CN110241851A - A kind of prefabricated tube coupling pressing device of pipe gallery - Google Patents

A kind of prefabricated tube coupling pressing device of pipe gallery Download PDF

Info

Publication number
CN110241851A
CN110241851A CN201910470357.9A CN201910470357A CN110241851A CN 110241851 A CN110241851 A CN 110241851A CN 201910470357 A CN201910470357 A CN 201910470357A CN 110241851 A CN110241851 A CN 110241851A
Authority
CN
China
Prior art keywords
tube coupling
pressing plate
prefabricated tube
swing arm
pipe gallery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910470357.9A
Other languages
Chinese (zh)
Other versions
CN110241851B (en
Inventor
邬毛志
颜龙
于恩亚
谢昭宇
张华军
许开军
张敏
张菊
李涛
朱神海
胡港
潘阳航
王林
黄佳
刘金风
容文娟
王媛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Jianke International Engineering Co Ltd
Original Assignee
Hubei Jianke International Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Jianke International Engineering Co Ltd filed Critical Hubei Jianke International Engineering Co Ltd
Priority to CN201910470357.9A priority Critical patent/CN110241851B/en
Publication of CN110241851A publication Critical patent/CN110241851A/en
Application granted granted Critical
Publication of CN110241851B publication Critical patent/CN110241851B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Quick-Acting Or Multi-Walled Pipe Joints (AREA)
  • Joints With Sleeves (AREA)

Abstract

The present invention relates to pipe gallery technical field of construction, a kind of prefabricated tube coupling pressing device of pipe gallery is provided, it include: pressing plate and for controlling the pressing plate along the pressure exerting arrangement of prefabricated pipe section axial pressure to be installed, the pressure exerting arrangement includes pedestal and the mechanical arm configuration that is mounted on the pedestal, the pressing plate is mounted on the free end of the mechanical arm configuration, is provided with pressure detecting part on the pressing plate.The prefabricated tube coupling pressing device of pipe gallery provided by the invention, pass through the position of mechanical arm structural adjustment pressing plate, and pressing plate is contacted with the end center of prefabricated tube coupling to be installed, it controls mechanical arm configuration and carries out axial pressure, in the compaction process of prefabricated tube coupling, the influence of human factor is eliminated using Fully-mechanized construct to greatest extent, ensure that the stabilization of construction quality;Pressure monitor is carried out by pressure detecting part, guarantees that parameters of the prefabricated pipe internode in installation connection procedure can reach design requirement.

Description

A kind of prefabricated tube coupling pressing device of pipe gallery
Technical field
The present invention relates to pipe gallery technical field of construction, compress more particularly, to a kind of prefabricated tube coupling of pipe gallery Device.
Background technique
Pipe gallery is exactly the comprehensive corridor of underground urban duct, i.e., builds a tunnel space in Urban Underground, by electric power, Communication, the various utilities pipelines such as combustion gas, heat supply, plumbing are integrated in one, and are equipped with special access hole, hoisting port and monitoring system System implements unified planning, Uniting, unified construction and management, is the important infrastructure and " life for ensureing city operations Line ".Therefore, the waterproof sealing of tube coupling is most important in pipe gallery.
Wherein, sealing waterproof includes the assembled constructional waterproofing of the self waterproofing and prefabricated tube coupling of prefabricated tube coupling, and prefabricated tube coupling is logical It crosses arrangement and forms overall structure, assembled constructional waterproofing system is extremely important for overall structure between contiguous prefabricated tube coupling, Other than the structure to prefabricated tube coupling optimizes, the fitting of prefabricated pipe internode is also required to be tightly formed good waterproof effect, Avoid leak, infiltration phenomenon occur between structural elements.
In existing construction method, after prefabricated tube coupling is placed to designated position, by manually directly tightening 2-section pipe internode Connection bolt carry out the compression and connection of tube coupling, this mode is affected by human factors larger, and compaction degree between tube coupling is difficult To reach design requirement, it is easy to cause leak at joints of segment.
Summary of the invention
(1) technical problems to be solved
The embodiment of the present invention provides a kind of prefabricated tube coupling pressing device of pipe gallery, to solve existing prefabricated tube coupling in internode The problem of being directly connected with when assembled and being easy to appear leak.
(2) technical solution
In order to solve the above-mentioned technical problem, the embodiment of the present invention provides a kind of prefabricated tube coupling pressing device of pipe gallery, packet Include: pressing plate and for controlling the pressing plate along the pressure exerting arrangement of prefabricated pipe section axial pressure to be installed, the pressure exerting arrangement includes Pedestal and the mechanical arm configuration being mounted on the pedestal, the pressing plate is mounted on the free end of the mechanical arm configuration, described Pressure detecting part is provided on pressing plate.
Further, the mechanical arm configuration is two groups, the arrangement of mechanical arm parallelism structural described in two groups, machinery described in two groups The free end of arm configuration is connect with the pressing plate.
Further, the mechanical arm configuration includes: the first swing arm and the second swing arm, first swing arm and the pedestal Hingedly, second swing arm and first swing arm are hinged, and the pressing plate and second swing arm are hinged;
The first turgor cylinder is provided between first swing arm and the pedestal, second swing arm is dynamic with described first It is provided with the second turgor cylinder between arm, is provided with third turgor cylinder between second swing arm and the pressing plate.
Further, locating slot or positioning sleeve are provided on the pressing plate, the diameter of the locating slot or positioning sleeve is greater than The diameter of the prefabricated tube coupling to be installed, the pressure detecting part are located in the locating slot or positioning sleeve.
Further, the angle between first swing arm and the pedestal is acute angle, second swing arm and described the One swing arm is in inverted V type structure, and second turgor cylinder is arranged in horizontal direction.
Further, control first turgor cylinder, the second turgor cylinder and third turgor cylinder make the pressing plate with The end center of the prefabricated tube coupling to be installed contacts, and shrinking second turgor cylinder makes the pressing plate to described to be installed pre- Tubulation section pressure.
Further, the side of the pedestal is provided with fixed ring, and the fixed ring is located on the pedestal far from described The side of mechanical arm configuration.
Further, the fixed ring is multiple, and multiple fixed rings are equidistantly spaced from horizontal direction.
Further, horizon detector is provided at the top of the pressing plate.
(3) beneficial effect
The prefabricated tube coupling pressing device of pipe gallery provided in an embodiment of the present invention, passes through the position of mechanical arm structural adjustment pressing plate It sets, and pressing plate is contacted with the end center of prefabricated tube coupling to be installed, control mechanical arm configuration and carry out axial pressure, in prefabricated pipe In the compaction process of section, the influence of human factor is eliminated using Fully-mechanized construct to greatest extent, ensure that construction quality Stablize;Pressure monitor is carried out by pressure detecting part, guarantees that parameters of the prefabricated pipe internode in installation connection procedure are equal Design requirement can be reached.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is the present invention Some embodiments for those of ordinary skill in the art without creative efforts, can also basis These attached drawings obtain other attached drawings.
Fig. 1 is the structural schematic diagram of the prefabricated tube coupling pressing device of pipe gallery of the embodiment of the present invention;
Fig. 2 is the top view of the prefabricated tube coupling pressing device of pipe gallery of the embodiment of the present invention;
In figure: 1, pedestal;2, control room;3, fixed ring;4, the first turgor cylinder;5, the second turgor cylinder;6, third rises Locking oil cylinder;7, the first swing arm;8, the second swing arm;9, pressing plate;10, pressure detecting part.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art Every other embodiment obtained without creative efforts, shall fall within the protection scope of the present invention.
In the description of the embodiment of the present invention, it should be noted that unless otherwise clearly defined and limited, term " peace Dress ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integrally Connection;It can be mechanical connection, be also possible to be electrically connected;Can be directly connected, can also indirectly connected through an intermediary, It can be the connection inside two elements.For the ordinary skill in the art, above-mentioned art can be understood with concrete condition The concrete meaning of language in the present invention.
As depicted in figs. 1 and 2, the embodiment of the present invention provides a kind of prefabricated tube coupling pressing device of pipe gallery, comprising: pressing plate 9 and pressure exerting arrangement, pressure exerting arrangement is for controlling pressing plate along the axial pressure of prefabricated tube coupling to be installed.In specific operation process, need Prefabricated tube coupling to be installed is subjected to installation connection with fixed prefabricated tube coupling has been installed, and when installing connection to be installed Prefabricated tube coupling applies preset pressure value, to guarantee the leakproofness connected between tube coupling.Pressure exerting arrangement can be various structures shape Formula, as long as can be realized the axial pressure of prefabricated tube coupling to be installed.
In order to realize flexible pressure, the pressure exerting arrangement in the embodiment of the present invention is using mechanical arm configuration, the pressure exerting arrangement Specifically include: pedestal 1 and mechanical arm configuration, the installation end of mechanical arm configuration are connected to 1 upper end of pedestal, and pressing plate 9 is fixedly mounted on The free end of mechanical arm configuration is at work adjusted pressing plate 9 into the end of prefabricated tube coupling to be installed by mechanical arm configuration Heart position.Pedestal 1 is mainly used for controlling the stability of whole device in course of exerting pressure, generally uses solid metal sheet material Material is made.
In order to accurately monitor the axial compressive force of prefabricated tube coupling to be installed, it is provided with pressure detecting part 10 on pressing plate 9, presses Whether power detection part 10 can reach preset requirement by eye-observation, can also be carried out corresponding by presetting target value Warning reminding.
The prefabricated tube coupling pressing device of pipe gallery provided by the above embodiment, passes through the position of mechanical arm structural adjustment pressing plate It sets, and pressing plate is contacted with the end center of prefabricated tube coupling to be installed, control mechanical arm configuration and carry out axial pressure, in prefabricated pipe In the compaction process of section, the influence of human factor is eliminated using Fully-mechanized construct to greatest extent, ensure that construction quality Stablize;Pressure monitor is carried out by pressure detecting part, guarantees that parameters of the prefabricated pipe internode in installation connection procedure are equal Design requirement can be reached.
On the basis of the above embodiments, in order to keep entire pressure exerting arrangement more stable, mechanical arm configuration can be two groups, Two groups of mechanical arm parallelism structural arrangements, the free end of two groups of machinery arm configurations is connect with pressing plate 9, and pressing plate 9 is protected always Water holding is put down or vertical state.
On the basis of the above embodiments, mechanical arm configuration uses secondary structure, to adapt to the peace of different prefabricated tube couplings Dress demand needs the position of corresponding adjustment pressing plate 9 for example, the pre-buried depth or length for prefabricated tube coupling change.Mechanical arm Structure specifically includes: the first swing arm 7 and the second swing arm 8, and the first swing arm 7 and pedestal 1 are hinged, and the second swing arm 8 and the first swing arm 7 are cut with scissors It connects, pressing plate 9 and the second swing arm 8 are hinged.
Meanwhile in order to realize the motion control between each component, set on the inside of the angle between the first swing arm 7 and pedestal 1 It is equipped with the first turgor cylinder 4, for controlling the angle of the first swing arm 7;In angle between the second swing arm 8 and the first swing arm 7 Side is provided with the second turgor cylinder 5, for controlling the angle between the second swing arm and the first swing arm 7;Second swing arm 8 and pressing plate 9 Between be provided with third turgor cylinder 6, for control the angle between pressing plate 9 and the second swing arm 8 (i.e. control pressing plate 9 side To).
Specifically, the angle between the first swing arm 7 and pedestal 1 is acute angle, and the second swing arm 8 and the first swing arm 7 are in inverted V type knot Structure, the second turgor cylinder 5 are arranged in horizontal direction.Pass through the first turgor cylinder 4 of control, the second turgor cylinder 5 and third tensioner Oil cylinder 6 adjusts the position of pressing plate 9, contacts pressing plate 9 and the end center of prefabricated tube coupling to be installed.Then risen by shrinking second Locking oil cylinder 5 makes pressing plate 9 press the axial direction of prefabricated pipe section to be installed.
Wherein, each turgor cylinder uses hydraulic control, and bearing capacity is larger, and can adapt to moist complicated in pipe gallery Working environment.It should be noted that when applying axial compressive force along prefabricated tube coupling to be installed, mainly pass through horizontally disposed the The contractions of two turgor cylinders 5 is realized.
It is above-mentioned respectively apply example on the basis of, for convenience to prefabricated pipe section to be installed apply axial compressive force, can also press The diameter of side (side towards prefabricated tube coupling) the setting locating slot or positioning sleeve of plate 9, locating slot or positioning sleeve be slightly larger than to The diameter of prefabricated tube coupling is installed, to guarantee that prefabricated tube coupling to be installed can just be inserted in locating slot or positioning sleeve and not generate dry Relating to is advisable.
It is above-mentioned respectively apply example on the basis of, be additionally provided with control room 2 on pedestal 1, be provided in control room 2 for controlling machine The console of tool arm configuration, by the operation bench in control room 2, i.e., the flexible motion of controllable mechanical arm structure, thus convenient Adjust the position of pressing plate 9.Further, since the complex environment of underground pipe gallery, control room 2 can play protection behaviour to a certain extent Make the effect of personnel's personal safety.
Further, digital pressure gauge specifically can be used in pressure detecting part 10, while setting and number on console The connected pressure alarm of pressure gauge and display indicator light, design pressure value can be preset in digital pressure gauge, when pressure reaches When design pressure value, display indicator light is for showing that digital pressure gauge whether in preset range of pressure values, shows indicator light Lighting can be installed, thus the installation effectiveness between improving tube coupling;When pressure is more than design pressure value a certain range, pressure Alarm equipment alarm, the alarming value general control of pressure alarm is 5% or so of design pressure value.
It is above-mentioned respectively apply example on the basis of, the side of pedestal 1 is provided with fixed ring 3, and fixed ring 3 can pass through pre-buried fixation Part is fixed, and mainly serves for ensuring the stability of pedestal.Fixed ring 3 is particularly located at one far from machinery arm configuration on pedestal 1 Side, to prevent device caused by the centre-of gravity shift of pedestal from turning on one's side.In order to reinforce the fixation to pedestal 1, fixed ring 3 may be configured as more A, multiple fixing pipes 3 are equidistantly spaced from horizontal direction in the side of pedestal 1.
It is above-mentioned respectively apply example on the basis of, in order to guarantee the levelness of pressing plate 9, the top of pressing plate 3 is provided with horizontal inspection Instrument is surveyed, horizon detector can be bonded on pressing plate 3 with bracket, and bubble detector or infrared water specifically can be used in horizon detector Flat detector.
Specific use process is as follows for pressing device in above-described embodiment: (1) it is by fixed ring 3 pedestal 1 is fixed, guarantee During compressing prefabricated tube coupling, pedestal 1 will not be moved;(2) prefabricated tube coupling to be installed is placed on installation site;(3) Each turgor cylinder is operated in control room 2, so that the inside of pressing plate 9 is contacted with the end center of prefabricated tube coupling;(4) operation is respectively risen Locking oil cylinder observes the reading of pressure detecting part or checks display indicator light to increase pressing plate 9 for the pressure of prefabricated tube coupling Whether light;(5) axial compressive force of tube coupling to be installed reaches design value, and installation tube coupling connection bolt is finally fixed.
Finally, it should be noted that the above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although Present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: it still may be used To modify the technical solutions described in the foregoing embodiments or equivalent replacement of some of the technical features; And these are modified or replaceed, technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution spirit and Range.

Claims (9)

1. a kind of prefabricated tube coupling pressing device of pipe gallery characterized by comprising pressing plate and for control the pressing plate along to The pressure exerting arrangement of prefabricated pipe section axial pressure is installed, the pressure exerting arrangement includes pedestal and the mechanical arm that is mounted on the pedestal Structure, the pressing plate are mounted on the free end of the mechanical arm configuration, are provided with pressure detecting part on the pressing plate.
2. the prefabricated tube coupling pressing device of pipe gallery according to claim 1, which is characterized in that it is described machinery arm configuration be Two groups, the arrangement of mechanical arm parallelism structural described in two groups, the free end of machinery arm configuration described in two groups is connect with the pressing plate.
3. the prefabricated tube coupling pressing device of pipe gallery according to claim 1 or 2, which is characterized in that the mechanical arm knot Structure includes: the first swing arm and the second swing arm, and first swing arm and the pedestal are hinged, and second swing arm is dynamic with described first Arm is hinged, and the pressing plate and second swing arm are hinged;
Be provided with the first turgor cylinder between first swing arm and the pedestal, second swing arm and first swing arm it Between be provided with the second turgor cylinder, be provided with third turgor cylinder between second swing arm and the pressing plate.
4. the prefabricated tube coupling pressing device of pipe gallery according to claim 1 or 2, which is characterized in that set on the pressing plate It is equipped with locating slot or positioning sleeve, the diameter of the locating slot or positioning sleeve is greater than the diameter of the prefabricated tube coupling to be installed, described Pressure detecting part is located in the locating slot or positioning sleeve.
5. the prefabricated tube coupling pressing device of pipe gallery according to claim 3, which is characterized in that first swing arm and institute Stating the angle between pedestal is acute angle, and second swing arm and first swing arm are in inverted V type structure, second turgor cylinder It is arranged in horizontal direction.
6. the prefabricated tube coupling pressing device of pipe gallery according to claim 5, which is characterized in that control first tensioner Oil cylinder, the second turgor cylinder and third turgor cylinder contact the pressing plate and the end center of the prefabricated tube coupling to be installed, Shrinking second turgor cylinder makes the pressing plate press the prefabricated tube coupling to be installed.
7. the prefabricated tube coupling pressing device of pipe gallery according to claim 1 or 2, which is characterized in that the side of the pedestal While being provided with fixed ring, the fixed ring is located at the side far from the mechanical arm configuration on the pedestal.
8. the prefabricated tube coupling pressing device of pipe gallery according to claim 7, which is characterized in that the fixed ring is more A, multiple fixed rings are equidistantly spaced from horizontal direction.
9. the prefabricated tube coupling pressing device of pipe gallery according to claim 1 or 2, which is characterized in that at the top of the pressing plate It is provided with horizon detector.
CN201910470357.9A 2019-05-31 2019-05-31 Prefabricated tube coupling closing device of utility tunnel Active CN110241851B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910470357.9A CN110241851B (en) 2019-05-31 2019-05-31 Prefabricated tube coupling closing device of utility tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910470357.9A CN110241851B (en) 2019-05-31 2019-05-31 Prefabricated tube coupling closing device of utility tunnel

Publications (2)

Publication Number Publication Date
CN110241851A true CN110241851A (en) 2019-09-17
CN110241851B CN110241851B (en) 2021-08-17

Family

ID=67885687

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910470357.9A Active CN110241851B (en) 2019-05-31 2019-05-31 Prefabricated tube coupling closing device of utility tunnel

Country Status (1)

Country Link
CN (1) CN110241851B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09112196A (en) * 1995-10-17 1997-04-28 Kawasaki Heavy Ind Ltd Operating method and equipment for articulated type erector
CN202202876U (en) * 2011-07-23 2012-04-25 上海市第二市政工程有限公司 Special machine for construction of mid-partition wall in tunnel
CN106677811A (en) * 2016-07-08 2017-05-17 山东大学 Tunnel automatic construction equipment and construction method
CN206529227U (en) * 2016-12-05 2017-09-29 由继军 Rubber-tyred lifting magnet crane
CN108167001A (en) * 2018-01-23 2018-06-15 上海隧道工程有限公司 For the prefabricated stand column assembling machine of double layer tunnel internal structure construction
CN208136981U (en) * 2018-04-18 2018-11-23 中电建水环境治理技术有限公司 Excavator with full wind-up

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09112196A (en) * 1995-10-17 1997-04-28 Kawasaki Heavy Ind Ltd Operating method and equipment for articulated type erector
CN202202876U (en) * 2011-07-23 2012-04-25 上海市第二市政工程有限公司 Special machine for construction of mid-partition wall in tunnel
CN106677811A (en) * 2016-07-08 2017-05-17 山东大学 Tunnel automatic construction equipment and construction method
CN206529227U (en) * 2016-12-05 2017-09-29 由继军 Rubber-tyred lifting magnet crane
CN108167001A (en) * 2018-01-23 2018-06-15 上海隧道工程有限公司 For the prefabricated stand column assembling machine of double layer tunnel internal structure construction
CN208136981U (en) * 2018-04-18 2018-11-23 中电建水环境治理技术有限公司 Excavator with full wind-up

Also Published As

Publication number Publication date
CN110241851B (en) 2021-08-17

Similar Documents

Publication Publication Date Title
CN104075854A (en) Shield segment joint anti-penetrability performance test device
CN110486792B (en) GPRS network-based heat supply network remote monitoring management system and method
CN110004963A (en) Well sinking overall process correction prevention alarm system and well sinking are rectified a deviation method
CN208441842U (en) A kind of shield launching counter-force support system
CN204212184U (en) The full-automatic inclination measurement system of bracing of foundation pit wall
CN110241851A (en) A kind of prefabricated tube coupling pressing device of pipe gallery
KR101836450B1 (en) Water leak sensing system of double watertight pipe
CN106840063A (en) Underwater concrete engineering expansion joint on-Line Monitor Device based on displacement transducer
KR101895441B1 (en) Water leak sensing system of double watertight pipe
CN212361264U (en) Pipeline presses robot to put in device in area
CN112431284A (en) Water conservancy construction land used pipe laying protector
CN109538854B (en) Automatic alarming equipotential bridging device for flange leakage
CN218409570U (en) Monitoring device for monitoring natural gas pipeline
CN214579523U (en) Flange for chemical pipeline
CN208280188U (en) Waterstop posting
CN215488182U (en) Water supply and drainage pipeline connecting structure for real estate building
CN215178592U (en) Floating seal ring simulated running-in device
CN210468655U (en) Pre-buried positioning sleeve for electrical installation construction
JP3239494U (en) Compensation amount indicating device for rotation compensator of long-distance industrial steam pipeline
CN210562337U (en) Deep foundation pit engineering construction and monitoring simulation test device
CN209012186U (en) A kind of pressure protected type meter connector and hydraulic system
CN112032471A (en) Pipeline presses robot to put in device in area
CN207315784U (en) Hydraulic pressure cylinder assembly and excavator
CN218972021U (en) Waterproof sleeve with self-checking function
CN221425885U (en) Pressurized pipeline leakage detection test box

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant