CN110295593A - A kind of hypogee lid digs the construction technology of steel pipe column - Google Patents

A kind of hypogee lid digs the construction technology of steel pipe column Download PDF

Info

Publication number
CN110295593A
CN110295593A CN201910574500.9A CN201910574500A CN110295593A CN 110295593 A CN110295593 A CN 110295593A CN 201910574500 A CN201910574500 A CN 201910574500A CN 110295593 A CN110295593 A CN 110295593A
Authority
CN
China
Prior art keywords
steel pipe
column
pipe column
construction
hypogee
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910574500.9A
Other languages
Chinese (zh)
Inventor
张殿忠
史立春
史清
曾巧异
肖忠新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910574500.9A priority Critical patent/CN110295593A/en
Publication of CN110295593A publication Critical patent/CN110295593A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/34Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses the construction technologies that a kind of hypogee lid digs steel pipe column, its method includes construction of working shaft and column pile driving construction, the method that the present invention uses branch's construction, excavation column first is carried out to active well, then opposition stanchion carries out precision construction, on the one hand the speed of application that hypogee lid digs steel pipe column is improved, it is ensured that on the other hand working security ensures construction quality.

Description

A kind of hypogee lid digs the construction technology of steel pipe column
Technical field
The present invention relates to engineering fields, and the construction technology of steel pipe column is dug more particularly to a kind of hypogee lid.
Background technique
Hypogee lid is dug newly applying for steel pipe column and is constructed using cavern-pile method, which includes filling pile construction in pilot tunnel Step extracts mud in steel pile casting, using artificial after the pile foundation concrete under steel pile casting protection wait pour reaches 70% intensity Stake top concrete is abolished to permanent steel pipe column bottom absolute altitude in underground, and locator installs installs steel pipe column again.
But construction method haves the defects that long construction period, complex procedures at present, and needs in work progress manually in well It is lower carry out bottom hole pile crown concrete cut and locator installation, there are many insecurity factors, steel pipe column long construction period is applied Work higher cost, has some limitations.
The invention discloses be inserted into steel pipe column in a kind of pilot tunnel internal drilling bored concrete pile by similar patent CN201510857418.9 One-pass molding construction method, comprising: 1, drawing hole construction is carried out in the pilot tunnel for pile operation;2, drilling machine positioning and drilling; 3, the steel reinforcement cage in the interior installation pile foundation steel bar cage of drilling, steel pipe column and column;4, using the hydraulic insertion machine of steel pipe column to steel pipe column essence Determine position, leveling;5, poured pile base concrete and steel pipe column concrete;6, rubble is backfilled between steel pipe column and stake;7, continue to be perfused Steel pipe column concrete;8, coarse sand is backfilled, the hydraulic insertion machine of steel pipe column is removed, extract mud out and changes tool pipe into first segment steel Tubing string;9, steel reinforcement cage in first segment steel pipe column is installed, steel pipe column concrete is perfused, pile is completed after the completion of concrete curing and is applied Work.
Above-mentioned patent uses cavern-pile method to construct, therefore that there are construction periods is longer, and working security is not high to ask Topic.
Summary of the invention
A kind of hypogee lid digs the preparation method of the construction technology of steel pipe column, construction technology include construction of working shaft and Column pile driving construction.
Preferably, the construction of working shaft step includes:
(1) active well is dug with rotary drilling rig, depth is determined according to design requirement;
(2) active well steel column support frame is placed on work well head;
(3) steel pipe column is passed through under support frame in active well, and is fixed by steel column support frame;
(4) in concrete perfusion to steel pipe column.
Preferably, the stand column pile construction procedure includes:
(1) rotary drilling rig align piles position underthrust casing into ground is used, casing digging stand column pile is passed through later and drills to projected depth;
(2) ultra-retardation concrete is perfused in the column stake holes, is poured into after design needs height, platform well mouth locator is pacified and is welded It is connected on casing;
(3) multifunctional platform, the adjustable levelness of multifunctional platform and height are set up after on platform well mouth locator;
(4) verticality for adjusting multifunctional platform, guarantees steel column verticality, the channel of steel pipe column under multifunctional platform is beaten It opens;
(5) tool section is sling, rotates clockwise screwed connection at the top of tool section and steel pipe column;
(6) steel pipe column is sling by tool section, and is lowered into stand column pile drilling out of multifunctional platform channel, in tool section Lower part is lowered into when maintain an equal level with channel roof, fastens channel, continues underthrust, is reached after design mark post on tool section top Bolt is to be fixed on channel top;(7) tool section is rotated clockwise, bracket direction is adjusted;
(8) after to super slow concrete setting, multifunctional platform integrally falls, and takes out positioning pin;
(9) rotation counterclockwise is turned round lower and takes out tool section, later removes multifunctional platform.
Preferably, the method that concrete perfusion uses enhancing perfusion in the step (4), parameter are injection pressure 56.74Mpa;Speed 15L/s is perfused.
Preferably, steel column support frame is placed on well head in the step (2), and support frame will be more than apart from well head diameter 50cm range.
Preferably, platform well mouth locator is equipped with circular through hole in the step (2), need to ensure the center pair of circular through hole The center of quasi- stand column pile drilling.
Preferably, need to guarantee the channel center of steel pipe column and well head locator under multifunctional platform in the step (3) Circular through hole center alignment.
The utility model has the advantages that method includes work the present invention provides the construction technology that a kind of hypogee lid digs steel pipe column Well construction and column pile driving construction, the method that the present invention uses branch's construction, first carry out excavation column to active well, then column Stake carries out precision construction, on the one hand improves the speed of application that hypogee lid digs steel pipe column, it is ensured that working security, it is another Aspect ensures construction quality, and the construction of working shaft step includes: that (1) with rotary drilling rig digs active well, and depth is according to design Demand determines;(2) active well steel column support frame is placed on work well head;(3) steel pipe column is passed through and arrives active well under support frame It is interior, and fixed by steel column support frame;(4) in concrete perfusion to steel pipe column, this method can effectively to construction well into Row is slightly constructed early period, determines that condition, the stand column pile construction procedure can be in previous work well construction conditions for subsequent construction On the basis of, further accurate construction cement injection, it is ensured that the quality of engineering, in the step (4) concrete perfusion using plus The method for pressing perfusion, parameter are injection pressure 56.74Mpa;Speed 15L/s is perfused, this method can effectively ensure to be perfused mixed Solidifying soil can be compacted, and prevent aeration concrete column quality, and steel column support frame is placed on well head in the step (2), Support frame will be more than 50cm range apart from well head diameter, and this method can effectively consolidate the position of support frame, prevent support frame from existing There is the problem of slump in construction ground, and platform well mouth locator is equipped with circular through hole in the step (2), need to ensure circular through hole The center of center alignment post stake drilling, need to guarantee in the step (3) under multifunctional platform the channel center of steel pipe column with The center of the circular through hole of well head locator is aligned, and this method can ensure the accuracy of construction location, prevents construction from occurring inclined Difference.
Specific embodiment
To be easy to understand the technical means, the creative features, the aims and the efficiencies achieved by the present invention, below with reference to Specific embodiment, the present invention is further explained.
Embodiment 1:
A kind of hypogee lid digs the construction technology of steel pipe column, and construction technology includes: construction of working shaft and column pile driving construction.
The construction of working shaft step includes:
(1) active well is dug with rotary drilling rig, depth is determined according to design requirement;
(2) active well steel column support frame is placed on work well head;
(3) steel pipe column is passed through under support frame in active well, and is fixed by steel column support frame;
(4) in concrete perfusion to steel pipe column.
The stand column pile construction procedure includes:
(1) rotary drilling rig align piles position underthrust casing into ground is used, casing digging stand column pile is passed through later and drills to projected depth;
(2) ultra-retardation concrete is perfused in the column stake holes, is poured into after design needs height, platform well mouth locator is pacified and is welded It is connected on casing;
(3) multifunctional platform, the adjustable levelness of multifunctional platform and height are set up after on platform well mouth locator;
(4) verticality for adjusting multifunctional platform, guarantees steel column verticality, the channel of steel pipe column under multifunctional platform is beaten It opens;
(5) tool section is sling, rotates clockwise screwed connection at the top of tool section and steel pipe column;
(6) steel pipe column is sling by tool section, and is lowered into stand column pile drilling out of multifunctional platform channel, in tool section Lower part is lowered into when maintain an equal level with channel roof, fastens channel, continues underthrust, is reached after design mark post on tool section top Bolt is to be fixed on channel top;(7) tool section is rotated clockwise, bracket direction is adjusted;
(8) after to super slow concrete setting, multifunctional platform integrally falls, and takes out positioning pin;
(9) rotation counterclockwise is turned round lower and takes out tool section, later removes multifunctional platform.
Embodiment 2:
A kind of hypogee lid digs the construction technology of steel pipe column, and construction technology includes: construction of working shaft and column pile driving construction.
The construction of working shaft step includes:
(1) active well is dug with rotary drilling rig, depth is determined according to design requirement;
(2) active well steel column support frame is placed on work well head, support frame will be more than 50cm range apart from well head diameter;
(3) steel pipe column is passed through under support frame in active well, and is fixed by steel column support frame;
(4) in concrete perfusion to steel pipe column, the method that concrete perfusion uses enhancing perfusion, parameter is injection pressure 56.74Mpa;Speed 15L/s is perfused.
The stand column pile construction procedure includes:
(1) rotary drilling rig align piles position underthrust casing into ground is used, casing digging stand column pile is passed through later and drills to projected depth;
(2) ultra-retardation concrete is perfused in the column stake holes, is poured into after design needs height, platform well mouth locator is pacified and is welded It is connected on casing, platform well mouth locator is equipped with circular through hole, need to ensure in the center alignment post stake drilling of circular through hole The heart;
(3) multifunctional platform, the adjustable levelness of multifunctional platform and height are set up on platform well mouth locator after, are needed Guarantee that the channel center of steel pipe column is aligned with the center of the circular through hole of well head locator under multifunctional platform;
(4) verticality for adjusting multifunctional platform, guarantees steel column verticality, the channel of steel pipe column under multifunctional platform is beaten It opens;
(5) tool section is sling, rotates clockwise screwed connection at the top of tool section and steel pipe column;
(6) steel pipe column is sling by tool section, and is lowered into stand column pile drilling out of multifunctional platform channel, in tool section Lower part is lowered into when maintain an equal level with channel roof, fastens channel, continues underthrust, is reached after design mark post on tool section top Bolt is to be fixed on channel top;(7) tool section is rotated clockwise, bracket direction is adjusted;
(8) after to super slow concrete setting, multifunctional platform integrally falls, and takes out positioning pin;
(9) rotation counterclockwise is turned round lower and takes out tool section, later removes multifunctional platform.
Embodiment 3:
A kind of hypogee lid digs the construction technology of steel pipe column, and construction technology includes: construction of working shaft and column pile driving construction.
The construction of working shaft step includes:
(1) active well is dug with rotary drilling rig, depth is determined according to design requirement;
(2) active well steel column support frame is placed on work well head;
(3) steel pipe column is passed through under support frame in active well, and is fixed by steel column support frame;
(4) in concrete perfusion to steel pipe column.
The stand column pile construction procedure includes:
(1) rotary drilling rig align piles position underthrust casing into ground is used, casing digging stand column pile is passed through later and drills to projected depth;
(2) ultra-retardation concrete is perfused in the column stake holes, is poured into after design needs height, platform well mouth locator is pacified and is welded It is connected on casing, platform well mouth locator is equipped with circular through hole, need to ensure in the center alignment post stake drilling of circular through hole The heart;
(3) multifunctional platform, the adjustable levelness of multifunctional platform and height are set up on platform well mouth locator after, are needed Guarantee that the channel center of steel pipe column is aligned with the center of the circular through hole of well head locator under multifunctional platform;
(4) verticality for adjusting multifunctional platform, guarantees steel column verticality, the channel of steel pipe column under multifunctional platform is beaten It opens;
(5) tool section is sling, rotates clockwise screwed connection at the top of tool section and steel pipe column;
(6) steel pipe column is sling by tool section, and is lowered into stand column pile drilling out of multifunctional platform channel, in tool section Lower part is lowered into when maintain an equal level with channel roof, fastens channel, continues underthrust, is reached after design mark post on tool section top Bolt is to be fixed on channel top;(7) tool section is rotated clockwise, bracket direction is adjusted;
(8) after to super slow concrete setting, multifunctional platform integrally falls, and takes out positioning pin;
(9) rotation counterclockwise is turned round lower and takes out tool section, later removes multifunctional platform.
It extracts each embodiment to be analyzed, and is compareed with the prior art, obtain following data:
Construction efficiency enhancing rate/% Construct accurate rate/% There is engineering accident rate/%
Embodiment 1 12% 99.5% 0.057%
Embodiment 2 13% 99.5% 0.048%
Embodiment 3 11% 99.5% 0.054%
Existing index 10% 95.2% 0.079%
According to above table data, it can be concluded that, when implementing 2 parameter of embodiment, a kind of hypogee lid of the present invention digs steel pipe column Construction technology technological parameter be construction efficiency enhancing rate 13%, construct accurate rate 99.5%, there is engineering accident rate 0.054%, And prior art standard is construction efficiency enhancing rate 10%, accurate rate 95.2% of constructing, and engineering accident rate 0.079%, therefore this occurs The construction technology construction efficiency for inventing a kind of hypogee lid digging steel pipe column is higher, and construction accuracy is higher, constructs safer, Therefore the present invention has significant superiority.
The present invention provides the construction technology that a kind of hypogee lid digs steel pipe column, method includes construction of working shaft and stands Stanchion construction, the method that the present invention uses branch's construction first carry out excavation column to active well, and the stanchion that then opposes carries out accurate On the one hand construction improves the speed of application that hypogee lid digs steel pipe column, it is ensured that on the other hand working security ensures Construction quality, the construction of working shaft step include: (1) with rotary drilling rig digging active well, and depth is determined according to design requirement; (2) active well steel column support frame is placed on work well head;(3) steel pipe column is passed through under support frame in active well, and passed through Steel column support frame is fixed;(4) in concrete perfusion to steel pipe column, this method effectively can slightly apply early period to construction well Work determines that condition, the stand column pile construction procedure can be on the basis of previous work well construction conditions, into one for subsequent construction The accurate construction cement injection of step, it is ensured that the quality of engineering, concrete perfusion uses the side of enhancing perfusion in the step (4) Method, parameter are injection pressure 56.74Mpa;Speed 15L/s is perfused, this method can effectively ensure that the concrete being perfused can press It is real, aeration concrete column quality is prevented, steel column support frame is placed on well head in the step (2), and support frame will be away from It is more than 50cm range from well head diameter, this method can effectively consolidate the position of support frame, prevent support frame from occurring in construction ground The problem of slump, platform well mouth locator is equipped with circular through hole in the step (2), need to ensure that the center alignment of circular through hole is vertical The center of stanchion drilling needs to guarantee the channel center of steel pipe column and well head locator under multifunctional platform in the step (3) Circular through hole center alignment, this method can ensure the accuracy of construction location, prevent construction from deviation occur.
What has been described above is only a preferred embodiment of the present invention, it is noted that for those of ordinary skill in the art For, without departing from the concept of the premise of the invention, various modifications and improvements can be made, these belong to the present invention Protection scope.

Claims (7)

1. the construction technology that a kind of hypogee lid digs steel pipe column, which is characterized in that the construction technology includes construction of working shaft With column pile driving construction.
2. the construction technology that hypogee lid according to claim 1 digs steel pipe column, which is characterized in that the active well is applied Work step includes: suddenly
(1) active well is dug with rotary drilling rig, depth is determined according to design requirement;
(2) active well steel column support frame is placed on work well head;
(3) steel pipe column is passed through under support frame in active well, and is fixed by steel column support frame;
(4) in concrete perfusion to steel pipe column.
3. the construction technology that hypogee lid according to claim 1 digs steel pipe column, which is characterized in that the stand column pile is applied Work step includes: suddenly
(1) rotary drilling rig align piles position underthrust casing into ground is used, casing digging stand column pile is passed through later and drills to projected depth;
(2) ultra-retardation concrete is perfused in the column stake holes, is poured into after design needs height, platform well mouth locator is pacified and is welded It is connected on casing;
(3) multifunctional platform, the adjustable levelness of multifunctional platform and height are set up after on platform well mouth locator;
(4) verticality for adjusting multifunctional platform, guarantees steel column verticality, the channel of steel pipe column under multifunctional platform is beaten It opens;
(5) tool section is sling, rotates clockwise screwed connection at the top of tool section and steel pipe column;
(6) steel pipe column is sling by tool section, and is lowered into stand column pile drilling out of multifunctional platform channel, in tool section Lower part is lowered into when maintain an equal level with channel roof, fastens channel, continues underthrust, is reached after design mark post on tool section top Bolt is to be fixed on channel top;
(7) tool section is rotated clockwise, bracket direction is adjusted;
(8) after to super slow concrete setting, multifunctional platform integrally falls, and takes out positioning pin;
(9) rotation counterclockwise is turned round lower and takes out tool section, later removes multifunctional platform.
4. the construction technology of the digging steel pipe column of the hypogee lid according to claim 2, which is characterized in that the step (4) The method that middle concrete perfusion uses enhancing perfusion, parameter are injection pressure 56.74Mpa;Speed 15L/s is perfused.
5. the construction technology that hypogee lid according to claim 2 digs steel pipe column, which is characterized in that the step (2) Middle steel column support frame is placed on well head, and support frame will be more than 50cm range apart from well head diameter.
6. the construction technology that hypogee lid according to claim 3 digs steel pipe column, which is characterized in that the step (2) Middle platform well mouth locator is equipped with circular through hole, need to ensure the center of the center alignment post stake drilling of circular through hole.
7. the construction technology that hypogee lid according to claim 3 digs steel pipe column, which is characterized in that the step (3) It is middle to need to guarantee that the channel center of steel pipe column is aligned with the center of the circular through hole of well head locator under multifunctional platform.
CN201910574500.9A 2019-06-28 2019-06-28 A kind of hypogee lid digs the construction technology of steel pipe column Pending CN110295593A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910574500.9A CN110295593A (en) 2019-06-28 2019-06-28 A kind of hypogee lid digs the construction technology of steel pipe column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910574500.9A CN110295593A (en) 2019-06-28 2019-06-28 A kind of hypogee lid digs the construction technology of steel pipe column

Publications (1)

Publication Number Publication Date
CN110295593A true CN110295593A (en) 2019-10-01

Family

ID=68029387

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910574500.9A Pending CN110295593A (en) 2019-06-28 2019-06-28 A kind of hypogee lid digs the construction technology of steel pipe column

Country Status (1)

Country Link
CN (1) CN110295593A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509263A (en) * 2009-03-09 2009-08-19 上海隧道工程股份有限公司 Digging method foundation pit structure of steel cover and plate cover, and construction method
CN105672314A (en) * 2016-01-19 2016-06-15 中建八局第三建设有限公司 Method for constructing steel pipe upright pile through semi-reversed-construction method
CN108374418A (en) * 2018-03-26 2018-08-07 中铁五局集团有限公司 Steel pipe column precise positioning Fast Installation construction technology in a kind of sheltered reverse excavation

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509263A (en) * 2009-03-09 2009-08-19 上海隧道工程股份有限公司 Digging method foundation pit structure of steel cover and plate cover, and construction method
CN105672314A (en) * 2016-01-19 2016-06-15 中建八局第三建设有限公司 Method for constructing steel pipe upright pile through semi-reversed-construction method
CN108374418A (en) * 2018-03-26 2018-08-07 中铁五局集团有限公司 Steel pipe column precise positioning Fast Installation construction technology in a kind of sheltered reverse excavation

Similar Documents

Publication Publication Date Title
CN104563098B (en) A kind of super-large diameter all steel casing does operation pore-creating filling pile construction method
CN109440762B (en) Construction method of filling pile for drainage pump station
CN201241335Y (en) Pile and post in one foundation structure of underground engineering
CN110206493A (en) A kind of full-sleeve full-rotation construction process for bored pile
CN102678134A (en) Collapse and sink intrusion limit construction method for treating wind accumulated sand loess tunnel through stride shed pipe
CN109488202A (en) A kind of gravel rock stratum pile foundation drilling construction engineering method containing gravel-boulder bed
CN109537583A (en) A kind of slip casting plant pile construction method of PHC tubular pole
CN108316291A (en) Deep mud pit cast-in-situ bored pile and construction method
CN107653889A (en) A kind of shaped steel pressure is poured water the construction method of soil curtain support pile
CN105369800B (en) One-time forming construction method for inserting steel pipe column into cast-in-situ bored pile in pilot tunnel
CN111364449A (en) Construction method and structure for penetrating karst cave of precast tubular pile
CN106284311B (en) A kind of dry efficient construction technology of pore-forming cast-in-place concrete pile of rotary drilling rig
CN107587502A (en) A kind of spiral-digging pore pressure pour water soil occlusion curtain pile construction method
CN201241329Y (en) Positioner of steel pipe column
CN106087996B (en) Manual digging pile construction method based on self leveling backpressure device
CN105064334A (en) Construction method for cast-in-situ bored pile
CN207582471U (en) A kind of Retaining Structure with Double-row Piles equipped with deep layer prestress anchorage cable
CN110762286B (en) Drainage pipe network artificial pipe jacking construction process
CN110295593A (en) A kind of hypogee lid digs the construction technology of steel pipe column
CN215669558U (en) Front-mounted inclined pile of foundation pit supporting system
CN1648402A (en) Root pile buried pipe excavator
CN107975027A (en) The construction method that shield launching is reinforced with reaching end soil body
CN205314093U (en) Excavation supporting structure of stake
CN114059921A (en) Hole-forming construction process for cast-in-place pile in karst strong development area
CN108049424A (en) Sunk type basement structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191001