CN110210097A - 一种基于bim技术的金属屋面优化施工方法 - Google Patents
一种基于bim技术的金属屋面优化施工方法 Download PDFInfo
- Publication number
- CN110210097A CN110210097A CN201910443837.6A CN201910443837A CN110210097A CN 110210097 A CN110210097 A CN 110210097A CN 201910443837 A CN201910443837 A CN 201910443837A CN 110210097 A CN110210097 A CN 110210097A
- Authority
- CN
- China
- Prior art keywords
- metal roof
- construction
- created
- method based
- bim
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Computer Hardware Design (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Software Systems (AREA)
- Computer Graphics (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Computational Mathematics (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
本发明公开了一种基于BIM技术的金属屋面优化施工方法,包含如下步骤:优化处理二维CAD施工图纸;将优化后的二维CAD施工图纸导入BIM建模软件中;在BIM建模软件的Revit中创建与施工图纸相同的基准标高和轴网;在Revit中创建金属屋面所依附的主体结构、钢结构和龙骨的三维模型结构的步骤,有效地避免了图纸设计错误或材料的生产加工制作精确不高存在着碰撞、尺寸偏差等问题导致安装难度大、安装效率低的问题。
Description
技术领域
本发明涉及建筑安装工程金属屋面优化施工方法,适用于金属屋面工程的一种施工方法。
背景技术
目前建筑安装工程金属屋面工程的施工,仍存在着许多的问题,由于图纸设计错误,材料的生产加工制作不精确存在着碰撞、尺寸偏差等问题导致安装难度大、安装效率低,因此采用BIM技术优化显得尤其重要,BIM模型能够提前将待建建筑物或构筑物以三维可视化形式展现在我们眼前,并且能够模拟虚拟现实动画,提前解决可能存在的问题,防患于未然,提高施工效率,给工程建设带来明显效益。
发明内容
针对现有技术中存在的技术问题,本发明目的是为了确保材料的生产加工制作精确,金属屋面与所依附的主体结构、钢结构、龙骨之间不存在碰撞冲突、位置偏差,提高安装效率和安装精度,提供一种基于BIM技术的金属屋面优化施工方法。为实现上述目的,本发明提供如下技术方案:
一种基于BIM技术的金属屋面优化施工方法,包含如下步骤:
(1)优化处理二维CAD施工图纸;
(2)将优化后的二维CAD施工图纸导入BIM建模软件中;
(3)在BIM建模软件的Revit中创建与施工图纸相同的基准标高和轴网;
(4)在Revit中创建金属屋面所依附的主体结构、钢结构和龙骨的三维模型结构;
(5)创建完整的金属屋面三维模型;
(6)检测创建的三维模型是否存在空间上的碰撞冲突和位置偏差方面的问题,对存在问题的项高亮显示;
(7)与设计人员沟通高亮显示的问题,对存在的问题进行修改;
(8)利用BIM技术软件中的Fuzor模拟虚拟现实进行安装;
(9)对管理人员和作业人员进行三维可视化技术交底和形成现场施工作业文件;
(10)将二维CAD图纸以及模型信息交至材料生产厂家以对材料进行生产加工制作;
(11)根据施工作业文件进行现场组装施工。
优选的,步骤1中所述对二维CAD图纸进行优化处理是将图纸的各图层进行分离,删除二维CAD图纸中存多余的点、线条和边框。
优选的,步骤4中创建金属屋面所依附的主体结构、钢结构和龙骨的三维模型结构,符合建模标准和规范。
优选的,步骤5中创建完整的金属屋面三维模型,符合建模标准和规范。
与现有技术相比,本发明的有益效果是:
本发明采用基于BIM技术的金属屋面优化施工方法,有效利用BIM技术三维可视化和虚拟现实动画的特点,展现待建建筑物或构筑物空间三维造型以及构件之间的空间几何关系是否存在碰撞冲突、尺寸偏差等,解决二维状态下不能直观表达和及时发现图纸中存在的问题,避免一些可以避免的错误,提高施工效率。
具体实施方式
下面对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
实施例1
一种基于BIM技术的金属屋面优化施工方法,包含如下步骤:
(1)优化处理二维CAD施工图纸;
(2)将优化后的二维CAD施工图纸导入BIM建模软件中;
(3)在BIM建模软件的Revit中创建与施工图纸相同的基准标高和轴网;
(4)在Revit中创建金属屋面所依附的主体结构、钢结构和龙骨的三维模型结构;
(5)创建完整的金属屋面三维模型;
(6)检测创建的三维模型是否存在空间上的碰撞冲突和位置偏差方面的问题,对存在问题的项高亮显示;
(7)与设计人员沟通高亮显示的问题,对存在的问题进行修改;
(8)利用BIM技术软件中的Fuzor模拟虚拟现实进行安装;
(9)对管理人员和作业人员进行三维可视化技术交底和形成现场施工作业文件;
(10)将二维CAD图纸以及模型信息交至材料生产厂家以对材料进行生产加工制作;
(11)根据施工作业文件按照模型信息进行现场组装施工。
实施例2
一种基于BIM技术的金属屋面优化施工方法,其特征在于:包含如下步骤:
(1)对二维CAD图纸进行优化处理是将图纸的各图层进行分离,并删除二维CAD图纸中存多余的点、线条和边框的优化处理;
(2)将优化后的二维CAD施工图纸导入BIM建模软件中;
(3)在BIM建模软件的Revit中创建与施工图纸相同的基准标高和轴网;
(4)在Revit中创建金属屋面所依附的主体结构、钢结构和龙骨的三维模型结构;
(5)创建完整的金属屋面三维模型;
(6)检测创建的三维模型是否存在空间上的碰撞冲突和位置偏差方面的问题,对存在问题的项高亮显示;
(7)与设计人员沟通高亮显示的问题,对存在的问题进行修改;
(8)利用BIM技术软件中的Fuzor模拟虚拟现实进行安装;
(9)对管理人员和作业人员进行三维可视化技术交底和形成现场施工作业文件;
(10)将二维CAD图纸以及模型信息交至材料生产厂家以对材料进行生产加工制作;
(11)根据施工作业文件进行现场组装施工。
实施例3
与实施例1的区别在于:在步骤4中创建金属屋面所依附的主体结构、钢结构和龙骨的三维模型结构时,符合建模软件使用规范及要求。
实施例4
与实施例1的区别在于:步骤5中创建完整的金属屋面三维模型时,符合建模使用规范及要求。
对于本领域技术人员而言,显然本发明不限于上述示范性实施例的细节,而且在不背离本发明的精神或基本特征的情况下,能够以其他的具体形式实现本发明。因此,无论从哪一点来看,均应将实施例看作是示范性的,而且是非限制性的,本发明的范围由所附权利要求而不是上述说明限定,因此旨在将落在权利要求的等同要件的含义和范围内的所有变化囊括在本发明内。
Claims (4)
1.一种基于BIM技术的金属屋面优化施工方法,其特征在于:包含如下步骤:
(1)优化处理二维CAD施工图纸;
(2)将优化后的二维CAD施工图纸导入BIM建模软件中;
(3)在BIM建模软件的Revit中创建与施工图纸相同的基准标高和轴网;
(4)在Revit中创建金属屋面所依附的主体结构、钢结构和龙骨的三维模型结构;
(5)创建完整的金属屋面三维模型;
(6)检测创建的三维模型是否存在空间上的碰撞冲突和位置偏差方面的问题,对存在问题的项高亮显示;
(7)与设计人员沟通高亮显示的问题,对存在的问题进行修改;
(8)利用BIM技术软件中的Fuzor模拟虚拟现实进行安装;
(9)对管理人员和作业人员进行三维可视化技术交底和形成现场施工作业文件;
(10)将二维CAD图纸以及模型信息交至材料生产厂家以对材料进行生产加工制作;
(11)根据施工作业文件进行现场组装施工。
2.根据权利要求1所述的一种基于BIM技术的金属屋面优化施工方法,其特征在于:步骤1中所述对二维CAD图纸进行优化处理是将图纸的各图层进行分离,删除二维CAD图纸中存多余的点、线条和边框。
3.根据权利要求1所述的一种基于BIM技术的金属屋面优化施工方法,其特征在于:步骤4中创建金属屋面所依附的主体结构、钢结构和龙骨的三维模型结构,符合建模标准和规范。
4.根据权利要求1所述的一种基于BIM技术的金属屋面优化施工方法,其特征在于:步骤5中创建完整的金属屋面三维模型,符合建模标准和规范。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910443837.6A CN110210097B (zh) | 2019-05-27 | 2019-05-27 | 一种基于bim技术的金属屋面优化施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910443837.6A CN110210097B (zh) | 2019-05-27 | 2019-05-27 | 一种基于bim技术的金属屋面优化施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110210097A true CN110210097A (zh) | 2019-09-06 |
CN110210097B CN110210097B (zh) | 2023-01-17 |
Family
ID=67788806
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910443837.6A Active CN110210097B (zh) | 2019-05-27 | 2019-05-27 | 一种基于bim技术的金属屋面优化施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110210097B (zh) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110685408A (zh) * | 2019-09-10 | 2020-01-14 | 南通四建集团有限公司 | 一种基于bim的扇形与三角形金属屋面板的施工方法及结构 |
CN111581705A (zh) * | 2020-05-12 | 2020-08-25 | 中国十七冶集团有限公司 | 一种基于bim技术的不规则曲面钢结构施工方法 |
CN111625889A (zh) * | 2020-05-26 | 2020-09-04 | 中国十七冶集团有限公司 | 一种基于bim技术的曲面异形钢结构施工方法 |
CN112329097A (zh) * | 2020-10-20 | 2021-02-05 | 湘潭大学 | 一种基于bim技术对地铁设计图纸的校正方法 |
CN113077140A (zh) * | 2021-03-31 | 2021-07-06 | 贵州建工梵净山建筑工程有限公司 | 一种基于bim技术的磷石膏施工优化方法 |
CN113094796A (zh) * | 2021-04-22 | 2021-07-09 | 中国十七冶集团有限公司 | 一种基于bim技术的金属屋面智能安装施工方法 |
CN113642066A (zh) * | 2021-07-01 | 2021-11-12 | 机械工业第九设计研究院有限公司 | 一种基于revit软件的总平面布置方法 |
CN113742824A (zh) * | 2021-08-26 | 2021-12-03 | 苏州筑百年建筑科技有限公司 | 一种轻量化钢结构智慧协同设计云平台及其操作方法 |
CN114351957A (zh) * | 2021-12-21 | 2022-04-15 | 中建八局第二建设有限公司 | 一种双曲面穹顶金属屋面施工方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20160210377A1 (en) * | 2015-01-20 | 2016-07-21 | Illinois Tool Works, Inc. | Method, computer program product and apparatus for providing a building options configurator |
CN107832498A (zh) * | 2017-10-18 | 2018-03-23 | 陕西有色建设有限公司 | 一种基于bim的复杂施工工艺技术交底方法 |
CN109784004A (zh) * | 2019-04-02 | 2019-05-21 | 中国十七冶集团有限公司 | 一种基于bim技术的异形金属屋面安装施工方法 |
-
2019
- 2019-05-27 CN CN201910443837.6A patent/CN110210097B/zh active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20160210377A1 (en) * | 2015-01-20 | 2016-07-21 | Illinois Tool Works, Inc. | Method, computer program product and apparatus for providing a building options configurator |
CN107832498A (zh) * | 2017-10-18 | 2018-03-23 | 陕西有色建设有限公司 | 一种基于bim的复杂施工工艺技术交底方法 |
CN109784004A (zh) * | 2019-04-02 | 2019-05-21 | 中国十七冶集团有限公司 | 一种基于bim技术的异形金属屋面安装施工方法 |
Non-Patent Citations (1)
Title |
---|
董强等: "BIM技术在机场航站区建设施工中的应用", 《建筑技术》 * |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110685408A (zh) * | 2019-09-10 | 2020-01-14 | 南通四建集团有限公司 | 一种基于bim的扇形与三角形金属屋面板的施工方法及结构 |
CN111581705A (zh) * | 2020-05-12 | 2020-08-25 | 中国十七冶集团有限公司 | 一种基于bim技术的不规则曲面钢结构施工方法 |
CN111625889A (zh) * | 2020-05-26 | 2020-09-04 | 中国十七冶集团有限公司 | 一种基于bim技术的曲面异形钢结构施工方法 |
CN112329097A (zh) * | 2020-10-20 | 2021-02-05 | 湘潭大学 | 一种基于bim技术对地铁设计图纸的校正方法 |
CN113077140A (zh) * | 2021-03-31 | 2021-07-06 | 贵州建工梵净山建筑工程有限公司 | 一种基于bim技术的磷石膏施工优化方法 |
CN113077140B (zh) * | 2021-03-31 | 2023-10-17 | 贵州建工梵净山建筑工程有限公司 | 一种基于bim技术的磷石膏施工优化方法 |
CN113094796A (zh) * | 2021-04-22 | 2021-07-09 | 中国十七冶集团有限公司 | 一种基于bim技术的金属屋面智能安装施工方法 |
CN113642066A (zh) * | 2021-07-01 | 2021-11-12 | 机械工业第九设计研究院有限公司 | 一种基于revit软件的总平面布置方法 |
CN113742824A (zh) * | 2021-08-26 | 2021-12-03 | 苏州筑百年建筑科技有限公司 | 一种轻量化钢结构智慧协同设计云平台及其操作方法 |
CN114351957A (zh) * | 2021-12-21 | 2022-04-15 | 中建八局第二建设有限公司 | 一种双曲面穹顶金属屋面施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN110210097B (zh) | 2023-01-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110210097A (zh) | 一种基于bim技术的金属屋面优化施工方法 | |
CN109766581B (zh) | 一种采用Dynamo软件建立桥梁BIM模型的方法 | |
CN104281729B (zh) | 一种应用于钢结构建筑数字化加工制造的bim方法 | |
CN106934163A (zh) | 基于bim的桥梁三维模型构建方法 | |
CN109800536A (zh) | 一种基于Revit与Dynamo参数化隧道模型快速建模方法 | |
CN109784004B (zh) | 一种基于bim技术的异形金属屋面安装施工方法 | |
CN107974945B (zh) | 基于变截面刚构桥连续梁悬臂浇筑施工的bim建模方法 | |
CN106372293B (zh) | 一种基于三维基准线的构筑物bim模型创建方法 | |
CN104778753B (zh) | 桥梁钢筋的三维建模实现方法 | |
KR101227723B1 (ko) | 파라메트릭 디자인 프로세스를 이용한 한옥설계 지원 정보시스템 구축방법 | |
CN110206212A (zh) | 一种基于bim技术的弧形金属屋面施工方法 | |
CN101377796B (zh) | 一种基于过程恢复的异构cad系统间参数化特征模型的数据交换方法 | |
CN104965947A (zh) | 一种基于bim技术的桥梁三维设计方法 | |
CN107622153A (zh) | 一种基于bim技术的大型设备吊装施工模拟方法 | |
CN109359347A (zh) | 一种基于bim的铁路信号室外设备三维布置方法及装置 | |
CN107229790A (zh) | 生成三维、二维图形的桥梁结构信息模型系统及使用方法 | |
CN105975655A (zh) | 一种基于bim的仿唐宋古建异形屋面瓦参数化建模方法 | |
CN112560134A (zh) | 一种基于cad与bim的装配式结构叠合板批量深化设计方法 | |
CN102608919A (zh) | 一种冲压单工位生产模拟验证方法 | |
CN103678737A (zh) | 一种杠杆系统虚拟装配方法 | |
CN108875167A (zh) | 一种基于bim技术的施工现场三维布置优化方法 | |
CN106951589A (zh) | 一种基于成熟度的运载火箭数字样机设计方法 | |
CN111210520A (zh) | 一种用于实物模型的逆向成形方法及系统 | |
CN107679332A (zh) | 基于Tekla平台的输电铁塔BIM模型构建方法 | |
CN102663168A (zh) | 电缆层二维图纸的三维转换及管线冲突处理方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |