CN110263460A - A kind of assembled 4D construction simulation safety monitoring system based on BIM - Google Patents

A kind of assembled 4D construction simulation safety monitoring system based on BIM Download PDF

Info

Publication number
CN110263460A
CN110263460A CN201910559001.2A CN201910559001A CN110263460A CN 110263460 A CN110263460 A CN 110263460A CN 201910559001 A CN201910559001 A CN 201910559001A CN 110263460 A CN110263460 A CN 110263460A
Authority
CN
China
Prior art keywords
construction
bim
component
assembled
early warning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910559001.2A
Other languages
Chinese (zh)
Inventor
张太玥
杨化奎
刘伟宏
王斯海
钱野
温巍
陆近涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Textile Vocational Technology College
Original Assignee
Nantong Textile Vocational Technology College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Textile Vocational Technology College filed Critical Nantong Textile Vocational Technology College
Priority to CN201910559001.2A priority Critical patent/CN110263460A/en
Publication of CN110263460A publication Critical patent/CN110263460A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • G06F30/23Design optimisation, verification or simulation using finite element methods [FEM] or finite difference methods [FDM]
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention discloses a kind of assembled 4D construction simulation safety monitoring system based on BIM, including on-site supervision management system, BIM assembled 4D construction simulation system, ABAQUS FEM calculation system and remote data acquisition system;The two-dimentional code labeling in scene is carried out to the component of assembled architecture by field monitoring management system, collects that the factory information of component, scantling, construction material, component is put in storage and information, the component installation location of outbound.The present invention can accomplish the people to scene, material, effective allotment of machine, ensure construction speed and construction quality, stress is acquired in the embedding sensing element of element joints, strain, displacement data, increase monitoring race's module by secondary development Revit software shows the safety classification color of sensing element to warn during 4D construction simulation, when unpredictable deformation and crack occurring assembled architecture is in load-bearing, it can be with on-call maintenance or evacuating people, and utilize the clear damaged part of visualization, manpower and material resources are reduced to be detected, avoid the preferably opportunity for therefore delaying maintenance.

Description

A kind of assembled 4D construction simulation safety monitoring system based on BIM
Technical field
The present invention relates to assembled architecture safety monitoring technology fields, more specifically, it relates to a kind of dress based on BIM With formula 4D construction simulation safety monitoring system.
Background technique
Construction industry has become one on sustainable development path because of Industrial Features such as high investment, high consumption, low circulations Only " roadblock ".Fabricated construction is built because the advantages that its speed of application is fast, construction quality is high, environmentally friendly, recyclable has become green The new support built simultaneously has obtained greatly developing for country.However the generally existing shock resistance of fabricated construction is poor, globality poor etc. lacks Point, such as existing defects, gently then causes crack, leakage etc. to find out its cause, the quality controllability of mainly component joint connection in site is poor Using upper problem, transmitting that is heavy then influencing power between component and component, component and support construction causes bearing capacity and secure side The problem of face, or even structure is caused to be disintegrated, the serious consequences such as collapse, therefore the construction monitoring emphasis of assembled architecture mainly exists In the joint connection in site construction of component.The modeling of BIM is complemented each other with assembled architecture, is all module construction, is realized using BIM The visualization safety monitoring of assembled architecture work progress seems particularly necessary.
Existing assembled 4D construction simulation safety monitoring system, cannot accomplish to scene people, material, machine effective tune Match, cannot ensure construction speed and construction quality, cannot corresponding data collection point show safety classification color to warn, when When unpredictable deformation and crack and leakage occur in load-bearing for assembled architecture, it is unable to on-call maintenance or withdraws Personnel, and cannot expend a large amount of manpower and material resources using clear damaged part is visualized and be detected, frequently result in therefore delay The preferably opportunity of maintenance, for this purpose, proposing a kind of assembled 4D construction simulation safety monitoring system based on BIM.
Summary of the invention
In view of the deficiencies of the prior art, the present invention intends to provide a kind of assembled 4D simulation based on BIM Cable construction safety monitoring system can accomplish effective allotment of the people, material, machine to scene, ensure construction speed and construction quality, Show that safety classification color to warn, occurs unpredictable assembled architecture is in load-bearing in corresponding data collection point Deformation and crack and when leakage, can subtract with on-call maintenance or evacuating people, and using clear damaged part is visualized Few manpower and material resources are detected, and avoid the preferably opportunity for therefore delaying maintenance, to solve the problems mentioned in the above background technology.
To achieve the above object, the present invention provides the following technical scheme that
A kind of assembled 4D construction simulation safety monitoring system based on BIM, including on-site supervision management system, BIM dress With formula 4D construction simulation system, ABAQUS FEM calculation system and remote data acquisition system;
The two-dimentional code labeling in scene is carried out by component of the field monitoring management system to assembled architecture, collects going out for component Factory's information, scantling, construction material, component storage and the information of outbound, component installation location, in component construction personnel's information Pass BIM cloud platform, the component relevant information can be transferred during assembled 4D construction simulation, accomplish to scene people, material, Effective allotment of machine ensures construction speed and construction quality;In the embedding sensing element in prefabricated member junction, by remotely counting ABAQUS FEM calculation system, which is imported, according to the ess-strain displacement data of acquisition system real-time collecting junction carries out stress point ABAQUS finite element model is analysed and generated, then is imported ABAQUS finite element model in Revit software by the port IFC, is passed through Critical touching shows safety classification color to early warning in corresponding data collection point.
Further, the on-site supervision management system is used to match each component in building element factory corresponding Two dimensional code, by scanning the two-dimensional code the factory information for being managed component, scantling, construction material, component storage and outbound Information, component installation location, component construction personnel's information;It is collected by the information of two dimensional code and uploads BIM cloud platform, the cloud is flat For the relatives of Taiwan compatriots living on the Mainland in web page operation, BIM model can also upload the platform simultaneously, and administrative staff are operated by logging in management account, The platform relevant information is transferred, component information and any stage for being in construction can be consulted, administrative staff is facilitated to slap The overall situation is held, it is very clear to fabricated construction process, it can effectively ensure construction speed and construction quality;Pass through on-site supervision system System can grasp position and the personnel of component installation in real time, can track situation and amendment in time to safe early warning.
Further, the real-time prison that the BIM assembled 4D construction simulation system is provided according to remote data acquisition system Measured data import finite element software in, calculate element joints real-time displacement, stress, strain, come judge junction safety, Stability, then will be imported in Revit when analysis fructufy, it is directly shown by BIM model, passes through the 4D construction simulation of BIM Assembled in situ formula work progress is instructed, secondary development is carried out to Revit software, increases the module of monitoring race, it can from 4D mould Transfer the module of monitoring in quasi- work progress, connection finite element analysis software analysis, will as the result is shown to during construction simulation, The general safety of real-time early warning fabricated construction, Revit monitor the exploitation of race, for transferring the information and stress of each monitoring race Situation, monitoring race directly display safety during 4D construction simulation by color difference, realize assembled architecture construction peace BIM model is finally uploaded BIM cloud platform by the visualization of full early warning, real time implementation, and each side by participating in construction can be at any time in electricity Brain, mobile phone, IPAD and other mobile terminals check that work progress monitors situation.
Further, the BIM assembled 4D construction simulation system is by BIM software, in construction horizontal layout, construction party These three aspects of case simulation and progress control establish the 4D construction simulation of assembled architecture, according to project site plan, apply Work figure, site contour figure, place size, existing water source, available house and facility etc., in accordance with the provisions of the relevant regulations issued by the State, rationally Design and construction plan view, and place three-dimensional modeling is realized using Civi 3D;According to the engineering construction figure, soil is completed using Revit Engineering BIM model creation is built, attempts the BIM model creation for carrying out installation profession, and carry out collision detection using Navisworks, Evade " mistakes and omissions are touched scarce " in work progress in advance;From engineering reality, sequence of construction, construction organization and construction party are selected Method, defines component sequence of construction and movement relation in BIM model, and counterweight difficult point part-to-item project carries out 4D arrangement and method for construction mould It is quasi-;It is rationally worked out using MS Project and Optimizing construction schedule, reality associated with BIM model by Navisworks The 4D construction simulation of existing overall process and the real-time update of schedule.
Further, the ABAOUS FEM calculation system is calculated by ABAOUS software, and the software is for establishing two dimension Model, while for generating threedimensional model, it is more careful that grid cell divides, and calculates more accurate.
Further, the ABAQUS finite element model Establishing process are as follows:
(1) material for defining each component, the preference pattern from the menu list of tree menu, enters back into characteristic value, Input material information in material data;
(2) cross section property for defining each component, the preference pattern from the menu list of tree menu, enters back into feature Value, defines cross section property on cross-section data, the size in the section, shape, title;
(3) node unit is established, node is established using the method that table generates node, utilizes the node of foundation, extension life At unit;
(4) buildings model entirety boundary condition is set, is fixed boundary condition at ground, the connection side of each component is set Boundary's condition, mutual interlocking;
(5) according to general stress condition analysis is built, mainly by static load, structural weight per square meter, flooring load, beam stress Load, and by the dynamic load in work progress, finally carry out the force analysis and linking parsing of monolithic architecture.
Further, when the remote data acquisition system is based on assembled architecture site operation, in each component The pre-buried sensing element in junction, uses Visual C++ for development platform, compiles out what teledata conduction was integrated with collection Software, the software are established by GPRS technology and field monitoring instrument and are communicated, and realize the long-range real-time reception storage of data, herein On the basis of the system should also include data real-time query, datagraphic visualization function.
Further, the safety classification color early warning includes following color early warning:
1), green early warning
The monitoring point of display green illustrates to carry out daily tour management at this time in stable and safety state, check The deformation of data conduction condition and Midas finite element software;
2), yellow early warning
Occur yellow early warning when load is loaded onto the 70% of control section ultimate load, monitors industry group in unit and lead to immediately Know that field operation group checks field device, while warning information is recorded, the position of record early warning appearance, early warning class Type, early warning value, normal value;
3), orange warning
There is orange warning when load is loaded onto the 80% of junction power limit load, monitors industry group in unit and lead to immediately Know that field operation group checks field device, and warning information recorded, record early warning occur position, early warning type, Early warning value, normal value, while interior industry group issues warning information to site operation project management department, project management department is connected to the warning information of publication After take stopping working measure, and Portable device is detected and is repaired to early warning position, until pre-warning signal releases;
4), red early warning
There is red early warning when load is loaded onto the 90% of junction power limit load, monitor in unit industry group immediately to Site operation project management department issues red early warning, and project management department is connected to after the warning information of publication takes stopping working measure at once, takes Carrying device is carried out detecting the degree of danger for judging the position and be repaired to early warning position, should manual demolition immediately if can not repair Risk factor zoning, or construction personnel is notified to withdraw, it constructs again again after releasing pre-warning signal.
In conclusion the present invention mainly has the advantages that
The assembled 4D construction simulation safety monitoring system based on BIM includes on-site supervision management system, BIM assembled 4D construction simulation system, ABAQUS FEM calculation system, remote data acquisition system, by field monitoring management system to dress Component with formula building carries out the two-dimentional code labeling in scene, collects the factory information of component, scantling, construction material, component and enters The information of library and outbound, component installation location, component construction personnel's information upload BIM cloud platform, in assembled 4D construction simulation The component relevant information can be transferred in the process, accomplishes effective allotment of the people, material, machine to scene, ensure construction speed and applied Working medium amount;In the embedding sensing element in prefabricated member junction, pass through answering for remote data acquisition system real-time collecting junction Stress-strain displacement data imports ABAQUS FEM calculation system and carries out force analysis, then by the port IFC that ABAQUS is limited Meta-model imports Revit software, by critical touching, in corresponding data collection point display safety classification color to warn, when When unpredictable deformation and crack and leakage occur in load-bearing for assembled architecture, with on-call maintenance or it can withdraw Personnel, and using clear damaged part is visualized, reduce manpower and material resources and are detected, avoid therefore delaying maintenance preferably when Machine.
Detailed description of the invention
Fig. 1 is a kind of configuration diagram of the assembled 4D construction simulation safety monitoring system based on BIM of embodiment;
Fig. 2 is the data transmission in a kind of assembled 4D construction simulation safety monitoring system based on BIM of embodiment Working principle diagram.
Specific embodiment
Below in conjunction with attached drawing 1-2, invention is further described in detail.
Embodiment
A kind of assembled 4D construction simulation safety monitoring system based on BIM, as shown in Figure 1, including on-site supervision management System, BIM assembled 4D construction simulation system, ABAQUS FEM calculation system and remote data acquisition system;
The two-dimentional code labeling in scene is carried out by component of the field monitoring management system to assembled architecture, collects going out for component Factory's information, scantling, construction material, component storage and the information of outbound, component installation location, in component construction personnel's information Pass BIM cloud platform, the component relevant information can be transferred during assembled 4D construction simulation, accomplish to scene people, material, Effective allotment of machine ensures construction speed and construction quality;In the embedding sensing element in prefabricated member junction, by remotely counting ABAQUS FEM calculation system, which is imported, according to the ess-strain displacement data of acquisition system real-time collecting junction carries out stress point ABAQUS finite element model is analysed and generated, then is imported ABAQUS finite element model in Revit software by the port IFC, is passed through Critical touching shows safety classification color to early warning in corresponding data collection point.
Preferably, the on-site supervision management system is used in building element factory to each component pairing corresponding two Code is tieed up, by scanning the two-dimensional code the factory information for being managed component, scantling, construction material, component storage and outbound Information, component installation location, component construction personnel's information;It is collected by the information of two dimensional code and uploads BIM cloud platform, the cloud platform Belong to web page operation, BIM model can also upload the platform simultaneously, and administrative staff operate by logging in management account, adjust The platform relevant information is taken, component information and any stage for being in construction can be consulted, administrative staff is facilitated to grasp The overall situation, it is very clear to fabricated construction process, it can effectively ensure construction speed and construction quality;Pass through Field Monitoring System Position and the personnel that component installation can be grasped in real time, can track situation and amendment to safe early warning in time.
Preferably, the real-time monitoring that the BIM assembled 4D construction simulation system is provided according to remote data acquisition system Data import in finite element software, calculate element joints real-time displacement, stress, strain, to judge the safety, steady of junction It is qualitative, then will analyze fructufy when import Revit in, directly shown by BIM model, by the 4D construction simulation of BIM come Assembled in situ formula work progress is instructed, secondary development is carried out to Revit software, increases the module of monitoring race, can be simulated from 4D Transfer the module of monitoring in work progress, connection finite element analysis software analysis will be real as the result is shown to during construction simulation When early warning fabricated construction general safety, Revit monitor race exploitation, for transfer it is each monitoring race information and stress feelings Condition, monitoring race are directly displayed safety by color difference during 4D construction simulation, realize assembled architecture construction safety BIM model is finally uploaded BIM cloud platform by the visualization of early warning, real time implementation, and each side by participating in construction can be at any time in electricity Brain, mobile phone, IPAD and other mobile terminals check work progress monitor situation, other described mobile terminals include laptop, Tablet computer.
Preferably, the BIM assembled 4D construction simulation system is by BIM software, in construction horizontal layout, arrangement and method for construction These three aspects of simulation and progress control establish the 4D construction simulation of assembled architecture, according to project site plan, construction Figure, site contour figure, place size, existing water source, available house and facility etc., in accordance with the provisions of the relevant regulations issued by the State, rationally set Construction plan is counted, and realizes place three-dimensional modeling using Civi 3D;According to the engineering construction figure, civil engineering is completed using Revit Engineering BIM model creation attempts the BIM model creation for carrying out installation profession, and carries out collision detection using Navisworks, mentions Before evade " mistakes and omissions are touched scarce " in work progress;From engineering reality, sequence of construction, construction organization and construction method are selected, Component sequence of construction and movement relation in BIM model are defined, counterweight difficult point part-to-item project carries out the simulation of 4D arrangement and method for construction;Benefit It is rationally worked out with MS Project and Optimizing construction schedule, it is associated with BIM model by Navisworks, realize full mistake The 4D construction simulation of journey and the real-time update of schedule.
Preferably, the ABAOUS FEM calculation system is calculated by ABAOUS software, the software is for establishing two-dimentional mould Type, while for generating threedimensional model, it is more careful that grid cell divides, and calculates more accurate.
Preferably, the ABAQUS finite element model Establishing process are as follows:
(1) material for defining each component, the preference pattern from the menu list of tree menu, enters back into characteristic value, Input material information in material data;
(2) cross section property for defining each component, the preference pattern from the menu list of tree menu, enters back into feature Value, defines cross section property on cross-section data, the size in the section, shape, title;
(3) node unit is established, node is established using the method that table generates node, utilizes the node of foundation, extension life At unit;
(4) buildings model entirety boundary condition is set, is fixed boundary condition at ground, the connection side of each component is set Boundary's condition, mutual interlocking;
(5) according to general stress condition analysis is built, mainly by static load, structural weight per square meter, flooring load, beam stress Load, and by the dynamic load in work progress, finally carry out the force analysis and linking parsing of monolithic architecture.
Preferably, when the remote data acquisition system is based on assembled architecture site operation, in the company of each component Connect the pre-buried sensing element in place, use Visual C++ for development platform, compile out teledata conduction be integrated with collection it is soft Part, the software are established by GPRS technology and field monitoring instrument and are communicated, and the long-range real-time reception storage of data are realized, in this base The system should also include data real-time query, datagraphic visualization function on plinth.
Obtain safety monitoring warning data information and mainly pass through three modes: (1) directly access passes through corresponding monitor Device monitoring data;(2) relevant information of the safety manager from routine safety management work;(3) laws and regulations of relevant information Analysis, standard and regulation, system and accident case data are obtained,
In the present embodiment, data acquisition and monitoring instrument is relied primarily on, assembled architecture is selected according to above-mentioned control section It is embedded into formula strain gauge and displacement meter monitoring instrument, is connect with service terminal, base station and movable signal tower, realizes real-time collecting number According to long-range monitoring and early warning, as shown in Fig. 2, the system mainly passes through in-site installation sensor and data acquisition transmission device, Collected data are read in SQL Server2005 database, uses Visual C++ for development platform, has compiled long-range number According to acquisition system, it can be established and be communicated by GPRS technology and field monitoring instrument, realize the long-range real-time reception storage of data, By ADO connection database on the basis of this, the functions such as data query, graph visualization are realized.
Preferably, the safety classification color early warning includes following color early warning:
1), green early warning
The monitoring point of display green illustrates to carry out daily tour management at this time in stable and safety state, check The deformation of data conduction condition and Midas finite element software;
2), yellow early warning
Occur yellow early warning when load is loaded onto the 70% of control section ultimate load, monitors industry group in unit and lead to immediately Know that field operation group checks field device, while warning information is recorded, the position of record early warning appearance, early warning class Type, early warning value, normal value;
3), orange warning
There is orange warning when load is loaded onto the 80% of junction power limit load, monitors industry group in unit and lead to immediately Know that field operation group checks field device, and warning information recorded, record early warning occur position, early warning type, Early warning value, normal value, while interior industry group issues warning information to site operation project management department, project management department is connected to the warning information of publication After take stopping working measure, and Portable device is detected and is repaired to early warning position, until pre-warning signal releases;
4), red early warning
There is red early warning when load is loaded onto the 90% of junction power limit load, monitor in unit industry group immediately to Site operation project management department issues red early warning, and project management department is connected to after the warning information of publication takes stopping working measure at once, takes Carrying device is carried out detecting the degree of danger for judging the position and be repaired to early warning position, should manual demolition immediately if can not repair Risk factor zoning, or construction personnel is notified to withdraw, it constructs again again after releasing pre-warning signal.
In summary: should assembled 4D construction simulation safety monitoring system based on BIM include on-site supervision management system, BIM assembled 4D construction simulation system, ABAQUS FEM calculation system, remote data acquisition system, pass through field monitoring pipe Reason system carries out the two-dimentional code labeling in scene to the component of assembled architecture, collects the factory information, scantling, component material of component Material, the information of component storage and outbound, component installation location, component construction personnel's information upload BIM cloud platform, in assembled 4D The component relevant information can be transferred during construction simulation, accomplishes effective allotment of the people, material, machine to scene, ensures construction Progress and construction quality;In the embedding sensing element in prefabricated member junction, connected by remote data acquisition system real-time collecting The ess-strain displacement data for meeting place imports ABAQUS FEM calculation system and carries out force analysis, then will by the port IFC ABAQUS finite element model imports Revit software, by critical touching, shows safety classification color in corresponding data collection point To warn, when unpredictable deformation and crack and leakage occurring assembled architecture is in load-bearing, can tie up in time It repairs or evacuating people, and using clear damaged part is visualized, reduces manpower and material resources and detected, avoid therefore delaying dimension The preferably opportunity repaired.
Part is not directed in the present invention to be the same as those in the prior art or can be realized by using the prior art.This specific implementation Example is only explanation of the invention, is not limitation of the present invention, those skilled in the art are reading this specification It can according to need the modification that not creative contribution is made to the present embodiment afterwards, but as long as in scope of the presently claimed invention Inside all by the protection of Patent Law.

Claims (8)

1. a kind of assembled 4D construction simulation safety monitoring system based on BIM, it is characterised in that: including on-site supervision management system System, BIM assembled 4D construction simulation system, ABAQUS FEM calculation system and remote data acquisition system;
The two-dimentional code labeling in scene is carried out by component of the field monitoring management system to assembled architecture, collects the factory letter of component Breath, scantling, construction material, component storage and the information of outbound, component installation location, the upload of component construction personnel's information BIM cloud platform can transfer the component relevant information during assembled 4D construction simulation, accomplish the people to scene, material, machine Effective allotment, ensure construction speed and construction quality;In the embedding sensing element in prefabricated member junction, pass through teledata The ess-strain displacement data of acquisition system real-time collecting junction imports ABAQUS FEM calculation system and carries out force analysis And ABAQUS finite element model is generated, then import ABAQUS finite element model in Revit software by the port IFC, by facing Boundary's touching shows safety classification color to early warning in corresponding data collection point.
2. a kind of assembled 4D construction simulation safety monitoring system based on BIM according to claim 1, feature exist In: the on-site supervision management system matches corresponding two dimensional code to each component when being used in building element factory, by sweeping Retouch factory information, scantling, construction material, component storage and the information of outbound, component peace that two dimensional code is managed component Holding position, component construction personnel's information;It is collected by the information of two dimensional code and uploads BIM cloud platform, which belongs to webpage behaviour Make, BIM model can also upload the platform simultaneously, and administrative staff are operated by logging in management account, transfer the platform phase Information is closed, component information and any stage for being in construction can be consulted, facilitates administrative staff to grasp global, to assembly Formula construction progress is very clear, can effectively ensure construction speed and construction quality;It can be grasped in real time by Field Monitoring System The position of component installation and personnel, can track situation and amendment to safe early warning in time.
3. a kind of assembled 4D construction simulation safety monitoring system based on BIM according to claim 1, feature exist In: the BIM assembled 4D construction simulation system is limited according to the Real-time Monitoring Data importing that remote data acquisition system provides In meta software, element joints real-time displacement, stress, strain are calculated, to judge safety, the stability of junction, then will be divided It is imported in Revit when analysing fructufy, is directly shown by BIM model, assembled in situ is instructed by the 4D construction simulation of BIM Formula work progress carries out secondary development to Revit software, increases the module of monitoring race, can adjust during 4D construction simulation Take the module of monitoring, connection finite element analysis software analysis will be as the result is shown to during construction simulation, real-time early warning assembled The general safety of construction, Revit monitor the exploitation of race, and for transferring the information and stress condition of each monitoring race, monitoring race exists Safety is directly displayed during 4D construction simulation by color difference, realizes the visual of assembled architecture construction safety early warning Change, real time implementation, can by BIM model upload BIM cloud platform, by participate in construction each side at any time computer, mobile phone, IPAD and its His mobile terminal checks that work progress monitors situation.
4. a kind of assembled 4D construction simulation safety monitoring system based on BIM according to claim 1, feature exist In: the BIM assembled 4D construction simulation system is by BIM software, in construction horizontal layout, arrangement and method for construction simulation and progress pipe The 4D construction simulation that these three aspects establish assembled architecture is managed, according to project site plan, construction drawing, site contour Figure, place size, existing water source, available house and facility etc. rationally design construction plane in accordance with the provisions of the relevant regulations issued by the State Figure, and place three-dimensional modeling is realized using Civi3D;According to the engineering construction figure, civil engineering BIM model is completed using Revit Creation attempts the BIM model creation for carrying out installation profession, and carries out collision detection using Navisworks, evades construction in advance " mistakes and omissions are touched scarce " in the process;From engineering reality, sequence of construction, construction organization and construction method are selected, defines BIM model Middle component sequence of construction and movement relation, counterweight difficult point part-to-item project carry out the simulation of 4D arrangement and method for construction;Utilize MS Project is rationally worked out and Optimizing construction schedule, associated with BIM model by Navisworks, realizes overall process The real-time update of 4D construction simulation and schedule.
5. a kind of assembled 4D construction simulation safety monitoring system based on BIM according to claim 1, feature exist In: the ABAOUS FEM calculation system is calculated by ABAOUS software, which is used to give birth to for establishing two dimensional model At threedimensional model, it is more careful that grid cell divides, and calculates more accurate.
6. a kind of assembled 4D construction simulation safety monitoring system based on BIM according to claim 1, feature exist In: the ABAQUS finite element model Establishing process are as follows:
(1) material for defining each component, the preference pattern from the menu list of tree menu, enters back into characteristic value, in material Input material information in data;
(2) cross section property for defining each component, the preference pattern from the menu list of tree menu, enters back into characteristic value, Cross section property is defined on cross-section data, the size in the section, shape, title;
(3) node unit is established, node is established using the method that table generates node, using the node of foundation, extension generates single Member;
(4) buildings model entirety boundary condition is set, is fixed boundary condition at ground, the fillet item of each component is set Part, mutual interlocking;
(5) according to general stress condition analysis is built, mainly by static load, structural weight per square meter, flooring load, beam stress lotus It carries, and by the dynamic load in work progress, finally carries out the force analysis and linking parsing of monolithic architecture.
7. a kind of assembled 4D construction simulation safety monitoring system based on BIM according to claim 1, feature exist In: when the remote data acquisition system is based on assembled architecture site operation, in the pre-buried induction in the junction of each component Element uses Visual C++ for development platform, compiles out teledata conduction and passes through with the software being integrated, the software is collected GPRS technology and field monitoring instrument, which are established, to be communicated, and realizes the long-range real-time reception storage of data, and the system is also on this basis It should include data real-time query, datagraphic visualization function.
8. a kind of assembled 4D construction simulation safety monitoring system based on BIM according to claim 1, feature exist In: the safety classification color early warning includes following color early warning:
1), green early warning
The monitoring point of display green illustrates to carry out daily tour management at this time in stable and safety state, check data The deformation of conduction condition and ABAQUS finite element software;
2), yellow early warning
Occur yellow early warning when load is loaded onto the 70% of junction power limit load, monitors industry group in unit and notify immediately Field operation group checks field device, while recording to warning information, record early warning occur position, early warning type, Early warning value, normal value;
3), orange warning
There is orange warning when load is loaded onto the 80% of junction power limit load, industry group notifies outer immediately in monitoring unit Industry group checks field device, and records to warning information, the position of record early warning appearance, early warning type, early warning Value, normal value, while interior industry group issues warning information to site operation project management department, project management department adopts after being connected to the warning information of publication Stopping working measure being taken, and Portable device is detected and repaired to early warning position, until pre-warning signal releases;
4), red early warning
There is red early warning when load is loaded onto the 90% of junction power limit load, industry group is immediately to scene in monitoring unit Construction project department issues red early warning, and project management department is connected to after the warning information of publication takes stopping working measure at once, and carrying is set It is standby early warning position is carried out detecting the degree of danger for judge position repair, should manual demolition danger immediately if can not repair Component, or construction personnel is notified to withdraw, it constructs again again after releasing pre-warning signal.
CN201910559001.2A 2019-06-26 2019-06-26 A kind of assembled 4D construction simulation safety monitoring system based on BIM Pending CN110263460A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910559001.2A CN110263460A (en) 2019-06-26 2019-06-26 A kind of assembled 4D construction simulation safety monitoring system based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910559001.2A CN110263460A (en) 2019-06-26 2019-06-26 A kind of assembled 4D construction simulation safety monitoring system based on BIM

Publications (1)

Publication Number Publication Date
CN110263460A true CN110263460A (en) 2019-09-20

Family

ID=67921671

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910559001.2A Pending CN110263460A (en) 2019-06-26 2019-06-26 A kind of assembled 4D construction simulation safety monitoring system based on BIM

Country Status (1)

Country Link
CN (1) CN110263460A (en)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111210365A (en) * 2020-01-02 2020-05-29 广州大学 Assembly type building construction safety monitoring system, method, device and medium
CN111291436A (en) * 2019-10-08 2020-06-16 中国建筑一局(集团)有限公司 BIM-based high formwork safety management monitoring method and monitoring system
CN111335186A (en) * 2020-03-05 2020-06-26 青岛理工大学 Safety monitoring and early warning method and system for swivel bridge, storage medium and early warning platform
CN111353191A (en) * 2020-02-28 2020-06-30 中国十七冶集团有限公司 Construction method of roof steel structure with multi-curvature special-shaped curved surface
CN111881501A (en) * 2020-07-23 2020-11-03 广东腾美建设工程有限公司 Assembly type building management method and system based on BIM and cloud service
CN112182706A (en) * 2020-09-28 2021-01-05 浙江精工钢结构集团有限公司 BIM steel structure-based complex construction process belt stress visualization analysis method
CN112685826A (en) * 2021-02-03 2021-04-20 西南交通大学 Foundation structure construction method, device, equipment and readable storage medium
CN112949130A (en) * 2021-03-05 2021-06-11 中国建筑第八工程局有限公司 Intelligent construction method and system for near-subway building
CN113191633A (en) * 2021-04-29 2021-07-30 谢亚奇 Building construction safety protection early warning system based on BIM
CN113222564A (en) * 2021-06-09 2021-08-06 合肥优尔电子科技有限公司 Progress management system and method based on BIM system
CN113297656A (en) * 2021-05-12 2021-08-24 中筑(山东)数字科技有限公司 Building construction safety early warning protection system and method based on BIM
CN113626920A (en) * 2021-08-12 2021-11-09 浙江大学 Engineering monitoring management system based on BIM +5G technology
CN113671548A (en) * 2021-09-08 2021-11-19 中交第四公路工程局有限公司 Integrated large-scale space structure construction guidance system and method
CN113761851A (en) * 2021-08-27 2021-12-07 北京水建研信息技术有限公司 Water conservancy unit engineering quality acceptance data acquisition system based on Internet of things
CN114234901A (en) * 2021-11-30 2022-03-25 中建四局第一建设有限公司 Information monitoring method and system for dismantling and modifying super high-rise building
CN114331081A (en) * 2021-12-22 2022-04-12 南京同筑盛世信息科技有限公司 BIM-based visual construction whole-course safety management system
CN116090078A (en) * 2023-04-07 2023-05-09 广东海洋大学 BIM model anti-seismic optimization method of road bridge structure
CN116337158A (en) * 2023-05-24 2023-06-27 中国建筑科学研究院有限公司 Building health monitoring device and method
CN117572903A (en) * 2024-01-16 2024-02-20 中国建筑科学研究院有限公司 Terminal induction feedback type load automatic adjustment method and system based on AI (advanced technology attachment) processing

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102706681A (en) * 2012-06-08 2012-10-03 武汉中岩科技有限公司 Bailey sheet detecting device and method
CN109472091A (en) * 2018-11-13 2019-03-15 四川华芯项目管理有限公司 A kind of assembled architecture construction and stage monitoring system and method for being on active service

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102706681A (en) * 2012-06-08 2012-10-03 武汉中岩科技有限公司 Bailey sheet detecting device and method
CN109472091A (en) * 2018-11-13 2019-03-15 四川华芯项目管理有限公司 A kind of assembled architecture construction and stage monitoring system and method for being on active service

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘占省: "BIM技术在风电塔架设计施工过程中的应用", 《第十七届全 国现代结构工程学术研讨会》 *
林智明: "基于BIM的建筑工程进度控制可视化平台的构建", 《中国优秀硕士学位论文全文数据库》 *

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111291436A (en) * 2019-10-08 2020-06-16 中国建筑一局(集团)有限公司 BIM-based high formwork safety management monitoring method and monitoring system
CN111210365A (en) * 2020-01-02 2020-05-29 广州大学 Assembly type building construction safety monitoring system, method, device and medium
CN111353191A (en) * 2020-02-28 2020-06-30 中国十七冶集团有限公司 Construction method of roof steel structure with multi-curvature special-shaped curved surface
CN111335186A (en) * 2020-03-05 2020-06-26 青岛理工大学 Safety monitoring and early warning method and system for swivel bridge, storage medium and early warning platform
CN111881501A (en) * 2020-07-23 2020-11-03 广东腾美建设工程有限公司 Assembly type building management method and system based on BIM and cloud service
CN111881501B (en) * 2020-07-23 2024-04-16 广东腾美建设工程有限公司 BIM and cloud service-based fabricated building management method and system
CN112182706A (en) * 2020-09-28 2021-01-05 浙江精工钢结构集团有限公司 BIM steel structure-based complex construction process belt stress visualization analysis method
CN112685826B (en) * 2021-02-03 2022-05-17 西南交通大学 Foundation structure construction method, device, equipment and readable storage medium
CN112685826A (en) * 2021-02-03 2021-04-20 西南交通大学 Foundation structure construction method, device, equipment and readable storage medium
CN112949130A (en) * 2021-03-05 2021-06-11 中国建筑第八工程局有限公司 Intelligent construction method and system for near-subway building
CN113191633A (en) * 2021-04-29 2021-07-30 谢亚奇 Building construction safety protection early warning system based on BIM
CN113297656A (en) * 2021-05-12 2021-08-24 中筑(山东)数字科技有限公司 Building construction safety early warning protection system and method based on BIM
CN113222564A (en) * 2021-06-09 2021-08-06 合肥优尔电子科技有限公司 Progress management system and method based on BIM system
CN113626920A (en) * 2021-08-12 2021-11-09 浙江大学 Engineering monitoring management system based on BIM +5G technology
CN113761851A (en) * 2021-08-27 2021-12-07 北京水建研信息技术有限公司 Water conservancy unit engineering quality acceptance data acquisition system based on Internet of things
CN113761851B (en) * 2021-08-27 2024-01-16 北京水建研信息技术有限公司 Hydraulic unit engineering quality acceptance data acquisition system based on Internet of things
CN113671548A (en) * 2021-09-08 2021-11-19 中交第四公路工程局有限公司 Integrated large-scale space structure construction guidance system and method
CN114234901A (en) * 2021-11-30 2022-03-25 中建四局第一建设有限公司 Information monitoring method and system for dismantling and modifying super high-rise building
CN114331081A (en) * 2021-12-22 2022-04-12 南京同筑盛世信息科技有限公司 BIM-based visual construction whole-course safety management system
CN116090078A (en) * 2023-04-07 2023-05-09 广东海洋大学 BIM model anti-seismic optimization method of road bridge structure
CN116337158A (en) * 2023-05-24 2023-06-27 中国建筑科学研究院有限公司 Building health monitoring device and method
CN117572903A (en) * 2024-01-16 2024-02-20 中国建筑科学研究院有限公司 Terminal induction feedback type load automatic adjustment method and system based on AI (advanced technology attachment) processing
CN117572903B (en) * 2024-01-16 2024-03-29 中国建筑科学研究院有限公司 Terminal induction feedback type load automatic adjustment method and system based on AI (advanced technology attachment) processing

Similar Documents

Publication Publication Date Title
CN110263460A (en) A kind of assembled 4D construction simulation safety monitoring system based on BIM
CN110263461B (en) Bridge safety monitoring and early warning system based on BIM
CN108875273B (en) BIM-based foundation pit engineering forward design and operation and maintenance management system
CN106227977A (en) A kind of method of steel structure net rack hydraulic pressure lift time-varying finite element analysis based on BIM
CN108681781A (en) A kind of subway operation management information system and method based on three-dimensional technology of Internet of things
CN102147597A (en) Health monitoring system for structures of great building and bridge
CN105425752A (en) Real-time monitoring system of pipe network and working method of same
Lin et al. Automating closed-loop structural safety management for bridge construction through multisource data integration
CN111145479A (en) Construction dangerous environment real-time early warning platform and method based on BIM positioning technology
CN103669366A (en) Remote monitoring early warning system for deep foundation pit support structure deformation
CN112097823A (en) Based on big dipper high accuracy location and BIM construction multiple spot synchronous monitoring system
CN208903300U (en) A kind of construction risk automatic monitoring system based on BIM technology
Zhou et al. A BIM-based identification and classification method of environmental risks in the design of Beijing subway
CN112464494A (en) Construction system is built to wisdom
Rui et al. Construction project management based on building information modeling (Bim)
Cao et al. A Digital Twin (DT) Framework at Design and Construction Phases
Han et al. An Online safety monitoring system of hydropower station based on expert system
CN107527162B (en) House safety identification system and use method thereof
Hou et al. A visual management system for structural health monitoring based on web-BIM and dynamic multi-source monitoring data-driven
Huang et al. Research on safety of operation and maintenance of utility tunnel based on BIM and computer technology
CN112347540B (en) Intelligent detection modeling system for building
Fan et al. Safety management system prototype/framework of deep foundation pit based on BIM and IoT
Liu et al. Integration of Building Information Modelling (BIM) and sensor technology: a review of current developments and future outlooks
CN113128709A (en) Water supply pipe network leakage management system
CN107783474A (en) A kind of building safety monitoring system and its application method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190920