of basement body 1 not with construction bottom plate 2 Rainwater impregnates;
S5: the processing of external wall construction post-cast strip: building model is built, the bottom of exterior wall is provided with wall horizontal reinforcement 15, compensation reinforcing bar 2 13, two compensation reinforcing bars 2 13 are respectively set in two sides above and below the exterior wall above wall horizontal reinforcement 15 Being horizontally disposed on the exterior wall of opposite side has multiple steel plate water stoppers 2 14, and the steel plate water stopper 14 2 avoids outside exterior wall The rainwater of wall penetrates into internal;
S6: floor slab back casting tape handling: after the completion of external wall construction, top surface carries out the fixed filling building of installation of template and support 900mm is arranged in board post poured band, floor slab back casting bandwidth, the beams of concrete 5 at floor slab back casting band respectively with building top bars 6, downstairs Layer reinforcing bar 7 does not turn off.
S7: the processing of beams of concrete post-cast strip: beams of concrete post-cast strip is set in the two sides of floor slab back casting band, keeps former design strong It is closely knit that degree grade proposes higher leveled concreting, and carries out surface covering curing, before the casting concrete of beams of concrete post-cast strip Surface should be cleaned out, and arrange to concrete beam reinforcing 19, that is, complete pouring for integrated building house.
When concreting, reinforcement should be taken to vibrate, conserve and moist keeping measures concrete, suitably increase curing time, Demoulding must not be shifted to an earlier date, concrete ambient relative humidity reaches 85%.
Before concrete setting, to prevent concrete surface from plasticity shrinking joint occur and because doing caused by the quick dehydration in surface Draw is stitched, and pressure should be smeared using wooden float 2 times before concrete initial set.
The side of the wall horizontal reinforcement 15 is provided with one layer of waterproof roll 16, the side of the waterproof roll 16 is set Set the wall protective layer 17 for protecting exterior wall.
The floor slab back casting band and beams of concrete post-cast strip are in construction, upstairs layer reinforcing bar 6 and downstairs between layer reinforcing bar 7 And the top of concrete beam reinforcing is provided with steel wire 8, concreting is on 8 top of steel wire.
In S7, the upper middle side part of the concrete beam reinforcing 19 is provided with Vierendeel girder 18, the top of the Vierendeel girder 18 It pours for compensating the compensating concrete 20 shunk.
Embodiment 3
Referring to Fig.1 shown in -6, the building construction method that pours of integration, specific steps include the following:
S1: basement process: floating sand and mud in place cleaning carry out mechanical excavation, smooth with excavator, loading machine, When to apart from designed elevation 300m, then it is manually smooth and be compacted with road roller, to casting concrete;
S2: casting concrete: after casting of concrete in mass, using moisturizing, temperature control measure in Ying 12h, in concrete The table temperature difference should not exceed 25 DEG C, and concreting body surface face and atmosphere temperature-difference should not exceed 20 DEG C, and to concreting body To curing time in 20d;
S3: the processing of raft board post poured band: multiple raft board post poured bands are uniformly arranged on ground, raft board post poured band bottom end is set Bottom cushion 11 is set, makes to form good separating effect, baseplate reinforcing bar 9, the baseplate reinforcing bar 9 is set on the bottom cushion 11 The raft board post poured band top and lower part on top are provided with compensation reinforcing bar 1, are provided between two compensation reinforcing bars 1 Steel plate water stopper 1, the steel plate water stopper 1 are to prevent the penetrating on raft board post poured band of underground water;
S4: open drain processing: respectively opening up a gutter in ground two sides, guarantees that draining is unobstructed, when the gutter It is made using raft slab muscle 4, and the depth that gutter is arranged is convenient for draining, in addition in the underground of outer Retaining wall seam in 250mm It is inserted into steel plate for sealing water 3 in outdoor wall 1, rainwater is avoided to impregnate ground, will receive outer wall of basement body 1 not with construction bottom plate 2 Rainwater impregnates;
S5: the processing of external wall construction post-cast strip: building model is built, the bottom of exterior wall is provided with wall horizontal reinforcement 15, compensation reinforcing bar 2 13, two compensation reinforcing bars 2 13 are respectively set in two sides above and below the exterior wall above wall horizontal reinforcement 15 Being horizontally disposed on the exterior wall of opposite side has multiple steel plate water stoppers 2 14, and the steel plate water stopper 14 2 avoids outside exterior wall The rainwater of wall penetrates into internal;
S6: floor slab back casting tape handling: after the completion of external wall construction, top surface carries out the fixed filling building of installation of template and support 1000mm is arranged in board post poured band, floor slab back casting bandwidth, the beams of concrete 5 at floor slab back casting band respectively with building top bars 6, downstairs Layer reinforcing bar 7 does not turn off.
S7: the processing of beams of concrete post-cast strip: beams of concrete post-cast strip is set in the two sides of floor slab back casting band, keeps former design strong It is closely knit that degree grade proposes higher leveled concreting, and carries out surface covering curing, before the casting concrete of beams of concrete post-cast strip Surface should be cleaned out, and arrange to concrete beam reinforcing 19, that is, complete pouring for integrated building house.
When concreting, reinforcement should be taken to vibrate, conserve and moist keeping measures concrete, suitably increase curing time, Demoulding must not be shifted to an earlier date, concrete ambient relative humidity reaches 90%.
Before concrete setting, to prevent concrete surface from plasticity shrinking joint occur and because doing caused by the quick dehydration in surface Draw is stitched, and pressure should be smeared using wooden float 3 times before concrete initial set.
The side of the wall horizontal reinforcement 15 is provided with one layer of waterproof roll 16, the side of the waterproof roll 16 is set Set the wall protective layer 17 for protecting exterior wall.
The floor slab back casting band and beams of concrete post-cast strip are in construction, upstairs layer reinforcing bar 6 and downstairs between layer reinforcing bar 7 And the top of concrete beam reinforcing is provided with steel wire 8, concreting is on 8 top of steel wire.
In S7, the upper middle side part of the concrete beam reinforcing 19 is provided with Vierendeel girder 18, the top of the Vierendeel girder 18 It pours for compensating the compensating concrete 20 shunk.
Reference examples
For designed by embodiment 1-3 go out test specimen wall, and respectively to time wall carry out crushing stress value, density, suction Water rate and clay content are checked that the code requirement comparison in detection numerical value and building trade is as shown in table 1:
Table 1
By table 1, it can be concluded that, the building that the technical solution in the present invention is made, crushing stress value needs MPa, and its Density, water absorption rate and clay content are superior to the numerical value of code requirement in industry, to make the integral waterproofing effect of building into one In addition step enhancing uses full cast-in-situ steel reinforced concrete shear wall structure, main building uses flat raft foundation, and supporting course is gravelly sand Layer, has reached good anti seismic efficiency.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (10)

1. the building construction method that integration pours, which is characterized in that specific steps include the following:
S1: basement process: floating sand and mud in place cleaning carry out mechanical excavation, smooth with excavator, loading machine, until away from When from designed elevation 250-300m, then it is manually smooth and be compacted with road roller, to casting concrete;
S2: after casting of concrete in mass, moisturizing, temperature control measure, table in concrete casting concrete: are used in Ying 10-12h The temperature difference should not exceed 25 DEG C, and concreting body surface face and atmosphere temperature-difference should not exceed 20 DEG C, and to concreting body pair Curing time is in 14-20d;
S3: the processing of raft board post poured band: being uniformly arranged multiple raft board post poured bands on ground, and bottom is arranged in raft board post poured band bottom end Plate bed course makes to form good separating effect, and baseplate reinforcing bar, the raft plate on the baseplate reinforcing bar top are arranged on the bottom cushion Post-cast strip top and lower part are provided with compensation reinforcing bar one, are provided with steel plate water stopper one between two compensation reinforcing bars one, The steel plate water stopper is first is that prevent the penetrating on raft board post poured band of underground water;
S4: open drain processing: respectively opening up a gutter in ground two sides, guarantees that draining is unobstructed, and when gutter utilizes Raft slab muscle is made, and the depth that gutter is arranged is convenient for draining, in addition in the underground of outer Retaining wall seam in 200-250mm It is inserted into steel plate for sealing water in outdoor wall, rainwater is avoided to impregnate ground, outer wall of basement body and construction bottom plate is made not to will receive rainwater It impregnates;
S5: the processing of external wall construction post-cast strip: building building model, the bottom of exterior wall be provided with wall horizontal reinforcement, Compensation reinforcing bar two is respectively set in two sides to exterior wall above wall horizontal reinforcement up and down, and two compensate the outer of the opposite side of reinforcing bar two Being horizontally disposed on wall has multiple steel plate water stoppers two, and the steel plate water stopper two avoids in the rainwater infiltration of exterior wall outer wall Portion;
S6: floor slab back casting tape handling: after the completion of external wall construction, after top surface carries out the fixed filling floor of installation of template and support Pour band, 800-1000mm is arranged in floor slab back casting bandwidth, the beams of concrete at floor slab back casting band respectively with building top bars, downstairs floor Reinforcing bar does not turn off.
S7: the processing of beams of concrete post-cast strip: beams of concrete post-cast strip is set in the two sides of floor slab back casting band, makes former design strength etc. It is closely knit that grade proposes higher leveled concreting, and carries out surface covering curing, beams of concrete post-cast strip casting concrete front surface It should clean out, and concrete beam reinforcing is arranged, that is, complete pouring for integrated building house.
2. the building construction method that integration as described in claim 1 pours, which is characterized in that the building is set It is set to rectangle, using full cast-in-situ steel reinforced concrete shear wall structure, main building uses flat raft foundation, and supporting course is gravelly sand Layer.
3. the building construction method that integration as claimed in claim 2 pours, which is characterized in that in S3, the raft Board post poured band construct when, by setting supporting steel bar measure come ensure baseplate reinforcing bar, two compensation reinforcing bar one position.
4. the building construction method that integration as claimed in claim 3 pours, which is characterized in that in S6-S7, mixed Before the solidifying post-cast strip Tu Liang casting concrete, the template of both side plate and support must not be removed, and be poured with accelerating beams of concrete post-cast strip It is formed after building.
5. the building construction method that integration according to any one of claims 1-4 pours, which is characterized in that in S2 Before casting concrete, concrete preparation, the concrete preparation cement small using contraction need to be first carried out, and take measures to fit When reducing cement consumption, the clay content of sandstone aggregate in concrete raw material should be reduced to the greatest extent, the control of coarse-fine aggregate clay content exists Within 2%.
6. the building construction method that integration as claimed in claim 5 pours, which is characterized in that when concreting, Reinforcement should be taken to vibrate, conserve and moist keeping measures concrete, suitably increase curing time, demoulding, concrete week must not be shifted to an earlier date It encloses relative humidity and reaches 80-90%.
7. the building construction method that integration as claimed in claim 6 pours, which is characterized in that before concrete setting, To prevent concrete surface from plasticity shrinking joint occur and because of desciccation crack caused by the quick dehydration in surface, answered before concrete initial set It is smeared pressure 2~3 times using wooden float.
8. the building construction method that integration according to any one of claims 1-4 pours, which is characterized in that in S5 In, the side of the wall horizontal reinforcement is provided with one layer of waterproof roll, the side of the waterproof roll is arranged for protecting The wall protective layer of exterior wall.
9. the building construction method that integration as claimed in claim 8 pours, which is characterized in that the floor slab back casting band With beams of concrete post-cast strip in construction, upstairs layer reinforcing bar and between the layer reinforcing bar and top of concrete beam reinforcing is equal downstairs It is provided with steel wire, concreting is on steel wire top.
10. the building construction method that integration as claimed in claim 9 pours, which is characterized in that described mixed in S7 The upper middle side part of solidifying soil beam steel is provided with Vierendeel girder, and the top of the Vierendeel girder is poured for compensating the compensation coagulation shunk Soil.
CN201910624887.4A 2019-07-11 2019-07-11 The building construction method that integration pours Pending CN110318543A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910624887.4A CN110318543A (en) 2019-07-11 2019-07-11 The building construction method that integration pours

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910624887.4A CN110318543A (en) 2019-07-11 2019-07-11 The building construction method that integration pours

Publications (1)

Publication Number Publication Date
CN110318543A true CN110318543A (en) 2019-10-11

Family

ID=68121862

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910624887.4A Pending CN110318543A (en) 2019-07-11 2019-07-11 The building construction method that integration pours

Country Status (1)

Country Link
CN (1) CN110318543A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112227522A (en) * 2020-10-26 2021-01-15 温州展业建设工程有限公司 Construction method for integrally cast building house
CN114277829A (en) * 2021-12-31 2022-04-05 中国建筑第五工程局有限公司 Integral fall raft foundation and construction method thereof
CN114309568A (en) * 2021-12-01 2022-04-12 上海二十冶建设有限公司 Slab continuous casting ladle turret base body construction process
CN115012537A (en) * 2022-06-30 2022-09-06 中国建筑一局(集团)有限公司 Construction method of settlement-spanning post-cast strip of stiffened steel transfer beam
CN115126006A (en) * 2022-06-30 2022-09-30 陕西帕源路桥建设有限公司 Post-pouring belt water stopping mechanism for house building construction

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103321257A (en) * 2013-06-18 2013-09-25 浙江海天建设集团有限公司 Anti-cracking seepage-proof construction method for ultra-long mass concrete structure basement
US8607518B2 (en) * 2010-09-16 2013-12-17 Rodney I. Smith Wall panel with extended integral post
CN103452187A (en) * 2013-09-30 2013-12-18 烟台金田科技有限公司 Steel structure concrete internal-external thermal insulation integration module house
CN206591692U (en) * 2017-01-18 2017-10-27 郑州中天建筑节能有限公司 A kind of steel wire net rack cast-in-place concrete exempts to tear compound external mold integrated plate for heat insulation open
CN107673713A (en) * 2017-10-18 2018-02-09 北京建工路桥工程建设有限责任公司 A kind of mass concrete mixture and its construction method for pouring wall

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8607518B2 (en) * 2010-09-16 2013-12-17 Rodney I. Smith Wall panel with extended integral post
CN103321257A (en) * 2013-06-18 2013-09-25 浙江海天建设集团有限公司 Anti-cracking seepage-proof construction method for ultra-long mass concrete structure basement
CN103452187A (en) * 2013-09-30 2013-12-18 烟台金田科技有限公司 Steel structure concrete internal-external thermal insulation integration module house
CN206591692U (en) * 2017-01-18 2017-10-27 郑州中天建筑节能有限公司 A kind of steel wire net rack cast-in-place concrete exempts to tear compound external mold integrated plate for heat insulation open
CN107673713A (en) * 2017-10-18 2018-02-09 北京建工路桥工程建设有限责任公司 A kind of mass concrete mixture and its construction method for pouring wall

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112227522A (en) * 2020-10-26 2021-01-15 温州展业建设工程有限公司 Construction method for integrally cast building house
CN114309568A (en) * 2021-12-01 2022-04-12 上海二十冶建设有限公司 Slab continuous casting ladle turret base body construction process
CN114277829A (en) * 2021-12-31 2022-04-05 中国建筑第五工程局有限公司 Integral fall raft foundation and construction method thereof
CN115012537A (en) * 2022-06-30 2022-09-06 中国建筑一局(集团)有限公司 Construction method of settlement-spanning post-cast strip of stiffened steel transfer beam
CN115126006A (en) * 2022-06-30 2022-09-30 陕西帕源路桥建设有限公司 Post-pouring belt water stopping mechanism for house building construction
CN115012537B (en) * 2022-06-30 2023-02-03 中国建筑一局(集团)有限公司 Construction method of settlement-spanning post-cast strip of stiffened steel transfer beam
CN115126006B (en) * 2022-06-30 2023-11-07 陕西帕源路桥建设有限公司 Post-pouring belt water stopping mechanism for house building construction

Similar Documents

Publication Publication Date Title
CN110318543A (en) The building construction method that integration pours
CN105178357B (en) Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition
CN207987983U (en) A kind of waterproof construction being used for underground engineering main body construction seam and post-cast strip
CN108360712A (en) A kind of assembled steel reinforced concrete shear force wall and its construction method
CN102392549A (en) Construction working method for seamless prestressed-concrete self-waterproof clean water reservoir
CN106499070A (en) The construction method of connecting sewing between assembled architecture component and component
CN103410173A (en) Construction method for vertical post pouring belt plugging of underground structural outer wall
CN106948502A (en) A kind of water-proof top cover and its construction method
CN207944339U (en) A kind of prefabricated superposed type anti-collision wall for urban viaduct
CN208056095U (en) I-shaped precast concrete and its compound soil-baffling structure of assembled cabin format
CN105756100A (en) Basement post-pouring belt system and making method thereof
CN107326924A (en) Outer wall of underground structure HCMW engineering methods overlap wall and its construction method
CN105064411B (en) Method for building post-pouring expansion reinforcing band of wallboard of underground structure
CN209293068U (en) A kind of open trench tunnel falsework system
CN114809000B (en) Rapid construction method of prefabricated plate brick moulding bed
JP2862147B2 (en) Basement wall construction method using concrete formwork panels
CN114855884A (en) Construction method facilitating early backfill of post-cast strip of underground foundation structure
Groot et al. Water permeance problems in single wythe masonry walls: the case of wind mills
CN207331699U (en) One kind cheats reinforced concrete barricade composite supporting construction in hole
CN112411590A (en) Underground diaphragm wall structure and construction method
CN206768879U (en) A kind of poured band of outer wall of basement structure
CN215052902U (en) Novel prefabricated tubular pile
CN209368898U (en) A kind of no uplift pile ground library float Structure
CN211646459U (en) One-time pouring decorative concrete retaining wall structure for wading
CN210713982U (en) Swimming pool bottom plate and wallboard and take-up platform and wallboard junction waterproof construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191011