CN110227241A CN201910348390.4A CN201910348390A CN110227241A CN 110227241 A CN110227241 A CN 110227241A CN 201910348390 A CN201910348390 A CN 201910348390A CN 110227241 A CN110227241 A CN 110227241A
Authority
CN
China
Prior art keywords
climbing
arc block
rod set
block
component
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910348390.4A
Other languages
Chinese (zh)
Inventor
王清国
王小鸽
王杨玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910348390.4A priority Critical patent/CN110227241A/en
Publication of CN110227241A publication Critical patent/CN110227241A/en
Pending legal-status Critical Current

Links

Classifications

    • AHUMAN NECESSITIES
    • A63SPORTS; GAMES; AMUSEMENTS
    • A63BAPPARATUS FOR PHYSICAL TRAINING, GYMNASTICS, SWIMMING, CLIMBING, OR FENCING; BALL GAMES; TRAINING EQUIPMENT
    • A63B27/00Apparatus for climbing poles, trees, or the like
    • A63B27/04Climbing devices for profile poles attachable to the feet

Landscapes

  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Physical Education & Sports Medicine (AREA)
  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

Electric power facility maintenance electric pole climbing tool.A kind of electric power facility maintenance electric pole climbing tool, including rod set frame, it is arranged component, multiple climbing components;The component that is arranged includes the first arc block, the second arc block and third arc block;First arc block, the second arc block and the third arc block is separately positioned on the bottom surface of rod set frame, and the tail end of the first arc block and the head end of the second arc block are hinged;The tail end of second arc block and the head end of third arc block are hinged;The tail end of third arc block is matched with the head end of the first arc block and is fixed;The inner ring of three pieces of arc blocks is connected to form annulus.The beneficial effects of the present invention are: adapting to the electric pole of different bar diameters, mitigate service personnel's operating pressure, promotes overhaul efficiency.

Description

A kind of electric power facility maintenance electric pole climbing tool
Technical field
The present invention relates to electric power facility maintenance field more particularly to a kind of electric power facility maintenance electric pole climbing tools.
Background technique
Electric pole be it is a kind of power supply, communicate important infrastructure, application is very extensive.Electric power is transmitted in daily life Majority be all to need power transmission line to complete, general power transmission line needs to complete to be delivered to use by the erection of electric pole Family, but power transmission line is frequently necessary to overhaul, at this moment service personnel needs to climb up electric pole completion service work, but this is climbed It is to use in previous most of maintenance process axis in the process if can have hidden danger to the safety of service personnel without good tool Pedal is climbed to the top of electric pole, but it is foot-operated to need service personnel oneself to move, and the movement that this is moved is time-consuming and laborious, together When need the spiritual high concentration of service personnel.
A kind of existing wire pole climbing tool transmission line of electricity as disclosed in the patent of Publication No. CN108853956A Maintenance concrete wire pole climbing tool, passes through the first wheel carrier, the second wheel carrier, drive wheel assemblies, footrest component and Lun Sha mechanism Between the work climbed automatically with concrete wire pole of the power transmission lines overhauling for cooperating with each other completion, pass through controller first On button control driving assembly by left climbing device and right climbing device assembled wire bar, then service personnel stands in two feet It steps on component and buckles well safety buckle rope, at this moment open the power switch of control drive wheel assemblies, service personnel needs one Foot applies pressure, another foot gently lifts, and the climbing device contact-making switch for the underfooting lifted will not be withstood driving by footrest component Wheel assembly will drive climbing device rising, and when certain altitude of rising will apply pressure on foot, another foot lifts, to complete to climb Work is climbed, also sets up power cut-out switch on controller, mechanism can lock driven wheel assembly when dump hour wheel brake, maintenance When personnel reach the top of electric pole, first thing needs to cut off the power supply of two climbing devices, needs when service personnel completes work First motor is arranged to invert by controller when getting off, then is moved down by above-mentioned same step, maintenance is reduced The labor intensity of personnel.Deficiency existing for existing wire pole climbing tool be it is inconvenient for operation, will by the extruding of brute spring Service personnel is fixed to be difficult to ensure by climbing stability on utility poles, and not for the electric pole adaptability of different bar diameters It is good.
Summary of the invention
The purpose of the present invention is: in view of the deficienciess of the prior art, providing carries out rod set frame just by being arranged component Step is arranged, and is preferably arranged effect convenient for playing while operation;While promoting climbing stability by three climbing components Improve overhaul efficiency;Mitigate service personnel's operating pressure, increase safety and promotes a kind of electric power facility inspection of overhaul efficiency It repairs with electric pole climbing tool and its climbing method.
For the purpose of the present invention, it is achieved using following technical scheme:
A kind of electric power facility maintenance electric pole climbing tool, including rod set frame, it is arranged component, multiple climbing components;Described Being arranged component includes the first arc block, the second arc block and third arc block;First arc block, the second arc block and Three arc blocks are separately positioned on the bottom surface of rod set frame, and the tail end of the first arc block and the head end of the second arc block are hinged;Second The tail end of arc block and the head end of third arc block are hinged;The tail end of third arc block matched with the head end of the first arc block into Row is fixed;The inner ring of three pieces of arc blocks is connected to form annulus;The side wall of rod set frame is circumferentially arranged in multiple climbing components On;Each climbing component includes climbing fixed link, climbing cylinder, belt-driven component;The two of the climbing fixed link End is fixedly connected with the bottom plate of the top plate of rod set frame and rod set frame respectively;Shifting chute is provided in the middle part of climbing fixed link;Described Movable block is provided on shifting chute;The two sides of the movable block are connected with hinge bar;Movable block and the climbing cylinder Moving portion connection;The fixed part for climbing cylinder is arranged by cylinder fixed block in climbing fixed link lower inside;The transmission Band driving assembly includes the first transmission band plate, the second transmission band plate, driving wheel, driven wheel, conveyer belt;First conveyer belt The two sides that plate and the second transmission band plate pass through two hinge bars and movable block respectively connect;The lower part of first transmission band plate It is connected with the lower part of the second transmission band plate by driving wheel;Driving motor is connected on the driving wheel;First transmission band plate Top connected with the top of the second transmission band plate by driven wheel, the conveyer belt is tensioned and is connected to driving wheel and driven wheel On.Lifting climbing is carried out on utility poles by the climbing device, mitigates service personnel's operating pressure, increases safety and is mentioned Rise overhaul efficiency.
Preferably, the rod set frame includes left pole-half stock and right panel rod set frame;The left pole-half stock and the right side The rod set frame that plate stem stock is composed of a fixed connection by fixed pin in hollow round tubular;The first support is provided on left pole-half stock Frame and the second support frame;First support frame and the second support frame be respectively provided at left pole-half stock middle front side and in after Side;And first support frame and the second support frame include two support risers and branch between two support risers are arranged in Duo Gen Support transverse slat;Third support frame is provided on the right panel rod set frame;The middle part of right panel rod set frame, institute is arranged in third support frame The third support frame stated includes that two support level plates supported between vertical plate are arranged in two support vertical plates and Duo Gen.It is logical Left pole-half stock and right panel rod set frame are crossed convenient for being tentatively arranged on utility poles, increases structural strength by multiple support frames.
Preferably, the head end of first arc block is hingedly provided with fixed link;It is arranged in the fixed link Coordinating block hemispherical;The tail end of the third arc block is provided with the mating groove to match with coordinating block, and described matches It closes block and mating groove is fixed by fixture nut;The tail end of third arc block is additionally provided with the fixed link entered for fixed link Slot, the fixed bar groove are communicated with mating groove.Carry out Primary Location is matched with third arc block by the first arc block, just In operation.
Preferably, the top surface of the left pole-half stock and right panel rod set frame is separately provided for preventing top from shaking The first Circular Plate;The bottom surface of left pole-half stock and right panel rod set frame is separately provided for the second annulus for preventing top from shaking Plate;The component that is arranged is arranged on the bottom surface of two piece of second Circular Plate.The left pole-half stock and right panel rod set frame Top is respectively arranged with the first curved baffle and the second curved baffle;First curved baffle and the second curved baffle is symmetrical Setting.Further prevent the phenomenon that occurring shaking in moving process or falling.Further protect electric pole and and electric pole Preferably cooperation.
Preferably, the climbing component count is 3, the angle between arbitrary neighborhood two climbing components is 120°.The stability of climbing is further increased, climbing efficiency is promoted.
Preferably, the lower part of the first transmission band plate and the second transmission band plate and the top two sides of climbing fixed link It is connected with the first rotating bar;The top of the first transmission band plate and the second transmission band plate and the top two of climbing fixed link Side is connected with the second rotating bar.Bonding strength is further increased, transfer tape assemble easy to remove promotes climbing efficiency.
Preferably, being provided on the inside of the first transmission band plate and the second transmission band plate multiple regularly arranged Assist guide wheel;Preferably, being provided with multiple climbing cross bars convenient for climbing on the conveyer belt.Advanced optimize climbing matter Amount promotes climbing efficiency.
Preferably, the third support frame is identical as the shape of the first support frame, and the length of support level plate is big In support transverse slat.
Preferably, being provided with connecting spring in the middle part of the hinge bar.Convenient for being preferably elastically engaged.
The electric power facility maintenance application method of electric pole climbing tool, passes sequentially through following steps:
(1) it is tentatively arranged: set being opened by the left pole-half stock of rod set frame and one end of right panel rod set frame and is set to the outer of electric pole On circle, tentatively it is arranged by the three pieces of arc blocks cooperation being arranged in component;
(2) bar diameter matches: driving movable block mobile to drive belt-driven component to clamp by climbing cylinder, makes to transmit It is bonded with the conveyer belt in driving assembly with the outer ring of electric pole;
(3) climbing maintenance: conveyer belt rotation is driven by the belt-driven component in climbing component, makes whole device in electricity Climbing maintenance up and down is carried out in line bar;Electric power facility maintenance is for example above-mentioned with electric pole climbing tool.
Compared with prior art, electric power facility maintenance of the present invention is to pass through bar with the beneficial effect of electric pole climbing tool Three support frames in stock further increase bonding strength and supportive, and convenient for preferably three climbing components of setting; It is played by the mutual cooperation between the first arc block being arranged in component and third arc block and is preferably tentatively arranged effect, Cooperated by hemispherical coordinating block in the first arc block and mating groove further increase firmness between the two and Stability;Component is climbed by three and increases the stability of structure in the bikini distribution of equilateral triangle, and passes through conveyer belt The electric pole that driving assembly adapts to different bar diameters promotes climbing efficiency and overhaul efficiency while increasing the scope of application.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention.
Fig. 2 is the structural schematic diagram for being arranged component.
Fig. 3 is the structural schematic diagram for climbing component.
The label in accompanying drawing is: rod set frame 1, fixed pin 101, left pole-half stock 11, the first support frame 111, second support 112, two support risers 1121 of frame, support transverse slat 1122, third support frame 113, support vertical plate 1131, support level plate 1132, right panel rod set frame 12, the first curved baffle 13, the second curved baffle 14, the first Circular Plate 15, the second Circular Plate 16, set If component 2, the first arc block 21, fixed link 211, coordinating block 212, the second arc block 22, third arc block 23, mating groove 231, Fixed bar groove 232, multiple climbing components 3, climbing fixed link 31, shifting chute 311, movable block 312, hinge bar 313, connecting spring 3131, cylinder 32, cylinder fixed block 321, belt-driven component 33, first are climbed and transmits the transmission band plate of band plate 331, second 332, driving wheel 333, driving motor 3331, driven wheel 334, conveyer belt 335, climbing cross bar 3351, the first rotating bar 34, second Rotating bar 35, auxiliary guide wheel 36.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.
In the description of the present invention, it is to be understood that, term " on ", "lower", "front", "rear", "left", "right", "top", The orientation or positional relationship of the instructions such as "bottom", "inner", "outside" is to be merely for convenience of describing based on attached drawing orientation or positional relationship The present invention and simplified description, rather than the device or element of indication or suggestion meaning must have a particular orientation, with specific Orientation construction and operation, therefore be not considered as limiting the invention.
As shown in Figure 1, a kind of electric power facility maintenance electric pole climbing tool, including rod set frame 1, it is arranged component 2, three Climb component 3;Rod set frame 1 includes left pole-half stock 11 and right panel rod set frame 12;Left pole-half stock 11 and right panel rod set frame 12 are logical Cross the rod set frame 1 that fixed pin 101 is composed of a fixed connection in hollow round tubular;The first support frame is provided on left pole-half stock 11 111 and second support frame 112;First support frame 111 and the second support frame 112 be respectively provided at left pole-half stock 11 middle front side and Middle rear side;And first support frame 111 and the second support frame 112 include two support risers 1121 and Duo Gen setting in two branch Support the support transverse slat 1122 between riser 1121.Supportive is further strengthened by the first support frame 111 and the second support frame 112 And increase bonding strength.Third support frame 113 is provided on right panel rod set frame 12;Third support frame 113 is arranged in right panel bar The middle part of stock 12, third support frame 113 include that two support vertical plates 1131 and Duo Gen are arranged in two support vertical plates Support level plate 1141 between 1131 enhances bonding strength by third support frame 113, while preferably supporting with first Frame 111 and the second support frame 112 match, and three climbing components 3 are arranged preferably between every two support frame.Third branch Support 113 is identical as the shape of the first support frame 111, and the length of support level plate 1141 is greater than support transverse slat 1122, into one Step makes three climbing components 3 are regularly arranged to be arranged between every two support frame.Left pole-half stock 11 and right panel rod set frame 12 Top surface is separately provided for the first Circular Plate 15 for preventing top from shaking, the top and bottom of left pole-half stock 11 and right panel bar The second Circular Plate 16 that the top and bottom of stock 12 are separately provided for preventing top from shaking, so further preferably with Electric pole matches, and increases and be adjacent to effect.The top of left pole-half stock 11 and right panel rod set frame 12 is respectively arranged with first Curved baffle 13 and the second curved baffle 14;First curved baffle 13 and the second curved baffle 14 are symmetrical arranged, and are further protected The effect of electric pole and preferably cooperate with electric pole.It is arranged component 2 to be arranged on the bottom surface of two piece of second Circular Plate 16, cover If component 2 is used to tentatively be arranged and be fitted in the outer ring of electric pole.The circumferential regularly arranged setting of three climbing components 3 is in bar On the side wall of stock 1, three climbing components 3 are any in three climbing components 3 for climbing the tool on utility poles Angle between two neighboring climbing component 3 is 120 °, further increases stability and supportive during climbing.
As depicted in figs. 1 and 2, being arranged component 2 includes the first arc block 21, the second arc block 22 and third arc block 23; First arc block 21, the second arc block 22 and third arc block 23 are separately positioned on the bottom surface of rod set frame 1, the first arc block 21 Head end be hingedly provided with fixed link 211;Coordinating block 212 hemispherical is arranged in fixed link 211;First arc block 21 Tail end and the head end of the second arc block 22 are hinged;The tail end of second arc block 22 and the head end of third arc block 23 are hinged;Third The tail end of arc block 23 is provided with the mating groove 231 to match with coordinating block 212, and coordinating block 212 and mating groove 231 pass through fixation Nut is fixed;The tail end of third arc block 23 be additionally provided with for fixed link enter fixed bar groove 232, fixed bar groove 232 with Mating groove 231 communicates, and the tail end of third arc block 23 is matched with the head end of the first arc block 21 and is fixed, and passes through coordinating block It cooperates between 212 and mating groove 231, convenient for being preferably fixed the first arc block 21 and third arc block 23, prevents It is only relatively rotated between two arc blocks, plays and be preferably tentatively arranged.The inner ring of three pieces of arc blocks is connected to form annulus, Preferably play the role of clamping tentatively being arranged by the cooperation of three pieces of arc blocks.
When work, by the hemispherical coordinating block 212 and third arc block 23 in 21 fixed link 211 of the first arc block Mating groove 231 cooperate, the first arc block 21 and 23 sets of third arc block are set on electric pole, make coordinating block 212 rotation Turn to be moved in mating groove 231, coordinating block 212 is fixed on by mating groove 231 by fixture nut, makes to be arranged the tentatively set of component 2 If on utility poles.
The component plays preferably preliminary set by the mutual cooperation between the first arc block 21 and third arc block 23 If effect, and firmness and stabilization between the two are further increased by coordinating block 212 and the mutual cooperation of mating groove 231 Property.
As shown in figures 1 and 3, each climbing component 3 includes climbing fixed link 31, climbing cylinder 32 and belt-driven Component 33;The both ends of climbing fixed link 31 are fixedly connected with the bottom plate of the top plate of rod set frame 1 and rod set frame 1 respectively;Climbing is fixed Shifting chute 311 is provided in the middle part of bar 31;Movable block 312 is provided on shifting chute 311;The two sides of movable block 312 are connected with hingedly Bar 313;Movable block 312 is connect with the moving portion of climbing cylinder 32;The fixed part of climbing cylinder 32 is set by cylinder fixed block 321 It sets in climbing 31 lower inside of fixed link, the position between climbing component 3 and electric pole is further adjusted by climbing cylinder 32, Conveniently adapt to the electric pole of different bar diameter sizes.Belt-driven component 33 includes that the first transmission band plate 331, second transmits band plate 332, driving wheel 333, driven wheel 334 and conveyer belt 335;First transmission band plate 331 and the second transmission band plate 332 pass through two respectively Root hinge bar 313 is connect with the two sides of movable block 312, drives 33 clamp or release of belt-driven component by movable block 312. The middle part of hinge bar 313 is provided with connecting spring 3131, convenient for being preferably elastically engaged and buffering effect, increases and uses Service life.The lower part of first transmission band plate 331 and the lower part of the second transmission band plate 332 are connected by driving wheel 333;Driving wheel 333 On be connected with driving motor 3331;The top of first transmission band plate 331 and the top of the second transmission band plate 332 pass through driven wheel 334 connections, the tensioning of conveyer belt 335 are connected on driving wheel 333 and driven wheel 334, drive conveyer belt by the rotation of conveyer belt 335 Dynamic component 33 is climbed on utility poles.Multiple climbing cross bars 3351 convenient for climbing are provided on conveyer belt 335, by climbing It climbs cross bar 3351 and further increases frictional force, convenient for more effectively being moved on utility poles.First transmission band plate 331 and the The lower part of two transmission band plates 332 and the top two sides of climbing fixed link 31 are connected with the first rotating bar 34;First transmission band plate 331 The second rotating bar 35 is connected with the top of the second transmission band plate 332 and the top two sides of climbing fixed link 31.Pass through first Rotating bar 34 and the second rotating bar 35 further increase bonding strength, convenient for being preferably convenient for the position of belt-driven component 33 It adjusts.Multiple regularly arranged auxiliary guide wheels 36 are provided on the inside of first transmission band plate 331 and the second transmission band plate 332, Promote the transmission effect of conveyer belt further by multiple auxiliary guide wheels 36 to further promote climbing effect.
When work, drives movable block 312 to move on shifting chute 311 by climbing cylinder 32, driven by movable block 312 The first transmission band plate 331 and the second transmission 332 clamp or release of band plate in belt-driven component 33, pass through driving motor 3331 drive driving wheel 333 to rotate, and are connected on driving wheel 333 and driven wheel 334 by the tensioning of conveyer belt 335, pass through driving Wheel 333 drives conveyer belt 335 to rotate, to make to climb the progress climbing motion of component 3.
The component drives 33 clamp or release of belt-driven component by climbing cylinder 32, adapts to the tool preferably The electric pole of different bar diameters, is climbed on utility poles convenient for belt-driven component 33;Pass through auxiliary guide wheel 36 and conveyer belt 335 On climbing cross bar 3351 further promoted climbing effect, prevented while increasing gearing tool be detached from electric pole;Pass through hinge The middle part of extension bar 313 is provided with connecting spring 3131, and further Promoting Layered Buffer effect increases while increasing structural strength and uses Service life.
The electric power facility maintenance application method of electric pole climbing tool, passes sequentially through following steps:
(4) it is tentatively arranged: set being opened by the left pole-half stock 11 of rod set frame 1 and one end of right panel rod set frame 12 and is set to electric wire On the outer ring of bar, tentatively it is arranged by the three pieces of arc blocks cooperation being arranged in component 2;
(5) bar diameter matches: drive movable block 312 mobile to drive belt-driven component 33 to clamp by climbing cylinder 32, It is bonded the conveyer belt 335 in belt-driven component 33 with the outer ring of electric pole;
(6) it climbing maintenance: drives conveyer belt 335 to rotate by the belt-driven component 33 in climbing component 3, makes entirely to fill It sets and carries out climbing maintenance up and down on utility poles.
In conclusion electric power facility maintenance is further by three support frames in rod set frame 1 with electric pole climbing tool Increase bonding strength and supportive, and convenient for preferably three climbing components of setting;Pass through the first arc being arranged in component 2 Mutual cooperation between block 21 and third arc block 23, which plays, is preferably tentatively arranged effect, by the first arc block 21 Hemispherical coordinating block 212 and the mutual cooperation of mating groove 231 further increase firmness and stability between the two;Pass through three A climbing component 3 increases the stability of structure in the bikini distribution of equilateral triangle, and suitable by belt-driven component 33 The electric pole of different bar diameters is answered to promote climbing efficiency and overhaul efficiency while increasing the scope of application.
The above are the descriptions to the embodiment of the present invention to keep this field special by the foregoing description of the disclosed embodiments Industry technical staff can be realized or using the present invention.Various modifications to these embodiments carry out those skilled in the art Saying will be apparent.The general principles defined herein can be the case where not departing from the spirit or scope of the present invention Under, it realizes in other embodiments.Therefore, the present invention is not intended to be limited to these implementation columns shown in this article, but to accord with Close the widest scope consistent with principles disclosed herein and novel point.

Claims (10)

1. a kind of electric power facility maintenance electric pole climbing tool, which is characterized in that including rod set frame (1), be arranged component (2), Multiple climbing components (3);Described be arranged component (2) include the first arc block (21), the second arc block (22) and third arc Block (23);First arc block (21), the second arc block (22) and the third arc block (23) is separately positioned on rod set frame (1) Bottom surface on, the tail end of the first arc block (21) and the head end of the second arc block (22) are hinged;The tail end of second arc block (22) It is hinged with the head end of third arc block (23);The tail end of third arc block (23) matched with the head end of the first arc block (21) into Row is fixed;The inner ring of three pieces of arc blocks is connected to form annulus;Multiple climbing components (3) are circumferentially arranged in rod set frame (1) Side wall on;Each climbing component (3) includes climbing fixed link (31), climbing cylinder (32), belt-driven component (33); The both ends of the climbing fixed link (31) are fixedly connected with the bottom plate of the top plate of rod set frame (1) and rod set frame (1) respectively;Climbing Shifting chute (311) are provided in the middle part of fixed link (31);Movable block (312) are provided on the shifting chute (311);The shifting The two sides of motion block (312) are connected with hinge bar (313);Movable block (312) is connect with the moving portion of the climbing cylinder (32); The fixed part for climbing cylinder (32) is arranged by cylinder fixed block (321) in climbing fixed link (31) lower inside;The biography Sending band driving assembly (33) includes the first transmission band plate (331), the second transmission band plate (332), driving wheel (333), driven wheel (334), conveyer belt (335);First transmission band plate (331) and the second transmission band plate (332) passes through described two respectively Root hinge bar (313) is connect with the two sides of movable block (312);The lower part of first transmission band plate (331) and the second transmission band plate (332) lower part is connected by driving wheel (333);Driving motor (3331) are connected on the driving wheel (333);First passes The top on the top and the second transmission band plate (332) of sending band plate (331) is connected by driven wheel (334), the conveyer belt (335) tensioning is connected on driving wheel (333) and driven wheel (334).
2. a kind of electric power facility maintenance electric pole climbing tool according to claim 1, which is characterized in that the bar Stock (1) includes left pole-half stock (11) and right panel rod set frame (12);The left pole-half stock (11) and right panel rod set frame (12) the rod set frame (1) being composed of a fixed connection by fixed pin (101) in hollow round tubular;Left pole-half stock is provided on (11) First support frame (111) and the second support frame (112);First support frame (111) and the second support frame (112) is set respectively Middle front side and middle rear side in left pole-half stock (11);And first support frame (111) and the second support frame (112) include two The support transverse slat (1122) for supporting riser (1121) and more settings to support between riser (1121) at two;The right panel bar Third support frame (113) are provided on stock (12);Third support frame (113) is arranged in the middle part of right panel rod set frame (12), institute The third support frame (113) stated include two support vertical plates (1131) and more be arranged two support vertical plates (1131) it Between support level plate (1132).
3. a kind of electric power facility maintenance electric pole climbing tool according to claim 1, which is characterized in that described the The head end of one arc block (21) is hingedly provided with fixed link (211);Hemispherical match is arranged in the fixed link (211) It closes block (212);The tail end of the third arc block (23) is provided with the mating groove (231) to match with coordinating block (212), institute The coordinating block (212) stated is fixed with mating groove (231) by fixture nut;The tail end of third arc block (23), which is additionally provided with, to be used for The fixed bar groove (232) that fixed link enters, the fixed bar groove (232) are communicated with mating groove (231).
4. a kind of electric power facility maintenance electric pole climbing tool according to claim 1, which is characterized in that the left side The top surface of half rod set frame (11) and right panel rod set frame (12) is separately provided for the first Circular Plate (15) for preventing top from shaking; The top and bottom of left pole-half stock (11) and the top and bottom of right panel rod set frame (12) are separately provided for preventing top The second Circular Plate (16) shaken;Described be arranged component (2) are arranged on the bottom surface of two piece of second Circular Plate (16);Described The first curved baffle (13) and the second curved baffle are respectively arranged at the top of left pole-half stock (11) and right panel rod set frame (12) (14);First curved baffle (13) and the second curved baffle (14) is symmetrical arranged.
5. a kind of electric power facility maintenance electric pole climbing tool according to claim 1, which is characterized in that described climbs Climbing component (3) quantity is 3, and the angle between arbitrary neighborhood two climbings component (3) is 120 °.
6. a kind of electric power facility maintenance electric pole climbing tool according to claim 1, which is characterized in that described the The top two sides of the lower part and climbing fixed link (31) of one transmission band plate (331) and the second transmission band plate (332) are connected with first Rotating bar (34);Top and climbing fixed link (31) of first transmission band plate (331) and the second transmission band plate (332) Top two sides be connected with the second rotating bar (35).
7. a kind of electric power facility maintenance electric pole climbing tool according to claim 1, which is characterized in that described the Multiple regularly arranged auxiliary guide wheels (36) are provided on the inside of one transmission band plate (331) and the second transmission band plate (332);Institute Multiple climbing cross bars (3351) convenient for climbing are provided on the conveyer belt (335) stated.
8. a kind of electric power facility maintenance electric pole climbing tool according to claim 1, which is characterized in that described the Three support frames (113) are identical as the shape of the first support frame (111), and the length of support level plate (1141) is greater than support transverse slat (1122).
9. a kind of electric power facility maintenance electric pole climbing tool according to claim 1, which is characterized in that the hinge Connecting spring (3131) are provided in the middle part of extension bar (313).
10. the application method that electric pole climbing tool is used in a kind of electric power facility maintenance, which is characterized in that pass sequentially through following step It is rapid:
It is tentatively arranged: set being opened by the left pole-half stock (11) of rod set frame (1) and one end of right panel rod set frame (12) and is set to electricity On the outer ring of line bar, tentatively it is arranged by the three pieces of arc blocks cooperation being arranged in component (2);
The matching of bar diameter: drive movable block (312) mobile to drive belt-driven component (33) to press from both sides by climbing cylinder (32) Tightly, it is bonded the conveyer belt (335) in belt-driven component (33) with the outer ring of electric pole;
Climbing maintenance: conveyer belt (335) rotation is driven by the belt-driven component (33) in climbing component (3), is made entire Device carries out climbing maintenance up and down on utility poles;
Electric power facility maintenance is as described in claim 1 with electric pole climbing tool.
CN201910348390.4A 2019-04-28 2019-04-28 A kind of electric power facility maintenance electric pole climbing tool Pending CN110227241A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910348390.4A CN110227241A (en) 2019-04-28 2019-04-28 A kind of electric power facility maintenance electric pole climbing tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910348390.4A CN110227241A (en) 2019-04-28 2019-04-28 A kind of electric power facility maintenance electric pole climbing tool

Publications (1)

Publication Number Publication Date
CN110227241A true CN110227241A (en) 2019-09-13

Family

ID=67860247

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910348390.4A Pending CN110227241A (en) 2019-04-28 2019-04-28 A kind of electric power facility maintenance electric pole climbing tool

Country Status (1)

Country Link
CN (1) CN110227241A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116077903A (en) * 2023-04-10 2023-05-09 国网山东省电力公司潍坊供电公司 Auxiliary device for operation maintenance of power transmission line

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1537229A (en) * 1976-07-21 1978-12-29 Gkn Mills Building Serv Scaffolding clamps
CH614905A5 (en) * 1977-05-02 1979-12-28 Ciba Geigy Ag Clamp
DE2918998A1 (en) * 1979-05-11 1980-11-13 Leybold Heraeus Gmbh & Co Kg TENSION RING FOR FLANGE CONNECTIONS
JPS62181979A (en) * 1986-02-04 1987-08-10 Ishikawajima Harima Heavy Ind Co Ltd Creepingly moving mechanism and creepingly moving device
CN101874922A (en) * 2010-06-25 2010-11-03 河南省电力公司洛阳供电公司 Portable wire pole climbing mechanism
WO2013113494A2 (en) * 2012-01-31 2013-08-08 Fachhochschule Aachen Climbing robot for masts
CN106422214A (en) * 2015-08-12 2017-02-22 国龙寿 Electric lifting type telegraph pole climbing device
CN107970576A (en) * 2017-11-25 2018-05-01 无锡锡东电力电气安装工程有限公司 A kind of pole climbing device for being used to climb linear pattern shaft tower
CN108635776A (en) * 2016-09-23 2018-10-12 青岛开疆拓土农业装备科技有限公司 The automatic climbing device of power cord bar
CN108700236A (en) * 2016-03-04 2018-10-23 德国诺玛公司 Shaping jig
CN109649522A (en) * 2018-11-14 2019-04-19 赵红丽 Straight rod member or oblique pull cable wire climb power drive unit

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1537229A (en) * 1976-07-21 1978-12-29 Gkn Mills Building Serv Scaffolding clamps
CH614905A5 (en) * 1977-05-02 1979-12-28 Ciba Geigy Ag Clamp
DE2918998A1 (en) * 1979-05-11 1980-11-13 Leybold Heraeus Gmbh & Co Kg TENSION RING FOR FLANGE CONNECTIONS
JPS62181979A (en) * 1986-02-04 1987-08-10 Ishikawajima Harima Heavy Ind Co Ltd Creepingly moving mechanism and creepingly moving device
CN101874922A (en) * 2010-06-25 2010-11-03 河南省电力公司洛阳供电公司 Portable wire pole climbing mechanism
WO2013113494A2 (en) * 2012-01-31 2013-08-08 Fachhochschule Aachen Climbing robot for masts
CN106422214A (en) * 2015-08-12 2017-02-22 国龙寿 Electric lifting type telegraph pole climbing device
CN108700236A (en) * 2016-03-04 2018-10-23 德国诺玛公司 Shaping jig
CN108635776A (en) * 2016-09-23 2018-10-12 青岛开疆拓土农业装备科技有限公司 The automatic climbing device of power cord bar
CN107970576A (en) * 2017-11-25 2018-05-01 无锡锡东电力电气安装工程有限公司 A kind of pole climbing device for being used to climb linear pattern shaft tower
CN109649522A (en) * 2018-11-14 2019-04-19 赵红丽 Straight rod member or oblique pull cable wire climb power drive unit

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116077903A (en) * 2023-04-10 2023-05-09 国网山东省电力公司潍坊供电公司 Auxiliary device for operation maintenance of power transmission line

Similar Documents

Publication Publication Date Title
CN201161903Y (en) Lift shaft
CN106166372B (en) Electric pole inspection platform voluntarily climbing device
CN205802720U (en) Hoistable platform and the tower with this hoistable platform
CN110510525A (en) A kind of single-beam gantry crane with hook
CN110227241A (en) A kind of electric power facility maintenance electric pole climbing tool
CN203655133U (en) Multifunctional repair working ladder
CN104577870A (en) Automatic obstacle-crossing type overhead earth wire pay-off tool for maintenance
CN209130725U (en) A kind of LED street lamp of easy access and disassembly
CN115319785A (en) Rotary clamping jaw
CN110977871B (en) Belt threading and dismounting device
CN212601586U (en) Assembly equipment is used in production of LED lamp
CN204039003U (en) Lifting monolock only struggles against mechanical and electric equipment installation mechanism of basket rotation substation
CN110158970A (en) A kind of high-rise feeder equipment of architectural engineering
CN109436655A (en) A kind of electric pole conveying device
CN111335723B (en) Automatic electric power transmission pole that goes up and down
CN201500394U (en) Rescuing machine for well
CN107651625A (en) A kind of power equipment installs lifting apparatus
CN209635228U (en) Feeding sprocket wheel transmission device
CN204039004U (en) Mechanical and electric equipment installation mechanism of the adjustable bucket of supporting leg basket lifting Dual-locking substation
CN116101946A (en) Three-dimensional positioning platform based on transformer substation operation personnel
CN206934767U (en) A kind of peoperty lowering or hoisting gear
CN112975716B (en) Polishing mechanism on fixed denture production line
CN221503186U (en) Power line lifting type crawling ladder
CN202142762U (en) Support for middle joint of large-cross section single core cable
CN105730974B (en) A kind of elevator with rollgang

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190913