CN209538212U - A Radical Composite Retaining Structure Resisting Horizontal Displacement - Google Patents
A Radical Composite Retaining Structure Resisting Horizontal Displacement Download PDFInfo
- Publication number
- CN209538212U CN209538212U CN201822101778.8U CN201822101778U CN209538212U CN 209538212 U CN209538212 U CN 209538212U CN 201822101778 U CN201822101778 U CN 201822101778U CN 209538212 U CN209538212 U CN 209538212U
- Authority
- CN
- China
- Prior art keywords
- wall
- grouted anchor
- anchor bar
- horizontal displacement
- steel tube
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Description
技术领域technical field
本实用新型属于基础及支护结构技术领域,特别涉及一种抗水平位移根式组合挡土结构,阻止基础水平位移,主要应用于道路、水利、铁道、岩土工程工程之中。The utility model belongs to the technical field of foundation and support structures, in particular to a root-type combined soil retaining structure resistant to horizontal displacement, which prevents the horizontal displacement of the foundation, and is mainly used in roads, water conservancy, railways and geotechnical engineering projects.
背景技术Background technique
随着我国经济建设的快速发展,基础设施建设和投资规模日益增大,深基坑、高边坡、高填方场地不断出现,为了保证土体的稳定性,对挡土结构的要求越来越高。传统的重力式挡土结构广泛用于道路、水利、铁道、岩土等工程领域。在实际工程中,挡土结构失稳的主要模式为滑动失稳和倾覆失稳,而造成其失稳的主要原因就是挡土结构自身重力不足或是墙后土压力过大。传统的锚杆加固挡土结构,将加固锚杆沿水平方向或斜向插入填土内,往往面临成孔困难、注浆过程中易漏浆、锚固深度较深等问题。With the rapid development of my country's economic construction, the scale of infrastructure construction and investment is increasing day by day, and deep foundation pits, high slopes, and high filling sites are constantly appearing. In order to ensure the stability of the soil, the requirements for retaining structures are increasing. higher. Traditional gravity retaining structures are widely used in road, water conservancy, railway, geotechnical and other engineering fields. In actual engineering, the main modes of retaining structure instability are sliding instability and overturning instability, and the main reasons for the instability are insufficient gravity of the retaining structure itself or excessive earth pressure behind the wall. In the traditional anchor bolt reinforced soil retaining structure, the reinforced anchor bolt is inserted into the filling soil along the horizontal direction or obliquely, which often faces problems such as difficulty in hole formation, easy grout leakage during the grouting process, and deep anchorage depth.
发明内容Contents of the invention
本实用新型在于提供一种抗水平位移根式组合挡土结构,在保证自身支护能力的同时阻止挡土结构水平位移,减少了挡土结构的工程造价、占地空间;为达到上述目的所采取的技术方案是:The utility model is to provide an anti-horizontal displacement root-type composite retaining structure, which prevents the horizontal displacement of the retaining structure while ensuring its own supporting capacity, and reduces the engineering cost and occupied space of the retaining structure; adopted in order to achieve the above purpose The technical solution is:
一种抗水平位移根式组合挡土结构,包括墙体、基底、多个注浆锚杆和多个钢管混凝土锚桩,所述墙体浇筑坐落在基底上,所述多个注浆锚杆沿着墙体纵向方向等间距分布在基座底部,所述注浆锚杆与墙体的墙踵位置相对应,且注浆锚杆竖向插入下部原地稳定基岩,注浆锚杆顶部与基座浇筑连接;所述多个钢管混凝土锚桩沿着墙体纵向方向等间距分布在基座底部,所述钢管混凝土锚桩与墙体的墙趾位置相对应,且钢管混凝土锚桩竖向设置。A root-type combined soil retaining structure resistant to horizontal displacement, including a wall, a base, multiple grouted anchors and multiple concrete-filled steel pipe anchor piles, the wall is poured on the base, and the multiple grouted anchors are placed along the The longitudinal direction of the wall is equally spaced at the bottom of the base, the grouting anchors correspond to the wall heels, and the grouting anchors are vertically inserted into the lower in-situ stable bedrock, and the tops of the grouting anchors are The base is poured and connected; the plurality of steel pipe concrete anchor piles are equally spaced at the bottom of the base along the longitudinal direction of the wall, the steel pipe concrete anchor piles correspond to the wall toe position of the wall, and the steel pipe concrete anchor piles are vertically set up.
优选的,所述基底为钢筋混凝土结构,墙体与基底一体成型制作。Preferably, the base is a reinforced concrete structure, and the wall and the base are integrally formed.
优选的,所述注浆锚杆和钢管混凝土锚桩均与基底垂直设置。Preferably, both the grouted anchor rod and the steel pipe concrete anchor pile are arranged vertically to the base.
优选的,所述注浆锚杆为金属锚杆、纤维锚杆或者预应力锚杆。Preferably, the grouting anchor is a metal anchor, a fiber anchor or a prestressed anchor.
优选的,所述注浆锚杆的锚固段灌浆体采用水泥浆或者水泥砂浆胶结材料,抗压强度不低于40MPa。Preferably, the grouting body of the anchoring section of the grouting anchor adopts cement slurry or cement mortar cementing material, and the compressive strength is not lower than 40 MPa.
优选的,所述相邻两个注浆锚杆之间的间距为150-300cm;所述相邻两个钢管混凝土锚桩之间的间距为150-300cm。Preferably, the distance between the two adjacent grouting anchors is 150-300cm; the distance between the two adjacent concrete-filled steel pipe anchor piles is 150-300cm.
优选的,所述注浆锚杆的直径为16-25mm, 注浆锚杆的长度2000-15000mm。Preferably, the diameter of the grouting anchor is 16-25mm, and the length of the grouting anchor is 2000-15000mm.
优选的,所述钢管混凝土锚桩的直径为100-250mm, 钢管混凝土锚桩的度5000-15000mm。Preferably, the diameter of the steel pipe concrete anchor pile is 100-250mm, and the thickness of the steel pipe concrete anchor pile is 5000-15000mm.
本实用新型所具有的有益效果为:在注浆锚杆和钢管混凝土锚桩的共同作用下,基础墙体结构尺寸得到优化,降低了重力式墙体地基要求,扩大了其使用范围,降低了工程成本。The utility model has the beneficial effects that: under the joint action of the grouting anchor rod and the steel pipe concrete anchor pile, the structural size of the foundation wall is optimized, the requirements for the gravity wall foundation are reduced, its application range is expanded, and the engineering cost.
另一方面,将注浆锚杆对应设置在墙踵位置处,利用注浆锚杆的拉力作用增加了体系抗水平位移及抗倾覆能力;将钢管混凝土锚桩对应设置在墙趾位置处,阻止了墙体的水平位移,提高了体系抗滑移能力。On the other hand, the grouting anchors are set at the wall heels, and the tensile force of the grouting anchors is used to increase the horizontal displacement and anti-overturning capabilities of the system; the steel pipe concrete anchors are set at the wall toes to prevent The horizontal displacement of the wall is reduced, and the anti-slip capability of the system is improved.
附图说明Description of drawings
图1为本实用新型的结构示意图。Fig. 1 is the structural representation of the utility model.
具体实施方式Detailed ways
下面结合附图对本实用新型进一步描述。Below in conjunction with accompanying drawing, the utility model is further described.
如图1所示,一种抗水平位移根式组合挡土结构,包括墙体5、基底10、多个注浆锚杆11和多个钢管混凝土锚桩1,所述墙体5浇筑坐落在基底8上,其中,墙体5包括墙面4、墙顶6、墙背7、墙底8、墙趾3和墙踵9,所述多个注浆锚杆11沿着墙体5纵向方向等间距分布在基座10底部,所述注浆锚杆11与墙体5的墙踵9位置相对应,且注浆锚杆11竖向插入下部原地稳定基岩,注浆锚杆11顶部与基座10浇筑连接;所述多个钢管混凝土锚桩1沿着墙体5纵向方向等间距分布在基座10底部,所述钢管混凝土锚桩1与墙体5的墙趾3位置相对应,且钢管混凝土锚桩竖1向设置;所述注浆锚杆11和钢管混凝土锚桩1均与基底10垂直设置。As shown in Figure 1, a root-type composite retaining structure resistant to horizontal displacement includes a wall 5, a base 10, a plurality of grouting anchors 11 and a plurality of steel pipe concrete anchor piles 1, and the wall 5 is poured and located on the base 8, wherein the wall 5 includes a wall surface 4, a wall top 6, a wall back 7, a wall bottom 8, a wall toe 3 and a wall heel 9, and the plurality of grouting anchor rods 11 are along the longitudinal direction of the wall 5, etc. The spacing is distributed at the bottom of the base 10, the position of the grouting anchor 11 corresponds to the wall heel 9 of the wall 5, and the grouting anchor 11 is vertically inserted into the lower in-situ stable bedrock, and the top of the grouting anchor 11 is connected to the The base 10 is poured and connected; the plurality of steel pipe concrete anchor piles 1 are equally spaced along the longitudinal direction of the wall 5 at the bottom of the base 10, and the steel pipe concrete anchor piles 1 correspond to the positions of the wall toes 3 of the wall 5, And the concrete-filled steel pipe anchor pile is arranged vertically; the grouted anchor rod 11 and the concrete-filled steel pipe anchor pile 1 are both vertically arranged with the base 10 .
其中,所述基底10为钢筋混凝土结构,墙体5与基底10一体成型制作;注浆锚杆11采用金属锚杆、纤维锚杆或者预应力锚杆均可以,同时,注浆锚杆11的锚固段灌浆体12采用水泥浆或者水泥砂浆胶结材料,抗压强度不低于40MPa,从而在减少打孔数量的的同时还满足了支撑要求。Wherein, the base 10 is a reinforced concrete structure, and the body of wall 5 and the base 10 are integrally formed; the grouting anchor 11 can be a metal anchor, a fiber anchor or a prestressed anchor, and at the same time, the grouting anchor 11 The grouting body 12 of the anchoring section adopts cement slurry or cement mortar cementing material, and the compressive strength is not less than 40MPa, thereby meeting the supporting requirements while reducing the number of perforated holes.
根据实际计算,优选的,所述相邻两个注浆锚杆11之间的间距为150-300cm;所述注浆锚杆11的直径为16-25mm, 注浆锚杆11的长度2000-15000mm。所述相邻两个钢管混凝土锚桩1之间的间距为150-300cm,所述钢管混凝土锚桩1的直径为100-250mm, 钢管混凝土锚桩1的度5000-15000mm。According to actual calculation, preferably, the distance between the two adjacent grouting anchors 11 is 150-300cm; the diameter of the grouting anchors 11 is 16-25mm, and the length of the grouting anchors 11 is 2000- 15000mm. The distance between the two adjacent concrete-filled steel pipe anchor piles 1 is 150-300cm, the diameter of the concrete-filled steel pipe anchor piles 1 is 100-250mm, and the thickness of the concrete-filled steel pipe anchor piles 1 is 5000-15000mm.
本实用新型的施工方法步骤为:Construction method steps of the present utility model are:
A:根据墙背7一侧土压力大小,确定墙体5的高度、截面尺寸;A: According to the earth pressure on the side of the wall back 7, determine the height and section size of the wall 5;
B:然后根据工程设计用测量仪器进行放线,并用测量仪器定位施工基底10的槽段位置;B: Then according to the engineering design, use the measuring instrument to set out the wire, and use the measuring instrument to locate the position of the groove section of the construction base 10;
C:在槽段位置上基底10的设计位置处进行开挖槽段,在槽段内用测量仪器确定注浆锚杆11和钢管混凝土锚桩1的位置;C: Excavate the groove section at the design position of the base 10 on the location of the groove section, and use a measuring instrument to determine the positions of the grouting anchor rod 11 and the steel pipe concrete anchor pile 1 in the groove section;
D:在槽段内注浆锚杆11的位置处使用钻孔机进行钻孔施工,然后将注浆锚杆11至于孔内,并灌入灌浆体12形成锚固段;同时将钢管混凝土锚桩1压入设计位置处;D: Use a drilling machine to drill holes at the position of the grouting anchor rod 11 in the groove section, then place the grouting anchor rod 11 in the hole, and pour it into the grouting body 12 to form an anchoring section; at the same time, place the steel pipe concrete anchor pile 1 Press into the design position;
E:待注浆锚杆11和钢管混凝土锚桩1全部施工完成后7~10天进行锚杆的张拉并锁定;E: After the grouting anchor 11 and the steel pipe concrete anchor pile 1 are all constructed, tension and lock the anchor 7 to 10 days;
F:绑扎基底10的钢筋并立模,并将注浆锚杆11顶部、钢管混凝土锚桩1顶部均与基底10的钢筋焊接牢固,然后浇筑混凝土形成基底10;F: Bind the steel bars of the base 10 and form the formwork, weld the top of the grouted anchor rod 11 and the top of the steel pipe concrete anchor pile 1 to the steel bars of the base 10 firmly, and then pour concrete to form the base 10;
G:在基底10上浇筑混凝土形成墙体5,待墙体5混凝土达到设计强度要求后,在基底10上进行土方回填即可。G: Concrete is poured on the base 10 to form the wall 5. After the concrete of the wall 5 reaches the design strength requirement, earthwork backfilling on the base 10 is sufficient.
最后应说明的是:以上实施例仅用以说明本实用新型的技术方案,而非对其限制;尽管参照前述实施例对本实用新型进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换,但这些修改或者替换,并不使相应技术方案的本质脱离本实用新型各实施例技术方案的精神和范围。Finally, it should be noted that: the above embodiments are only used to illustrate the technical solutions of the present utility model, and are not intended to limit it; although the utility model has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: It is still possible to modify the technical solutions described in the foregoing embodiments, or perform equivalent replacements for some of the technical features, but these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit of the technical solutions of the various embodiments of the present invention and range.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201822101778.8U CN209538212U (en) | 2018-12-14 | 2018-12-14 | A Radical Composite Retaining Structure Resisting Horizontal Displacement |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201822101778.8U CN209538212U (en) | 2018-12-14 | 2018-12-14 | A Radical Composite Retaining Structure Resisting Horizontal Displacement |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN209538212U true CN209538212U (en) | 2019-10-25 |
Family
ID=68264428
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201822101778.8U Expired - Fee Related CN209538212U (en) | 2018-12-14 | 2018-12-14 | A Radical Composite Retaining Structure Resisting Horizontal Displacement |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN209538212U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113431083A (en) * | 2021-06-10 | 2021-09-24 | 中南勘察设计院集团有限公司 | Light supporting structure of pile foundation joist and construction method thereof |
-
2018
- 2018-12-14 CN CN201822101778.8U patent/CN209538212U/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113431083A (en) * | 2021-06-10 | 2021-09-24 | 中南勘察设计院集团有限公司 | Light supporting structure of pile foundation joist and construction method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105840207B (en) | Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body | |
| CN104264688B (en) | Manually digging hole non-uniform pile support construction process | |
| CN203741868U (en) | Reinforced concrete retaining wall structure with combined anchor wire | |
| CN104631440B (en) | A kind of existing large-section in-situ concrete pile strength core increases foundation pit supporting construction and constructional method | |
| CN106522270A (en) | Pile foundation and retaining wall anti-earthquake retaining structure comprising EPS buffer layers and construction method | |
| CN102926400B (en) | Combined earth retaining wall structure and construction method thereof | |
| WO2021004007A1 (en) | Foundation reinforcement method for conventional building | |
| CN110777836A (en) | Reinforced concrete plate-anchor rod composite foundation and using method thereof | |
| CN112095656A (en) | A tension-compression composite prestressed anchor cable retaining wall structure | |
| CN102561377A (en) | Seismic-resistant-columned rock bolt foundation with enlarged toe and construction method of seismic-resistant-columned rock bolt foundation with enlarged toe | |
| CN202323970U (en) | Combined reinforcement system for side slope | |
| CN107964980A (en) | Lattice counterfort wall and construction method with earth anchor | |
| CN104196014A (en) | Combined rock-embedded anchor cable slide-resistant pile where round steel is implanted and construction method thereof | |
| CN211200426U (en) | Anti-sliding supporting and retaining structure for miniature steel pipe pile retaining wall | |
| CN107100179A (en) | Light-duty combination retaining structure and the method for administering a wide range of tall earth fill engineering | |
| CN109610473A (en) | A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration | |
| CN108824412B (en) | Soft foundation treatment method based on gabion wall reinforced soil and dynamic compaction | |
| CN210194711U (en) | A pile foundation settlement reinforcement jacking and leveling structure | |
| CN208996052U (en) | The drilling tool of supporting construction and use that foundation pit anchor wall draws anchor supporting to be formed | |
| CN108914947A (en) | Foundation pit anchor wall draws the construction method of anchor supporting and its supporting construction of drilling tool and formation | |
| CN204941565U (en) | A kind of novel tunnel inverted arch structure | |
| CN207484290U (en) | Super large diameter hollow pile group anchorage | |
| CN206625207U (en) | A kind of collapsible loess foundation rubble frame structure reinforcement system | |
| CN114482013A (en) | A suspension type rock-socketed composite pile structure of a prefabricated pile with expansion and introduction hole and its construction method | |
| CN110805049B (en) | Construction method of mountain slope ultra-thickness spray anchor permanent supporting structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191025 Termination date: 20201214 |