CN110243654A CN201910185103.2A CN201910185103A CN110243654A CN 110243654 A CN110243654 A CN 110243654A CN 201910185103 A CN201910185103 A CN 201910185103A CN 110243654 A CN110243654 A CN 110243654A
Authority
CN
China
Prior art keywords
target plate
glan
axis
lid
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910185103.2A
Other languages
Chinese (zh)
Inventor
王波
屈焕成
刘国弼
张小平
张祖哲
屈红岗
于鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huadian Electric Power Research Institute Co Ltd
Original Assignee
Huadian Electric Power Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huadian Electric Power Research Institute Co Ltd filed Critical Huadian Electric Power Research Institute Co Ltd
Priority to CN201910185103.2A priority Critical patent/CN110243654A/en
Publication of CN110243654A publication Critical patent/CN110243654A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B08CLEANING
    • B08BCLEANING IN GENERAL; PREVENTION OF FOULING IN GENERAL
    • B08B9/00Cleaning hollow articles by methods or apparatus specially adapted thereto
    • B08B9/02Cleaning pipes or tubes or systems of pipes or tubes
    • B08B9/027Cleaning the internal surfaces; Removal of blockages
    • B08B9/032Cleaning the internal surfaces; Removal of blockages by the mechanical action of a moving fluid, e.g. by flushing
    • B08B9/0321Cleaning the internal surfaces; Removal of blockages by the mechanical action of a moving fluid, e.g. by flushing using pressurised, pulsating or purging fluid
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01MTESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
    • G01M13/00Testing of machine parts
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N1/00Sampling; Preparing specimens for investigation
    • G01N1/28Preparing specimens for investigation including physical details of (bio-)chemical methods covered elsewhere, e.g. G01N33/50, C12Q
    • G01N1/34Purifying; Cleaning

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Biomedical Technology (AREA)
  • Molecular Biology (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Mechanical Engineering (AREA)
  • Pipe Accessories (AREA)

Abstract

The present invention relates to a kind of sweeping steam pipeline target plate device, the through hole perpendicular with its axial direction is offered on target plate casing, the both ends of the through hole are welded to connect Glan set;It opens up at least two contrary and not in the target plate slot of sustained height on target plate axis, target plate is installed in target plate slot;Target plate axis passes through Glan set and through hole, and is positioned by Glan lid, and after positioning, at least one target plate is located in the through hole of target plate casing.The present invention is extracted by target axis play realization target plate, installation is synchronous, it can be achieved that continuous purge, and device intensity and toughness is big, target plate axis is not easy to deform, and operator directly facing device, does not avoid and scalds risk by high-temperature steam, working efficiency significantly improves, and working environment significantly improves.

Description

Sweeping steam pipeline target plate device
Technical field
The present invention relates to steam pipe system installing areas, in particular, being related to a kind of sweeping steam pipeline target plate device.
Background technique
Publication in National Energy Board's on November 28th, 2013, on 04 01st, 2014 People's Republic of China's electric power row implemented Industry standard (DL/T 5295-2013): unit is whole in " thermal power generation construction project unit regulation inspection of quality and assessment routine " The condition inspection table 4.4.2 that should have before set starting luck is provided: the commissioning of individual system of boiler profession is completed, and has been handled quality and tested Visa is received, technical data is complete;Steam-line blowing construction unit checks and accepts blowpipe quality control standards (QCS) " 1) target plate in table 3.3.3-23 Spot granularity≤0.8mm or by manufactory's requirement;2) it target plate spot quantity≤8 (0.2mm or less disregards) or is wanted by manufactory It asks;3) target plate: length >=interim pipe diameter and is not less than 25mm at pipe diameter where width >=8% target plate, material aluminium sheet or by system Make factory's requirement;4) re-pack number: continuously blowing 2 times or by manufactory's requirement ".
Specified in background paper the precondition that should have of Turbo-generator Set the whole series starting test run first is that steam pipe Road purging is qualified, prevents from unqualified causing in jet chimney the impurity such as solid particle to enter steam turbine to damage because not purging or purging Passage component or blocking flow passage component influence turbine expansion acting ability.With the extensive use of " "four news" (new ideas " technology, high parameter, Large sized unit has become the main force of national grid generating set, and backward in technique, inefficiency, waste discharge be not up to standard Unit is gradually backed out active service, and the board-like technology that proposes still is widely applied in sweeping steam pipeline target plate device at present, installation and more Personnel are careless slightly to can suffer from high-temperature steam scald closely directly facing target plate device when changing target plate, and install, extract Target plate speed is slow, cannot continuously replace target plate, does not meet the inspection target plate standard requirements twice that continuously re-pack.Such as Publication No. CN202661091, the Chinese patent that authorized announcement date is 2013.01.09: the built-in purging target plate of gas pipeline, the patent skill Art scenario-frame is simple, manufacture difficulty is low, but cannot synchronize and realize target plate installation and extract.
Therefore, it is necessary to which existing target plate device is improved and is optimized.
Summary of the invention
It is an object of the invention to overcome the above deficiencies in the existing technologies, and provide it is a kind of reasonable in design, Realize that target plate extracts, installation synchronizes, it can be achieved that the target plate device continuously purged.
Technical solution used by the present invention solves the above problems is: a kind of sweeping steam pipeline target plate device, including with The target plate casing to be linked together by the interim gland steam exhauster of purging pipeline, it is characterised in that: further include target plate axis, Glan set and Glan Lid;The through hole perpendicular with its axial direction is offered on the target plate casing, the both ends of the through hole are welded to connect Glan set; It opens up at least two contrary and not in the target plate slot of sustained height on the target plate axis, target plate is installed in target plate slot;It is described Target plate axis passes through Glan set and through hole, and is positioned by Glan lid, and after positioning, at least one target plate is located at target plate set In the through hole of pipe.
Preferably, target plate casing of the present invention with by the interim gland steam exhauster of purging pipeline by being welded together, target The nominal diameter of sleeve-board pipe is equal with by the nominal diameter of the interim gland steam exhauster of purging pipeline.
Preferably, filling indentation graphite packing is sealed at the faying face of Glan set and target plate axis of the present invention.
Preferably, the both ends of target plate axis of the present invention are respectively provided with the thin axis that one section of cross section is square.
Preferably, it is provided with location hole on the thin axis in target plate shaft end of the present invention portion and the short tube of Glan lid, led to It is inserted into positioning pin in passing location hole, realizes the positioning to target plate axis and Glan lid.
Preferably, Glan set and Glan lid of the present invention are fastenedly connected by screw bolt and nut, the Glan set and lattice Orchid lid is the structure with short tube and the flange plate faying face connecting with short tube, on the plate faying face of the Glan set It opens up fluted, shaft is welded in groove, an end cap of the bolt can rotate around the shaft in shaft.
Preferably, countersunk screw holes are offered in the groove bottom of target plate slot of the present invention, is consolidated target plate by counter-sunk screw It is scheduled in target plate slot.
Compared with prior art, the present invention having the following advantages that and effect: this target plate device is a kind of detachable, repeatable The mechanical device used need to only extract the positioning pin in the location hole of target plate axis one end out when extracting target plate, hit with a hammer target plate axis Another side end face scurries into the target plate axis that target plate has been installed in the other side in target plate casing, by being after positioning finger setting target plate axis The extractable target plate to inspection scurried out out of target plate casing, alters shaft type due to taking, realize it is online carry out target plate extraction, Change the outfit work, and working efficiency greatly improves, meet blowpipe quality control standards (QCS) in steam-line blowing construction unit " continuously blow 2 times or By manufactory's requirement " the number requirement that re-packs;Filled graphite packing in Glan set realizes pressure by Glan lid and bolt, nut Tight packing, sealing target plate axis effect, prevent steam from leaking out along target plate axis, scald staff;In addition, since target plate is to alter axis Formula carries out in target plate axis side when staff extracts installation target plate and separate device, working environment is improved, personal safety It is protected.
Detailed description of the invention
It, below will be to specific implementation in order to illustrate more clearly of the specific embodiment of the invention or scheme in the prior art Mode or attached drawing needed to be used in the description of the prior art are briefly described, it should be apparent that, the accompanying drawings in the following description It is some embodiments of the present invention, for those skilled in the art, without creative efforts, may be used also To obtain other drawings based on these drawings.
Fig. 1 is the structural schematic diagram of the embodiment of the present invention.
Description of symbols: target plate casing 1, target plate axis 2, Glan set 3, Glan lid 4, graphite packing 5, bolt 6, nut 7, Countersunk screw holes 8, target plate slot 9, location hole 10, shaft 11.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawing and by embodiment, and following embodiment is to this hair Bright explanation and the invention is not limited to following embodiments.
Embodiment.
Referring to Fig. 1.
The present embodiment be a kind of sweeping steam pipeline target plate device, including target plate axis 2, Glan set 3, Glan lid 4 and with The target plate casing 1 to be linked together by the interim gland steam exhauster of purging pipeline.Target plate casing 1 passes through with by the interim gland steam exhauster of purging pipeline It is welded together, the nominal diameter of target plate casing 1 is equal with by the nominal diameter of the interim gland steam exhauster of purging pipeline.Glan set 3 and Glan lid 4 be the structure type with short tube and the flange plate faying face being connect with short tube.
In the present embodiment, the through hole perpendicular with its axial direction is offered on target plate casing 1, the both ends of the through hole are welded Glan set 3 is connect in succession.Both direction is opened up on target plate axis 2 on the contrary and not in the target plate slot 9 of sustained height, the slot bottom of target plate slot 9 Countersunk screw holes 8 are offered on face, and target plate is fixed in target plate slot 9 by counter-sunk screw.The length of target plate slot 9 should traverse target plate 1 internal diameter of casing, width >=25% target plate casing, 1 diameter, depth, which should ensure that, can guarantee that target plate axis 2 is easily altered when cold conditions is packed into target plate It is dynamic;Since target plate is different with 2 material of target plate axis, the coefficient of expansion is different, therefore circular screwhole should be processed in the middle part of target plate, two sides processing Oval screw hole, it is ensured that free wxpansion under target plate high temperature, and the screw hole opened up on target plate should be counter sink, guarantee counter-sunk screw head Without exposed gap between target plate, avoid leading to screw loosening because gap steam enters, target plate falls off, in addition, target plate meets steam side It should polish on one side, it is ensured that be easy to examine purging effect after purging.
In the present embodiment, target plate axis 2 passes through Glan set 3 and through hole, and is positioned by Glan lid 4, after positioning, until A rare target plate is located in the through hole of target plate casing 1.In order to realize sealing, prevents steam from leaking out along target plate axis, scald work Make personnel, filling indentation graphite packing 5, graphite packing 5 should be layered indentation and cut at the faying face of Glan set 3 and target plate axis 2 Mouth should be staggered.
In the present embodiment, the both ends of target plate axis 2 are respectively provided with the thin axis that one section of cross section is square, thin axis and Glan Location hole 10 is provided on the short tube of lid 4, by realizing to target plate axis 2 and Glan lid 4 toward the inner insertion positioning pin of location hole 10 Positioning.Glan set 3 and Glan lid 4 are fastenedly connected by bolt 6 and nut 7, are offered on the plate faying face of Glan set 3 recessed Slot is welded with shaft 11 in groove, and an end cap of bolt 6, and can 11 rotation around the shaft in shaft 11.
In the present embodiment, referring to Fig. 1, to extract it is purged positioned at the first target plate of upper end when, by 2 upper end of target plate axis The positioning pin in portion is extracted out, is tapped after target plate installed and alter axis in place with hammer from the lower end of target plate axis 2, is clamped target with open-end wrench Then target plate axis 2 is rotated 180 ° and adjusts target plate position, it is ensured that the second target positioned at lower end by the thin axis of 2 lower end of board shaft Plate face steam direction can remove the first target plate at this time and carry out inspection then to the positioning finger setting of 2 lower end of target plate axis.
Target plate device only need to weld again target plate casing 1, looser a bolt 6, nut 7, light with hammer when reusing Strike nut 7, bolt 6, nut 7 slip, and remove Glan lid 4, dig out old graphite packing and restore after the new packing that changes the outfit Glan lid 4 and It can.
In addition, it should be noted that, the specific embodiments described in this specification, the shape of parts and components are named Title etc. can be different, and above content is only to structure of the invention example explanation described in this specification.It is all according to According to equivalence changes or simple change that the structure, feature and principle that the invention patent is conceived is done, it is included in of the invention special In the protection scope of benefit.Those skilled in the art can do described specific embodiment various The similar mode of modify or supplement or adopt substitute, without departing from structure of the invention or surmount the claims institute The range of definition, is within the scope of protection of the invention.

Claims (7)

1. a kind of sweeping steam pipeline target plate device, including with the target plate casing that is linked together by the interim gland steam exhauster of purging pipeline (1), it is characterised in that: further include target plate axis (2), Glan set (3) and Glan lid (4);Offered on the target plate casing (1) with Its axial perpendicular through hole, the both ends of the through hole are welded to connect Glan set (3);Opened up on the target plate axis (2) to Few both direction is opposite and target plate is not installed in the target plate slot (9) of sustained height, target plate slot (9);The target plate axis (2) is worn Glan set (3) and through hole are crossed, and is positioned by Glan lid (4), after positioning, at least one target plate is located at target plate casing (1) in through hole.
2. sweeping steam pipeline target plate device according to claim 1, it is characterised in that: the target plate casing (1) and quilt The purging interim gland steam exhauster of pipeline by being welded together, temporarily arrange with by purging pipeline by the nominal diameter of target plate casing (1) The nominal diameter of steam pipe is equal.
3. sweeping steam pipeline target plate device according to claim 1, it is characterised in that: the Glan set (3) and target plate Filling indentation graphite packing (5) is sealed at the faying face of axis (2).
4. sweeping steam pipeline target plate device according to claim 1, it is characterised in that: the both ends of the target plate axis (2) Portion is respectively provided with the thin axis that one section of cross section is square.
5. sweeping steam pipeline target plate device according to claim 4, it is characterised in that: target plate axis (2) end Location hole (10) are provided on the short tube of thin axis and Glan lid (4), by being inserted into positioning pin toward location hole (10) is inner, are realized Positioning to target plate axis (2) and Glan lid (4).
6. sweeping steam pipeline target plate device according to claim 1, it is characterised in that: the Glan set (3) and Glan Lid (4) is fastenedly connected by bolt (6) and nut (7), the Glan set (3) and Glan lid (4) be with short tube and with The structure of the flange plate faying face of short tube connection opens up fluted, weldering in groove on the plate faying face of the Glan set (3) It is connected to shaft (11), an end cap of the bolt (6) (11) can rotate around the shaft on shaft (11).
7. sweeping steam pipeline target plate device according to claim 1, it is characterised in that: the slot bottom of the target plate slot (9) Countersunk screw holes (8) are offered on face, and target plate is fixed in target plate slot (9) by counter-sunk screw.
CN201910185103.2A 2019-03-12 2019-03-12 Sweeping steam pipeline target plate device Pending CN110243654A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910185103.2A CN110243654A (en) 2019-03-12 2019-03-12 Sweeping steam pipeline target plate device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910185103.2A CN110243654A (en) 2019-03-12 2019-03-12 Sweeping steam pipeline target plate device

Publications (1)

Publication Number Publication Date
CN110243654A true CN110243654A (en) 2019-09-17

Family

ID=67883098

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910185103.2A Pending CN110243654A (en) 2019-03-12 2019-03-12 Sweeping steam pipeline target plate device

Country Status (1)

Country Link
CN (1) CN110243654A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111141752A (en) * 2020-02-25 2020-05-12 镇江华东电力设备制造厂有限公司 Automatic target plate device for preventing steam scald
CN111774381A (en) * 2020-03-18 2020-10-16 华电电力科学研究院有限公司 Automatic purging device for coal-fired power plant hearth pressure switch sampling pipe and control method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202661091U (en) * 2012-05-15 2013-01-09 中国二十冶集团有限公司 Built-in purging target plate for gas pipeline
CN203376145U (en) * 2013-04-23 2014-01-01 中国联合工程公司 Target plate installation structure in steam pipeline purging system
CN106338076A (en) * 2016-11-07 2017-01-18 中国化学工程第四建设有限公司 The purging and targeting device for high-pressure steam pipeline
CN109332307A (en) * 2018-11-27 2019-02-15 中国电建集团贵州工程有限公司 A kind of pipeline purging target plate system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202661091U (en) * 2012-05-15 2013-01-09 中国二十冶集团有限公司 Built-in purging target plate for gas pipeline
CN203376145U (en) * 2013-04-23 2014-01-01 中国联合工程公司 Target plate installation structure in steam pipeline purging system
CN106338076A (en) * 2016-11-07 2017-01-18 中国化学工程第四建设有限公司 The purging and targeting device for high-pressure steam pipeline
CN109332307A (en) * 2018-11-27 2019-02-15 中国电建集团贵州工程有限公司 A kind of pipeline purging target plate system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111141752A (en) * 2020-02-25 2020-05-12 镇江华东电力设备制造厂有限公司 Automatic target plate device for preventing steam scald
CN111774381A (en) * 2020-03-18 2020-10-16 华电电力科学研究院有限公司 Automatic purging device for coal-fired power plant hearth pressure switch sampling pipe and control method thereof
CN111774381B (en) * 2020-03-18 2023-12-05 华电电力科学研究院有限公司 Automatic purging device for sampling tube of hearth pressure switch of coal-fired power plant and control method of automatic purging device

Similar Documents

Publication Publication Date Title
CN110243654A (en) Sweeping steam pipeline target plate device
CN104436919A (en) Natural gas filtering device and using and disassembling method thereof
CN112901289B (en) Blade vibration monitoring device at top of low-pressure final-stage moving blade of steam turbine
US20190093483A1 (en) Systems and methods for producing one or more cooling holes in an airfoil for a gas turbine engine
CN210087407U (en) Protection mechanism of steam turbine
CN203835469U (en) Turbine low-pressure shaft seal steam supply system
CN102798502B (en) A kind of method of obtaining Turbine Shaft Gland System Leakage tolerance
CN204457882U (en) A kind of combined type bearing housing shaft end seal system
CN213933235U (en) Self-sealing flat-head coal powder sampling gun
CN210090149U (en) Steam pipeline sweeps target plate device
CN204881239U (en) Device is changed to condenser cooling tube
CN204514655U (en) A kind of closed coal dust sampling system
CN209246138U (en) A kind of controller for gas of commercial stove
CN209587127U (en) A kind of simple connecting shaft protective device for small miniature pressure energy of natural gas power generation
CN206860239U (en) Seal protecting device and steam turbine for the cylinder of steam turbine
CN112228169A (en) Split assembling method for high-pressure outer cylinder of nuclear turbine
CN216899748U (en) Precooler for chemical high-temperature water vapor sampling
CN221592007U (en) Wall end plugging device is worn to gas pipeline
CN203096234U (en) Anti-explosion device for vacuum pipeline of silicon carbide single crystal furnace
CN206185777U (en) A removal tool for turbo generator set vapor seal piece
CN212869329U (en) Disc type thermal power steam trap with thermal insulation cap
CN218523031U (en) Sealing device for platinum resistance thermometer of sulfur burning furnace
CN205175566U (en) High pressure resistant thermocouple with online flexible function
CN215218867U (en) Boiler thermal state primary wind speed test hole measuring device with sealing and blowing functions
CN214699171U (en) Sleeve sealing device used between steam turbine regulating valve and air cylinder

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190917