CN110219301A - A kind of PHC pipe pile static-pressure construction method - Google Patents

A kind of PHC pipe pile static-pressure construction method Download PDF

Info

Publication number
CN110219301A
CN110219301A CN201910616402.7A CN201910616402A CN110219301A CN 110219301 A CN110219301 A CN 110219301A CN 201910616402 A CN201910616402 A CN 201910616402A CN 110219301 A CN110219301 A CN 110219301A
Authority
CN
China
Prior art keywords
cushion hole
tubular pole
pipe pile
pressure
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910616402.7A
Other languages
Chinese (zh)
Inventor
曾翔
黄隆营
郭锦明
仲兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Hope Construction Engineering Co Ltd
Original Assignee
Guangdong Hope Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Hope Construction Engineering Co Ltd filed Critical Guangdong Hope Construction Engineering Co Ltd
Priority to CN201910616402.7A priority Critical patent/CN110219301A/en
Publication of CN110219301A publication Critical patent/CN110219301A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a kind of PHC pipe pile static-pressure construction methods, comprising the following steps: S1, tubular pole surveying and locating, cushion hole locating holes, stake machine are in place, tubular pole is in place, pipe pile static-pressure, pile extension operation, pile follower operation, final pressure operation, washing and cleaning operation, telephone-moving operation block operation.The present invention has the effect of that the Pile side soil body lateral displacement of adjacent tubular pole is not easy to be superimposed.

Description

A kind of PHC pipe pile static-pressure construction method
Technical field
The present invention relates to the technical fields of pile foundation engineering, more particularly, to a kind of PHC pipe pile static-pressure construction method.
Background technique
With the continuous propulsion that China's construction industry develops, free area area is gradually reduced, and causes building along vertical It is greatly improved to short transverse, plane figure is substantially compressed, and distance constantly reduces between adjacent buildings, the stake to building More stringent requirements are proposed for basic engineering and construction.
The construction of PHC pipe pile static-pressure is a kind of method of engineering pile foundation construction, is now widely used for pile foundation construction.Pass through The mechanism of pile of static pile press, with the counterweight in pile press machine self weight and rack provides counter-force and will be heavy in prefabricated pile indentation soil Stake technique.
But construct in PHC pipe pile static-pressure, especially the soil body around construction of pile groups region, tubular pole is arranged around It squeezes, the soil body of surrounding is made to be disturbed, cause with the soil body of tubular pole volume equivalent in the process of sinking to occurring around tubular pole It larger lateral displacement and being filled with, the vertical decrement of Pile side soil body of adjacent tubular pole is larger, due to the superposition in construction of pile groups, The soil body for making respectively to close on pipe pile side generates biggish lateral displacement and floating, the soil body of the tubular pole being driven underground because of displacement It is floated up under the drive of frictional force, causes the second-rate of construction of pile groups, and surrounding house, road cracking and underground occur The problems such as pipeline is displaced.
Summary of the invention
The object of the present invention is to provide during a kind of construction of pile groups, the Pile side soil body lateral displacement of adjacent tubular pole is not easy The PHC pipe pile static-pressure construction method of superposition.
Foregoing invention purpose of the invention has the technical scheme that
A kind of PHC pipe pile static-pressure construction method, comprising the following steps:
S1, tubular pole surveying and locating are determined axis and the measuring of stake position with theodolite and steel ruler according to the coordinate that construction drawing gives Position, and hammer soil layer with timber and mark, the prominent ground 10cm to 20cm of timber;
S2, cushion hole locating holes, it is smooth to construction site progress, according to stake site, determines the position of cushion hole, make cushion hole In clump of piles region, gutter is opened up in cushion hole surrounding, and cushion hole is drilled with by drilling machine;
S3, stake machine are in place, and stake position surrounding opens up gutter, and stake machine gradient is less than 1%;
S4, tubular pole are in place, and staff carries out the centering of stake position, verticality correction, when ground is inserted into the lifting of first segment tubular pole in place Perpendicularity deviation be not greater than 0.5%;
The counterweight of stake machine is adjusted to 20% greater than pressure pile resistance, after keeping the axial compression of tubular pole, by tubular pole by S5, pipe pile static-pressure It is continuously disposably pressed onto bottom, and pours into microdilatancy crushed stone concrete after having pressed and carries out back cover;
S6, pile extension operation lift by crane new tubular pole to the top for the tubular pole for being pressed into ground, keep the axis of two tubular poles consistent, misplace Deviation is less than 2mm, is pressed into the tubular pole 0.5m-1.0m above ground level on ground, staff's symmetrical spot welding between two tubular poles at this time 4-6 point, and it is symmetrically layered welding, the welding number of plies is greater than 2 layers, natural cooling 8min after the completion of welding;
S7, pile follower operation, staff are sent tubular pole to design of pile top absolute altitude using Pile feeder;
S8, final pressure operation after tubular pole reaches design of pile top absolute altitude, carry out final pressure operation, are pressed again tubular pole three times, are observed under tubular pole Heavy amount is pressed again again when tubular pole deflection is greater than 1mm, until tubular pole deflection is less than 1mm;
S9, washing and cleaning operation clean tubular pole inner wall;
S10, telephone-moving operation, telephone-moving is to next position after tubular pole stops pressure;
S11, operation is blocked, staff blocks cushion hole.
By using above-mentioned technical proposal, during making construction of pile groups, cushion hole is opened up near adjacent tubular pole, when When the soil body of pipe pile side squeezes around, the soil body of lateral displacement presses to cushion hole, during alleviating construction of pile groups, pipe pile The amount of the soil body lateral displacement of side reduces, and is not easy to be superimposed, the land movement amount in construction of pile groups region is smaller;Meanwhile cushion hole Being drilled with allows staff to dig the geological mapping that situation carries out further clump of piles region according to the brill of cushion hole, after determining The depth of phase pile sinking, the counterweight of stake machine and the depth of later period pile extension.
Preferably, the depth of the cushion hole is 1-1.2 times of PHC tubular pole depth, and the cushion hole includes close to ground Upper section and the closely lower section two parts at bottom, the internal diameter of cushion hole upper section is greater than the internal diameter of cushion hole lower section, the cushion hole The depth of upper section is the 1/2-1/3 of cushion hole total depth.
By using above-mentioned technical proposal, the soil body is produced when being walked within the scope of construction of pile groups due to biggish stake machine of being self-possessed Raw level squeezes the top that stress is easily transmitted to tubular pile body, generates horizontal shear force, is easy the shallower tubular pole top of pile follower Fracture, the setting of cushion hole are squeezed a machine at stress transfer to cushion hole to the level that the soil body generates, are reduced to tubular pole top Horizontal shear force.
Preferably, the position of the cushion hole is circumferentially distributed using the central point in clump of piles region as the center of circle.
By using above-mentioned technical proposal, keep the soil body lateral displacement in clump of piles region more uniform, improve pile quality, Reduce the appearance for the construction problems such as the house outside clump of piles region is damaged, road cracks and underground utilities deviate.
Preferably, after the completion of the cushion hole is drilled with, staff is by the bottom hole filling diameter of cushion hole greater than 3.0mm's Then coarse sand is placed drainpipe and is entered in cushion hole, is located at the water inlet of drainpipe on coarse sand, and continue to fill up diameter and be greater than The coarse sand of 1.0mm is to the water inlet for not crossing drainpipe, and the coarse sand diameter at water-bearing layer is greater than 3.0mm, and drainpipe persistently draws water.
By using above-mentioned technical proposal, cushion hole is near water-bearing layer due to squeezing during soil body lateral displacement The effect of compression has a large amount of water body and is precipitated, and the effect of coarse sand plays the filtration of part, keeps water quality preferable, drained The water body of the extraction of pipe can apply to more environment;In addition the coarse sand filled plays certain supporting role to cushion hole inner wall Reduce the inner wall of cushion hole during water body is extracted out, the soil body is not easily to fall off;The setting of filling coarse sand, increases soil in cushion hole The obstruction of body lateral displacement makes cushion hole be not easy to collapse;A large amount of moisture extracted in water-bearing layer, make tubular pole carry out static pressure operation When, the moisture for pouring in tubular pole inner wall is less, is convenient for PHC pipe pile static-pressure construction operation.
Preferably, in the cushion hole, the coarse sands layer filled with different-diameter, each coarse sands layer inclination interaction is in cushion hole It is interior, it is plane near the coarse sands layer upper surface of near surface.
By using above-mentioned technical proposal, coarse sands layer in cushion hole is made to be layered filling and stress surface inclined surface, when The soil body of pipe pile side is to when extruding, the coarse sand in cushion hole is along the sliding of the inclined-plane of layering or upward, diameter at cushion hole Less coarse sand enters in the gap for the coarse sand being relatively large in diameter, and the buffering soil body lateral extruding while reinforces cushion hole Nell wall Support strength.
Preferably, the coarse sands layer in the cushion hole is filled to the intersection for closing on cushion hole upper section and lower section, and close There are the gap of 1m between the coarse sands layer and cushion hole upper section on ground, cushion hole is filled with metalling, the upper table of the metalling Face is higher than cushion hole lower end 1m.
By using above-mentioned technical proposal, there are the surpluses of deformation for cushion hole upper section, and the soil body of pipe pile side is made to carry out side To cushion hole when displacement, is squeezed, the contraction of cushion hole inner wall squeezes coarse sands layer and metalling shifts up, rubble in metalling Between gap it is larger, be convenient for cushion hole inner wall compressive.
Preferably, in final pressure operation process, when the pipe pile that buries is long is greater than 9m less than 16m, final pressure value is 5000kN, eventually It fully loaded must only be pressed again three times before piling;It is greater than 16m when the pipe pile that buries is long, is less than 25m, final pressure value is 4000kN, terminates piling Preceding fully loaded multiple pressure is twice;It is greater than 25m when the pipe pile that buries is long, final pressure value is 3700kN, is fully loaded with multiple pressure twice before terminating piling.
By using above-mentioned technical proposal, the setting of final pressure value makes tubular pole overcome the anti-of pile top soil layer during the pile driving process The frictional force of punching resistance and the pile body periphery soil body makes on the pile top build-in of tubular pole to the suitable supporting course in clump of piles region, meanwhile, By final pressure operation, the soil body of compacted pile top improves the mechanical property of the soil body near pile top, obtains at the higher pile top soil body Ultimate resistance;Obtain higher bearing capacity of single pile.
Preferably, during washing and cleaning operation, the mud of tubular pole bottom is manually removed first, tubular pole inner wall is rinsed, After precipitating 3h, first the water body on upper layer in tubular pole is extracted, then extracts the slurry mixture of lower layer in tubular pole, mud is mixed It closes object to be extracted by water pump, is evacuated to after filling core depth, stiff pat of cement is blocked;Brushing pure water on tubular pole inner wall Mud.
By using above-mentioned technical proposal, the setting of pat of cement, for blocking the water burst of tubular pole bottom;The painting of neat slurry Brush improves PHC tube pile construction quality for enhancing the adhesion strength filled out between core material and tubular pole inner wall.
Preferably, it blocks in operation process, staff fills C40 slightly expanded concrete to cushion hole, and passes through Cement vibrating head is inserted to set and be stirred on metalling.
By using above-mentioned technical proposal, make the C40 slightly expanded concrete in cushion hole under the stirring of cement vibrating head, Metalling and coarse sands layer are flowed into, reinforces the support strength in cushion hole, plays certain firm effect.
In conclusion advantageous effects of the invention are as follows:
1. the setting of cushion hole, during making construction of pile groups, the soil body of lateral displacement presses to cushion hole, alleviate construction of pile groups mistake The amount of Cheng Zhong, the soil body lateral displacement of pipe pile side reduce, and are not easy to be superimposed, the land movement amount in construction of pile groups region is smaller;Together When, being drilled with for cushion hole allows staff to dig the geology that situation carries out further clump of piles region according to the brill of cushion hole Prospecting, determines the depth of later period pile sinking, the counterweight of stake machine and the depth of later period pile extension.
Detailed description of the invention
Fig. 1 is construction process schematic diagram of the invention.
Fig. 2 is the cross-sectional view of cushion hole.
In figure, 1, cushion hole;2, drainpipe;3, metalling;4, coarse sands layer.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
In conjunction with Fig. 1 and Fig. 2 it is found that being a kind of PHC pipe pile static-pressure construction method disclosed by the invention, the construction of pile groups region It is interior, it is all made of Φ 500*125AB type HPC tubular pole, about 416, about 10400m;Single stake is about 25m;The following steps are included:
S1, tubular pole surveying and locating are determined axis and the measuring of stake position with theodolite and steel ruler according to the coordinate that construction drawing gives Position, and hammer soil layer with timber and mark, iron nail, the prominent ground 10cm to 20cm of timber, mark are hammered into stake site on timber Height records on the regular payroll, and control axis is led to home, to restore axis and check to use;It is fixed to unwrapping wire before construction Each axis and stake position of position are checked once again, check whether size and stake position dimension meet construction drawing between each axis Design requirement, ground elevation are measured with level, it is ensured that datum mark is protected in precision
S2,1 locating holes of cushion hole, it is smooth to construction site progress, it according to stake site, determines the position of cushion hole 1, makes to buffer Hole 1 is located in clump of piles region, and is drilled with cushion hole 1 by drilling machine;The position of cushion hole 1 is in as the center of circle using the central point in clump of piles region Circle distribution.Gutter is opened up in 1 surrounding of cushion hole, the depth of cushion hole 1 is 1-1.2 times of PHC tubular pole depth, cushion hole 1 Including the upper section and the closely lower section two parts at bottom close to ground, the internal diameter of 1 upper section of cushion hole is interior greater than 1 lower section of cushion hole Diameter, the depth of 1 upper section of cushion hole are the 1/2-1/3 of 1 total depth of cushion hole;After the completion of cushion hole 1 is drilled with, staff will be buffered The bottom hole filling diameter in hole 1 is greater than the coarse sand of 3.0mm, then places drainpipe 2 and enters in cushion hole 1, makes the water inlet of drainpipe 2 Mouth is located on coarse sand, and continues to fill up coarse sand of the diameter greater than 1.0mm to the water inlet for not crossing drainpipe 2, is formed multiple and different The coarse sands layer 4 of diameter, the coarse sand diameter at water-bearing layer are greater than 3.0mm, and drainpipe 2 persistently draws water;Each coarse sands layer 4 inclination interaction in In cushion hole 1, it is plane near 4 upper surface of coarse sands layer of near surface and there are the gap of 1m between 1 upper section of cushion hole, between being somebody's turn to do Metalling 3 is filled in gap, the upper surface of metalling 3 is higher than 1 lower end 1m of cushion hole.
S3, stake machine are in place, and stake position surrounding opens up gutter, and smooth to the progress of construction of pile groups scene again, and stake machine inclines Less than 1%, the vertical sight alignment of pitching pile must not deviate gradient.
S4, tubular pole are in place, and staff carries out the centering of stake position, verticality correction, first segment tubular pole lifting insertion ground in place Perpendicularity deviation when face is not greater than 0.5%;And it is corrected with strip levelling rod or other measuring instruments.
S5, pipe pile static-pressure carry out review correction according to axis to every pile, should carry out repetition measurement school to axial line control stake daily Just;Pile position deviation is not greater than 20mm;The counterweight of stake machine is adjusted to 20% greater than pressure pile resistance, keeps the axial compression of tubular pole Afterwards, tubular pole is disposably continuously pressed onto bottom, and pours into microdilatancy crushed stone concrete after having pressed and carries out back cover.
S6, pile extension operation lift by crane new tubular pole to the top for the tubular pole for being pressed into ground, keep the axis of two tubular poles consistent, The deviation that misplaces is less than 2mm, is pressed into the tubular pole 0.5m-1.0m above ground level on ground at this time, and staff is symmetrical between two tubular poles 4-6 point of spot welding, and it is symmetrically layered welding, the welding number of plies is greater than 2 layers, natural cooling 8min after the completion of welding.
S7, pile follower operation, staff are sent tubular pole to design of pile top absolute altitude using Pile feeder.
S8, final pressure operation after tubular pole reaches design of pile top absolute altitude, carry out final pressure operation, are pressed again tubular pole three times, observation tube Stake deflection is pressed again again when tubular pole deflection is greater than 1mm, until tubular pole deflection is less than 1mm;When burying, pipe pile is grown up Final pressure value is 5000kN when 9m is less than 16m, must be fully loaded with multiple pressure three times before terminating piling;It is greater than 16m when the pipe pile that buries is long, it is small In 25m, final pressure value is 4000kN, is fully loaded with multiple pressure twice before terminating piling;It is greater than 25m when the pipe pile that buries is long, final pressure value is 3700kN is fully loaded with multiple pressure twice before terminating piling.
S9, washing and cleaning operation clean tubular pole inner wall;The mud for manually removing tubular pole bottom first, to tubular pole inner wall It is rinsed, after precipitating 3h, first extracts the water body on upper layer in tubular pole, then take out the slurry mixture of lower layer in tubular pole It takes, slurry mixture is extracted by water pump, is evacuated to after filling core depth, stiff pat of cement is blocked;Tubular pole inner wall Upper brushing neat slurry.
S10, telephone-moving operation, telephone-moving is to next position after tubular pole stops pressure.
S11, operation is blocked, staff blocks cushion hole 1;Staff fills C40 slightly expanded concrete To cushion hole 1, and inserts to set by cement vibrating head and be stirred on metalling 3.
The embodiment of present embodiment is presently preferred embodiments of the present invention, not limits protection of the invention according to this Range, therefore: the equivalence changes that all structures under this invention, shape, principle are done, should all be covered by protection scope of the present invention it It is interior.

Claims (9)

1. a kind of PHC pipe pile static-pressure construction method, comprising the following steps:
S1, tubular pole surveying and locating are determined axis and the measuring of stake position with theodolite and steel ruler according to the coordinate that construction drawing gives Position, and hammer soil layer with timber and mark, the prominent ground 10cm to 20cm of timber;
S2, cushion hole locating holes, it is smooth to construction site progress, according to stake site, determines the position of cushion hole, make cushion hole In clump of piles region, gutter is opened up in cushion hole surrounding, and cushion hole is drilled with by drilling machine;
S3, stake machine are in place, and stake position surrounding opens up gutter, and stake machine gradient is less than 1%;
S4, tubular pole are in place, and staff carries out the centering of stake position, verticality correction, when ground is inserted into the lifting of first segment tubular pole in place Perpendicularity deviation be not greater than 0.5%;
The counterweight of stake machine is adjusted to 20% greater than pressure pile resistance, after keeping the axial compression of tubular pole, by tubular pole by S5, pipe pile static-pressure It is continuously disposably pressed onto bottom, and pours into microdilatancy crushed stone concrete after having pressed and carries out back cover;
S6, pile extension operation lift by crane new tubular pole to the top for the tubular pole for being pressed into ground, keep the axis of two tubular poles consistent, misplace Deviation is less than 2mm, is pressed into the tubular pole 0.5m-1.0m above ground level on ground, staff's symmetrical spot welding between two tubular poles at this time 4-6 point, and it is symmetrically layered welding, the welding number of plies is greater than 2 layers, natural cooling 8min after the completion of welding;
S7, pile follower operation, staff are sent tubular pole to design of pile top absolute altitude using Pile feeder;
S8, final pressure operation after tubular pole reaches design of pile top absolute altitude, carry out final pressure operation, are pressed again tubular pole three times, are observed under tubular pole Heavy amount is pressed again again when tubular pole deflection is greater than 1mm, until tubular pole deflection is less than 1mm;
S9, washing and cleaning operation clean tubular pole inner wall;
S10, telephone-moving operation, telephone-moving is to next position after tubular pole stops pressure;
S11, operation is blocked, staff blocks cushion hole.
2. PHC pipe pile static-pressure construction method according to claim 1, it is characterised in that: the depth of the cushion hole is PHC 1-1.2 times of tubular pole depth, the cushion hole include the upper section and the closely lower section two parts at bottom close to ground, on cushion hole The internal diameter of section is greater than the internal diameter of cushion hole lower section, and the depth of the cushion hole upper section is the 1/2-1/3 of cushion hole total depth.
3. PHC pipe pile static-pressure construction method according to claim 1, it is characterised in that: the position of the cushion hole is with group The central point in stake region is that the center of circle is circumferentially distributed.
4. PHC pipe pile static-pressure construction method according to claim 2, it is characterised in that: after the completion of the cushion hole is drilled with, The bottom hole filling diameter of cushion hole is greater than the coarse sand of 3.0mm by staff, is then placed drainpipe and is entered in cushion hole, makes to arrange The water inlet of water pipe is located on coarse sand, and continues to fill up the water inlet of coarse sand of the diameter greater than 1.0mm to no mistake drainpipe, aqueous Coarse sand diameter at layer is greater than 3.0mm, and drainpipe persistently draws water.
5. PHC pipe pile static-pressure construction method according to claim 4, it is characterised in that: in the cushion hole, filled with not With the coarse sands layer of diameter, each coarse sands layer inclination interaction is plane near the coarse sands layer upper surface of near surface in cushion hole.
6. PHC pipe pile static-pressure construction method according to claim 5, it is characterised in that: the coarse sands layer in the cushion hole It fills to the intersection for closing on cushion hole upper section and lower section, and there are 1m's between the coarse sands layer and cushion hole upper section on ground Gap, cushion hole are filled with metalling, and the upper surface of the metalling is higher than cushion hole lower end 1m.
7. PHC pipe pile static-pressure construction method according to claim 1, it is characterised in that: in final pressure operation process, when burying Final pressure value is 5000kN when pipe pile length is greater than 9m less than 16m, and palpus is fully loaded before termination piling presses three times again;When the pipe pile that buries is long Greater than 16m, it is less than 25m, final pressure value is 4000kN, is fully loaded with multiple pressure twice before terminating piling;It is greater than 25m when the pipe pile that buries is long, Final pressure value is 3700kN, is fully loaded with multiple pressure twice before terminating piling.
8. PHC pipe pile static-pressure construction method according to claim 1, it is characterised in that: during washing and cleaning operation, people first Work removes the mud of tubular pole bottom, is rinsed to tubular pole inner wall, after precipitating 3h, first takes out the water body on upper layer in tubular pole It takes, then extracts the slurry mixture of lower layer in tubular pole, slurry mixture is extracted by water pump, is evacuated to and is filled core depth Afterwards, stiff pat of cement is blocked;Brushing neat slurry on tubular pole inner wall.
9. PHC pipe pile static-pressure construction method according to claim 6, it is characterised in that: block in operation process, work people Member fills C40 slightly expanded concrete to cushion hole, and inserts to set by cement vibrating head and stir on metalling.
CN201910616402.7A 2019-07-09 2019-07-09 A kind of PHC pipe pile static-pressure construction method Pending CN110219301A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910616402.7A CN110219301A (en) 2019-07-09 2019-07-09 A kind of PHC pipe pile static-pressure construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910616402.7A CN110219301A (en) 2019-07-09 2019-07-09 A kind of PHC pipe pile static-pressure construction method

Publications (1)

Publication Number Publication Date
CN110219301A true CN110219301A (en) 2019-09-10

Family

ID=67812310

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910616402.7A Pending CN110219301A (en) 2019-07-09 2019-07-09 A kind of PHC pipe pile static-pressure construction method

Country Status (1)

Country Link
CN (1) CN110219301A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113668520A (en) * 2021-08-23 2021-11-19 广州东宇王建筑工程有限公司 PHC pipe pile static pressure construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101294393A (en) * 2007-04-29 2008-10-29 上海市第七建筑有限公司 Construction method with dewatering water well equipped outside of foundation pit
KR20110087175A (en) * 2010-01-25 2011-08-02 (주)씨엠파트너스건축사사무소 From first of all excavation reclamation methodof phc pickets will improve and the method will be able to the method
CN204940313U (en) * 2015-06-16 2016-01-06 乌海市公路工程有限公司 Pipe well points constructing structure is used in a kind of quicksand formation construction
CN205502044U (en) * 2016-03-22 2016-08-24 上海岩土工程勘察设计研究院有限公司 Be applied to precipitation structure in grittiness water -bearing stratum under building
CN206090597U (en) * 2016-09-28 2017-04-12 上海广联环境岩土工程股份有限公司 Haplopore multitube tubular well
CN208701650U (en) * 2018-05-31 2019-04-05 上海建工二建集团有限公司 A kind of anti-extrusion soil structure of PHC tube pile construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101294393A (en) * 2007-04-29 2008-10-29 上海市第七建筑有限公司 Construction method with dewatering water well equipped outside of foundation pit
KR20110087175A (en) * 2010-01-25 2011-08-02 (주)씨엠파트너스건축사사무소 From first of all excavation reclamation methodof phc pickets will improve and the method will be able to the method
CN204940313U (en) * 2015-06-16 2016-01-06 乌海市公路工程有限公司 Pipe well points constructing structure is used in a kind of quicksand formation construction
CN205502044U (en) * 2016-03-22 2016-08-24 上海岩土工程勘察设计研究院有限公司 Be applied to precipitation structure in grittiness water -bearing stratum under building
CN206090597U (en) * 2016-09-28 2017-04-12 上海广联环境岩土工程股份有限公司 Haplopore multitube tubular well
CN208701650U (en) * 2018-05-31 2019-04-05 上海建工二建集团有限公司 A kind of anti-extrusion soil structure of PHC tube pile construction

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘昌林: "PHC高强预应力管桩在城市密集地区的应用", 《西部探矿工程》 *
国家电网公司基建部组: "《国家电网公司输变电工程标准工艺》", 31 July 2012, 中国电力出版社 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113668520A (en) * 2021-08-23 2021-11-19 广州东宇王建筑工程有限公司 PHC pipe pile static pressure construction method

Similar Documents

Publication Publication Date Title
CN102277867B (en) Construction method for collapsible loess foundation
CN107524138B (en) Construction method of ultra-deep foundation pit underground diaphragm wall
CN102733376B (en) Composite pile and its construction method
CN102943466B (en) Construction method for miniature steel pipe concrete pile to penetrate through roadbed layer for reinforcing soft foundation construction
CN103821138B (en) The construction method of composite pile
CN108797587A (en) A kind of novel sinking construction technology of static pressed pile
CN102535263B (en) Roadbed having pile-net combination structure and construction method thereof
CN102011399B (en) PHC pile-based multiple high jet pedestal pile construction method
CN102720186B (en) Underwater once pouring method for variable cross-section bored cast-in-place pile
CN107299650B (en) A kind of remote open caisson casting method for correcting error
CN103184734A (en) Implanted and grouted compound pile and construction method
CN110469332B (en) Advanced support consolidation method for tunnel penetrating through debris flow accumulation body
CN106436788A (en) Foundation reinforcement and inclination correction method for friction piles of high-rise building
CN111456081A (en) Pile foundation retaining wall structure and construction method
CN203213101U (en) Embedding grouting combined pile
CN101942829B (en) Implantable corrosion-proof preformed pile for use in salt oil foundation and construction method thereof
CN110258512A (en) It constructs in a kind of basement rock the method for diaphram wall
CN110219301A (en) A kind of PHC pipe pile static-pressure construction method
CN104196488A (en) Underwater exploratory hole sealing technology
CN208996052U (en) The drilling tool of supporting construction and use that foundation pit anchor wall draws anchor supporting to be formed
CN206467656U (en) Simple soil nailing manual pore-forming's angle controller
CN210151776U (en) Structure of balance weight type retaining wall
CN108487226A (en) Multisection type composite bushing punching press sandy pile construction engineering method
CN107675700A (en) The construction method of diaphram wall
CN209538212U (en) A kind of anti-horizontal displacement radical combination soil-baffling structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190910