CN110217734A - 液压提升施工工艺 - Google Patents
液压提升施工工艺 Download PDFInfo
- Publication number
- CN110217734A CN110217734A CN201910525666.1A CN201910525666A CN110217734A CN 110217734 A CN110217734 A CN 110217734A CN 201910525666 A CN201910525666 A CN 201910525666A CN 110217734 A CN110217734 A CN 110217734A
- Authority
- CN
- China
- Prior art keywords
- inner cylinder
- steel inner
- group
- decline
- promoted
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66F—HOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
- B66F11/00—Lifting devices specially adapted for particular uses not otherwise provided for
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Geology (AREA)
- Mechanical Engineering (AREA)
- Structural Engineering (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
本发明实施例公开了一种液压提升施工工艺,包括以下步骤:第一组钢内筒组装;提升梁下降、提升支座焊接;第一组钢内筒提升、下一组钢内筒提升单元组装、分段提升到位;钢筒下降,使筒体落到临时支撑底座上;切除第一组钢内筒的支座;提升梁下降;下一组钢内筒的提升支座焊接;继续实施下一组钢内筒提升;依此循环直至施工结束,本发明通过更改现有的提升顺序,将多组钢内筒分别组装和提升,单次提升重量较轻,经过多次提升后,实现提升整个的钢内筒。
Description
技术领域
本发明涉及钛钢复合板安装领域,尤其涉及一种液压提升施工工艺。
背景技术
热电厂的烟囱钢内筒材料大部分为普通碳钢,安装时用液压油缸内部提升的方式进行,由于液压提升部件需要与内筒接触,因此该液压内部提升的方式可能会对烟囱内表面造成损伤。部分钢内筒开始使用钛钢复合钢板材料,如授权公告号为CN202766206U公开一种烟囱钢内筒液压提升施工工艺,该装置位于烟囱钢内筒的外部,包括液压支架和位于液压支架上的液压千斤顶,液压千斤顶包括液压油缸,液压提升施工工艺还包括连接部分,连接部分包括提升杆,提升杆穿过液压千斤顶,提升杆下端与烟囱钢内筒的外部抱箍连接在一起,连接部分还包括能卡紧提升杆的上卡头和下卡头,由于超高钢内筒高度超过200m,施工效率低,现有的施工工艺成本高,危险性高。
发明内容
针对上述存在的问题,本发明实施例公开了一种液压提升施工工艺,可提升较大重量的钢内筒,同时大大提升了钢内筒的安装效率。
本发明实施例公开了一种液压提升施工工艺,液压提升施工工艺,包括以下步骤:
步骤一:第一组钢内筒组装;
步骤二:提升梁下降、提升支座焊接;
步骤三:第一组钢内筒提升、下一组钢内筒提升单元组装、分段提升到位;
步骤四:钢筒下降,使筒体落到临时支撑底座上;
步骤五:切除第一组钢内筒的支座;
步骤六:提升梁下降;
步骤七:下一组钢内筒的提升支座焊接;
步骤八:继续实施下一组钢内筒提升;
步骤九:依此循环直至施工结束。
在步骤一中,钢内筒在立柱的底部组装。
在步骤二中,提升梁需要下降时,利用三个10t电动葫芦拉住圈梁,将上下卡头手动松开,慢慢将圈梁下降至下一阶段施工位。
在步骤四中,依靠液压系统的提升逆向操作,使钢内筒落至底座上,检查落定可靠后,切除第一组提升支座,同时提升梁下降,焊接下一组提升支座,施工过程中,实时监测钢内筒的中心线及垂直度,及时纠偏,确保提升安全。
本发明具有如下优点:
本发明通过更改现有的提升顺序,将多组钢内筒分别组装和提升,单次提升重量较轻,经过多次提升后,实现提升整个的钢内筒。
附图说明
通过阅读参照以下附图对非限制性实施例所作的详细描述,本发明及其特征、外形和优点将会变得更加明显。在全部附图中相同的标记指示相同的部分。并未可以按照比例绘制附图,重点在于示出本发明的主旨。
图1是本发明实施例示意图。
具体实施方式
下面结合附图和具体的实施例对本发明中的结构作进一步的说明,但是不作为本发明的限定。
如图1所示,本发明实施例公开了一种液压提升施工工艺,液压提升施工工艺,包括以下步骤:
步骤一:第一组钢内筒组装;
步骤二:提升梁下降、提升支座焊接;
步骤三:第一组钢内筒提升、下一组钢内筒提升单元组装、分段提升到位;
步骤四:钢筒下降,使筒体落到临时支撑底座上;
步骤五:切除第一组钢内筒的支座;
步骤六:提升梁下降;
步骤七:下一组钢内筒的提升支座焊接;
步骤八:继续实施下一组钢内筒提升;
步骤九:依此循环直至施工结束。
在本发明一实施例中,在步骤一中,钢内筒在立柱的底部组装。
在本发明一实施例中,在步骤二中,提升梁需要下降时,利用三个10t电动葫芦拉住圈梁,将上下卡头手动松开,慢慢将圈梁下降至下一阶段施工位。
在本发明一实施例中,在步骤四中,依靠液压系统的提升逆向操作,使钢内筒落至底座上,检查落定可靠后,切除第一组提升支座,同时提升梁下降,焊接下一组提升支座,施工过程中,实时监测钢内筒的中心线及垂直度,及时纠偏,确保提升安全。
以上对本发明的较佳实施例进行了描述。需要理解的是,本发明并不局限于上述特定实施方式,其中未尽详细描述的设备和结构应该理解为用本领域中的普通方式予以实施;任何熟悉本领域的技术人员,在不脱离本发明技术方案范围情况下,都可利用上述揭示的方法和技术内容对本发明技术方案做出许多可能的变动和修饰,或修改为等同变化的等效实施例,这并不影响本发明的实质内容。因此,凡是未脱离本发明技术方案的内容,依据本发明的技术实质对以上实施例所做的任何简单修改、等同变化及修饰,均仍属于本发明技术方案保护的范围内。
Claims (4)
1.液压提升施工工艺,其特征在于,包括以下步骤:
步骤一:第一组钢内筒组装;
步骤二:提升梁下降、提升支座焊接;
步骤三:第一组钢内筒提升、下一组钢内筒提升单元组装、分段提升到位;
步骤四:钢筒下降,使筒体落到临时支撑底座上;
步骤五:切除第一组钢内筒的支座;
步骤六:提升梁下降;
步骤七:下一组钢内筒的提升支座焊接;
步骤八:继续实施下一组钢内筒提升;
步骤九:依此循环直至施工结束。
2.如权利要求1所述的液压提升施工工艺,其特征在于,在步骤一中,钢内筒在立柱的底部组装。
3.如权利要求1所述的液压提升施工工艺,其特征在于,在步骤二中,提升梁需要下降时,利用三个10t电动葫芦拉住圈梁,将上下卡头手动松开,慢慢将圈梁下降至下一阶段施工位。
4.如权利要求1所述的液压提升施工工艺,其特征在于,在步骤四中,依靠液压系统的提升逆向操作,使钢内筒落至底座上,检查落定可靠后,切除第一组提升支座,同时提升梁下降,焊接下一组提升支座,施工过程中,实时监测钢内筒的中心线及垂直度,及时纠偏,确保提升安全。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910525666.1A CN110217734A (zh) | 2019-06-18 | 2019-06-18 | 液压提升施工工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910525666.1A CN110217734A (zh) | 2019-06-18 | 2019-06-18 | 液压提升施工工艺 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110217734A true CN110217734A (zh) | 2019-09-10 |
Family
ID=67817592
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910525666.1A Pending CN110217734A (zh) | 2019-06-18 | 2019-06-18 | 液压提升施工工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110217734A (zh) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2587393A1 (fr) * | 1985-09-17 | 1987-03-20 | Morel Roger | Procede et dispositif de construction de cheminees en beton arme |
CN103243961A (zh) * | 2013-03-15 | 2013-08-14 | 东北电业管理局烟塔工程公司 | 火力发电厂烟囱钛板钢内筒倒装施工装置 |
CN104563590A (zh) * | 2015-01-16 | 2015-04-29 | 江西建工第二建筑有限责任公司 | 烟囱钢内筒液压提升施工装置及其方法 |
CN204418784U (zh) * | 2015-01-16 | 2015-06-24 | 江西建工第二建筑有限责任公司 | 烟囱钢内筒液压提升施工装置 |
CN204960473U (zh) * | 2015-09-01 | 2016-01-13 | 山东电力建设第一工程公司 | 一种钢内筒液压顶升装置 |
-
2019
- 2019-06-18 CN CN201910525666.1A patent/CN110217734A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2587393A1 (fr) * | 1985-09-17 | 1987-03-20 | Morel Roger | Procede et dispositif de construction de cheminees en beton arme |
CN103243961A (zh) * | 2013-03-15 | 2013-08-14 | 东北电业管理局烟塔工程公司 | 火力发电厂烟囱钛板钢内筒倒装施工装置 |
CN104563590A (zh) * | 2015-01-16 | 2015-04-29 | 江西建工第二建筑有限责任公司 | 烟囱钢内筒液压提升施工装置及其方法 |
CN204418784U (zh) * | 2015-01-16 | 2015-06-24 | 江西建工第二建筑有限责任公司 | 烟囱钢内筒液压提升施工装置 |
CN204960473U (zh) * | 2015-09-01 | 2016-01-13 | 山东电力建设第一工程公司 | 一种钢内筒液压顶升装置 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1668244B1 (en) | Equipment for mounting on the hub of a wind turbine and method of conducting service on a wind turbine using such equipment | |
CN102184747B (zh) | 一种模块化钢制安全壳环吊梁及其组装方法 | |
CN108868193A (zh) | 钢结构建筑逆向拆除的施工方法 | |
EP2305840A1 (en) | Method for constructing and repairing body of blast furnace | |
CN102500660A (zh) | 一种长细弦梁结构的整体矫正装置及矫正方法 | |
CN202894651U (zh) | 圆锥台形壳体构件组对胎具 | |
CN110217734A (zh) | 液压提升施工工艺 | |
CN102496771B (zh) | 大型钢结构天线的安装方法及装置 | |
CN105339555A (zh) | 由塔和单桩组成的组件 | |
CN102494536B (zh) | 烧结室降尘管施工方法 | |
CN106544959A (zh) | 含有鞍座的主塔吊装节段及桥梁主塔鞍座的施工方法 | |
KR102176840B1 (ko) | 발전소 연돌내부 연통구조물의 모듈화 시공방법 | |
CN214883609U (zh) | 钢管桩连接桩帽 | |
CN208165235U (zh) | 一种风帆骨架与升降系统的连接装置 | |
CN207057378U (zh) | 一种便于清理废料的角钢冲孔用冲床 | |
CN109972846A (zh) | 一种针对钢圆筒倒装顶升施工的胎架及其施工方法 | |
CN212316694U (zh) | 一种用于桥梁施工的支架 | |
CN107419671A (zh) | 一种钢桁梁下弦杆的修复方法 | |
CN210703369U (zh) | 一种分块式钢管环焊接工装 | |
CN202534957U (zh) | 用于变压器线圈检修的纸筒拆装工装 | |
CN212761739U (zh) | 激光切割支撑平台 | |
CN216380718U (zh) | 一体化定型马镫钢支撑结构 | |
CN101701498A (zh) | 一种跨越既有铁路线钢管套接防护棚施工方法 | |
CN205932911U (zh) | 火力发电烟风管道组合用快速吊装装置 | |
CN115573578A (zh) | 一种移动式吊装平台及其使用方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190910 |
|
RJ01 | Rejection of invention patent application after publication |