CN110255368A - A kind of detachable pipeline docking facilities - Google Patents

A kind of detachable pipeline docking facilities Download PDF

Info

Publication number
CN110255368A
CN110255368A CN201910661128.5A CN201910661128A CN110255368A CN 110255368 A CN110255368 A CN 110255368A CN 201910661128 A CN201910661128 A CN 201910661128A CN 110255368 A CN110255368 A CN 110255368A
Authority
CN
China
Prior art keywords
support rod
vertical support
bar
cross
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910661128.5A
Other languages
Chinese (zh)
Other versions
CN110255368B (en
Inventor
刘月生
肖祥辉
徐辉
万宇
郑仕平
罗婕莹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guizhou Electric Power Engineering Co Ltd
Original Assignee
PowerChina Guizhou Electric Power Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guizhou Electric Power Engineering Co Ltd filed Critical PowerChina Guizhou Electric Power Engineering Co Ltd
Priority to CN201910661128.5A priority Critical patent/CN110255368B/en
Publication of CN110255368A publication Critical patent/CN110255368A/en
Application granted granted Critical
Publication of CN110255368B publication Critical patent/CN110255368B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25BTOOLS OR BENCH DEVICES NOT OTHERWISE PROVIDED FOR, FOR FASTENING, CONNECTING, DISENGAGING OR HOLDING
    • B25B11/00Work holders not covered by any preceding group in the subclass, e.g. magnetic work holders, vacuum work holders
    • B25B11/02Assembly jigs
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/22Rigid members, e.g. L-shaped members, with parts engaging the under surface of the loads; Crane hooks
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L3/00Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Supports For Pipes And Cables (AREA)
  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The invention discloses a kind of detachable pipeline docking facilities, comprising: 2 horizontal support bars;2 vertical support rods;Cross bar;The vertical support rod is that horizontal cross-section is criss-cross stock, and the vertical support rod matches with the cross jack, and the vertical support rod is plugged on the horizontal support bar by the cross jack.To solve the problems, such as that the prior art is extremely difficult due to integral type shelf volume and weight also larger movement.

Description

A kind of detachable pipeline docking facilities
Technical field
The present invention relates to pipeline docking technique field more particularly to a kind of detachable pipeline docking facilities.
Background technique
Pipeline docking is commonly used construction problem in Thermal Power Plant Construction, it is therefore an objective to by two pipelines according to certain essence Degree requires to link together in two pipelines.Pipeline is hung up realization pair using integral type shelf by existing pipeline docking It connects.
But problem of the existing technology is, since the pipeline for needing to lift is usually larger, leads to integral type shelf volume It is also larger with weight, once it needs from a position to be moved to a position, very due to device volume and the larger movement of weight It is difficult.
Summary of the invention
In order to solve the disadvantage that the above prior art and shortcoming, primary and foremost purpose of the invention are to provide a kind of detachable Formula pipeline docking facilities.
The technical scheme is that a kind of detachable pipeline docking facilities,
Include:
2 horizontal support bars, the horizontal support bar are located at same level and are parallel to each other, the horizontally-supported boom end It is mutually aligned;
2 vertical support rods, the vertical support rod direction is vertical, in the vertical support rod lower end and the horizontal support bar Portion's connection;
Cross bar is parallel to the horizontal plane, and the cross bar both ends are separately connected the vertical support rod;
Upper surface is fixedly connected with cross jack in the middle part of the horizontal support bar, the one of hole wall of the cross jack and water Flat support rod is parallel;
The vertical support rod is that horizontal cross-section is criss-cross stock, the vertical support rod and the cross jack phase Match, the vertical support rod is plugged on the horizontal support bar by the cross jack.
The vertical support rod wall parallel with the horizontal support bar length direction is equipped with along the vertical support rod The equally distributed hole of length direction;
The cross bar is the angle steel that both ends have side wall, is provided with hole on the side wall, the cross bar is bolted described On vertical support rod.
The horizontal support bar further include:
2 auxiliary drawstrings, described auxiliary drawstring one end are connected to the horizontally-supported boom end other end and connect vertical support rod.
The auxiliary drawstring further include:
Hook, the hook are connected to one end that the auxiliary drawstring leans on vertical support rod, link up on size and vertical support rod Hole match, the auxiliary drawstring is by the hole being articulated on the vertical support rod.
The horizontal support bar further include:
Rope reeling mechanism, the rope reeling mechanism are fixedly connected on the horizontally-supported boom end, and the auxiliary drawstring passes through the receipts Rope mechanism is connect with horizontally-supported boom end.
The rope reeling mechanism includes:
Twisted wire column harasses and disturbs the auxiliary drawstring on the twisted wire column;
Knob, one end are fixedly connected on the twisted wire column, and the knob is equipped with equally distributed around the twisted wire column one week Dynamic card hole;
The horizontally-supported boom end is equipped with the horizontal support bar length direction perpendicular to and at the mounting hole on horizontal plane, The twisted wire column is rotatably installed on mounting hole by mounting hole;
The horizontally-supported boom end be equipped with the horizontal support bar length direction perpendicular to and on horizontal plane around installation The equally distributed quiet card hole in hole, the quiet card hole is at a distance from mounting hole and dynamic card hole is identical at a distance from twisted wire column, quiet card hole Match with dynamic card hole.
The detachable pipeline docking facilities further include:
Secondary cross bar, the pair cross bar are the angle steel that both ends have side wall, and hole is provided on the side wall, and the pair cross bar passes through bolt It is connected on the vertical support rod, the pair cross bar height is less than cross bar.
The beneficial effects of the present invention are:
Compared with prior art, the present invention is linked together horizontal support bar and vertical support rod by inserting mode, can be The fractionation of the realization device by way of dismantling horizontal support bar and vertical support rod when mobile device is needed, device is split into 3 A component, each component are reduced compared with device overall volume and weight, therefore are more easier mobile and are carried;Horizontal cross-section It is criss-cross vertical support rod while guaranteeing vertical support rod bending resistance, decreases vertical support rod materials, More convenient carrying.
Detailed description of the invention
Fig. 1 is three-dimensional view of the invention;
Fig. 2 is the perspective view of horizontal support bar of the present invention;
Fig. 3 is the enlarged view at A of the present invention;
Fig. 4 is the perspective view of the vertical support rod of the present invention;
Fig. 5 is the perspective view of cross bar of the present invention and secondary cross bar.
Specific embodiment
With reference to the accompanying drawing and invention is described further in specific embodiment:
Referring to figs. 1 to Fig. 5, a kind of detachable pipeline docking facilities, comprising: 2 horizontal support bars 1, the horizontal support bar 1 It positioned at same level and is parallel to each other, 1 end of horizontal support bar is mutually aligned;2 vertical support rods 2, it is described perpendicular 2 direction of support bars is vertical, connects in the middle part of vertical 2 lower end of support rod and the horizontal support bar 1;Cross bar 3, with horizontal plane In parallel, 3 both ends of cross bar are separately connected the vertical support rod 2;The 1 middle part upper surface of horizontal support bar is fixedly connected with ten Font jack 101, the one of hole wall of the cross jack 101 are parallel with horizontal support bar 1;The vertical support rod 2 is Horizontal cross-section is criss-cross stock, and the vertical support rod 2 matches with the cross jack 101, the vertical support Bar 2 is plugged on the horizontal support bar 1 by the cross jack 101.
The present invention is linked together horizontal support bar 1 and vertical support rod 2 by inserting mode, can need mobile dress When setting by way of dismantling horizontal support bar 1 and vertical support rod 2 realization device fractionation, device is split into 3 components, often A component is all reduced compared with device overall volume and weight, therefore is more easier mobile and is carried;Horizontal cross-section is cross Vertical support rod while guaranteeing vertical 2 bending resistance of support rod, decrease vertical support rod materials, it is more convenient It carries.In addition vertical support rod 2 is plugged on horizontal support bar 1 by cross jack 101, so that on vertical support rod 2 Hole site accurately keeps in one direction, cross bar 3 being facilitated to install always.
The vertical support rod 2 wall parallel with 1 length direction of horizontal support bar is equipped with along the vertical support The equally distributed hole of 2 length direction of bar;The cross bar 3 is the angle steel that both ends have side wall, is provided with hole, the cross on the side wall Bar 3 is bolted on the vertical support rod 2.
The hole being connect by changing cross bar 3 with vertical support rod 2, so that 3 height of cross bar is adjusted, to adapt to different pipes The installation requirement in road, is on the other hand bolted, so that cross bar 3 and vertical support rod 2 are removable separated, component further increases It is more, more convenient carrying.
The horizontal support bar 1 further include: 2 auxiliary drawstrings 102,102 one end of auxiliary drawstring bolt are propped up in level The 1 end other end of strut is by bolt or is articulated on vertical support rod 2.
Auxiliary drawstring 102 can further consolidate vertical support rod 2, and also act as and reduce vertical support rod 2 to cross The effect of 101 pressure of jack.
The auxiliary drawstring 102 further include: hook 107, the hook 107 are connected to the auxiliary drawstring 102 by vertical One end of support rod 2,107 sizes of hook match with the hole on vertical support rod 2, and the auxiliary drawstring 102 passes through the extension Hook 107 is articulated on the hole on the vertical support rod 2.
Auxiliary drawstring 102 can be easily articulated on vertical support rod 2 by hook 107.
The horizontal support bar 1 further include: rope reeling mechanism, the rope reeling mechanism are fixedly connected on the horizontal support bar 1 End, the auxiliary drawstring 102 are connect by the rope reeling mechanism with 1 end of horizontal support bar.
Rope reeling mechanism can tighten auxiliary drawstring 102, be inserted with increasing the stability of vertical support rod 2 and reducing cross The pressure in hole 101.
The rope reeling mechanism includes: twisted wire column 103, and the auxiliary drawstring 102 is harassed and disturbed on the twisted wire column 103;Rotation Button 104, one end are fixedly connected on the twisted wire column 103, and the knob 104 is equipped with uniform around the twisted wire column 103 1 weeks The dynamic card hole 105 of distribution;1 end of horizontal support bar is equipped with 1 length direction of horizontal support bar perpendicular to and at water Mounting hole 108 in plane, the twisted wire column 103 are rotatably installed on mounting hole 108 by mounting hole 108;The horizontal branch 1 end of strut is equipped with 1 length direction of horizontal support bar perpendicular to and at being uniformly distributed on horizontal plane around mounting hole 108 Quiet card hole 105, the quiet card hole 105 is at a distance from mounting hole 108 and dynamic card hole 105 is identical at a distance from twisted wire column 103, quiet Card hole 105 matches with dynamic card hole 105.
In use, rotation knob 104 can will auxiliary drawstring 102 be wrapped on twisted wire column 103 make assist drawstring 102 into The tightening of one step injects dynamic card hole 106 and quiet card hole 105 using rod, so that twisted wire column when tightening to a certain extent simultaneously 103 will not rotate, to make that drawstring 102 is assisted not loosen.
The detachable pipeline docking facilities further include: secondary cross bar 4, the pair cross bar 4 are the angle that both ends have side wall Steel is provided with hole on the side wall, and the pair cross bar 4 is bolted on the vertical support rod 2, and the pair cross bar 4 is high Degree is less than cross bar 3.
Secondary cross bar 4 plays the role of enhancement device structure, and 22 lower parts of vertical support rod is avoided to open or close up.
The above content is a further detailed description of the present invention in conjunction with specific preferred embodiments, and it cannot be said that Specific implementation of the invention is only limited to these instructions.For those of ordinary skill in the art to which the present invention belongs, exist Under the premise of not departing from present inventive concept, a number of simple deductions or replacements can also be made, all shall be regarded as belonging to of the invention Protection scope.

Claims (7)

1. a kind of detachable pipeline docking facilities, which is characterized in that
Include:
2 horizontal support bars (1), the horizontal support bar (1) is located at same level and is parallel to each other, described horizontally-supported Bar (1) end is mutually aligned;
2 vertical support rods (2), vertical support rod (2) direction is vertical, vertical support rod (2) lower end and the water Connection in the middle part of flat support rod (1);
Cross bar (3), is parallel to the horizontal plane, and cross bar (3) both ends are separately connected the vertical support rod (2);
Upper surface is fixedly connected cross jack (101) in the middle part of the horizontal support bar (1), the cross jack (101) its In a hole wall it is parallel with horizontal support bar (1);
It is criss-cross stock that the vertical support rod (2), which is horizontal cross-section, and the vertical support rod (2) and the cross are inserted Hole (101) matches, and the vertical support rod (2) is plugged on the horizontal support bar (1) by the cross jack (101) On.
2. detachable pipeline docking facilities according to claim 1, which is characterized in that
The vertical support rod (2) wall parallel with the horizontal support bar (1) length direction is equipped with along the vertical support Bar (2) equally distributed hole of length direction;
The cross bar (3) is the angle steel that both ends have side wall, is provided with hole on the side wall, the cross bar (3) is bolted On the vertical support rod (2).
3. detachable pipeline docking facilities according to claim 1, which is characterized in that
The horizontal support bar (1) further include:
2 auxiliary drawstrings (102), it is perpendicular that described auxiliary drawstring (102) one end is connected to the connection of horizontal support bar (1) the end other end Support bars (2).
4. detachable pipeline docking facilities according to claim 3, which is characterized in that
The auxiliary drawstring (102) further include:
It links up with (107), the hook (107) is connected to one end that auxiliary drawstring (102) leans on vertical support rod (2), hook (107) size matches with the hole on vertical support rod (2), and the auxiliary drawstring (102) is articulated in by the hook (107) On hole on the vertical support rod (2).
5. detachable pipeline docking facilities according to claim 3, which is characterized in that
The horizontal support bar (1) further include:
Rope reeling mechanism, the rope reeling mechanism are fixedly connected on the horizontal support bar (1) end, and the auxiliary drawstring (102) is logical The rope reeling mechanism is crossed to connect with horizontal support bar (1) end.
6. detachable pipeline docking facilities according to claim 5, which is characterized in that
The rope reeling mechanism includes:
Twisted wire column (103) harasses and disturbs the auxiliary drawstring (102) on the twisted wire column (103);
Knob (104), one end are fixedly connected on the twisted wire column (103), and the knob (104) is equipped with around the twisted wire column (103) one weeks equally distributed dynamic card holes (105);
Horizontal support bar (1) end is equipped with the horizontal support bar (1) length direction perpendicular to and on horizontal plane Mounting hole (108), the twisted wire column (103) are rotatably installed on mounting hole (108) by mounting hole (108);
Horizontal support bar (1) end is equipped with the horizontal support bar (1) length direction perpendicular to and on horizontal plane Around the equally distributed quiet card hole (105) of mounting hole (108), the quiet card hole (105) is at a distance from mounting hole (108) and dynamic card hole (105) identical at a distance from twisted wire column (103), quiet card hole (105) matches with dynamic card hole (105).
7. detachable pipeline docking facilities according to claim 2, which is characterized in that
The detachable pipeline docking facilities further include:
Secondary cross bar (4), the pair cross bar (4) are the angle steel that both ends have side wall, and hole, the pair cross bar are provided on the side wall (4) it is bolted on the vertical support rod (2), the pair cross bar (4) is highly less than cross bar (3).
CN201910661128.5A 2019-07-22 2019-07-22 Detachable pipeline interfacing apparatus Active CN110255368B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910661128.5A CN110255368B (en) 2019-07-22 2019-07-22 Detachable pipeline interfacing apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910661128.5A CN110255368B (en) 2019-07-22 2019-07-22 Detachable pipeline interfacing apparatus

Publications (2)

Publication Number Publication Date
CN110255368A true CN110255368A (en) 2019-09-20
CN110255368B CN110255368B (en) 2024-03-26

Family

ID=67927612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910661128.5A Active CN110255368B (en) 2019-07-22 2019-07-22 Detachable pipeline interfacing apparatus

Country Status (1)

Country Link
CN (1) CN110255368B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201746248U (en) * 2010-05-21 2011-02-16 中国人民解放军海军航空工程学院 Simple gantry crane
CN203602256U (en) * 2013-10-16 2014-05-21 国家电网公司 Hoisting portal frame
JP2014189383A (en) * 2013-03-28 2014-10-06 Kandenko Co Ltd Hoisting fixture for heavy material
CN205203063U (en) * 2015-12-22 2016-05-04 徐晰 Detachable carrier
CN106429870A (en) * 2016-10-21 2017-02-22 周东宁 Combined structure movable crane
CN207423966U (en) * 2017-11-15 2018-05-29 丁碧江 A kind of concrete slump test device
CN210438272U (en) * 2019-07-22 2020-05-01 中国电建集团贵州电力设计研究院有限公司 Detachable pipeline butt-joint structural

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201746248U (en) * 2010-05-21 2011-02-16 中国人民解放军海军航空工程学院 Simple gantry crane
JP2014189383A (en) * 2013-03-28 2014-10-06 Kandenko Co Ltd Hoisting fixture for heavy material
CN203602256U (en) * 2013-10-16 2014-05-21 国家电网公司 Hoisting portal frame
CN205203063U (en) * 2015-12-22 2016-05-04 徐晰 Detachable carrier
CN106429870A (en) * 2016-10-21 2017-02-22 周东宁 Combined structure movable crane
CN207423966U (en) * 2017-11-15 2018-05-29 丁碧江 A kind of concrete slump test device
CN210438272U (en) * 2019-07-22 2020-05-01 中国电建集团贵州电力设计研究院有限公司 Detachable pipeline butt-joint structural

Also Published As

Publication number Publication date
CN110255368B (en) 2024-03-26

Similar Documents

Publication Publication Date Title
CN208363546U (en) A kind of adjustable construction scaffolding
CN203923914U (en) Solely stub bent cap support
CN205116715U (en) Cast -in -situ box girder template bracing device
CN208417748U (en) A kind of connector for adjustable installing bracket
CN110255368A (en) A kind of detachable pipeline docking facilities
CN207110466U (en) Pulling-on piece formula aluminum alloy mould plate reinforcing member and pulling-on piece formula template system
CN204877802U (en) Angle can be adjusted support and small wind turbine machine
CN209509655U (en) A kind of project installation protection fence
CN210438272U (en) Detachable pipeline butt-joint structural
CN206820438U (en) It is a kind of to be easy to fixed quantum communications electric wire
CN207004155U (en) A kind of adjustable tower erection instrument
CN204510814U (en) Beam for building jacking
CN211965496U (en) Pipeline bending platform for concentrated solution system installation
CN110725619B (en) Fender is enclosed in construction convenient to dismantle
CN207853369U (en) A kind of cable bearer
CN210289043U (en) Anti-toppling scaffold
CN209273355U (en) A kind of fastening straight screw sleeve connection tool
CN110043297A (en) A kind of tunnel inverted arch buried water strip fixture
CN206707239U (en) A kind of elevator Integral hoisting operating platform
CN208749069U (en) A kind of hanging basket adjustable lifting
CN207319851U (en) Transformer rack
CN207829493U (en) A kind of steel structure net rack supporting device for welding
CN105178596A (en) Cast-in-place box girder formwork diagonal bracing device
CN207143742U (en) A kind of large-span steel girder hoisting appliance
CN205077677U (en) Pull rod formula steel construction point type glass curtain wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant