CN110310048A CN201910617837.3A CN201910617837A CN110310048A CN 110310048 A CN110310048 A CN 110310048A CN 201910617837 A CN201910617837 A CN 201910617837A CN 110310048 A CN110310048 A CN 110310048A
Authority
CN
China
Prior art keywords
data
distribution
library
strategy
planning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910617837.3A
Other languages
Chinese (zh)
Other versions
CN110310048B (en
Inventor
杨金东
王科
刘红文
聂鼎
关静恩
董涛
黄明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of Yunnan Power System Ltd
Original Assignee
Electric Power Research Institute of Yunnan Power System Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of Yunnan Power System Ltd filed Critical Electric Power Research Institute of Yunnan Power System Ltd
Priority to CN201910617837.3A priority Critical patent/CN110310048B/en
Publication of CN110310048A publication Critical patent/CN110310048A/en
Application granted granted Critical
Publication of CN110310048B publication Critical patent/CN110310048B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Data Mining & Analysis (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Game Theory and Decision Science (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

This application discloses a kind of distribution planning overall process appraisal procedure and devices, extract three-phase imbalance data, low-voltage heavy-overload data, the high lossy data of route, power supply reliability index and distribution rack data respectively from the operation data of the multi-specialized equipment of multisystem, the data of integration are pre-processed again, obtain preprocessed data;Preprocessed data is calculated by tidal current analysis, analyzes distribution problem base assessment strategy, distribution planned project assessment strategy and planning construction recruitment evaluation strategy;It is whether feasible to manually generated problem library and project library, useful, assess comprehensively according to the corresponding problem base of these strategy generatings and project library.The application plans that control requires according to distribution, based on multi-specialized Data Integration distribution business datum, assessment strategy is calculated to distribution planning problem library and distribution planned project, facilitate development to assess distribution planning problem, distribution planned project and planned project construct effects of biology automatically, effectively assesses the overall process of distribution planning.

Description

A kind of distribution planning overall process appraisal procedure and device
Technical field
This application involves technical field of power systems more particularly to a kind of distribution planning overall process appraisal procedure and devices.
Background technique
The assessment of the processes such as current domestic " problem, project, Effect on construction " in distribution planning, is established fixed manually Property evaluation model on, entire evaluation process lacks quantitative analysis means, and distribution is caused to plan each process link evaluation work Amount is big, and assessment result not can accurately reflect the practical executive condition of planning.Therefore, the full mistake of distribution planning how is effectively assessed Journey becomes those skilled in the art's urgent problem to be solved.
Summary of the invention
This application provides a kind of distribution planning overall process appraisal procedure and devices, can effectively assess distribution planning Process.
This application provides a kind of distributions to plan overall process appraisal procedure, comprising:
Extract three-phase imbalance data, low-voltage heavy-overload number respectively from the operation data of the multi-specialized equipment of multisystem According to, the high lossy data of route, power supply reliability index and distribution rack data;
By three-phase imbalance data, low-voltage heavy-overload data, the high lossy data of route, power supply reliability index and distribution Rack Data Integration is pre-processed, and preprocessed data is obtained;
The preprocessed data is calculated by tidal current analysis, analyzes distribution problem base assessment strategy, distribution planned project Assessment strategy and planning construction recruitment evaluation strategy;
Artificial planning problem library, artificial planned project library are obtained respectively and have carried out planned project library;
Distribution problem base is generated according to the distribution problem base assessment strategy, using distribution problem base to artificial planning problem Library is assessed, and assessment result is obtained;
Distribution project library is generated according to the distribution planned project assessment strategy, using distribution project library to artificial plan item Mesh library is assessed, and assessment result is obtained;
According to the planning construction recruitment evaluation strategy generating construct effects of biology project library, using construct effects of biology project library to Carry out planned project library to be assessed, obtains assessment result.
Optionally, the operation data of the multi-specialized equipment of the multisystem be respectively from production management system, SCADA system and The data obtained in metering automation system.
Optionally, the assessment result that obtains includes:
Analyse whether that there are rack weak spots;The rack weak spot include N-1 be unsatisfactory for, heavy-overload, low-voltage, power supply Radius is too long, at least one of line loss per unit senior middle school;
Rack weak spot if it does not exist, then assessment result is feasible, and otherwise, assessment result is infeasible.
Optionally, described to analyse whether that there are rack weak spots and include:
Provide the node data of some node in distribution;Node data includes voltage, electric current, power data and line loss number According to;
By node data and artificial planning problem library, artificial planned project library or corresponding mark in planned project library is carried out Quasi- value is compared, if node data is not inconsistent with standard value, determines present node for rack weak spot.
Present invention also provides a kind of distribution planning overall processes to assess device, comprising:
Data acquisition module, for extracting three-phase imbalance number respectively from the operation data of the multi-specialized equipment of multisystem According to, low-voltage heavy-overload data, the high lossy data of route, power supply reliability index and distribution rack data;It is also used to obtain respectively It takes artificial planning problem library, artificial planned project library and has carried out planned project library;
Preprocessing module is used for three-phase imbalance data, low-voltage heavy-overload data, the high lossy data of route, power supply Reliability index and distribution rack Data Integration are pre-processed, and preprocessed data is obtained;
Strategy obtains module, for calculating the preprocessed data by tidal current analysis, analyzes the assessment of distribution problem base Strategy, distribution planned project assessment strategy and planning construction recruitment evaluation strategy;
Evaluation module matches network planning according to described for generating distribution problem base according to the distribution problem base assessment strategy Project evaluation strategy generating distribution project library is drawn, according to the planning construction recruitment evaluation strategy generating construct effects of biology project library; Be respectively adopted distribution problem base, distribution project library, construct effects of biology project library to artificial planning problem library, artificial planned project library, Carry out planned project library to be assessed, obtains assessment result.
Optionally, the operation data of the multi-specialized equipment of the multisystem be respectively from production management system, SCADA system and The data obtained in metering automation system.
Optionally, the evaluation module further include:
Analytical unit, for analysing whether that there are rack weak spots;The rack weak spot include N-1 be unsatisfactory for, mistake again Load, low-voltage, radius of electricity supply be too long, at least one of line loss per unit senior middle school.
Optionally, the analytical unit includes:
Data acquisition subelement, for providing the node data of some node in distribution;Node data includes voltage, electricity Stream, power data and line loss data;
Comparing subunit, for by node data and artificial planning problem library, artificial planned project library or having carried out planning Corresponding standard value is compared in project library, if node data is not inconsistent with standard value, determines present node for rack weakness Point.
From the above technical scheme, this application provides a kind of distribution planning overall process appraisal procedure and device, from more Three-phase imbalance data, low-voltage heavy-overload data, the loss of route height are extracted in the operation data of the multi-specialized equipment of system respectively Data, power supply reliability index and distribution rack data, then these integration are pre-processed, obtain preprocessed data;Pass through Tidal current analysis calculates preprocessed data, analyzes distribution problem base assessment strategy, distribution planned project assessment strategy and planning and builds If recruitment evaluation strategy;Corresponding problem base and project library are generated respectively according to these strategies, thus to manually generated problem Library and whether project library is feasible, useful, comprehensive is effectively assessed.The technical solution of the application is wanted according to distribution planning control It asks, is based on multi-specialized Data Integration distribution business datum, assessment strategy is calculated to distribution planning problem library and distribution planned project, Hereafter, it can carry out and distribution planning problem, distribution planned project and planned project construct effects of biology are assessed automatically, effectively comment Estimate the overall process of distribution planning.
Detailed description of the invention
In order to illustrate more clearly of the technical solution of the application, attached drawing needed in case study on implementation will be made below Simply introduce, it should be apparent that, for those of ordinary skills, in the premise of not making the creative labor property Under, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is the flow chart that overall process appraisal procedure is planned in a kind of distribution provided by the embodiments of the present application;
Fig. 2 is that a kind of distribution provided by the embodiments of the present application plans that overall process assesses the structural block diagram of device;
Fig. 3 is the flow chart provided by the embodiments of the present application for obtaining each assessment result.
Specific embodiment
In order to make those skilled in the art better understand the technical solutions in the application, below in conjunction with attached drawing, it is right Technical solution in the embodiment of the present application is clearly and completely described.
Fig. 1 is the flow chart that overall process appraisal procedure is planned in a kind of distribution provided by the embodiments of the present application.As shown in Figure 1, This method comprises:
S101 extracts three-phase imbalance data, low-voltage mistake again respectively from the operation data of the multi-specialized equipment of multisystem Carry data, the high lossy data of route, power supply reliability index and distribution rack data;The operation of the multi-specialized equipment of multisystem Data are the data obtained from production management system, SCADA system and metering automation system respectively.
Specifically, platform area, resident and 10kV special line continuous data are obtained from metering automation system respectively, from SCADA 35kV-110kV trend operation data and the operation of 10kV public line outlet breaker are obtained in system (dispatch automated system) Data, the data of above-mentioned acquisition can be collectively referred to as distribution operation data.
S102, by three-phase imbalance data, low-voltage heavy-overload data, the high lossy data of route, power supply reliability index It is pre-processed with distribution rack Data Integration, obtains preprocessed data.
S103 calculates the preprocessed data by tidal current analysis, analyzes distribution problem base assessment strategy, distribution planning Project evaluation strategy and planning construction recruitment evaluation strategy.Trend meter is carried out to preprocessed data first in the embodiment of the present application It calculates, analyzes distribution problem base assessment strategy, then by distribution problem base assessment strategy in conjunction with distribution operation data, Load flow calculation After obtain distribution planned project assessment strategy;Finally based on obtained preprocessed data, planning construction recruitment evaluation plan is analyzed Slightly.For low-voltage, voltage data is obtained from metering automation system, it is low-voltage problem that voltage, which is less than 180V, with Manually generated low-voltage problem is compared by computer, if identical, illustrates that manually generated low-voltage problem is effective, no Same then increase substitutes artificial original low-voltage problem.
S104 obtains artificial planning problem library, artificial planned project library respectively and has carried out planned project library.In this implementation In example, due to planning problem library, artificial planned project library and to have carried out planned project library be the prior art, for specific Acquisition modes are no longer described in detail in the application;The purpose for obtaining above-mentioned database is the data obtained with the multi-specialized analysis of multisystem Library is compared, effectively to be assessed problem base or project library feasibility.
S105 generates distribution problem base according to the distribution problem base assessment strategy, using distribution problem base to artificial rule It draws problem base to be assessed, obtains assessment result.
S106 generates distribution project library according to the distribution planned project assessment strategy, using distribution project library to artificial Planned project library is assessed, and assessment result is obtained.
S107, according to the planning construction recruitment evaluation strategy generating construct effects of biology project library, using construct effects of biology project Library is assessed planned project library has been carried out, and assessment result is obtained.
The sequence of above-mentioned steps S105-S107 in time is not defined, and can be assessed simultaneously, can also be random Exchange assessment sequence, for the acquisition modes of assessment result, can not limit with a kind of multilevel iudge mode, such as:
Optionally, in a kind of possible embodiments, the assessment result that obtains includes:
Analyse whether that there are rack weak spots;The rack weak spot include N-1 be unsatisfactory for, heavy-overload, low-voltage, power supply Radius is too long, at least one of line loss per unit senior middle school;
Rack weak spot if it does not exist illustrates distribution normal operation, then assessment result is feasible, and otherwise, assessment result is It is infeasible;At this moment, need to take the modes such as advise to repair means to the project implementation of problems.
Further, described to analyse whether that there are rack weak spots and include:
Provide the node data of some node in distribution;Node data includes voltage, electric current, power data and line loss number According to;After carrying out Load flow calculation analysis, voltage, electric current, power data and line loss data of each node of network etc. are provided, Compared with standard value, see whether voltage out-of-limit, route whether heavy duty and overload etc., and if so, adjustment problem base, project library, Iterate calculating, until meeting standard.
By node data and artificial planning problem library, artificial planned project library or corresponding mark in planned project library is carried out Quasi- value is compared, if node data is not inconsistent with standard value, determines present node for rack weak spot.For example, work as section When point data is voltage, can check whether voltage is more than restriction maximum voltage value, or check whether route occurs heavy duty or mistake Phenomena such as load, to achieve the purpose that effectively to assess.
In addition, distribution problem base can also be established using preprocessed data in the embodiment of the present application, according to distribution problem Library further establishes distribution problem base assessment models and has carried out planning construction project evaluation model, right again according to distribution problem base Distribution project library and distribution project library and its assessment models should be established, respectively by distribution problem base assessment models to manual sorting Distribution problem base assessed, distribution problem base assessment result is obtained, by distribution project library assessment models to manually establishing Distribution project library is assessed, and obtains the distribution project evaluation as a result, by having carried out planning construction project evaluation model to having carried out Planning construction project assessed, obtain and carried out the assessment result of planning construction project, obtain the tool of each assessment result Body process is as shown in Figure 3.
The application can also can be illustrated below with a specific evaluation process:
Firstly, all data is extracted from obtaining in platform area, resident and 10kV special line continuous data in metering automation system, And it carries out process of data preprocessing and integrates all data;
Secondly, being based on well known tidal current computing method, carries out tidal current analysis and calculate, using tidal current analysis model to pretreatment Data are calculated, and show that distribution problem base assessment strategy, distribution planned project assessment strategy and planning construction effect are commented respectively Estimate strategy, and corresponding distribution problem base, distribution project library and construct effects of biology project library are produced according to above-mentioned strategy respectively.
Finally, the artificial planning problem library that will acquire respectively, artificial planned project library and carried out planned project library with It is respectively compared according to the distribution problem base, distribution project library and construct effects of biology project library of strategy generating, obtains assessment result.
The technical solution of the application is able to solve during existing distribution planning application, cannot be fully assessed in time with network planning The problem of drawing, and working efficiency low problem when artificial development distribution planning appraisal.The application uses Software engineering thought Each process node, which is analyzed, to be planned to distribution, completes eventually by Intellectual Analysis Technology to distribution planning problem library data, match Network planning draws the overall process comprehensive assessment of project library data and distribution planned project construct effects of biology, and then preferably distribution is supported to plan Work.
Fig. 2 is that a kind of distribution provided by the embodiments of the present application plans that overall process assesses the structural block diagram of device.Such as Fig. 2 institute Show, which includes:
Data acquisition module 21, for extracting three-phase imbalance number respectively from the operation data of the multi-specialized equipment of multisystem According to, low-voltage heavy-overload data, the high lossy data of route, power supply reliability index and distribution rack data;It is also used to obtain respectively It takes artificial planning problem library, artificial planned project library and has carried out planned project library;
Preprocessing module 22 is used for three-phase imbalance data, low-voltage heavy-overload data, the high lossy data of route, confession Electric reliability index and distribution rack Data Integration are pre-processed, and preprocessed data is obtained;
Strategy obtains module 23 and analyzes distribution problem base for calculating the preprocessed data by tidal current analysis and comment Estimate strategy, distribution planned project assessment strategy and planning construction recruitment evaluation strategy;
Evaluation module 24, for generating distribution problem base according to the distribution problem base assessment strategy, according to the distribution Planned project assessment strategy generates distribution project library, according to the planning construction recruitment evaluation strategy generating construct effects of biology project Library;Distribution problem base, distribution project library, construct effects of biology project library is respectively adopted to artificial planning problem library, artificial planned project Library has been carried out planned project library and has been assessed, and assessment result is obtained.
Optionally, the operation data of the multi-specialized equipment of the multisystem be respectively from production management system, SCADA system and The data obtained in metering automation system.
Optionally, the evaluation module further include:
Analytical unit, for analysing whether that there are rack weak spots;The rack weak spot include N-1 be unsatisfactory for, mistake again Load, low-voltage, radius of electricity supply be too long, at least one of line loss per unit senior middle school.
Optionally, the analytical unit includes:
Data acquisition subelement, for providing the node data of some node in distribution;Node data includes voltage, electricity Stream, power data and line loss data;
Comparing subunit, for by node data and artificial planning problem library, artificial planned project library or having carried out planning Corresponding standard value is compared in project library, if node data is not inconsistent with standard value, determines present node for rack weakness Point.
From the above technical scheme, this application provides a kind of distribution planning overall process appraisal procedure and device, from more Three-phase imbalance data, low-voltage heavy-overload data, the loss of route height are extracted in the operation data of the multi-specialized equipment of system respectively Data, power supply reliability index and distribution rack data, then these integration are pre-processed, obtain preprocessed data;Pass through Tidal current analysis calculates preprocessed data, analyzes distribution problem base assessment strategy, distribution planned project assessment strategy and planning and builds If recruitment evaluation strategy;Distribution planning problem library data, distribution planned project library data are respectively obtained according to these strategies and are matched Network planning draws the assessment data of project construction effect.The technical solution of the application plans that control requires according to distribution, based on multi-specialized Data Integration distribution business datum calculates assessment strategy to distribution planning problem library and distribution planned project, hereafter, can carry out pair Distribution planning problem, distribution planned project and planned project construct effects of biology are assessed automatically, effectively assess distribution planning Overall process.
Those skilled in the art will readily occur to its of the application after considering specification and practicing application disclosed herein Its embodiment.This application is intended to cover any variations, uses, or adaptations of the application, these modifications, purposes or Person's adaptive change follows the general principle of the application and including the undocumented common knowledge in the art of the application Or conventional techniques.The description and examples are only to be considered as illustrative, and the true scope and spirit of the application are by following Claim is pointed out.
It should be understood that the application is not limited to the precise structure that has been described above and shown in the drawings, and And various modifications and changes may be made without departing from the scope thereof.Scope of the present application is only limited by the accompanying claims.

Claims (8)

1. overall process appraisal procedure is planned in a kind of distribution characterized by comprising
Extract three-phase imbalance data, low-voltage heavy-overload data, line respectively from the operation data of the multi-specialized equipment of multisystem The high lossy data in road, power supply reliability index and distribution rack data;
By three-phase imbalance data, low-voltage heavy-overload data, the high lossy data of route, power supply reliability index and distribution rack Data Integration is pre-processed, and preprocessed data is obtained;
Load flow calculation is carried out to preprocessed data, analyzes distribution problem base assessment strategy, then by distribution problem base assessment strategy Distribution planned project assessment strategy is obtained in conjunction with distribution operation data, after Load flow calculation;Finally based on obtained pretreatment number According to analyzing planning construction recruitment evaluation strategy;
Artificial planning problem library, artificial planned project library are obtained respectively and have carried out planned project library;
According to the distribution problem base assessment strategy generate distribution problem base, using distribution problem base to artificial planning problem library into Row assessment, obtains assessment result;
Distribution project library is generated according to the distribution planned project assessment strategy, using distribution project library to artificial planned project library It is assessed, obtains assessment result;
According to the planning construction recruitment evaluation strategy generating construct effects of biology project library, using construct effects of biology project library to having carried out Planned project library is assessed, and assessment result is obtained.
2. the method according to claim 1, wherein the operation data of the multi-specialized equipment of the multisystem is difference The data obtained from production management system, SCADA system and metering automation system.
3. the method according to claim 1, wherein the assessment result that obtains includes:
Analyse whether that there are rack weak spots;The rack weak spot include N-1 be unsatisfactory for, heavy-overload, low-voltage, radius of electricity supply It is at least one of too long, line loss per unit senior middle school;
Rack weak spot if it does not exist, then assessment result is feasible, and otherwise, assessment result is infeasible.
4. according to the method described in claim 3, it is characterized in that, described analyse whether that there are rack weak spots and include:
Provide the node data of some node in distribution;Node data includes voltage, electric current, power data and line loss data;
By node data and artificial planning problem library, artificial planned project library or corresponding standard value in planned project library is carried out It is compared, if node data is not inconsistent with standard value, determines present node for rack weak spot.
5. a kind of distribution planning overall process assesses device characterized by comprising
Data acquisition module, for extracting three-phase imbalance data, low respectively from the operation data of the multi-specialized equipment of multisystem Voltage heavy-overload data, the high lossy data of route, power supply reliability index and distribution rack data;It is also used to obtain respectively artificial Planning problem library, artificial planned project library and planned project library is carried out;
Preprocessing module, for three-phase imbalance data, low-voltage heavy-overload data, the high lossy data of route, power supply is reliable Property index and distribution rack Data Integration are pre-processed, and preprocessed data is obtained;
Strategy obtains module, for calculating the preprocessed data by tidal current analysis, analyze distribution problem base assessment strategy, Distribution planned project assessment strategy and planning construction recruitment evaluation strategy;
Evaluation module, for generating distribution problem base according to the distribution problem base assessment strategy, according to the distribution plan item Mesh assessment strategy generates distribution project library, according to the planning construction recruitment evaluation strategy generating construct effects of biology project library;Respectively Using distribution problem base, distribution project library, construct effects of biology project library to artificial planning problem library, artificial planned project library, opened Exhibition planned project library is assessed, and assessment result is obtained.
6. device according to claim 5, which is characterized in that the operation data of the multi-specialized equipment of multisystem is difference The data obtained from production management system, SCADA system and metering automation system.
7. device according to claim 5, which is characterized in that the evaluation module further include:
Analytical unit, for analysing whether that there are rack weak spots;The rack weak spot includes that N-1 is unsatisfactory for, is heavy-overload, low Voltage, radius of electricity supply be too long, at least one of line loss per unit senior middle school.
8. device according to claim 7, which is characterized in that the analytical unit includes:
Data acquisition subelement, for providing the node data of some node in distribution;Node data include voltage, electric current, Power data and line loss data;
Comparing subunit, for by node data and artificial planning problem library, artificial planned project library or having carried out planned project Corresponding standard value is compared in library, if node data is not inconsistent with standard value, determines present node for rack weak spot.
CN201910617837.3A 2019-07-10 2019-07-10 Distribution network planning overall process evaluation method and device Active CN110310048B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910617837.3A CN110310048B (en) 2019-07-10 2019-07-10 Distribution network planning overall process evaluation method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910617837.3A CN110310048B (en) 2019-07-10 2019-07-10 Distribution network planning overall process evaluation method and device

Publications (2)

Publication Number Publication Date
CN110310048A true CN110310048A (en) 2019-10-08
CN110310048B CN110310048B (en) 2023-07-04

Family

ID=68080007

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910617837.3A Active CN110310048B (en) 2019-07-10 2019-07-10 Distribution network planning overall process evaluation method and device

Country Status (1)

Country Link
CN (1) CN110310048B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111103465A (en) * 2019-12-27 2020-05-05 国网福建省电力有限公司 Real-time state early warning method based on distribution automation master station distribution transformer
CN111861184A (en) * 2020-07-14 2020-10-30 云南电网有限责任公司电力科学研究院 Power grid planning method

Citations (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6567814B1 (en) * 1998-08-26 2003-05-20 Thinkanalytics Ltd Method and apparatus for knowledge discovery in databases
US20040059588A1 (en) * 2002-09-19 2004-03-25 Burritt David B. Method of managing a project
CN103310298A (en) * 2013-05-16 2013-09-18 国家电网公司 Multistage comprehensive evaluation method for power distribution network planning scheme
CN103455596A (en) * 2013-09-02 2013-12-18 广东省计算中心 Science and technology project establishment evaluation method based on big data
CN104504183A (en) * 2014-12-10 2015-04-08 广州供电局有限公司 Power distribution network intelligent planning system based on automatic optimization
CN105321123A (en) * 2015-10-10 2016-02-10 国网山西省电力公司 Comprehensive evaluation system and review method for power distribution network of project
CN105868891A (en) * 2016-03-24 2016-08-17 国网辽宁省电力有限公司经济技术研究院 Optimizing and ordering method for power distribution network planning projects
CN106327081A (en) * 2016-08-24 2017-01-11 湖北省电力勘测设计院 Power distribution network project reliability benefit evaluation method based on total life cycle
CN106447522A (en) * 2016-06-30 2017-02-22 国网福建省电力有限公司电力科学研究院 Full voltage sequence integrated power grid reliability and risk evaluation method
CN106447209A (en) * 2016-10-11 2017-02-22 上海博辕信息技术服务有限公司 Determination method and device for evaluation factor of power distribution network project
CN106529708A (en) * 2016-10-31 2017-03-22 国网浙江省电力公司温州供电公司 Distribution network planning system based on cloud platform
CN106779344A (en) * 2016-11-28 2017-05-31 云南电网有限责任公司大理供电局 A kind of method based on distribution network planning of the battalion with information integration
CN106991531A (en) * 2017-03-30 2017-07-28 国家电网公司 Power distribution network project construction effect Post-assessment Method based on BP neural network
CN107918827A (en) * 2017-11-15 2018-04-17 昆明能讯科技有限责任公司 A kind of automatic method for optimizing of distribution network planning project based on preference policy
CN107959308A (en) * 2018-01-10 2018-04-24 云南电网有限责任公司电力科学研究院 Power distribution network distributed energy accesses adaptability teaching method and device
WO2018075995A1 (en) * 2016-10-21 2018-04-26 DataRobot, Inc. Systems for predictive data analytics, and related methods and apparatus
US20180146004A1 (en) * 2016-11-22 2018-05-24 Aon Global Operations Ltd (Singapore Branch) Systems and methods for cybersecurity risk assessment
CN108416531A (en) * 2018-03-19 2018-08-17 国网安徽省电力有限公司经济技术研究院 A kind of automatic evaluation method of distribution automation planning design effect
US20180240202A1 (en) * 2015-08-19 2018-08-23 China Electric Power Research Institute Company Limited Method of predicting distribution network operation reliability
CN109636189A (en) * 2018-12-13 2019-04-16 国网山东省电力公司经济技术研究院 A kind of Transmission Expansion Planning in Electric schemes evaluation method and system based on weight comprehensive assessment
CN109726880A (en) * 2017-10-30 2019-05-07 中国电力科学研究院有限公司 A kind of transmission line parameter reasonable evaluation method and system
CN109886649A (en) * 2019-02-13 2019-06-14 深圳供电局有限公司 Project full-tracking management method and system based on grid-based
CN109980642A (en) * 2019-04-26 2019-07-05 云南电网有限责任公司信息中心 A kind of digital intelligent distribution network planning auxiliary system

Patent Citations (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6567814B1 (en) * 1998-08-26 2003-05-20 Thinkanalytics Ltd Method and apparatus for knowledge discovery in databases
US20040059588A1 (en) * 2002-09-19 2004-03-25 Burritt David B. Method of managing a project
CN103310298A (en) * 2013-05-16 2013-09-18 国家电网公司 Multistage comprehensive evaluation method for power distribution network planning scheme
CN103455596A (en) * 2013-09-02 2013-12-18 广东省计算中心 Science and technology project establishment evaluation method based on big data
CN104504183A (en) * 2014-12-10 2015-04-08 广州供电局有限公司 Power distribution network intelligent planning system based on automatic optimization
US20180240202A1 (en) * 2015-08-19 2018-08-23 China Electric Power Research Institute Company Limited Method of predicting distribution network operation reliability
CN105321123A (en) * 2015-10-10 2016-02-10 国网山西省电力公司 Comprehensive evaluation system and review method for power distribution network of project
CN105868891A (en) * 2016-03-24 2016-08-17 国网辽宁省电力有限公司经济技术研究院 Optimizing and ordering method for power distribution network planning projects
CN106447522A (en) * 2016-06-30 2017-02-22 国网福建省电力有限公司电力科学研究院 Full voltage sequence integrated power grid reliability and risk evaluation method
CN106327081A (en) * 2016-08-24 2017-01-11 湖北省电力勘测设计院 Power distribution network project reliability benefit evaluation method based on total life cycle
CN106447209A (en) * 2016-10-11 2017-02-22 上海博辕信息技术服务有限公司 Determination method and device for evaluation factor of power distribution network project
WO2018075995A1 (en) * 2016-10-21 2018-04-26 DataRobot, Inc. Systems for predictive data analytics, and related methods and apparatus
CN106529708A (en) * 2016-10-31 2017-03-22 国网浙江省电力公司温州供电公司 Distribution network planning system based on cloud platform
US20180146004A1 (en) * 2016-11-22 2018-05-24 Aon Global Operations Ltd (Singapore Branch) Systems and methods for cybersecurity risk assessment
CN106779344A (en) * 2016-11-28 2017-05-31 云南电网有限责任公司大理供电局 A kind of method based on distribution network planning of the battalion with information integration
CN106991531A (en) * 2017-03-30 2017-07-28 国家电网公司 Power distribution network project construction effect Post-assessment Method based on BP neural network
CN109726880A (en) * 2017-10-30 2019-05-07 中国电力科学研究院有限公司 A kind of transmission line parameter reasonable evaluation method and system
CN107918827A (en) * 2017-11-15 2018-04-17 昆明能讯科技有限责任公司 A kind of automatic method for optimizing of distribution network planning project based on preference policy
CN107959308A (en) * 2018-01-10 2018-04-24 云南电网有限责任公司电力科学研究院 Power distribution network distributed energy accesses adaptability teaching method and device
CN108416531A (en) * 2018-03-19 2018-08-17 国网安徽省电力有限公司经济技术研究院 A kind of automatic evaluation method of distribution automation planning design effect
CN109636189A (en) * 2018-12-13 2019-04-16 国网山东省电力公司经济技术研究院 A kind of Transmission Expansion Planning in Electric schemes evaluation method and system based on weight comprehensive assessment
CN109886649A (en) * 2019-02-13 2019-06-14 深圳供电局有限公司 Project full-tracking management method and system based on grid-based
CN109980642A (en) * 2019-04-26 2019-07-05 云南电网有限责任公司信息中心 A kind of digital intelligent distribution network planning auxiliary system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
徐晓帅: "主动配电网不平衡潮流算法综述" *
臧宝志: "基于智能运营视角的配网项目投资效能评估体系研究", 《互联网+应用》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111103465A (en) * 2019-12-27 2020-05-05 国网福建省电力有限公司 Real-time state early warning method based on distribution automation master station distribution transformer
CN111861184A (en) * 2020-07-14 2020-10-30 云南电网有限责任公司电力科学研究院 Power grid planning method

Also Published As

Publication number Publication date
CN110310048B (en) 2023-07-04

Similar Documents

Publication Publication Date Title
Medjroubi et al. Open data in power grid modelling: new approaches towards transparent grid models
CN102722764B (en) Integration network optimization computer-aided decision support System
CN106096810B (en) Method and system for planning based on power distribution network operation data Yu geographical topology information
CN102567603B (en) Method for automatically generating BPA calculation file based on actual measurement topology and measured data
CN109286188B (en) 10kV power distribution network theoretical line loss calculation method based on multi-source data set
CN101930481B (en) Method used for generating CIM model describing power grid change in designated time slot and system thereof
CN110909935B (en) Grid rack diagnosis analysis and intelligent auxiliary system based on power grid planning data
CN106814286B (en) Power distribution network fault positioning system, method and server based on multi-element fault acquisition
CN104933631A (en) Power distribution network operation online analysis and evaluation system
CN109685558A (en) A kind of Cost for Electric Power Engineering evaluation system based on BIM technology
CN112418532A (en) Routing inspection path planning method, device, equipment and storage medium for power transmission line
CN113361108B (en) Electric power system future time period simulation method and system based on real-time and predicted data
CN105119282A (en) On-line calculation system and method for theoretical line loss of power grid
CN105354680A (en) GIS-based auxiliary determination and analysis method for grid section
CN110427392A (en) Power distribution network grid management information system based on cloud platform
CN103887792B (en) A kind of low-voltage distribution network modeling method containing distributed power source
CN110310048A (en) A kind of distribution planning overall process appraisal procedure and device
CN110610297A (en) Medium-voltage distribution network grid planning method
CN111401789A (en) Building construction intelligent supervision system based on BIM
CN109447466B (en) Overall process visual management and control system based on power distribution network communication network construction
CN117674221A (en) Intelligent power supply regulation and control method and system for micro-grid charging pile
CN104218572A (en) Fuzzy inference based topological real-time specification and correction method for CIM (common information model)
CN114818632B (en) Method and device for compiling power limit sequence table for super-planning
Lühn et al. Multi-criteria analysis of grid expansion concepts on the low voltage level
Aadithya Application of energy value stream mapping as auditing tool for non-value added industrial energy management

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant