CN110219649B - 缓冲卸压带与宽巷柔性墙防治坚硬顶板留巷冲击地压方法 - Google Patents

缓冲卸压带与宽巷柔性墙防治坚硬顶板留巷冲击地压方法 Download PDF

Info

Publication number
CN110219649B
CN110219649B CN201910509373.4A CN201910509373A CN110219649B CN 110219649 B CN110219649 B CN 110219649B CN 201910509373 A CN201910509373 A CN 201910509373A CN 110219649 B CN110219649 B CN 110219649B
Authority
CN
China
Prior art keywords
wall
roadway
pressure relief
coal
expanding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910509373.4A
Other languages
English (en)
Other versions
CN110219649A (zh
Inventor
潘立友
唐鹏
孙久政
陈理强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University of Science and Technology
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN201910509373.4A priority Critical patent/CN110219649B/zh
Publication of CN110219649A publication Critical patent/CN110219649A/zh
Application granted granted Critical
Publication of CN110219649B publication Critical patent/CN110219649B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/18Methods of underground mining; Layouts therefor for brown or hard coal
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/103Dams, e.g. for ventilation
    • E21F17/107Dams, e.g. for ventilation inflatable
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques

Abstract

本发明公开了一种缓冲卸压带与宽巷柔性墙防治坚硬顶板留巷冲击地压方法,其特征在于;首先将原留巷煤壁侧进行扩帮挖底,将扩帮下来的煤体装入编织袋中备用;按照常规方法在扩帮后的煤壁上打眼爆破人工制造宽度的8‑12m缓冲卸压带;将以装好的物料的编织袋为墙体材料,沿扩帮后的空间位置垒砌成宽度1.5‑1.6m米的人工墙;采用防护网与单体支柱联合技术对柔性墙进行加固阻挡。通过缓冲卸压,改变了煤体冲击属性;采用人工柔性墙与巷帮内爆破形成软体而实现留巷的防冲。

Description

缓冲卸压带与宽巷柔性墙防治坚硬顶板留巷冲击地压方法
技术领域
本发明属于煤矿开采技术领域。
背景技术
沿空留巷(简称留巷)是煤矿在上一区段工作面采过后,将其运输巷扩修和用专门的支护材料进行维护,使此保留下来作为下一区段工作面的回风巷。这种一条巷道可以得到两次利用,是无煤柱开采技术中的一种方式。沿空留巷可以最大限度回收资源,避免煤炭损失。
冲击地压是最严重的动力灾害之一,影响冲击地压的地质因素包括构造、埋深、顶板、煤层硬度、开采因素等;越到深部地质因素越起到决定作用,且破坏显现日趋严重,其中坚硬顶板导致的冲击地压占据较大比重,且破坏性也较严重。由于坚硬顶板往往导致存在悬顶结构,面临较大的静态应力场,尤其工作面开采期间再附加侧向高动态应力,会导致应力场突然释放,冲击地压危险更加增大。采用常规方法的常规技术参数对坚硬顶板型冲击地压解危效果较差,且难以达到解除危险的效果。到目前为止,还没有针对坚硬顶板的具体煤层条件下,在沿空留巷扩修维护与回采期间的冲击地压能达到完全控制的相应技术措施。
发明内容
本发明的目的是针对目前坚硬顶板条件下沿空巷冲击地压的解危问题,提出一种缓冲卸压带与宽巷柔性墙防治沿空留巷冲击地压方法。
本发明的技术方案是:
一种缓冲卸压带与宽巷柔性墙防治坚硬顶板留巷冲击地压方法,其特征在于:
一、 首先将原留巷煤壁侧进行扩帮挖底,扩帮宽度1.5-1.6m,挖底深度0.5 m,将扩帮下来的煤体装入编织袋中备用,将挖底下来的矸石和水泥混合后装入编织袋中备用,扩帮挖底后作为垒砌人工墙的空间位置;
二、按照常规方法在扩帮后的煤壁上进行打眼深孔爆破,爆破深度8-12m,沿留巷人工制造出一个宽度的8-12m缓冲卸压带;
三、将以装好物料的编织袋为墙体材料,沿扩帮后的空间位置垒砌成宽度1.5-1.6m米的人工墙;垒砌高度至巷道顶板;下部编织袋内为装有矸石和水泥混合物的编织袋,作为墙体底部承载,上部编制袋内为装有煤体的编织袋,构成可压缩变形的柔性墙主体;
四、在柔性墙形成后,采用防护网与单体支柱联合技术对柔性墙进行加固阻挡。
本发明的积极效果是:
1、通过对巷帮实施爆破技术,人工制造缓冲卸压,带改变了煤层应力分布,将应力向深部转移,同时破坏了煤体,从根本上改变了煤体冲击属性,防止冲击地压发生;
2、采用将原巷道拓宽建墙、拓宽挖掘的煤体和矸石在原地制作成建墙矸石袋,再在原地用矸石袋垒砌成人工墙,就地取材,减少了取材运材环节,提高工作效率减少工程成本。
3、采用人工柔性墙与巷帮内爆破形成软体而实现留巷的防冲,对留巷起到支护作用与防护墙作用,一旦再有冲击地压发生,对巷道内的工作人员起到保护作用,避免伤亡事故。
下面结合附图说明本发明的实施。
附图说明
图1是实施例的扩帮与缓冲泄压带平面布置示意图,图2是实施例的人工柔性墙平面结构示意图。
具体实施方式
本领域技术人员根据发明内容所述的技术方案和图1、图2所示的示意图即可实施,在此不再详述。

Claims (1)

1.一种缓冲卸压带与宽巷柔性墙防治坚硬顶板留巷冲击地压方法,其特征在于:
1) 首先将原留巷煤壁侧进行扩帮挖底,扩帮宽度1.5-1.6m,挖底深度0.5 m,将扩帮下来的煤体装入编织袋中备用,将挖底下来的矸石和水泥混合后装入编织袋中备用,扩帮挖底后作为垒砌人工墙的空间位置;
2)按照常规方法在扩帮后的煤壁上进行打眼深孔爆破,爆破深度8-12m,沿留巷人工制造出一个宽度为8-12m的缓冲卸压带;
3)将已装好物料的编织袋为墙体材料,沿扩帮后的空间位置垒砌成宽度1.5-1.6m米的人工墙;垒砌高度至巷道顶板;下部编织袋内为装有矸石和水泥混合物的编织袋,作为墙体底部承载,上部编制袋内为装有煤体的编织袋,构成可压缩变形的柔性墙主体;
4)在柔性墙形成后,采用防护网与单体支柱联合技术对柔性墙进行加固阻挡。
CN201910509373.4A 2019-06-13 2019-06-13 缓冲卸压带与宽巷柔性墙防治坚硬顶板留巷冲击地压方法 Active CN110219649B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910509373.4A CN110219649B (zh) 2019-06-13 2019-06-13 缓冲卸压带与宽巷柔性墙防治坚硬顶板留巷冲击地压方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910509373.4A CN110219649B (zh) 2019-06-13 2019-06-13 缓冲卸压带与宽巷柔性墙防治坚硬顶板留巷冲击地压方法

Publications (2)

Publication Number Publication Date
CN110219649A CN110219649A (zh) 2019-09-10
CN110219649B true CN110219649B (zh) 2020-11-10

Family

ID=67816911

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910509373.4A Active CN110219649B (zh) 2019-06-13 2019-06-13 缓冲卸压带与宽巷柔性墙防治坚硬顶板留巷冲击地压方法

Country Status (1)

Country Link
CN (1) CN110219649B (zh)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112483095A (zh) * 2020-12-18 2021-03-12 山东科技大学 一种断层破碎区巷道冲击地压防治方法
CN112483098A (zh) * 2020-12-18 2021-03-12 山东科技大学 一种采场超前破碎顶板冲击地压防治方法
CN112483096A (zh) * 2020-12-18 2021-03-12 山东科技大学 一种向斜轴部采场冲击地压防治方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1664310A (zh) * 2005-02-28 2005-09-07 清华大学 煤矿孤岛煤柱冲击地压控制方法
RU2391507C2 (ru) * 2008-04-14 2010-06-10 Григорий Кондратьевич Александров Бесцеликовый способ выработки угольных пластов
CN102661169A (zh) * 2012-04-28 2012-09-12 山东科技大学 一种用于无煤柱开采的锚栓网矸石袋墙体沿空留巷方法
CN102678120A (zh) * 2012-05-18 2012-09-19 河南大有能源股份有限公司 冲击地压卸压解危方法
CN104790954A (zh) * 2015-03-27 2015-07-22 黑龙江科技大学 巷旁充填沿空留巷切顶爆破卸压方法
CN107035405A (zh) * 2016-12-06 2017-08-11 太原理工大学 一种用于沿空留巷双充填墙结构切顶卸压方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1664310A (zh) * 2005-02-28 2005-09-07 清华大学 煤矿孤岛煤柱冲击地压控制方法
RU2391507C2 (ru) * 2008-04-14 2010-06-10 Григорий Кондратьевич Александров Бесцеликовый способ выработки угольных пластов
CN102661169A (zh) * 2012-04-28 2012-09-12 山东科技大学 一种用于无煤柱开采的锚栓网矸石袋墙体沿空留巷方法
CN102678120A (zh) * 2012-05-18 2012-09-19 河南大有能源股份有限公司 冲击地压卸压解危方法
CN104790954A (zh) * 2015-03-27 2015-07-22 黑龙江科技大学 巷旁充填沿空留巷切顶爆破卸压方法
CN107035405A (zh) * 2016-12-06 2017-08-11 太原理工大学 一种用于沿空留巷双充填墙结构切顶卸压方法

Also Published As

Publication number Publication date
CN110219649A (zh) 2019-09-10

Similar Documents

Publication Publication Date Title
CN110219649B (zh) 缓冲卸压带与宽巷柔性墙防治坚硬顶板留巷冲击地压方法
CN108643907B (zh) 一种破碎直接顶沿空放顶成巷无煤柱开采方法
CN104763432B (zh) 一种高应力巷道围岩卸压控制大变形的方法
CN105317459B (zh) 一种用于控制坚硬顶板大面积垮落灾害的分区充填方法
CN103821558B (zh) 煤矿采空区充填采矿及沿空留巷充填工艺
CN104533467B (zh) 一种高承压水、断层破碎巷道的支护方法
CN110173264B (zh) 断顶与常规卸压防治坚硬顶板留巷冲击地压方法
CN111305876A (zh) 深部巷道锚固-劈裂注浆-水力压裂卸压协同控制方法
WO2011103620A1 (en) A method of reducing subsidence or windblast impacts from longwall mining
WO2019085052A1 (zh) 一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法
CN104532818A (zh) 一种露天矿采空区的治理方法
AU2021355609B2 (en) Method for mining by filling and caving
AP893A (en) Undercut excavation with protection against seismic events or excessive ground movement.
CN110469340A (zh) 一种岩爆隧道双护盾tbm卡机脱困施工方法
EA027129B1 (ru) Способ выемки с подрубкой с непрерывными бетонными перекрытиями
CN111005392B (zh) 一种含缓倾软弱夹层矿山高陡滑坡的治理方法
CN110259448B (zh) 卸压破顶与宽巷柔性墙防治坚硬顶板留巷冲击地压方法
CN110145307B (zh) 宽巷与柔性硐室墙防治坚硬顶板留巷冲击地压方法
CN104989408A (zh) 一种用于山区金属矿山安全高效的采矿方法
CN113586086B (zh) 一种半封闭式大断面巷道软弱破碎底板加固方法
CN105937400B (zh) 一种一次掘进留设双巷采掘作业生产线
CN112031857A (zh) 底板岩石巷道联合钻孔爆破卸压强化瓦斯抽采的方法
CN110552731A (zh) 一种放顶煤回采巷道注浆锚索支护结构及其超前支护方法
CN113123358B (zh) 一种采煤不均匀沉降作用下船池变形防治结构及施工方法
CN204919559U (zh) 地裂缝的修复系统

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 266590 No. 579, Bay Road, Huangdao District, Shandong, Qingdao

Applicant after: Shandong University of Science and Technology

Address before: 271000 Shandong Province, Tai'an city Taishan District mountain Street No. 223 Tai'an campus of Shandong University of Science and Technology

Applicant before: Shandong University of Science and Technology

GR01 Patent grant
GR01 Patent grant