CN110258890A - A kind of broken line type exterior wall is connected the construction method of concrete structure with roofing - Google Patents

A kind of broken line type exterior wall is connected the construction method of concrete structure with roofing Download PDF

Info

Publication number
CN110258890A
CN110258890A CN201910546607.2A CN201910546607A CN110258890A CN 110258890 A CN110258890 A CN 110258890A CN 201910546607 A CN201910546607 A CN 201910546607A CN 110258890 A CN110258890 A CN 110258890A
Authority
CN
China
Prior art keywords
concrete
broken line
exterior wall
line type
roofing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910546607.2A
Other languages
Chinese (zh)
Other versions
CN110258890B (en
Inventor
张军
张凯平
杜平
杜兴
杜冬雨
袁明
黄晓凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong University
Original Assignee
Nantong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong University filed Critical Nantong University
Priority to CN201910546607.2A priority Critical patent/CN110258890B/en
Publication of CN110258890A publication Critical patent/CN110258890A/en
Application granted granted Critical
Publication of CN110258890B publication Critical patent/CN110258890B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/02Roofs; Roof construction with regard to insulation with plane sloping surfaces, e.g. saddle roofs
    • E04B7/04Roofs; Roof construction with regard to insulation with plane sloping surfaces, e.g. saddle roofs supported by horizontal beams or the equivalent resting on the walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/08Forms, which are completely dismantled after setting of the concrete and re-built for next pouring
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of broken line type exterior walls to be connected the construction method of concrete structure with roofing, include the following steps: CAD setting-out → field lofting → measurement and positioning → template support frame body set up → template construct, installation → reinforcement fabrication, installation → broken line type exterior wall first time concrete placings, maintenance → construction joint pick chisel, second of concrete placings of cleaning → broken line type exterior wall and roofing, maintenance → demoulding.The connected construction technology of engineering multispan broken line type concrete exterior wall and roofing in the present invention, broken line type concrete structure and component construction method are summed up, overcome the deficiency in previous construction, template construct is simple, size is accurate, reinforcing is convenient, component broken line rate controls in place, concrete impression quality is good, and provides reference value for the construction of similar engineering.

Description

A kind of broken line type exterior wall is connected the construction method of concrete structure with roofing
Technical field
The invention belongs to the realm of building construction, and in particular to a kind of broken line type exterior wall is connected the applying of concrete structure with roofing Work method.
Background technique
With construction industry development and use the raising of functional requirement, the more and more novel uniqueness of the moulding of building construction, broken line The features such as type building is unique, serious, visual sensory is good with its external form is widely used, and unique model becomes urban construction In one of beautiful landscape.But broken line type architecture construction is complex, template subdivisional work from design, setting-out, be fabricated into peace It is cumbersome to fill technique, axial location and sectional dimension location control difficulty is big, required precision is high, structure and component broken line rate are difficult to control System, reinforcing bar binds quality control and safety problem perplexs unit in charge of construction, and concrete Forming Quality is difficult to ensure.The attached Rugao dragon trip of Beijing Foreign Language Studies University Lake School of Foreign Languages performing arts center, type of taking out stitches concrete exterior wall are to extend to roofing (3.3m~15.3m) from ground floor Broken line type structure, using wooden model steel tube fastener scaffold support system, broken line position template, reinforcement fabrication refer to CAD full-page proof Figure one-pass molding, concrete placings sequence first pour broken line two sides pour again top, the slump of strict control concrete, pour finish it is laggard No less than 7 days moisture-keeping maintainings of row.Project management department has formulated detailed construction by combining theory and practice together and conscientiously discussing, study Scheme achieves preferable effect by well construction.
Summary of the invention
Goal of the invention: in order to solve the deficiencies in the prior art, the present invention provides a kind of broken line type exterior walls to be connected with roofing The construction method of concrete structure.
Technical solution: a kind of broken line type exterior wall is connected the construction method of concrete structure with roofing, includes the following steps:
CAD setting-out → field lofting → measurement and positioning → template support frame body sets up → template construct, installation → reinforcing bar system Work, installation → broken line type exterior wall first time concrete placings, maintenance → construction joint pick second of chisel, cleaning → broken line type exterior wall and roofing Concrete placings, maintenance → demoulding;Wherein:
The template support frame body is set up, and concrete operations are as follows:
It carries out frame body according to the position line of support frame system and absolute altitude to set up, broken line type exterior wall support frame every upright bar of system Absolute altitude is all different, symmetrical as center both sides using broken line, and upright bar vertically and horizontally spacing 800mm, bar of sweeping the floor is away from ground 200mm, horizon bar Spacing is not more than 1500mm, and bottom of upright rod makees backing plate with 50mm solid wood;Upright bar, horizontal knock-off joint are staggered no less than 1 across It is connected, is forbidden using overlap joint using joint fastener, supporting frame is horizontal, vertical direction is respectively provided with vertically and horizontally bridging, and top is certainly Diagonal brace is arranged to both sides in center, it is ensured that the overall stability of frame body;During formwork erection, reinforcing bar binding, concrete placings, Frame body is monitored, discovery has displacement to be adjusted in time;
The template construct, installation, concrete operations are as follows:
Since broken line type concrete exterior wall has batter post, beam, broken line plate, negative ridge, positive ridge, causing template to be laid with cannot be according to routine Method carries out, and will cause the waste of template, flitch like that, so that construction cost increases;When template construct, according to the template of in-depth Drawing carries out accurate setting-out in template, and each piece of template of each broken line plate is numbered, and mosaic part will be with section Saving is principle, it is desirable that blanking is accurate, size is correct, using all leftover pieces, and the big big use of material, the small small use of material;
When template is installed, column, the beam forms between multispan broken line plate need to be first installed, this part-structure position and absolute altitude are not easy Control, need to directly measure according to the control line and absolute altitude of lower floor, according to code requirement arch camber in the middle part of beam slab;Broken line template die plate It installs, girder usesSteel pipe is laid with, and makes broken line type according to drawing, the spacing and mark required further according to scheme Height is mounted at the top of support frame in upright bar;45 × 95mm flitch secondary beam is laid on girder steel pipe, then spacing 200mm is laid with 15mm thickness glued board, fixation as required between glued board and flitch, flitch and steel pipe;
For convenient for broken line type exterior wall concrete placings, to reinforcing bar binding after, it is pre-buried in broken line plate according to layout design 10 steel bar end@900 × 900, at the same it is pre-buried18 soil font reinforcing bars, in order to set up interim steel pipe protective frame;Steel pipe protective frame Set up need it is solid and reliable, be convenient for concrete placings and subsequent external wall construction, protective frame upright bar spacing be not more than 2400mm, horizontal tube Spacing is not more than 1500mm, can carry out broken line type exterior wall first time concrete placings after qualified by inspection;
The reinforcement fabrication, installation, concrete operations are as follows:
The reinforcing bar of broken line type concrete exterior wall and roofing carries out turning over sample and live blanking processing according to drawing in advance, and uses CAD The groupware that charts carries out size review, and the broken line degree of reinforcing bar must be consistent with drawing, and otherwise the protective layer thickness of reinforcing bar will not Easy to control, board bottom muscle, which is used, controls concrete cover thickness using reinforcing bar stirrup with Concrete seat pad, plate upper layer muscle, and cushion block and stirrup are vertical Horizontal spacing is 1000mm, and blossom type is staggeredly arranged, and double steel bar mesh sheet is full bundle, to prevent concrete from gliding, two layers of reinforcing bar No more than 800mm, the steel fabric sheet that mesh is 20 × 20mm is bound the intermediate spacing that is all made of of net;
The broken line type exterior wall first time concrete placings, maintenance → construction joint pick chisel, cleaning → broken line type exterior wall and roofing Second of concrete placings, maintenance, concrete operations are as follows:
Concreting avoids the rainy day from constructing, and concrete uses commerical ready-mixed concrete, and strict control is marched into the arena concrete mix And the slump, concrete strip thickness control standard point is carried out before pouring, design thickness and the plate thickness to guarantee concrete are uniform;Broken line Type concrete exterior wall and roofing, which pour concrete, must have special messenger to be responsible for, unified command coordination, since concrete placings amount is big, and be broken line type, will The joints of concrete projects of broken line type concrete exterior wall and roofing is located at the inner corner trim of folded plate, first pours triangular form inclined-plane, is wanted to concrete strength satisfaction Concrete at construction joint is carried out after asking to pick chisel, is then washed with water completely, and go stone concrete to carry out connecing slurry with same label, then pour yin The above broken line type concrete exterior wall in angle and roofing concrete;
It is poured upwards since broken line type exterior wall bottom edge from bottom to top when pouring concrete, first pours broken line type exterior wall two sides, most It at the top of after-pouring, is vibrated using poker vibrator, concrete is with smashing with vibration, and vibration point uniformly, pull out slowly, until surface by fast insert Unobvious sinking, until not occurring bubble and glowing mortar, to ensure the density of casting and compacting of concrete;Strict control concrete when pouring The slump, broken line type exterior wall two sides and roofing sun ridge control respectively, and since the two sides gradient is larger, concrete slump is answered smaller; The difficulty of construction for pouring opposite exterior wall of broken line type roofing concrete is smaller, and roofing is pushed ahead i.e. with the progress that pours of exterior wall It can;But it is noted that the positive ridge of broken line type roofing and exterior wall needs band line to modify, and check the deviation of size;After concrete vibration compacting first Just put down, carries out second plastering, covering maintenance before final set again after concrete initial set;
Maintenance work need to especially be carried out, on the broken line plate for having poured concrete, using gunnysack or carpet cloth water seasoning come Concrete surface moisture state is kept, curing time is no less than 7 round the clock, forbids upper people during maintenance and carry out operation on it, Demoulding is carried out after reaching concrete strength;
The demoulding, concrete operations are as follows:
Form bracing system is removed after concrete strength reaches 100%, when dismounting according to " first prop up tear open afterwards, rear branch it is first Tear open " principle, from top to bottom, successively carry out, material is forbidden to forbid to prize firmly using crowbar, must not break from eminence throwing when dismounting The corner angle on bad concrete surface, after dismounting, material should be stacked neat by different cultivars, specification classification.
As optimization: the CAD setting-out, concrete operations are as follows: the broken line degree of broken line type exterior wall and position pass through support The position of frame controls, and broken line template is abutted and connect with support girder, and support girder with support girder is abutted and connect, therefore Setting up for support frame will be arranged meticulously, calculated;In order to guarantee template broken line degree, to each upright bar before the setting up of support frame Meticulous arrangement is carried out with the position of broken line type rod piece, absolute altitude, is calculated, and carries out rod piece height by means of the CAD drawing groupware Measurement, reinforcing bar arrangement, plate muscle blanking, template and axial dimension review.
As optimization: the field lofting, concrete operations are as follows:
Broken line type concrete exterior wall and roofing are before supporting frame is set up, it is necessary to which ability is real after being sufficiently ready work at the scene It applies, so it is also difficult point that the absolute altitude of support frame and batter post that carpenter sets up and positioning, which are the emphasis for first having to solve when construction, tool Body absolute altitude and positioning cooperate carpenter to complete by technical staff by the multiple measurement and the positioning of projection line of bench mark;It is constructing Before, the line setting of bottom is particularly important, and project management department technical staff requires carpenter teams and groups first to carry out by the gross data of CAD setting-out The practical setting-out in scene, that is, after support frame is set up, first by the standard of 8 span centres across i.e. from western second eastwards across it is oblique Column, beam, Side fascia formwork erection in place, then by field technician and design drawing, the data school repeatedly of CAD setting-out It, can large-area construction after confirmation field lofting accurately meets construction requirement to rear.
As optimization: the measurement and positioning, concrete operations are as follows: according to CAD full-size drawing and construction drawing, to one layer of axis Line, component, absolute altitude carry out unwrapping wire, positioning, levelling, and broken line wallboard and roofing position should have axis, sideline, control line, according to mould Plate special construction plan releases " cross " position line of support frame system upright bar, and checks each spots localization unwrapping wire, draws It control point and makes a record out, it is ensured that tolerance is in specification prescribed limit.
As optimization: material prepares as follows: formwork bracing system frame body supervisor usesSteel pipe, template use 15mm thickness clad can wood plywood, girder use 45 × 95mm flitch, and frame body steel pipe, fastener, adjustable bracket, template, flitch exist Conscientiously it should be checked and be selected when marching into the arena, steel pipe, fastener use the live sampling inspection of preceding progress after marching into the arena, after detection is qualified again It uses, it is serious to appearance corrosion, slight crack, depression defect to forbid using template and flitch are selecting specification unified just Product material.
The construction technology the utility model has the advantages that the engineering multispan broken line type concrete exterior wall and roofing in the present invention are connected, has summed up folding Line style concrete structure and component construction method overcome the deficiency in previous construction, and template construct is simple, size is accurate, reinforces just Victory, component broken line rate control in place, and concrete impression quality is good, and provides reference value for the construction of similar engineering.
Detailed description of the invention
Fig. 1 is CAD setting-out structural schematic diagram of the invention.
Specific embodiment
The technical scheme in the embodiments of the invention will be clearly and completely described below, so that the technology of this field Personnel can better understand advantages and features of the invention, to make apparent boundary to protection scope of the present invention It is fixed.Embodiment described in the invention is only a part of the embodiment of the present invention, instead of all the embodiments, based on the present invention In embodiment, those of ordinary skill in the art's every other implementation obtained without making creative work Example, shall fall within the protection scope of the present invention.
Embodiment
The type concrete exterior wall of taking out stitches of certain engineering extends to roofing (15.3m) from ground floor (3.3m), by eight Span Continuous Broken line wallboard composition, broken line degree is respectively 33 degree, 41 degree and 47 degree, and exterior wall and roof boarding plate thickness are respectively 120mm and 130mm, Two-layer two-way reinforcement;One layer of column cross-section size of exterior wall are as follows: 900 × 1200,700 × 700mm, the batter post section being connected with Side fascia Having a size of 400 × (750~1200) mm;Broken line type concrete roof beam section size are as follows: 300 × (500~700), 350 × (800~ 1400), 400 × 750,450 × 500mm.Template is installed since raft plate top surface, is installed height and is up to 18.95m, high-supported formwork Vertically and horizontally horizontal direction maximum span is respectively 18.6 meters and 8 meters in region, and one layer of column concrete grade of concrete strength grade is C40, with folding Line style concrete exterior wall phase pedestal concrete grade is C35;Broken line type concrete exterior wall and roof girder, plate concrete grade are C30.
1. process flow
Broken line type concrete exterior wall of the invention is different from general plate and inclined plate, the setting up of formwork-support, template and steel Production of muscle and installation etc. are both needed to by accurately calculating and line setting, can guarantee the accurate of structure cross-section dimensions and absolute altitude Property.Its process flow is as follows:
CAD setting-out → field lofting → measurement and positioning → template support frame body sets up → template construct, installation → reinforcing bar system Work, installation → broken line type exterior wall first time concrete placings, maintenance → construction joint pick second of chisel, cleaning → broken line type exterior wall and roofing Concrete placings, maintenance → demoulding.
2. preparation of construction
2.1 technique preparation
Before construction, Project Technical responsible person organizes surveyor, builder, technician, class monitor and group leader etc. to be conscientiously familiar with drawing, learns Specification and quality standard are practised, makes practicable arrangement and method for construction, and by safe software for calculation of siping tea to formwork-support Carry out safety check, it is ensured that support system is safe and reliable.It is expected that it will be likely encountered the problem of drawing and in work progress The problem of etc. aggregated, tissue drawing joint examination and technical solution symposium, set up construction special interest group, establish wechat Group, it is ensured that construct, communicate unimpeded, so that problem can fed back at the first time and solved, do for broken line type concrete structure construction Good technique preparation and support.2.2 personnel prepare
Labour, especially carpenter, bar bender, concrete work are conscientiously organized according to construction schedule and engineering characteristic, excellent It first selects and participated in similar engineering construction, there is stronger practical operation experience, the preferable skilled worker of physical fitness.It is applied according to this engineering Work drawing and technological difficulties are conscientiously organized to carry out skilled worker in conjunction with broken line type structure construction feature and engineering practice It is detailed to confide a technological secret and live practical operation analogue technique guidance, it is ensured that each worker can be familiar with the construction method and stream of this work post Journey.According to sequence of construction and process, determine people and determine region quantitatively to calibrate standard, it is ensured that preparation of construction, work progress, inspection, check and accept it is complete Process control is in place.
2.3 materials prepare
By construction requirement, sequence of construction and materials plan, fed in time by construction material management system, it is existing to meet construction Field needs.Formwork bracing system frame body supervisor usesSteel pipe, template use 15mm thickness clad can wood plywood, girder Using 45 × 95mm flitch, frame body steel pipe, fastener, adjustable bracket, template, flitch conscientiously should be checked and be chosen when marching into the arena Choosing, steel pipe, fastener march into the arena after using the live sampling inspection of preceding progresss, reused after detection is qualified, to occur corrosion seriously, split The defects of trace, recess, forbids to use, and template and flitch select certified products material that regular producer produces, that specification is unified Material, it is ensured that a variety of materials meet design and operational requirement.
2.4 construction installations prepare
2.4.1 safety devices: broken line type structure construction, safety guarantee be it is primary, before construction, it is necessary to assure foot hand The operation layer of frame completely spreads scaffold board, guard rail rod of setting up defences, hangs up Dense mesh screen, safety net, and qualified by inspection.
2.4.2 construction machinery: vertical transport derrick crane, it is necessary to assure have enough safe altitudes and operation is good It is good.
2.4.3 small-sized construction equipment: electric saw, electric planer, Portable vibrator etc., mechanical performance is good.
3. construction method
3.1CAD setting-out
The broken line degree of broken line type exterior wall and position are controlled by the position of support frame, broken line template and support girder It abuts and connects, support girder is abutted and connect with support girder, therefore to be arranged, be calculated meticulously to setting up for support frame.For Guarantee template broken line degree carries out the position of each upright bar and broken line type rod piece, absolute altitude before the setting up of support frame meticulous Arrangement, calculate.As shown in the CAD setting-out structural schematic diagram of Fig. 1, the survey of rod piece height is carried out by means of the CAD drawing groupware Amount, reinforcing bar arrangement, plate muscle blanking, template and axial dimension review etc..
3.2 field lofting
Broken line type concrete exterior wall and roofing are before supporting frame is set up, it is necessary to which ability is real after being sufficiently ready work at the scene It applies, so it is also difficult point that the absolute altitude of support frame and batter post that carpenter sets up and positioning, which are the emphasis for first having to solve when construction, tool Body absolute altitude and positioning cooperate carpenter to complete by technical staff by the multiple measurement and the positioning of projection line of bench mark.It is constructing Before, the line setting of bottom is particularly important, and project management department technical staff requires carpenter teams and groups first to carry out by the gross data of CAD setting-out The practical setting-out in scene, that is, after support frame is set up, first by the standard of 8 span centres across i.e. from western second eastwards across it is oblique Column, beam, Side fascia formwork erection in place, then by field technician and design drawing, the data school repeatedly of CAD setting-out It, can large-area construction after confirmation field lofting accurately meets construction requirement to rear.
3.3 measurement and positioning
According to CAD full-size drawing and construction drawing, unwrapping wire, positioning, levelling, broken line wallboard are carried out to one layer of axis, component, absolute altitude And roofing position should have axis, sideline, control line, and " cross " of the upright bar of support frame system is released according to template special construction plan Position line, and each spots localization unwrapping wire is checked, control point is drawn and is made a record, it is ensured that tolerance is provided in specification In range.
3.4 template support frame bodies are set up
It carries out frame body according to the position line of support frame system and absolute altitude to set up, broken line type exterior wall support frame every upright bar of system Absolute altitude is all different, symmetrical as center both sides using broken line, and upright bar vertically and horizontally spacing 800mm, bar of sweeping the floor is away from ground 200mm, horizon bar Spacing is not more than 1500mm, and bottom of upright rod makees backing plate with 50mm solid wood.Upright bar, horizontal knock-off joint are staggered no less than 1 across It is connected, is forbidden using overlap joint using joint fastener, supporting frame is horizontal, vertical direction is respectively provided with vertically and horizontally bridging, and top is certainly Diagonal brace is arranged to both sides in center, it is ensured that the overall stability of frame body.During formwork erection, reinforcing bar binding, concrete placings, Frame body is monitored, discovery has displacement to be adjusted in time.
3.5 template constructs, installation
Since broken line type concrete exterior wall has batter post, beam, broken line plate, negative ridge, positive ridge, causing template to be laid with cannot be according to routine Method carries out, and will cause the waste of template, flitch like that, so that construction cost increases.When template construct, according to the template of in-depth Drawing carries out accurate setting-out in template, and each piece of template of each broken line plate is numbered, and mosaic part will be with section Saving is principle, it is desirable that blanking is accurate, size is correct, using all leftover pieces, and the big big use of material, the small small use of material.
When template is installed, column, the beam forms between multispan broken line plate need to be first installed, this part-structure position and absolute altitude are not easy Control, need to directly measure according to the control line and absolute altitude of lower floor, according to code requirement arch camber in the middle part of beam slab.Broken line template die plate It installs, girder usesSteel pipe is laid with, and makes broken line type according to drawing, the spacing and mark required further according to scheme Height is mounted at the top of support frame in upright bar.45 × 95mm flitch secondary beam is laid on girder steel pipe, then spacing 200mm is laid with 15mm thickness glued board, fixation as required between glued board and flitch, flitch and steel pipe.
For convenient for broken line type exterior wall concrete placings, to reinforcing bar binding after, it is pre-buried in broken line plate according to layout design 10 steel bar end@900 × 900, at the same it is pre-buried18 soil font reinforcing bars, in order to set up interim steel pipe protective frame.Steel pipe protective frame Set up need it is solid and reliable, be convenient for concrete placings and subsequent external wall construction, protective frame upright bar spacing be not more than 2400mm, horizontal tube Spacing is not more than 1500mm, can carry out broken line type exterior wall first time concrete placings after qualified by inspection.
3.6 reinforcement fabrications, installation
The reinforcing bar of broken line type concrete exterior wall and roofing carries out turning over sample and live blanking processing according to drawing in advance, and uses CAD The groupware that charts carries out size review, and the broken line degree of reinforcing bar must be consistent with drawing, and otherwise the protective layer thickness of reinforcing bar will not Easy to control, board bottom muscle, which is used, controls concrete cover thickness using reinforcing bar stirrup with Concrete seat pad, plate upper layer muscle, and cushion block and stirrup are vertical Horizontal spacing is 1000mm, and blossom type is staggeredly arranged, and double steel bar mesh sheet is full bundle, to prevent concrete from gliding, two layers of reinforcing bar No more than 800mm, the steel fabric sheet that mesh is 20 × 20mm is bound the intermediate spacing that is all made of of net.
3.7 concretings, maintenance
Concreting avoids the rainy day from constructing, to ensure broken line type concrete exterior wall and roofing concrete placings construction quality and safety. Concrete uses commerical ready-mixed concrete, and strict control is marched into the arena concrete mix and the slump.Concrete plate thickness control is carried out before pouring Standard point processed, design thickness and the plate thickness to guarantee concrete are uniform.Broken line type concrete exterior wall and roofing, which pour concrete, must special messenger Be responsible for, unified command is coordinated, since concrete placings amount is big, and be broken line type, pouring construction difficulty is big, my project management department and designing unit It links up, in the case where approving by designing unit, requires to set the joints of concrete projects of broken line type concrete exterior wall and roofing according to scheme At the inner corner trim of folded plate, triangular form inclined-plane is first poured, concrete at construction joint is carried out after concrete strength is met the requirements to pick chisel, is then used Water cleans up, and goes stone concrete to carry out connecing slurry with same label, then pours the above broken line type concrete exterior wall of inner corner trim and roofing concrete.It pours It is poured upwards since broken line type exterior wall bottom edge from bottom to top when concrete, first pours broken line type exterior wall two sides, finally poured top, adopt It being vibrated with poker vibrator, concrete is with smashing with vibration, and vibration point uniformly, pull out slowly by fast insert, until the unobvious sinking in surface, no Until bubble occur and glowing mortar, to ensure the density of casting and compacting of concrete.Strict control concrete slump when pouring, broken line type Exterior wall two sides and roofing sun ridge control respectively, and since the two sides gradient is larger, concrete slump is answered smaller.Broken line type roofing concrete The difficulty of construction for pouring opposite exterior wall is smaller, and roofing is pushed ahead with the progress that pours of exterior wall.But it is noted that broken line The positive ridge of type roofing and exterior wall needs band line to modify, and checks the deviation of size.It first carries out just putting down after concrete vibration compacting, at the beginning of concrete Carry out second plastering, covering maintenance after solidifying before final set again.
The construction of broken line type concrete exterior wall and roofing is many-sided by high-rise working, gradient size, the variation of type shape and groove etc. Influence, formwork and casting concrete, concrete curing are relatively difficult.Since the broken line plate gradient is not easy greatly water storage, surface in addition Product is big, and dehydration fastly and personnel's reasons such as watering difficulty up and down, therefore need to especially carry out maintenance work.In the broken line plate for having poured concrete On, concrete surface moisture state is kept using gunnysack or carpet cloth water seasoning, curing time is no less than 7 round the clock, maintenance Period forbids upper people and carries out operation on it, carries out demoulding after reaching concrete strength.
3.8 demoulding
Form bracing system is removed after concrete strength reaches 100%, when dismounting adhere to " first prop up tear open afterwards, rear branch it is first Tear open " principle, from top to bottom, successively carry out, material is forbidden to forbid to prize firmly using crowbar, must not break from eminence throwing when dismounting The corner angle on bad concrete surface, after dismounting, material should be stacked neat by different cultivars, specification classification.
4. mass control and finished product protection
During broken line type concrete exterior wall and roofing construction, it is necessary to strictly press " construction quality during concrete engineering acceptance specification " (GB50204-2015) requirement carry out construction and inspection of quality, the dominant item of the subdivisional works such as template, reinforcing bar, concrete with The inspection of quality of general data has to comply with code requirement.
4.1 template lofts will reduce the piece quantity of plate face to the greatest extent, while ensure geometric dimension, broken line rate and bright and clean Degree, meets design requirement.
4.2 broken line type templates should place steadily, to handle with care in construction, prevent modification;To guarantee appearance, prevent Spillage, formwork edge joint are connected using ribbet, and side board and bottom plate, side board and side board seam paste single side paper self-adhesive tape, it is ensured that template Piece quality.
It to be carried out by program when 4.3 form removable, and the release agent of brushing in time, forbid to be tapped with sledgehammer or crowbar prizes mould firmly Plate.
4.4 reinforcement detailing emphasis consider different nodes cutting length and broken line rate, splice position, the lap of splice, Anchorage length, end crotch etc..
The positioning of 4.5 reinforcing bars and protective layer are combined using Concrete seat pad and reinforcing bar stirrup, control thickness of protection tier.
4.6 in order to prevent concrete structure and component there is crack, to control the match ratio and slump of concrete, reinforce vibration Pound the maintenance work of concrete.
5. safety measure
5.1 set up supporting steel pipe scaffold, operation layer by " construction fastener type steel pipe scaffold act of technique for security " Floor surrounding will take guard rail and safety net, it is ensured that protection is in place.
5.2 all electricity consumption facilities will be by regulation wiring, and installs earth leakage protective device, carries on construction work at night, it is necessary to have enough Illumination, various power supply line application insulated wires do not allow to be directly anchored on reinforcing bar.
The combustible materials such as 5.3 templates will keep fire away stacking, and be equipped with fire-fighting equipment.
5.4 construction sites will send full-time security official and shift electrician, and inspection implements safety measure, finds the problem and entangle in time Just.
The connected construction technology of engineering multispan broken line type concrete exterior wall and roofing in the present invention, has summed up broken line type concrete structure And component construction method, the deficiency in previous construction is overcome, template construct is simple, size is accurate, reinforcing is convenient, component broken line Rate controls in place, and concrete impression quality is good, and provides reference value for the construction of similar engineering.

Claims (5)

  1. The construction method of concrete structure 1. a kind of broken line type exterior wall is connected with roofing, characterized by the following steps:
    CAD setting-out → field lofting → measurement and positioning → template support frame body sets up → template construct, installation → reinforcement fabrication, peace Dress → broken line type exterior wall first time concrete placings, maintenance → construction joint pick chisel, second of concrete of cleaning → broken line type exterior wall and roofing pours It builds, maintenance → demoulding;Wherein:
    The template support frame body is set up, and concrete operations are as follows:
    It carries out frame body according to the position line of support frame system and absolute altitude to set up, broken line type exterior wall support frame every upright bar absolute altitude of system It is all different, symmetrical as center both sides using broken line, upright bar vertically and horizontally spacing 800mm, bar of sweeping the floor is away from ground 200mm, horizontal distance between tie rods No more than 1500mm, bottom of upright rod makees backing plate with 50mm solid wood;Upright bar, horizontal knock-off joint are staggered no less than 1 across being all made of Joint fastener connection is forbidden using overlap joint, and supporting frame is horizontal, vertical direction is respectively provided with vertically and horizontally bridging, and top is from center Diagonal brace is arranged to both sides in position, it is ensured that the overall stability of frame body;During formwork erection, reinforcing bar binding, concrete placings, to frame Body is monitored, and discovery has displacement to be adjusted in time;
    The template construct, installation, concrete operations are as follows:
    Since broken line type concrete exterior wall has batter post, beam, broken line plate, negative ridge, positive ridge, cause template laying cannot be conventionally It carries out, will cause the waste of template, flitch like that, so that construction cost increases;When template construct, according to the template full-page proof of in-depth Figure carries out accurate setting-out in template, and each piece of template of each broken line plate is numbered, and mosaic part will be to save Principle, it is desirable that blanking is accurate, size is correct, using all leftover pieces, the big big use of material, the small small use of material;
    When template is installed, column, the beam forms between multispan broken line plate need to be first installed, this part-structure position and absolute altitude be not easily-controllable System, need to directly measure according to the control line and absolute altitude of lower floor, according to code requirement arch camber in the middle part of beam slab;Broken line template die plate branch If girder usesSteel pipe is laid with, and makes broken line type according to drawing, the spacing and mark required further according to scheme Height is mounted at the top of support frame in upright bar;45 × 95mm flitch secondary beam is laid on girder steel pipe, then spacing 200mm is laid with 15mm thickness glued board, fixation as required between glued board and flitch, flitch and steel pipe;
    For convenient for broken line type exterior wall concrete placings, to reinforcing bar binding after, it is pre-buried in broken line plate according to layout designSteel Muscle head@900 × 900, at the same it is pre-buriedSoil font reinforcing bar, in order to set up interim steel pipe protective frame;Steel pipe protective frame is taken If need to be solid and reliable, it be convenient for concrete placings and subsequent external wall construction, protective frame upright bar spacing is not more than 2400mm, horizontal tube spacing No more than 1500mm, broken line type exterior wall first time concrete placings can be carried out after qualified by inspection;
    The reinforcement fabrication, installation, concrete operations are as follows:
    The reinforcing bar of broken line type concrete exterior wall and roofing carries out turning over sample and live blanking processing according to drawing in advance, and is charted using CAD The groupware carries out size review, and the broken line degree of reinforcing bar must be consistent with drawing, and otherwise the protective layer thickness of reinforcing bar will not be easily-controllable System, board bottom muscle, which is used, controls concrete cover thickness using reinforcing bar stirrup with Concrete seat pad, plate upper layer muscle, and cushion block and stirrup are vertically and horizontally Spacing is 1000mm, and blossom type is staggeredly arranged, and double steel bar mesh sheet is full bundle, to prevent concrete from gliding, in two layers of steel mesh Between be all made of spacing no more than 800mm, the steel fabric sheet that mesh is 20 × 20mm is bound;
    The broken line type exterior wall first time concrete placings, maintenance → construction joint pick chisel, cleaning → broken line type exterior wall and roofing second Secondary concrete placings, maintenance, concrete operations are as follows:
    Concreting avoids the rainy day from constructing, and concrete uses commerical ready-mixed concrete, and strict control, which is marched into the arena, concrete mix and collapses Degree of falling carries out concrete strip thickness control standard point before pouring, design thickness and the plate thickness to guarantee concrete are uniform;Broken line type concrete Exterior wall and roofing, which pour concrete, must have special messenger to be responsible for, unified command coordination, since concrete placings amount is big, and be broken line type, by broken line The joints of concrete projects of type concrete exterior wall and roofing is located at the inner corner trim of folded plate, triangular form inclined-plane is first poured, after concrete strength is met the requirements Concrete at construction joint is carried out to pick chisel, then washes with water clean, and goes stone concrete to carry out connecing slurry with same label, then pour inner corner trim with Upper broken line type concrete exterior wall and roofing concrete;
    It is poured upwards since broken line type exterior wall bottom edge from bottom to top when pouring concrete, first pours broken line type exterior wall two sides, finally pour Top is built, is vibrated using poker vibrator, concrete is with smashing with vibration, and vibration point uniformly, pull out slowly by fast insert, until surface is unknown Aobvious sinking, until not occurring bubble and glowing mortar, to ensure the density of casting and compacting of concrete;Strict control concrete collapses when pouring Degree, broken line type exterior wall two sides and roofing sun ridge control respectively, and since the two sides gradient is larger, concrete slump is answered smaller;Broken line The difficulty of construction for pouring opposite exterior wall of type roofing concrete is smaller, and roofing is pushed ahead with the progress that pours of exterior wall;But It is noted that the positive ridge of broken line type roofing and exterior wall needs band line to modify, and check the deviation of size;It is first carried out after concrete vibration compacting It is just flat, carry out second plastering, covering maintenance before final set again after concrete initial set;
    Maintenance work need to be especially carried out, on the broken line plate for having poured concrete, is kept using gunnysack or carpet cloth water seasoning Concrete surface moisture state, curing time are no less than 7 round the clock, forbid upper people during maintenance and carry out operation on it, reach Demoulding is carried out after concrete strength;
    The demoulding, concrete operations are as follows:
    Form bracing system is removed after concrete strength reaches 100%, according to " first prop up tear open afterwards, rear branch is first torn open " when dismounting Principle from top to bottom, successively carries out, and material is forbidden to forbid to prize firmly using crowbar, must not destroy concrete table from eminence throwing when dismounting The corner angle in face, after dismounting, material should be stacked neat by different cultivars, specification classification.
  2. The construction method of concrete structure 2. broken line type exterior wall according to claim 1 is connected with roofing, it is characterised in that: The CAD setting-out, concrete operations are as follows: the broken line degree of broken line type exterior wall and position are controlled by the position of support frame, folding Line template is abutted and is connect with support girder, and support girder is abutted and connect with support girder, therefore is wanted to setting up for support frame Arrangement, calculating meticulously;In order to guarantee template broken line degree, to the position of each upright bar and broken line type rod piece before the setting up of support frame Set, absolute altitude carries out meticulous arrangement, calculate, by means of CAD drawing the groupware carry out rod piece elevation carrection, reinforcing bar arrangement, plate Muscle blanking, template and axial dimension review.
  3. The construction method of concrete structure 3. broken line type exterior wall according to claim 1 is connected with roofing, it is characterised in that: The field lofting, concrete operations are as follows:
    Broken line type concrete exterior wall and roofing are before supporting frame is set up, it is necessary to could implement after being sufficiently ready work at the scene, So it is also difficult point that the absolute altitude of support frame and batter post that carpenter sets up and positioning, which are the emphasis for first having to solve when construction, it is specific to mark High and positioning cooperates carpenter to complete by technical staff by the multiple measurement and the positioning of projection line of bench mark;Before construction, The line setting of bottom is particularly important, and project management department technical staff requires carpenter teams and groups first to show by the gross data of CAD setting-out Practical setting-out, that is, after support frame is set up, first by the standard of 8 span centres across i.e. from western second eastwards across it is oblique Column, beam, Side fascia formwork erection in place, then by field technician and design drawing, the data school repeatedly of CAD setting-out It, can large-area construction after confirmation field lofting accurately meets construction requirement to rear.
  4. The construction method of concrete structure 4. broken line type exterior wall according to claim 1 is connected with roofing, it is characterised in that: The measurement and positioning, concrete operations are as follows: according to CAD full-size drawing and construction drawing, putting to one layer of axis, component, absolute altitude Line, positioning, levelling, broken line wallboard and roofing position should have axis, sideline, control line, be released according to template special construction plan " cross " position line of support frame system upright bar, and each spots localization unwrapping wire is checked, control point is drawn and is made a record, Ensure tolerance in specification prescribed limit.
  5. The construction method of concrete structure 5. broken line type exterior wall according to claim 1 is connected with roofing, it is characterised in that: Material prepares as follows: formwork bracing system frame body supervisor usesSteel pipe, template are closed using 15mm thickness clad can wood glue Plate, girder use 45 × 95mm flitch, and frame body steel pipe, fastener, adjustable bracket, template, flitch should carry out conscientiously when marching into the arena Check and select, steel pipe, fastener march into the arena after using the live sampling inspection of preceding progresss, reused after detection qualification, to corroding Seriously, the certified products material for forbidding to select specification unified using, template and flitch of slight crack, depression defect.
CN201910546607.2A 2019-06-24 2019-06-24 Construction method of concrete structure with connected broken line type outer wall and roof Active CN110258890B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910546607.2A CN110258890B (en) 2019-06-24 2019-06-24 Construction method of concrete structure with connected broken line type outer wall and roof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910546607.2A CN110258890B (en) 2019-06-24 2019-06-24 Construction method of concrete structure with connected broken line type outer wall and roof

Publications (2)

Publication Number Publication Date
CN110258890A true CN110258890A (en) 2019-09-20
CN110258890B CN110258890B (en) 2021-03-26

Family

ID=67920664

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910546607.2A Active CN110258890B (en) 2019-06-24 2019-06-24 Construction method of concrete structure with connected broken line type outer wall and roof

Country Status (1)

Country Link
CN (1) CN110258890B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112144899A (en) * 2020-09-11 2020-12-29 西安建筑科技大学 Positioning method of special-shaped inclined bent concrete wall

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1088699A (en) * 1996-09-12 1998-04-07 Sekisui House Ltd Hollowed-out external wall panel
CN1986989A (en) * 2006-11-27 2007-06-27 青岛建设集团公司 Three dimension arch steel concrete structure formwork and construction method
CN101864818A (en) * 2009-04-14 2010-10-20 武汉建工股份有限公司 Construction method of cast-in-situ oblique arc-suspended concrete shear wall
CN102345377A (en) * 2011-07-15 2012-02-08 广州市第三建筑工程有限公司 Method for making spatial multi-curved-surface as-cast finish concrete stay in place formwork by using plywood
CN103074894A (en) * 2013-02-14 2013-05-01 张永忠 Fold line wall forming device
CN104358410A (en) * 2014-10-29 2015-02-18 中冶建工集团有限公司 Space positioning control method of reverse arc wall template
CN107893500A (en) * 2017-12-22 2018-04-10 贵州大学 A kind of large-span concrete prismatic surface arch grid shell roof structure and preparation method thereof
CN109537876A (en) * 2018-11-28 2019-03-29 龙元建设集团股份有限公司 Space variable curvature concrete city wall formwork positioning mode

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1088699A (en) * 1996-09-12 1998-04-07 Sekisui House Ltd Hollowed-out external wall panel
CN1986989A (en) * 2006-11-27 2007-06-27 青岛建设集团公司 Three dimension arch steel concrete structure formwork and construction method
CN101864818A (en) * 2009-04-14 2010-10-20 武汉建工股份有限公司 Construction method of cast-in-situ oblique arc-suspended concrete shear wall
CN102345377A (en) * 2011-07-15 2012-02-08 广州市第三建筑工程有限公司 Method for making spatial multi-curved-surface as-cast finish concrete stay in place formwork by using plywood
CN103074894A (en) * 2013-02-14 2013-05-01 张永忠 Fold line wall forming device
CN104358410A (en) * 2014-10-29 2015-02-18 中冶建工集团有限公司 Space positioning control method of reverse arc wall template
CN107893500A (en) * 2017-12-22 2018-04-10 贵州大学 A kind of large-span concrete prismatic surface arch grid shell roof structure and preparation method thereof
CN109537876A (en) * 2018-11-28 2019-03-29 龙元建设集团股份有限公司 Space variable curvature concrete city wall formwork positioning mode

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112144899A (en) * 2020-09-11 2020-12-29 西安建筑科技大学 Positioning method of special-shaped inclined bent concrete wall

Also Published As

Publication number Publication date
CN110258890B (en) 2021-03-26

Similar Documents

Publication Publication Date Title
CN104846744B (en) Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode
CN103615110B (en) Random oblique netted nine-squares beam Hyperbolic Roof construction method
CN107882321A (en) Diameter Silo slding form operation engineering method
CN107297810A (en) A kind of making of precast wall body component and installation method
CN103590603B (en) Large span multi-curvature shell structure of reinforced concrete method
CN104234012B (en) A kind of concrete loose rock dam ultra-long concrete sliding formwork body and construction method thereof
CN108330835A (en) The construction method of setting bracket
CN105780976B (en) Compound concrete shear wall structure and its concreting method
CN205444887U (en) Slope roofing template system
CN103469806A (en) Construction method for replacing brick forming die with prefabricated concrete foundation bearing platform side die
CN108677743A (en) A kind of concrete cast-in-situ box girder construction method of viaduct
CN102877486A (en) Integral cast-in-situ construction method for cable ducts
CN201924289U (en) Bracket structure for 0# block of high-pier long-span continuous rigid frame bridge
CN103806659B (en) Super thick prestressing force change-over panel individual layer comprehensively supports and splits temperature control construction technology with control
CN108342993B (en) Underwater bearing platform suspension supporting platform and construction method thereof
CN104594633B (en) The construction method and its formwork structure of umbrella shape space curved surface clear-water concrete
CN108277777A (en) Wave wall substep pouring construction process
CN110219422A (en) Anti-seismic concrete staircase design method
CN103243912B (en) Multilayer is without plate framework construction method
CN109112903A (en) Solid concrete roabed trackless construction technology is cheated in a kind of phase library inner column formula inspection
CN110258890A (en) A kind of broken line type exterior wall is connected the construction method of concrete structure with roofing
CN108677722A (en) Hollow High Pier with Thin Wall stub top section construction technology
CN110468729A (en) A kind of frame bridge construction method
CN116910854A (en) Large-span arch concrete structure construction method based on digital construction
CN109881699A (en) The concrete moulding bed fabrication and installation method of the general raft foundation of assembled tongue and groove Miller type

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant