CN110216788A - A kind of Intelligentized control method of bridge subsection precasting yard - Google Patents
A kind of Intelligentized control method of bridge subsection precasting yard Download PDFInfo
- Publication number
- CN110216788A CN110216788A CN201910634126.7A CN201910634126A CN110216788A CN 110216788 A CN110216788 A CN 110216788A CN 201910634126 A CN201910634126 A CN 201910634126A CN 110216788 A CN110216788 A CN 110216788A
- Authority
- CN
- China
- Prior art keywords
- information
- terminal
- bridge subsection
- construction
- bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 40
- 238000010276 construction Methods 0.000 claims abstract description 82
- 238000013523 data management Methods 0.000 claims abstract description 12
- 238000012986 modification Methods 0.000 claims abstract description 6
- 230000004048 modification Effects 0.000 claims abstract description 6
- 230000005540 biological transmission Effects 0.000 claims abstract description 5
- 238000012795 verification Methods 0.000 claims abstract description 3
- 230000008569 process Effects 0.000 claims description 12
- 238000013461 design Methods 0.000 claims description 11
- 230000002787 reinforcement Effects 0.000 claims description 6
- 238000012790 confirmation Methods 0.000 claims description 5
- 238000012545 processing Methods 0.000 claims description 5
- 238000012552 review Methods 0.000 claims description 5
- 229910000831 Steel Inorganic materials 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims description 3
- 239000010959 steel Substances 0.000 claims description 3
- 238000009826 distribution Methods 0.000 claims description 2
- 238000003860 storage Methods 0.000 claims description 2
- 238000012360 testing method Methods 0.000 claims 1
- 238000007726 management method Methods 0.000 abstract description 8
- 238000004519 manufacturing process Methods 0.000 description 21
- 238000005516 engineering process Methods 0.000 description 10
- 238000009417 prefabrication Methods 0.000 description 7
- 230000008859 change Effects 0.000 description 5
- 238000004458 analytical method Methods 0.000 description 3
- 230000003014 reinforcing effect Effects 0.000 description 3
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 2
- 238000004364 calculation method Methods 0.000 description 2
- 230000015271 coagulation Effects 0.000 description 2
- 238000005345 coagulation Methods 0.000 description 2
- 239000004035 construction material Substances 0.000 description 2
- 238000001514 detection method Methods 0.000 description 2
- 239000002994 raw material Substances 0.000 description 2
- 238000012800 visualization Methods 0.000 description 2
- 238000012550 audit Methods 0.000 description 1
- 238000013475 authorization Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000013070 change management Methods 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000009430 construction management Methods 0.000 description 1
- 238000005314 correlation function Methods 0.000 description 1
- 235000013399 edible fruits Nutrition 0.000 description 1
- 238000011156 evaluation Methods 0.000 description 1
- 239000012634 fragment Substances 0.000 description 1
- 238000002513 implantation Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 230000010365 information processing Effects 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000008521 reorganization Effects 0.000 description 1
- 230000008054 signal transmission Effects 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 230000007704 transition Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B15/00—General arrangement or layout of plant ; Industrial outlines or plant installations
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B17/00—Details of, or accessories for, apparatus for shaping the material; Auxiliary measures taken in connection with such shaping
- B28B17/0063—Control arrangements
- B28B17/0081—Process control
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06312—Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
- G06T17/10—Constructive solid geometry [CSG] using solid primitives, e.g. cylinders, cubes
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Economics (AREA)
- General Physics & Mathematics (AREA)
- Strategic Management (AREA)
- Mechanical Engineering (AREA)
- Geometry (AREA)
- Ceramic Engineering (AREA)
- Entrepreneurship & Innovation (AREA)
- Marketing (AREA)
- General Business, Economics & Management (AREA)
- Chemical & Material Sciences (AREA)
- Tourism & Hospitality (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Game Theory and Decision Science (AREA)
- Educational Administration (AREA)
- Development Economics (AREA)
- Computer Graphics (AREA)
- Software Systems (AREA)
- Automation & Control Theory (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of Intelligentized control methods of bridge subsection precasting yard, comprise the steps that the model that bridge subsection precasting yard is established in BIM data management platform;According to the division of labor difference of staff in precasting yard, terminal device is divided into the first terminal that project manager uses and the second terminal that site operation personnel use;Site operation personnel upload information corresponding to completed project under construction to background server by second terminal, and the information received is compared in background server;If comparison result has exceeded the error range of permission, to pending instructions such as first terminal transmissions;First terminal carries out manual examination and verification to the information, if project manager thinks that information meets the requirements, it can then be sent to second terminal by checking and accepting instruction, if project manager thinks that the information is undesirable, modification can be sent to second terminal by first terminal.The present invention can carry out intelligent and precise management to bridge construction project.
Description
Technical field
It is prefabricated more particularly to a kind of bridge subsection the present invention relates to a kind of intelligent production line control method of precasting yard
The intelligent production method of field.
Background technique
Bridge prefabrication mounting technology is that the high-end construction technique of bridge industry and High-Speed Railway Bridge Construction move towards industry
Change, the most direct effective mode of greenization.But compared to traditional bridge construction mode, bridge prefabrication mounting technology is to pre-
The control management of the key links such as field construction processed, work progress, assembling proposes high requirement, relies solely on artificial pipe
Reason mode and conventional information technology, not can guarantee the high-precision control of prefabrication and assembly construction technical requirements, can not give full play to pre-
The efficiency of mounting technology processed.
In recent years, as Building Information Model (Building Information Modelling, BIM) technology is prefabricated
Extensive use in mounting technology field, prefabrication and assembly construction technology start from traditional manual, extensiveization gradually to industrialization, essence
Trueization and standardized direction transition.BIM technology is collected by establishing digital model to project structures using computer technology
At the engineering information, including physical message, geological information, assembly information etc. in each stage in building life cycle, finally
It is proposed feasible solution in the PC component Deepen Design stage, for example, the Project design stage carry out different schemes ratio choosing,
Collision detection and building performance detection etc., Projects during Construction Stage carries out construction Deepen Design, three-dimensional visualization is told somebody what one's real intentions are, is constructed
Program simulation, quantities calculation and application of bidding stage etc., and space management, Assets Reorganization Taking are carried out in the project O&M stage
Reason and plant maintenance etc..
The case in the more flow line production that BIM technology is applied to precasting yard is had existed in the prior art,
But in actual production process, existing precasting yard intelligence degree is also unable to satisfy assembly line also in reduced levels
The construction management requirement of specific link in operation, and the level of informatization between each process is lower, and staff applies project
Work information is grasped not comprehensive, progress and is reported and submitted not in time, and construction material can not supply on demand, caused construction delay.
Summary of the invention
The technical problems such as intelligent production level to solve bridge subsection precasting yard existing in the prior art is relatively low, this
Invention proposes that one kind can visualize project under construction, is intelligent, is accurate for bridge subsection in each stage of construction
Change a kind of Intelligentized control method of bridge subsection precasting yard of management
A kind of Intelligentized control method of bridge subsection precasting yard, the Intelligentized control method are by BIM data pipe
Platform carries out visualized management to the prefabrication process of bridge subsection, which is characterized in that has specifically included following steps:
S1. the model of bridge subsection precasting yard is established in BIM data management platform, it is defeated according to the needs of bridge erection
Enter the order information of precast segmental beam;
S2. according to the division of labor difference of staff in precasting yard, terminal device is divided into that project manager uses
The second terminal that one terminal and site operation personnel use, the first terminal have be different from the second terminal to backstage
The permission of the final review of the unqualified information of server feedback;
S3. site operation personnel are after the project under construction for completing distribution, by the second terminal to the background service
Device uploads information corresponding to completed project under construction, and the background server is in the letter for receiving the second terminal transmission
After breath, which is compared;If comparison result is identical or within error range, the background server is to described second
Terminal is sent by checking and accepting instruction, if comparison result has exceeded the error range of permission, the background server is to described the
The pending instructions such as one terminal transmission;
S4. the first terminal is uploaded to the backstage to the second terminal and takes after the pending instruction such as receiving
The information of business device carries out manual examination and verification, if auditing result meets the requirements, is sent and is led to the second terminal by first terminal
Examination instruction is crossed, if auditing result is undesirable, modification is sent to the second terminal by the first terminal;
S5. the second terminal is updated really the construction information of bridge subsection after receiving by checking and accepting instruction
Recognize, and the construction information updated after confirming is uploaded to the background server;The second terminal is receiving modification
Afterwards, do not have the permission that confirmation is updated to the construction information of bridge subsection temporarily.
Further, the S2 is further comprised, pre-buried to bridge subsection progress chip, and chip is fitted into lamp cap box, and
It is connect with fixing piece with steel reinforcement cage, is implanted into the product information for storing corresponding bridge subsection in the chip of bridge subsection, institute
Stating product information includes that the number of bridge subsection, structure size information, arrangement of reinforcement information, installation of embedded parts information and concrete pour
Build information.
Further, the construction information of corresponding bridge subsection is also stored in the chip, the construction information includes
The initial time of process and end time, construction location, construction personnel's information and construction task performance, site operation personnel
Product information and construction information in bridge subsection chip are read by the second terminal, and can be to the construction task
Performance is updated confirmation.
Further, in the S3, the information includes text information and image information, and the text information includes
The personal information of project under construction is completed, the beginning and ending time of project under construction, design value is poured and pours actual value.
Further, it is described image information that the background server, which receives the information that the second terminal is sent, after
The message processing module of platform server includes at least the treatment process of described image information: described image information is converted to
Structural model under three-dimensional system of coordinate, by will respectively indicate coordinate unit information a little and BIM data management in the structural model
The coordinate unit information of each mark point in platform in established design structure model is compared, if coordinate unit information ratio
Pair result match each other within error range, then be judged as by check and accept, if the result of coordinate unit information comparison exceeds
Error range is then judged as etc. pending.
Further, the chip is RFID chip, using ultra-high frequency RFID label.
Further, further comprise in the S3: the second terminal can read the position mark in bridge subsection chip
Show the location information in module, and the location information is uploaded to the background server, the background server is to described
Location information is saved, when there is second terminal to be read out the location mark module in bridge subsection chip again, institute
The location information of bridge subsection of second terminal upload can be received again by by stating background server, and the background server is to bridge section
The location information of section is updated.
Further, it further comprises: including signal emission module in S6. bridge subsection chip, be arranged on portal jib crane
There is the signal receiving module being mutually matched with the signal emission module, when the signal receiving module on the portal jib crane
After completing to the accurate positioning of the bridge subsection, the portal jib crane begins to bale handle operation, completes the transport of bridge subsection
With storage.
Beneficial effects of the present invention:
1. difference of the present invention according to the function of each staff in precasting yard, is divided into project manager for terminal device
The second terminal that the first terminal and site operation personnel used uses is responsible for according to project manager and site operation personnel
First terminal and the correlation function of second terminal are carried out differentiated design, utilize first terminal, second terminal by the difference of work
And background server, construction personnel can at the first time feed back site operation situation to background server, and administrative staff
Background server can be accessed using first terminal in first time, the condition of construction at scene be understood, thus by precasting yard
All construction speed visualizations are presented, even if being not present in administrative staff in precasting yard also is understood that construction speed, and right
Specific project under construction carries out an acceptance inspection, underproof for checking and accepting, and remotely proposes improving suggestions for site operation personnel, is conducive to pipe
Reason personnel timely adjust subsequent construction arrangement.
2. the present invention is to the analysis that the examination of bridge subsection project under construction is by background server to scene image information
It is realized with processing, site operation personnel can be effectively improved to the construction quality of bridge subsection, and reduce administrative staff
To the work load of engineering supervision;Manual review's function also joined to the project under construction audited not over machine simultaneously, be
Site operation personnel need adjustment member construction working to provide convenience according to actual construction, by intelligentized control method and manually
Rationally intervene and combine, effectively raises the production efficiency of bridge subsection.
3. the present invention is implanted into chip in bridge subsection, site operation personnel can be facilitated to read different bridge subsections
Product information and construction information can be facilitated by the matching of the second terminal of the chip and site operation personnel of bridge subsection
Administrative staff arrange construction task, and administrative staff's later period is facilitated to carry out evaluation judgement to the work of construction personnel.Utilize bridge section
The positioning function of section chip, enables the staff in precasting yard to be quickly found out the position of bridge subsection.Utilize bridge section
The signal transmission function of section can help gantry crane to realize the operation of automatic bale handle, improve the fortune in precasting yard to bridge subsection
Defeated efficiency.
Detailed description of the invention
Fig. 1 is the flow chart of the Intelligentized control method of bridge subsection precasting yard of the invention.
Specific embodiment
The present invention is described in further detail below with reference to embodiment, embodiments of the present invention are not limited thereto.
The Intelligentized control method of bridge subsection precasting yard in present embodiment, it is necessary first to flat in BIM data management
One is established in platform for producing the precasting yard of precast segmental beam, planar design drawing, precasting yard Nei Gesheng to the precasting yard
Deployment scenarios, precasting yard production equipment, project personnel's information and the information of Prefabrication component etc. for producing subregion input,
Above-mentioned data are subjected to confluence analysis in BIM data management platform, establish the BIM model of bridge subsection precasting yard.
According to the practical erection needs of bridge, the order information of precast segmental beam, order letter are inputted on BIM management platform
Breath includes mainly raw material information needed for the information and engineering of each beam sections of bridge.The information of each segment of its Bridge includes
Size, concrete grade, reinforcing bar grade, bar diameter, reinforcing bar shape, built-in fitting position and the coagulation of production prefabricated case beam
The size etc. of clay model plate, and raw material information can specifically be divided into concrete information, reinforcing bar information, built-in fitting information etc..
Based on the model of above-mentioned bridge subsection precasting yard, BIM data management platform can analyze be calculated complete it is above-mentioned
Order information, the man power and material put into required for the bridge subsection precasting yard, while according to existing equipment and place information,
The production and construction plan for automatically generating precasting yard, determine construction speed arrangement, construction material requested and equipment, personnel and equipment into
Field time, adjacent working procedure duration, the personnel equipment in every procedure between personnel placement, each working procedure turn
Change management and the transport etc. with finished product member.
In order to which allocation optimum is made in the production and construction plan to precasting yard, BIM data management platform can be according to locality
Weather, climate change and local government provide different production and construction plan ratios to objective factors such as the limitations of construction time
Scheme is selected, construction personnel can select optimal production plan according to the scheme analysis listed.
Method of the invention is realized by a kind of intelligent control system of bridge subsection precasting yard, the system packet
Included background server, first terminal, second terminal and bridge subsection chip, background server included at least receiving module,
Message processing module and sending module, first terminal have function at least identical with second terminal, and first terminal also has spy
Different access right, Special use permission make the first terminal have the function of being different from second terminal, bridge subsection core again
Piece is set in each bridge subsection, and the number of bridge subsection chip and the number of bridge subsection are consistent, bridge subsection chip
Implantation be and to be connect with fixing piece and to be realized with steel reinforcement cage by the way that chip to be fitted into lamp cap box.
The function of first terminal and second terminal is explained further below, in the production line operation of precasting yard
In, since the division of labor of staff in field has differences, the function of first terminal and second terminal is done further thin
Point, wherein the user of first terminal can be project manager, and the user of second terminal can be site operation personnel.
Second terminal has the basic function of terminal device, and the terminal device can be laptop, tablet computer, mobile phone, vehicle
Computer and palm PC (PDA) etc. are carried, site operation personnel can read the basic letter of bridge subsection chip using second terminal
Breath, can also be after completing project under construction to background server upload information, and the information that second terminal uploads includes and constructs
The relevant text information of project and image information.First terminal also wraps other than having function possessed by above-mentioned second terminal
Included with receive background server send etc. pending instruction, to the permission of the review of second terminal upload information, and
The function of review result is directly sent to second terminal.
Construction method of the invention utilizes BIM data management platform, the concrete operations side in the production process of precasting yard
Method is as follows: site operation personnel read the essential information in bridge subsection chip using second terminal, and second terminal reads bridge
The method of segment chip can be using the method for scanning RFID chip or the side by the wireless communication modules such as bluetooth, infrared
Method, after having read bridge subsection chip, the product information and construction information of the available bridge subsection of site operation personnel,
Wherein product information includes: number, structure size information, arrangement of reinforcement information, installation of embedded parts information and the coagulation of bridge subsection
Soil pours information etc., and the construction information includes: the initial time of process and end time, construction location, construction personnel's letter
Breath and construction task performance etc., after the product information and construction information for checking above-mentioned bridge subsection, site operation personnel
It can start oneself responsible associated production work, after completing above-mentioned production work, site operation personnel can use second
Terminal is modified the construction task performance in the construction information of bridge subsection, but to construction task performance
Before being modified, information corresponding to completed project under construction is first sent to background server audit, the information
It include text information and image information, wherein text information includes: completing personal information, the project under construction of project under construction
Beginning and ending time pours design value and pours actual value etc., and image information can be the photo or image to associated construction project
Evidence obtaining etc..
In next step, background server handles the information received, and the process of information processing includes that will receive
Information be compared with presupposed information, which is by the BIM management platform good knot of analytical calculation before the start of production
Fruit, if comparison result shows that the information received is consistent with presupposed information or result is within error range, background server
Directly to be fed back to second terminal, the update for agreeing to that site operation personnel complete to construction task performance confirms, and
It can start the construction of progress next process.It, will if comparison result shows that the information received and presupposed information are inconsistent
Comparison result is sent to first terminal.
In next step, first terminal can prompt project manager to check comparison result after receiving comparison result,
Project manager is after checking comparison result, if it is considered to the information received and presupposed information are implicitly present in larger difference,
Then information directly can be issued to second terminal by first terminal, clearly where informing site operation personnel issue and make its heavy
It newly constructs, if project manager, which thinks that comparison result has differences, such as to be produced as caused by other reasons
Before, site operation personnel, the interim adjustment to the initial time of some process of bridge subsection, end time or hoisting point position
Etc. being put on record, project manager can issue authorized order to second terminal by first terminal, agree to that the scene is applied
Worker person carries out the operation of next process, while giving second terminal and updating and confirming that the construction task of current bridge subsection is completed
The permission of situation.
The preferred embodiment of the present invention includes:
Further, site operation personnel utilize the step of image information of second terminal typing are as follows: when construction personnel is complete
It when at a certain process, such as after the completion of bridge subsection skeleton reinforcing steel bar is set up, needs to weld built-in fitting in skeleton reinforcing steel bar, when applying
After worker person completes the welding of whole built-in fittings, the image information by all built-in fittings of second terminal typing is needed, and will
The image information is uploaded to background server, and background server is by being analyzed and being calculated to above-mentioned image information, in three-dimensional
The coordinate unit (X, Y, Z) that each built-in fitting location information is established under coordinate system, by the coordinate unit (X, Y, Z) and BIM data
The coordinate unit (x, y, z) for the bridge subsection Designing of Pre-embedded Pieces in Concrete Structures position having built up in management platform is compared, if coordinate list
Member is mutually matched within error range, then is judged as by checking and accepting, if it fails to match within error range for coordinate unit,
Comparison result is sent to first terminal.
Further, bridge subsection chip includes location mark module, and the location mark module is used for bridge section
Fragment position is positioned.When second terminal reads bridge subsection chip, second terminal while the bridge section that can will be read
The position of section is uploaded to background server, and background server stores the location information of bridge subsection, when having second again
When terminal is read out bridge subsection chip, background server will be received again by the location information of the bridge subsection, and again
The position of bridge subsection is stored.It therefore, can be to the change of each location information of bridge subsection in background server
It is stored and is recorded, when having first terminal or second terminal access background server, need to only input corresponding bridge subsection
Label information, background server can automatically generate the bridge subsection in the location of different production periods, and should
Information is sent to first terminal or second terminal.
Further, the product information stored in bridge subsection chip is that BIM data management platform is ordered according to what is received
Single Automatic generation of information is calculated by BIM data management platform in the design phase of product, can not be repaired by terminal
Change.And construction information is can to modify after the production project for completing each stage, site operation personnel pass through second
Modification of the terminal to construction information needs the authorization by background server or first terminal.When applying in bridge subsection chip
After work information is modified, background server can automatically be saved the real-time status of manufacturing schedule, while will send a command to
The site operation personnel of subsequent processing and project manager remind them to start to carry out the production plan arrangement of next stage.
Further, signal emission module is further comprised in bridge subsection chip, signal emission module is for realizing bridge
The accurate positioning of segment and portal jib crane.After the completion of the Prefabrication of bridge subsection, portal jib crane is controlled to prefabricated bridge
Girder segment is moved, and the signal receiver to match with signal emission module is provided on portal jib crane, when on portal jib crane
Signal receiver complete bridge subsection accurate positioning after, bale handle operation can be carried out to it, to realize bridge subsection
Automatically beam is deposited.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, without departing from the technical principles of the invention, several improvement and replacement can also be made, these are improved and replacement
Also it should be regarded as protection scope of the present invention.
Claims (8)
1. a kind of Intelligentized control method of bridge subsection precasting yard, which is characterized in that specifically included following steps:
S1. the model that bridge subsection precasting yard is established in BIM data management platform, according to the needs of bridge erection, input is pre-
The order information of beam sections processed;
S2. according to the division of labor difference of staff in precasting yard, terminal device is divided into the first end that project manager uses
End and the second terminal that uses of site operation personnel, the first terminal have be different from the second terminal to background service
The permission of the final review of the unqualified information of device feedback;
S3. site operation personnel are after the project under construction for completing distribution, through the second terminal on the background server
Information corresponding to completed project under construction is passed, the background server is in the information for receiving the second terminal transmission
Afterwards, which is compared;If comparison result is identical or within error range, the background server is whole to described second
End is sent by checking and accepting instruction, if comparison result has exceeded the error range of permission, the background server is to described first
The pending instructions such as terminal transmission;
S4. the first terminal is uploaded to the background server to the second terminal after the pending instruction such as receiving
Information carry out manual examination and verification, if auditing result meets the requirements, sent to the second terminal by testing by first terminal
Instruction is received, if auditing result is undesirable, modification is sent to the second terminal by the first terminal;
S5. the second terminal is updated confirmation to the construction information of bridge subsection after receiving by checking and accepting instruction, and
The construction information updated after confirming is uploaded to the background server;The second terminal is after receiving modification, temporarily
When do not have the permission that confirmation is updated to the construction information of bridge subsection.
2. a kind of Intelligentized control method of bridge subsection precasting yard according to claim 1, which is characterized in that the S2
It further comprises, it is pre-buried to bridge subsection progress chip, chip fixing piece is connect with steel reinforcement cage, is implanted into the described of bridge subsection
The product information of corresponding bridge subsection is stored in chip, the product information includes the number of bridge subsection, structure size
Information, arrangement of reinforcement information, installation of embedded parts information and concreting information.
3. a kind of Intelligentized control method of bridge subsection precasting yard according to claim 2, which is characterized in that the core
The construction information of corresponding bridge subsection is also stored in piece, the construction information includes the initial time of process at the end of
Between, construction location, construction personnel's information and construction task performance, site operation personnel pass through the second terminal and read bridge
Product information and construction information in girder segment chip, and confirmation can be updated to the construction task performance.
4. a kind of Intelligentized control method of bridge subsection precasting yard according to claim 1, which is characterized in that the S3
In, the information includes text information and image information, the text information include the personal information for completing project under construction,
The beginning and ending time of project under construction pours design value and pours actual value.
5. a kind of Intelligentized control method of bridge subsection precasting yard according to claim 4, which is characterized in that after described
It is described image information, the message processing module pair of background server that platform server, which receives the information that the second terminal is sent,
The treatment process of described image information includes at least: described image information is converted to the structural model under three-dimensional system of coordinate,
By will respectively indicate coordinate unit information a little and established design structure mould in BIM data management platform in the structural model
The coordinate unit information of each mark point in type is compared, if the result of coordinate unit information comparison is mutual within error range
Match, be then judged as by checking and accepting, if the result of coordinate unit information comparison exceeds error range, is judged as etc. pending
Core.
6. a kind of Intelligentized control method of bridge subsection precasting yard according to claim 2, which is characterized in that the core
Piece is RFID chip, using ultra-high frequency RFID label.
7. a kind of Intelligentized control method of bridge subsection precasting yard according to claim 6, which is characterized in that the S3
In further comprise: the second terminal can read the location information in the location mark module in bridge subsection chip, and will
The location information is uploaded to the background server, and the background server saves the location information, when again
When having second terminal to be read out the location mark module in bridge subsection chip, the background server can be received again by
The location information for the bridge subsection that two terminals upload, the background server are updated the location information of bridge subsection.
8. a kind of Intelligentized control method of bridge subsection precasting yard according to claim 6, which is characterized in that further include
: include signal emission module in S6. bridge subsection chip, is provided on portal jib crane mutual with the signal emission module
Matched signal receiving module, when the signal receiving module on the portal jib crane is completed to the accurate of the bridge subsection
After positioning, the portal jib crane begins to bale handle operation, completes the transport and storage of bridge subsection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910634126.7A CN110216788B (en) | 2019-07-15 | 2019-07-15 | Intelligent control method for bridge segment prefabricating field |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910634126.7A CN110216788B (en) | 2019-07-15 | 2019-07-15 | Intelligent control method for bridge segment prefabricating field |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110216788A true CN110216788A (en) | 2019-09-10 |
CN110216788B CN110216788B (en) | 2021-03-30 |
Family
ID=67813297
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910634126.7A Active CN110216788B (en) | 2019-07-15 | 2019-07-15 | Intelligent control method for bridge segment prefabricating field |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110216788B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110853310A (en) * | 2019-10-17 | 2020-02-28 | 北京华跃博弈科技有限公司 | Intelligent decoration construction system and data acquisition method thereof |
CN111210199A (en) * | 2020-01-03 | 2020-05-29 | 广西路桥工程集团有限公司 | Bridge prefab BIM information management system |
CN111475881A (en) * | 2020-04-07 | 2020-07-31 | 中国电建集团华东勘测设计研究院有限公司 | BIM-based pipe burying and embedding construction management method |
CN111506949A (en) * | 2020-04-10 | 2020-08-07 | 中国电建集团昆明勘测设计研究院有限公司 | BIM-based visualization method for road soft foundation treatment construction progress |
CN111898932A (en) * | 2020-08-27 | 2020-11-06 | 南京六的平方信息技术有限公司 | Precast beam machining control method and system |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20060230433A1 (en) * | 2005-03-29 | 2006-10-12 | Invented Corporation | Client device reservation system and method |
CN106408172A (en) * | 2016-08-31 | 2017-02-15 | 广东达安项目管理股份有限公司 | Project management system |
CN109064133A (en) * | 2018-07-27 | 2018-12-21 | 福建京力信息科技有限公司 | A kind of engineering whole process management system based on BIM+AR |
CN109110646A (en) * | 2018-08-06 | 2019-01-01 | 新疆机汇网络科技有限公司 | Implementation method, system and the storage medium of a kind of pair of safety of tower crane inspection management |
CN109165869A (en) * | 2018-09-14 | 2019-01-08 | 广东电网有限责任公司 | A kind of construction managing and control system and management-control method |
CN109284919A (en) * | 2018-09-13 | 2019-01-29 | 深圳市栋森工程项目管理有限公司 | A kind of project cost project management system |
CN109408981A (en) * | 2018-10-31 | 2019-03-01 | 广西路桥工程集团有限公司 | A kind of information management system of road and bridge highway engineering construction |
CN109658067A (en) * | 2018-12-20 | 2019-04-19 | 山东晟光电力设备安装工程有限公司 | A kind of power engineering project control platform and system |
-
2019
- 2019-07-15 CN CN201910634126.7A patent/CN110216788B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20060230433A1 (en) * | 2005-03-29 | 2006-10-12 | Invented Corporation | Client device reservation system and method |
CN106408172A (en) * | 2016-08-31 | 2017-02-15 | 广东达安项目管理股份有限公司 | Project management system |
CN109064133A (en) * | 2018-07-27 | 2018-12-21 | 福建京力信息科技有限公司 | A kind of engineering whole process management system based on BIM+AR |
CN109110646A (en) * | 2018-08-06 | 2019-01-01 | 新疆机汇网络科技有限公司 | Implementation method, system and the storage medium of a kind of pair of safety of tower crane inspection management |
CN109284919A (en) * | 2018-09-13 | 2019-01-29 | 深圳市栋森工程项目管理有限公司 | A kind of project cost project management system |
CN109165869A (en) * | 2018-09-14 | 2019-01-08 | 广东电网有限责任公司 | A kind of construction managing and control system and management-control method |
CN109408981A (en) * | 2018-10-31 | 2019-03-01 | 广西路桥工程集团有限公司 | A kind of information management system of road and bridge highway engineering construction |
CN109658067A (en) * | 2018-12-20 | 2019-04-19 | 山东晟光电力设备安装工程有限公司 | A kind of power engineering project control platform and system |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110853310A (en) * | 2019-10-17 | 2020-02-28 | 北京华跃博弈科技有限公司 | Intelligent decoration construction system and data acquisition method thereof |
CN111210199A (en) * | 2020-01-03 | 2020-05-29 | 广西路桥工程集团有限公司 | Bridge prefab BIM information management system |
CN111210199B (en) * | 2020-01-03 | 2022-06-07 | 广西路桥工程集团有限公司 | Bridge prefab BIM information management system |
CN111475881A (en) * | 2020-04-07 | 2020-07-31 | 中国电建集团华东勘测设计研究院有限公司 | BIM-based pipe burying and embedding construction management method |
CN111506949A (en) * | 2020-04-10 | 2020-08-07 | 中国电建集团昆明勘测设计研究院有限公司 | BIM-based visualization method for road soft foundation treatment construction progress |
CN111898932A (en) * | 2020-08-27 | 2020-11-06 | 南京六的平方信息技术有限公司 | Precast beam machining control method and system |
Also Published As
Publication number | Publication date |
---|---|
CN110216788B (en) | 2021-03-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110216788A (en) | A kind of Intelligentized control method of bridge subsection precasting yard | |
CN110216789A (en) | A kind of intelligent control system of bridge subsection precasting yard | |
CN110909972B (en) | BIM-based steel structure full life cycle management system and method | |
CN107038554A (en) | Steel construction BIM informatization management methods and system based on Cloud Server | |
CN107423865A (en) | High-speed railway KXG based on BIM | |
CN111210199A (en) | Bridge prefab BIM information management system | |
CN107256005A (en) | A kind of reinforcing steel bar numerical control processing method and equipment based on BIM technology | |
CN116029529B (en) | BIM-based bridge construction progress management method and system | |
CN106997511A (en) | Railway beam course management system and railway beam a management method based on BIM technology | |
CN113610389B (en) | Prefabricated component production quality management system based on BIM and RFID | |
CN106991214A (en) | The informatization management method of high speed railway prefabricating Liang Chang based on BIM | |
CN112884290A (en) | BIM-based field construction management method | |
CN112364428A (en) | BIM technology-based pre-stressed variable cross-section box girder steel bar collision detection method | |
CN116011859A (en) | Complete set management method for digital concrete engineering construction | |
CN108133107A (en) | A kind of FRP- concrete assembly methods based on BIM models | |
Laurini et al. | Technology 4.0 for buildings management: from building site to the interactive building book | |
CN107832951A (en) | Application processes and system of the BIM in precast concrete supply chain | |
CN106951621A (en) | A kind of simulation optimization method that Plan rescheduling is carried for ship | |
CN110348145B (en) | Construction method for building tunnel based on BIM technology | |
CN116561871A (en) | Deep construction method for mounting embedded part of bridge bearing platform | |
CN112711788A (en) | Bridge erection process dynamic prediction and control method based on BIM technology | |
CN101736925A (en) | Modular construction method for nuclear island of nuclear power station | |
CN113449374B (en) | Equipment self-organization strategy optimization method and system adaptive to steel structure construction characteristics | |
CN114925908A (en) | Information control method for construction progress of fabricated building | |
CN101748915A (en) | Modularization construction method for nuclear power station nuclear island |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: 510220 Guangzhou Tianhe District, Guangdong Province, 23 Sicheng Road, Hongtai Wisdom Valley Building 2 Floor 239A Applicant after: Hanyang International Engineering Consulting Co., Ltd Address before: 510220 Guangzhou Tianhe District, Guangdong Province, 23 Sicheng Road, Hongtai Wisdom Valley Building 2 Floor 239A Applicant before: Guangzhou Hanyang Engineering Consulting Co.,Ltd. |
|
CB02 | Change of applicant information | ||
GR01 | Patent grant | ||
GR01 | Patent grant |