CN110282577A - A kind of device and construction method of the field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation - Google Patents
A kind of device and construction method of the field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation Download PDFInfo
- Publication number
- CN110282577A CN110282577A CN201910606109.2A CN201910606109A CN110282577A CN 110282577 A CN110282577 A CN 110282577A CN 201910606109 A CN201910606109 A CN 201910606109A CN 110282577 A CN110282577 A CN 110282577A
- Authority
- CN
- China
- Prior art keywords
- reinforced plastic
- plastic tank
- glass fiber
- fiber reinforced
- tank
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000011152 fibreglass Substances 0.000 title claims abstract description 93
- 238000009434 installation Methods 0.000 title claims abstract description 35
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 27
- 238000005260 corrosion Methods 0.000 title claims abstract description 26
- 238000010276 construction Methods 0.000 title claims abstract description 25
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 18
- 239000010959 steel Substances 0.000 claims abstract description 18
- 239000011521 glass Substances 0.000 claims abstract description 10
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims description 14
- 230000006641 stabilisation Effects 0.000 claims description 6
- 238000011105 stabilization Methods 0.000 claims description 6
- 230000002787 reinforcement Effects 0.000 claims description 3
- 239000011248 coating agent Substances 0.000 abstract description 7
- 238000000576 coating method Methods 0.000 abstract description 7
- 230000003628 erosive effect Effects 0.000 abstract description 7
- 230000006378 damage Effects 0.000 abstract description 5
- 238000011900 installation process Methods 0.000 abstract description 3
- 230000010354 integration Effects 0.000 abstract description 2
- 230000032258 transport Effects 0.000 description 55
- 238000000034 method Methods 0.000 description 8
- 238000010586 diagram Methods 0.000 description 6
- 230000008569 process Effects 0.000 description 6
- 238000003466 welding Methods 0.000 description 4
- 238000003860 storage Methods 0.000 description 3
- 239000000126 substance Substances 0.000 description 2
- 238000012935 Averaging Methods 0.000 description 1
- 230000009471 action Effects 0.000 description 1
- 230000037396 body weight Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009854 hydrometallurgy Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005272 metallurgy Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 230000002441 reversible effect Effects 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B61—RAILWAYS
- B61D—BODY DETAILS OR KINDS OF RAILWAY VEHICLES
- B61D15/00—Other railway vehicles, e.g. scaffold cars; Adaptations of vehicles for use on railways
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66F—HOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
- B66F7/00—Lifting frames, e.g. for lifting vehicles; Platform lifts
- B66F7/10—Lifting frames, e.g. for lifting vehicles; Platform lifts with platforms supported directly by jacks
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66F—HOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
- B66F7/00—Lifting frames, e.g. for lifting vehicles; Platform lifts
- B66F7/22—Lifting frames, e.g. for lifting vehicles; Platform lifts with tiltable platforms
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66F—HOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
- B66F7/00—Lifting frames, e.g. for lifting vehicles; Platform lifts
- B66F7/28—Constructional details, e.g. end stops, pivoting supporting members, sliding runners adjustable to load dimensions
Abstract
The present invention provides the device and construction method of a kind of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation, including rail module, running gear, lifting support and curved support part, wherein, rail module rides upon above erosion resistant coating, orbit connection glass fiber reinforced plastic tank rolls region and glass fiber reinforced plastic tank installation region, running gear is driven mobile in orbit by hoist engine, lifting support rides upon on running gear, location hole is equipped on lifting support and running gear, it is connected by pin shaft, running gear is equipped with the height that jack is used to adjust lifting support, curved support part rides upon on lifting support, bearing glass cylinder of steel, the present invention is by the production of glass fiber reinforced plastic tank in anti-corrosion foundation, transport, installation integration, streamlined, it reduces equipment conveying cost and improves production, installation effectiveness, erosion resistant coating in entire manufacture and installation process on the basis of Without destruction.
Description
Technical field
The invention belongs to chemical industry, technical field of wet metallurgy, make peace in anti-corrosion foundation more particularly, to one kind
The device and construction method of glaze steel group's tank.
Background technique
The industries such as chemical industry, hydrometallurgy usually have the glass fiber reinforced plastic tank storage tank equipment of enormous amount, and this kind of equipment is by transport item
Part restricts and the limitation of economy, is often made, transported and is installed in erecting bed, and continuous productive process is formed, and reduction is set
Standby long-distance transport cost and raising system peace efficiency.Meanwhile the tank body rapid wear of glass steel material, to avoid transport and hoisting process from working as
In, its unnecessary damage is caused, fabrication and installation are also necessary at the scene.In addition, to avoid the erosion resistant coating on the basis of from making
It at damage, needs to take corresponding measure, avoids tank body from having bad luck process and anticorrosion basic unit is damaged.The art of this patent is namely based on
The above reason development is mainly organically merged by being made and being installed the technology of two links, to realize live glass
The peace integration of glass cylinder of steel system, the construction efficiency purpose at the scene of improving.
Summary of the invention
The present invention has made improvements in view of the above-mentioned problems of the prior art, i.e., the present invention provides one kind in anti-corrosion foundation
The device and construction method of field fabrication installation glass reinforced plastic group tank, continuous productive process production and installation glass fiber reinforced plastic tank storage tank equipment, drop
Low equipment conveying cost and raising, which are made, pacifies efficiency, and the erosion resistant coating in manufacture and installation process on the basis of is without destruction.
In order to solve the above technical problem, the present invention provides one kind to make installation glass reinforced plastic group tank in anti-corrosion foundation
Device and construction method, including rail module, running gear, lifting support and curved support part, wherein
The rail module includes two parallel tracks and and the connector that is arranged between two tracks;
The running gear includes pedestal, and the pedestal is boxed frame structure, and support column, institute are provided on the pedestal
Stating support column is box-structure, setting location hole in interval on the support column, and aperture places thousand at the support column bottom web
Jin top, the base side are provided with multiple traveling wheels, and the traveling wheel is adapted with the track;
The lifting support includes vertical supporting element and horizontal support member, is provided on the vertical supporting element and the branch
The compatible location hole of location hole on dagger, the lifting support are connected by location hole with pin shaft with the running gear,
The vertical supporting element is socketed the support column and opposite sliding occurs in vertical direction, and the jack is located at lifting branch
Below frame;
The curved support part includes arc panel and the fixing card for being fixed on arc panel two sides, the fixing card and the liter
The vertical supporting element upper end of descending branch frame overlaps, and the radian of the arc panel is consistent with glass fiber reinforced plastic tank radian.
Preferably, welding is equipped with support base in the fixing card, and the support base size is greater than the vertical supporting element hole
Diameter, the support base ride over and the weight of the curved support part and glass fiber reinforced plastic tank stabilization are transmitted to the lifting on vertical supporting element
Bracket.
Preferably, traction piece is fixedly installed on the forward and backward side of the pedestal.
Preferably, reinforcement by connection part is welded between the vertical supporting element and the horizontal support member.
Preferably, the arc panel upper surface is equipped with rubber slab for protecting glass fiber reinforced plastic tank.
Preferably, rubber slab is equipped with below the track.
The invention also discloses a kind of construction methods, comprising the following steps:
1. being laid with track;
2. running gear, lifting support and curved support part are completed transport vehicle, transport vehicle is moved to glass reinforced plastic
Tank body rolls below region;
3. the height of the lifting support using jack adjustment transport vehicle, rolling its arc panel height with glass fiber reinforced plastic tank makes
Mold height coincide, the assembling of traveling mold;
4. after set of molds fills, the lifting support of the transport vehicle being reduced using jack, meets mold rotation
It is required that glass fiber reinforced plastic tank rolls;
After the completion of 5. glass fiber reinforced plastic tank rolls, using the height of jack Lifting Convey vehicle lifting support to the curved support
Part is contacted with glass fiber reinforced plastic tank external surface, and gradually the stable glass fiber reinforced plastic tank weight power that is promoted to is entirely applied to curved support part
On, mold is removed, jack is fallen after rise, while connecting the lifting support of transport vehicle and running gear by location hole using pin shaft
It connects;
6. passing through the traction piece of traction device connection transportation vehicle, glass reinforced plastic tank body is transported into reserved installation site, it is fixed
Keep transport vehicle motionless;
7. glass reinforced plastic tank body is sling, overturn, removes track, glass reinforced plastic tank body is placed into scheduled installation site.
Preferably, step 2. in, cooperated according to the multiple transport vehicles of the length of glass fiber reinforced plastic tank selection, it is multiple described
It is connected by the traction piece with connector between transport vehicle.
Preferably, step 7. in, glass reinforced plastic tank body sling before by the connector of the traction piece between adjacent transport vehicle
Connection is released sequentially to remove the transport vehicle for lifting by crane end during the lifting of glass reinforced plastic tank body.
Preferably, step 1. in, two track ends are fixed with the workshop column of its two sides respectively, it is ensured that entire track
The stabilization of system.
Through the above technical solution, glass fiber reinforced plastic tank storage tank equipment from produce, roll to transport, install in workshop into
Row, transportation range, time are very short, streamlined operation, improve the efficiency of system peace, reduce overall cost, entirely produced
Cheng Zhong, the device and components released with erosion resistant coating is laid with rubber pad, to erosion resistant coating without destruction in construction, installation process.
Detailed description of the invention
Fig. 1 is a kind of side view of the device of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation of the embodiment of the present invention
Figure;
Fig. 2 is a kind of facing for the device of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation of the embodiment of the present invention
Figure;
Fig. 3 is a kind of walking of the device of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation of the embodiment of the present invention
The side view of device;
Fig. 4 is a kind of walking of the device of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation of the embodiment of the present invention
The front view of device;
Fig. 5 is a kind of lifting of the device of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation of the embodiment of the present invention
The structural schematic diagram of bracket;
Fig. 6 is a kind of arc of the device of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation of the embodiment of the present invention
The structural schematic diagram of supporting element;
Fig. 7 is the side view that transport vehicle transports glass fiber reinforced plastic tank reserved installation site in the construction method of the embodiment of the present invention
Figure;
Fig. 8 is that glass fiber reinforced plastic tank is transported facing for reserved installation site by transport vehicle in the construction method of the embodiment of the present invention
Figure;
Fig. 9 is the construction signal for removing part transport vehicle in the construction method of the embodiment of the present invention after glass fiber reinforced plastic tank lifting
Figure;
Figure 10 is that last transport vehicle moves backward during glass fiber reinforced plastic tank lifting in the construction method of inventive embodiments
Construction schematic diagram;
Figure 11 is to be placed in pre-installed position after glass fiber reinforced plastic tank overturning in the construction method of the embodiment of the present invention;
Figure 12 is the front view of glass fiber reinforced plastic tank lifting process in the construction method of the embodiment of the present invention;
Figure 13 is a kind of fortune of the device of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation of the embodiment of the present invention
The connected mode schematic diagram of defeated vehicle;
In figure:
1, pedestal 2, support column 3, lifting support
31, vertical supporting element 32, horizontal support member 33, reinforcement by connection part
4, curved support part 41, arc panel 42, fixing card
43, support base 5, traction piece 6, traveling wheel
7, location hole 8, glass fiber reinforced plastic tank 9, connector
10, the ground after track 11, glass fiber reinforced plastic tank basis 12, anticorrosive construction
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description.Obviously, described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that term " center ", "front", "rear", "upper", "lower", " left side ",
The orientation or positional relationship of the instructions such as " right side ", "vertical", "horizontal", "inner", "outside" is orientation based on the figure or position
Relationship is merely for convenience of description of the present invention and simplification of the description, rather than the device or element of indication or suggestion meaning must have
There is specific orientation, be constructed and operated in a specific orientation, therefore is not considered as limiting the invention.
The present invention provides the device and construction method of a kind of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation, device
Including rail module, running gear, lifting support 3 and curved support part 4.
Illustratively, Fig. 3, Fig. 4 are that one kind of the embodiment of the present invention makes installation glass in anti-corrosion foundation respectively
The side view and front view of the running gear of the device of steel group's tank, wherein running gear includes pedestal 1, and pedestal 1 is combined by channel steel
The boxed frame being welded.4 support columns 2 are equipped on the left side, right side of pedestal 1, support column 2 combines weldering by channel steel
Box-structure is connect, support column is symmetrical, and location hole 7 is equipped at intervals on support column 2, and lancing can be used in support column 2 in scene
Location hole 7 is cut on web.The left and right side of pedestal 1 is provided with traveling wheel 6.Preferred a kind of scheme, in pedestal 1
Leading flank, trailing flank are provided with traction piece 5.A kind of preferred scheme, raise-lower hydraulic is placed in aperture at 2 bottom web of support column
Jack, the jack are located at 3 lower section of lifting support, can realize the effect for adjusting height by jacking up lifting support 3.
Wherein, traction piece 5, for example, being connect with hoist engine and wirerope with traction piece 5, can be incited somebody to action with external connection power equipment
Specified position is dragged to by the transport vehicle that running gear, lifting support 3 and curved support part 4 form.
Wherein, if glass fiber reinforced plastic tank excessive height, the single transport vehicle is unable to satisfy transportation function, can will it is multiple described in
It is connected between transport vehicle by the connector 9 of traction piece 5, multiple transport vehicles cooperation transporting glass cylinder of steels.
Illustratively, Fig. 5 is a kind of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation of the embodiment of the present invention
The structural schematic diagram of the lifting support 3 of device, lifting support 3 include vertical supporting element 31 and horizontal support member 32.Preferably, it erects
Allotment support member 31 and horizontal support member 32 can use channel steel Combination Welding box-structure, set up separately on vertical supporting element 31 and are equipped with and support
The compatible location hole of location hole 7 on column 2, lifting support 3 and running gear use pin shaft by the location hole 7 on support column 2
Connection, the location hole 7 of different height determine that lifting support 3 is in different height.Vertical supporting element 31 is socketed in support column 2
Together, the two can do sliding relative movement.
Illustratively, the dress of a kind of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation of Fig. 6 embodiment of the present invention
The structural schematic diagram for the curved support part 4 set, curved support part 4 include arc panel 41 and the fixation for being fixed on 41 two sides of arc panel
Card 42, it is preferred that fixing card 42 is welded using channel steel, it is further preferred that connection type is welding.Preferably, fixed
The size of card 42 is less than the size of vertical supporting element 31, and fixing card 42 protrudes into vertical supporting element 31 from vertical 31 upper end of supporting element
Inner space.
Wherein, the radian of arc panel 41 and the radian of glass fiber reinforced plastic tank are consistent.A kind of preferred scheme, 41 upper surface of arc panel
Equipped with rubber slab, for protecting glass fiber reinforced plastic tank outer surface not to be damaged.
Wherein, preferred a kind of scheme, welding is equipped with support base 43 in fixing card 42, it is preferred that support base 43 uses slot
Steel is welded, and 43 size of support base is greater than the size of vertical supporting element 31, for by the weight of curved support part 4 and glass fiber reinforced plastic tank
Stable delivery is measured to the lifting support 3, improves the stability of device.
Illustratively, Fig. 1, Fig. 2 are respectively that one kind of the embodiment of the present invention makes installation glass in anti-corrosion foundation
The traveling wheel 6 of the side view and front view of the device of steel group's tank, running gear rolls on guide rail 10, sets between two guide rails 10
There is connector, it is preferred that guide rail 10 selects channel steel to be welded, it is preferred that two tracks 10 are spaced 3 meters and use angle steel as company
Fitting is welded to connect.
Wherein, lifting support 3 is socketed on support column 2, and lifting support 3 and support column 2 are solid with pin shaft by location hole 7
It is fixed.Curved support part 4 is socketed on lifting support 3.
The invention also discloses a kind of construction methods, comprising the following steps:
1. being laid with track;
2. running gear, lifting support 3 and curved support part 4 are completed transport vehicle, transport vehicle is moved to glass
Cylinder of steel body rolls below region;
3. the height of the lifting support 3 using jack adjustment transport vehicle, rolls up its 41 height of arc panel with glass fiber reinforced plastic tank
It makes the mold height used to coincide, the assembling of traveling mold;
4. the lifting support 3 of the transport vehicle is reduced using jack, meets mold rotation after set of molds fills
It is required that glass fiber reinforced plastic tank rolls;
After the completion of 5. glass fiber reinforced plastic tank rolls, using the height of jack Lifting Convey vehicle lifting support 3 to curved support part 3
It is contacted with glass fiber reinforced plastic tank external surface, and gradually the stable glass fiber reinforced plastic tank weight power that is promoted to is entirely applied on curved support part 3,
Mold is removed, jack is fallen after rise, while connecting the lifting support 3 of transport vehicle by location hole 7 with running gear using pin shaft;
6. passing through the traction piece 5 of traction device connection transportation vehicle, glass reinforced plastic tank body is transported into reserved installation site, it is fixed
Keep transport vehicle motionless;
7. glass reinforced plastic tank body is sling, overturn, removes track 10, glass reinforced plastic tank body is placed into scheduled installation site.
A kind of preferred scheme, step 2. in, cooperated according to the multiple transport vehicles of the length of glass fiber reinforced plastic tank selection,
It is connected between multiple transport vehicles by the connector 9 of traction piece 5.
A kind of preferred scheme, step 7. in, glass reinforced plastic tank body sling before by the traction piece 5 between adjacent transport vehicle
Connector 9 release connection, glass reinforced plastic tank body lifting during, sequentially the transport vehicle for lifting by crane end is removed.
A kind of preferred scheme, step 1. in, workshop column of two 10 ends of track respectively with its two sides is fixed, really
Protect the stabilization of entire rail system.
Workflow of the invention: such as Fig. 7, before construction, first track 10 is arranged on the ground of travel region, track 10
The rubber slab of 5mm is set between glass fiber reinforced plastic tank basis, to protect it from damaging the erosion resistant coating on glass fiber reinforced plastic tank basis 11.
Two tracks 10 are spaced 3 meters and are welded to connect using angle steel, and two tracks 10 are consolidated with the workshop column of its two sides respectively
It is fixed, it is ensured that the stabilization of entire rail system.
Transport vehicle is placed on track 10, as shown in figure 13, multiple transport vehicles are used into connector 9 sequentially by bail 5
Transport vehicle is then pulled to tank body with hoist engine and rolls region by connection, is adjusted in synchronism jack and then is adjusted the height of transport vehicle,
Its 41 height of arc panel is set to coincide with the mold height used is rolled, the assembling of traveling mold.
After set of molds dress to be produced, reuses jack and be reduced to transport vehicle lifting support 3 and meet mold
The requirement of rotation.
After glass fiber reinforced plastic tank rolls, the lifting support 3 of transport vehicle is promoted and glass fiber reinforced plastic tank outer surface using jack
Contact, and gradually the stable glass fiber reinforced plastic tank body weight that is promoted to falls on transport vehicle the condition for meeting mold dismounting.It has been removed to mold
Bi Hou, jack fall after rise and withdraw, while company is fixed in the lifting support 3 of transport vehicle and running gear using alignment pin
It connects.
Glass fiber reinforced plastic tank transport, hoist engine wirerope is connect with the traction piece 5 of transport vehicle end, and starting hoist engine makes to transport
Defeated vehicle slowly runs to pre-installed position along track 10.
Transport vehicle is fixed on pre-installed position, it is preferred that in the forward and backward setting block of traveling wheel 6 of transport vehicle, remove volume
The wirerope of machine is raised, removing connector 9 makes each transport vehicle be in separate state.
Glass fiber reinforced plastic tank lifting overturning, is bundled at the top of glass fiber reinforced plastic tank using rope winding and 1/3 or more is located, two elevators
Sling is oriented to by pulley and is connect with the lash rope on glass fiber reinforced plastic tank, and the forward and backward block of transport vehicle traveling wheel 6 is dismantled, and is had
The condition of standby overturning lifting.
Overturning and in place, two hoist engines of synchronous averaging slowly promote glass fiber reinforced plastic tank top until transport fortune below
The First transport vehicle of glass fiber reinforced plastic tank below an upper section is moved away, is continued to lift up by the no longer load-bearing of defeated vehicle, and second transport vehicle is moved
It opens then to connect the traction piece 5 of the wirerope of hoist engine glass cylinder of steel upper end close with third platform transport vehicle, starts elevator
Machine prevents overturning lifting process transport vehicle and the successive amplitude of fluctuation of tank body too big, causes hidden danger, continuous with height
It is promoted, third platform transport vehicle is under reversely the pulling of hoist engine, constantly along the slowly walking forward of track 10, until glass reinforced plastic
Tank completes overturning, is in plumbness, then moves third platform transport vehicle.Reverse operating promotes elevator and falls after rise just by glass fiber reinforced plastic tank
Position, assembling are fixed.
The embodiments of the present invention have been described in detail above, but content is only the preferred embodiment of the present invention,
It should not be considered as limiting the scope of the invention.Any changes and modifications in accordance with the scope of the present application,
It should still be within the scope of the patent of the present invention.
Claims (10)
1. a kind of device of the field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation, it is characterised in that: including rail module, row
Walking apparatus, lifting support and curved support part, wherein
The rail module includes two parallel tracks and and the connector that is arranged between two tracks;
The running gear includes pedestal, and the pedestal is boxed frame structure, and support column, the branch are provided on the pedestal
Dagger is box-structure, setting location hole in interval on the support column, and jack is placed in aperture at the support column bottom web,
The base side is provided with multiple traveling wheels, and the traveling wheel is adapted with the track;
The lifting support includes vertical supporting element and horizontal support member, is provided on the vertical supporting element and the support column
On the compatible location hole of location hole, the lifting support is connected by location hole with pin shaft with the running gear, described
Vertical supporting element is socketed the support column and opposite sliding occurs in vertical direction, and the jack is located under the lifting support
Side;
The curved support part includes arc panel and the fixing card for being fixed on arc panel two sides, and the fixing card and the lifting are propped up
The vertical supporting element upper end of frame overlaps, and the arc panel radian is consistent with glass fiber reinforced plastic tank radian.
2. a kind of device of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation according to claim 1, feature
Be: the fixing card is equipped with support base, and the support base size is greater than the vertical supporting element aperture, and the support base is taken
The weight of the curved support part and glass fiber reinforced plastic tank stabilization is transmitted to the lifting support on vertical supporting element.
3. a kind of device of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation according to claim 2, feature
It is: is fixedly installed traction piece on the forward and backward side of pedestal.
4. a kind of device of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation according to claim 3, feature
It is: is welded with reinforcement by connection part between the vertical supporting element and the horizontal support member.
5. a kind of device of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation according to claim 4, feature
Be: the arc panel upper surface is equipped with rubber slab for protecting glass fiber reinforced plastic tank.
6. a kind of device of field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation according to claim 3, feature
It is: is equipped with rubber slab below the track.
7. a kind of using glass is installed in field fabrication in anti-corrosion foundation described in claim 1 to 6 any one claim
The construction method of steel group's tank, which comprises the following steps:
1. being laid with track;
2. running gear, lifting support and curved support part are completed transport vehicle, transport vehicle is moved to glass reinforced plastic tank body
It rolls below region;
3. the height of the lifting support using jack adjustment transport vehicle, makes its arc panel height and glass fiber reinforced plastic tank is rolled and used
Mold height coincide, the assembling of traveling mold;
After 4. set of molds fills, the lifting support of the transport vehicle is reduced using jack, meets the requirement of mold rotation,
Glass fiber reinforced plastic tank rolls;
After the completion of 5. glass fiber reinforced plastic tank rolls, using jack Lifting Convey vehicle lifting support height to the curved support part with
The contact of glass fiber reinforced plastic tank external surface, and gradually the stable glass fiber reinforced plastic tank weight power that is promoted to is entirely applied on curved support part, is torn open
Except mold, jack is fallen after rise, while being connect the lifting support of transport vehicle by location hole with running gear using pin shaft;
6. passing through the traction piece of traction device connection transportation vehicle, glass reinforced plastic tank body is transported into reserved installation site, fixation makes to transport
Defeated vehicle is motionless;
7. glass reinforced plastic tank body is sling, overturn, removes track, glass reinforced plastic tank body is placed into scheduled installation site.
8. construction method according to claim 7, which is characterized in that step 2. in, according to the length of glass fiber reinforced plastic tank select
Multiple transport vehicles cooperate, and are connected by the traction piece with connector between multiple transport vehicles.
9. construction method according to claim 8, which is characterized in that step 7. in, glass reinforced plastic tank body sling before by phase
Connector between adjacent transport vehicle releases connection, and during the lifting of glass reinforced plastic tank body, the transport vehicle for sequentially nearly lifting by crane end is moved
It walks.
10. construction method according to claim 7, which is characterized in that step 1. in, two track ends respectively with its two sides
Workshop column be fixed, it is ensured that the stabilization of entire rail system.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910606109.2A CN110282577B (en) | 2019-07-05 | 2019-07-05 | Device for manufacturing and installing glass fiber reinforced plastic group tank on site on anti-corrosion basis and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910606109.2A CN110282577B (en) | 2019-07-05 | 2019-07-05 | Device for manufacturing and installing glass fiber reinforced plastic group tank on site on anti-corrosion basis and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110282577A true CN110282577A (en) | 2019-09-27 |
CN110282577B CN110282577B (en) | 2023-10-31 |
Family
ID=68020760
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910606109.2A Active CN110282577B (en) | 2019-07-05 | 2019-07-05 | Device for manufacturing and installing glass fiber reinforced plastic group tank on site on anti-corrosion basis and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110282577B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113428796A (en) * | 2021-06-30 | 2021-09-24 | 石家庄职业技术学院 | Short-distance displacement lifting device for chemical production |
Citations (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0586723A (en) * | 1991-09-27 | 1993-04-06 | Japan Steel & Tube Constr Co Ltd | Turning type scaffolding device for storage tank roof construction |
US20020005334A1 (en) * | 2000-07-12 | 2002-01-17 | Murata Kikai Kabushiki Kaisha | Conveying device with plurality of running motors |
US20050067129A1 (en) * | 2001-10-11 | 2005-03-31 | Falck Giorgio Enrico | Method for the production of hollow ingots of a metallic material or of a plurality of metallic materials |
CN101575907A (en) * | 2009-06-05 | 2009-11-11 | 中建三局建设工程股份有限公司 | Lateral mobile mould base with multi-supports for bridge construction |
CN201592969U (en) * | 2009-11-02 | 2010-09-29 | 杭州钱江电气集团股份有限公司 | Movable lifting trolley |
CN102513787A (en) * | 2011-12-08 | 2012-06-27 | 中国海洋石油总公司 | Process for production line of an ocean engineering structural steel pipes |
JP2013079515A (en) * | 2011-10-04 | 2013-05-02 | Takenaka Komuten Co Ltd | Cutting/demolition method for concrete filling steel tube column and steel tube cutting device |
CN104476192A (en) * | 2014-11-27 | 2015-04-01 | 山东兴邦工业装备有限公司 | Automatic winding and forming device of tank and forming method |
CN204379755U (en) * | 2014-12-26 | 2015-06-10 | 四川工程职业技术学院 | A kind of Ai Zhu machine for rolling and molding |
CN106082012A (en) * | 2016-08-29 | 2016-11-09 | 中国冶集团有限公司 | Piping lane interior conduit transport erecting device |
CN205777592U (en) * | 2016-07-01 | 2016-12-07 | 中建一局集团安装工程有限公司 | A kind of height adjustable moves assembled Pipeline lift auxiliary device |
CN106352158A (en) * | 2016-11-30 | 2017-01-25 | 二十二冶集团天津建设有限公司 | Pipe gallery pipeline transporting and installing method |
CN107598008A (en) * | 2017-08-03 | 2018-01-19 | 台山市万通罐机工业有限公司 | One kind tank processing unit (plant) |
CN107697849A (en) * | 2017-10-31 | 2018-02-16 | 上海宝冶集团有限公司 | Pipeline lift car and its application method in restricted clearance |
CN207112124U (en) * | 2017-08-10 | 2018-03-16 | 盖文哲 | A kind of chemical proof floor conveyance conduit |
CN108560927A (en) * | 2018-01-25 | 2018-09-21 | 涿州蓝天网架有限公司 | A kind of Lift-on/Lift-off System and its application method of reinforced concrete column |
CN108591612A (en) * | 2018-04-23 | 2018-09-28 | 江苏谷登工程机械装备有限公司 | A kind of ejector sleeve device |
CN210457330U (en) * | 2019-07-05 | 2020-05-05 | 中冶天工集团有限公司 | Device for manufacturing and installing glass fiber reinforced plastic group tank on anti-corrosion basis on site |
-
2019
- 2019-07-05 CN CN201910606109.2A patent/CN110282577B/en active Active
Patent Citations (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0586723A (en) * | 1991-09-27 | 1993-04-06 | Japan Steel & Tube Constr Co Ltd | Turning type scaffolding device for storage tank roof construction |
US20020005334A1 (en) * | 2000-07-12 | 2002-01-17 | Murata Kikai Kabushiki Kaisha | Conveying device with plurality of running motors |
US20050067129A1 (en) * | 2001-10-11 | 2005-03-31 | Falck Giorgio Enrico | Method for the production of hollow ingots of a metallic material or of a plurality of metallic materials |
CN101575907A (en) * | 2009-06-05 | 2009-11-11 | 中建三局建设工程股份有限公司 | Lateral mobile mould base with multi-supports for bridge construction |
CN201592969U (en) * | 2009-11-02 | 2010-09-29 | 杭州钱江电气集团股份有限公司 | Movable lifting trolley |
JP2013079515A (en) * | 2011-10-04 | 2013-05-02 | Takenaka Komuten Co Ltd | Cutting/demolition method for concrete filling steel tube column and steel tube cutting device |
CN102513787A (en) * | 2011-12-08 | 2012-06-27 | 中国海洋石油总公司 | Process for production line of an ocean engineering structural steel pipes |
CN104476192A (en) * | 2014-11-27 | 2015-04-01 | 山东兴邦工业装备有限公司 | Automatic winding and forming device of tank and forming method |
CN204379755U (en) * | 2014-12-26 | 2015-06-10 | 四川工程职业技术学院 | A kind of Ai Zhu machine for rolling and molding |
CN205777592U (en) * | 2016-07-01 | 2016-12-07 | 中建一局集团安装工程有限公司 | A kind of height adjustable moves assembled Pipeline lift auxiliary device |
CN106082012A (en) * | 2016-08-29 | 2016-11-09 | 中国冶集团有限公司 | Piping lane interior conduit transport erecting device |
CN106352158A (en) * | 2016-11-30 | 2017-01-25 | 二十二冶集团天津建设有限公司 | Pipe gallery pipeline transporting and installing method |
CN107598008A (en) * | 2017-08-03 | 2018-01-19 | 台山市万通罐机工业有限公司 | One kind tank processing unit (plant) |
CN207112124U (en) * | 2017-08-10 | 2018-03-16 | 盖文哲 | A kind of chemical proof floor conveyance conduit |
CN107697849A (en) * | 2017-10-31 | 2018-02-16 | 上海宝冶集团有限公司 | Pipeline lift car and its application method in restricted clearance |
CN108560927A (en) * | 2018-01-25 | 2018-09-21 | 涿州蓝天网架有限公司 | A kind of Lift-on/Lift-off System and its application method of reinforced concrete column |
CN108591612A (en) * | 2018-04-23 | 2018-09-28 | 江苏谷登工程机械装备有限公司 | A kind of ejector sleeve device |
CN210457330U (en) * | 2019-07-05 | 2020-05-05 | 中冶天工集团有限公司 | Device for manufacturing and installing glass fiber reinforced plastic group tank on anti-corrosion basis on site |
Non-Patent Citations (2)
Title |
---|
武旭升;彭育芬;张晓飞;: "干海子大桥非标准尺寸管径钢管现场卷制技术", 铁道建筑技术, no. 09, pages 86 - 88 * |
赵清: "大型贮罐制作时用的简易起重法", 石油化工设备, no. 12, pages 31 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113428796A (en) * | 2021-06-30 | 2021-09-24 | 石家庄职业技术学院 | Short-distance displacement lifting device for chemical production |
CN113428796B (en) * | 2021-06-30 | 2022-05-17 | 石家庄职业技术学院 | Short-distance displacement lifting device for chemical production |
Also Published As
Publication number | Publication date |
---|---|
CN110282577B (en) | 2023-10-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN2898099Y (en) | Crane trolley for spreading lane board in tunnel | |
CN109653105B (en) | Main truss system of box girder bridge cantilever construction hanging basket and use method thereof | |
CN112627059A (en) | Pier-beam integrated bridge girder erection machine and via hole construction method | |
CN110282577A (en) | A kind of device and construction method of the field fabrication installation glass reinforced plastic group tank in anti-corrosion foundation | |
CN102190249A (en) | Method for hoisting equipment positioned at bottom of multilayer frame platform | |
CN212251443U (en) | Special pipeline of old factory building dust removal pipeline transformation installation removes hoist device | |
CN102145353B (en) | O-forming machine mounting method | |
CN108625270A (en) | Nose girder gantry crane installs bridge prefabrication box girder construction method | |
CN102774624B (en) | Overhaul and transport vehicle and overhauling and transport method | |
CN108004930A (en) | The construction method of vertical shift bowstring arch bridge | |
CN110758421B (en) | Vehicle maintenance vehicle suitable for air rail transit system | |
CN210457330U (en) | Device for manufacturing and installing glass fiber reinforced plastic group tank on anti-corrosion basis on site | |
CN112030777A (en) | Descending movable formwork support bracket crossing type transfer construction method | |
CN101314801B (en) | Cross sliding type sublance system | |
CN113944323B (en) | Ultra-high concrete roof template support and construction system | |
CN113602963B (en) | Monorail crane installation method | |
CN201849911U (en) | Conveying device for heavy equipment | |
CN214828509U (en) | Single case roof beam bank bridge is with operation dolly | |
CN205836825U (en) | Railway D type construction beam vertical shift accessory cart | |
CN201309802Y (en) | Walking assembly-type gantry hoisting apparatus | |
CN210480630U (en) | Heavy roller transport means | |
CN209795521U (en) | Steel pipe travelling bogie with lifting and steering device | |
CN202703378U (en) | Maintenance carrier vehicle of water feeding pump motor | |
CN207347856U (en) | Railway track construction is hung with just beam is traversing | |
CN220013239U (en) | Portable rail collecting and paving machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |