CN108875167A - 一种基于bim技术的施工现场三维布置优化方法 - Google Patents
一种基于bim技术的施工现场三维布置优化方法 Download PDFInfo
- Publication number
- CN108875167A CN108875167A CN201810562302.6A CN201810562302A CN108875167A CN 108875167 A CN108875167 A CN 108875167A CN 201810562302 A CN201810562302 A CN 201810562302A CN 108875167 A CN108875167 A CN 108875167A
- Authority
- CN
- China
- Prior art keywords
- construction site
- dimensional
- arrangement
- software
- dimensional arrangement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Computer Hardware Design (AREA)
- Evolutionary Computation (AREA)
- Computational Mathematics (AREA)
- Civil Engineering (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Architecture (AREA)
- Computer Graphics (AREA)
- Software Systems (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Processing Or Creating Images (AREA)
Abstract
本发明公开了一种基于BIM技术的施工现场三维布置优化方法,包含以下步骤:步骤一、仔细阅读并熟练掌握施工现场平面布置图纸并对图纸进行优化,以便场地布置三维模型的创建;步骤二、将优化后的施工现场平面布置图纸导入广联达BIM施工现场三维布置软件中,依据图纸创建三维模型;步骤三、对整个施工现场进行三维漫游,初步排查现场布置不合理之处,及时进行修改更正;步骤四、应用BIM技术信息数据之间的共享功能,将创建的三维场布模型导入BIM5D软件中,进行各种仿真动画模拟,进一步排查现场塔吊布置、材料堆放位置是否合理,道路规划是否容易造成场地内交通不畅等等;步骤五、及时解决发现的问题,进一步优化场地布置;步骤六、依据优化后的三维场布指导施工现场三维布置。
Description
技术领域
本发明涉及领域,尤其涉及一种基于BIM技术的施工现场三维布置优化方法。
背景技术
目前,建设工程项目施工现场布置经常性的会发生由于材料堆放位置不合理导致材料需进行二次搬运,道路规划布置不合理造成场地内交通不畅等等一系列问题。
新技术BIM(Building Information Modeling)的应用,可以提前创建三维场布模型,进行三维漫游和各种仿真动画模拟,提前排查不合理之处,及时进行纠正和优化,提高施工场地的利用效率,给工程建设带来效益。
发明内容
本发明所要解决的技术问题是:针对现有技术中存在的问题,本发明目的是为了提供一种基于BIM技术的施工现场三维布置优化方法。
一种基于BIM技术的施工现场三维布置优化方法,包括以下步骤:
步骤一、仔细阅读并熟练掌握施工现场平面布置图纸并对图纸进行优化,以便场地布置三维模型的创建;
步骤二、将优化后的施工现场平面布置图纸导入广联达BIM施工现场三维布置软件中,依据图纸创建三维模型;
步骤三、对整个施工现场进行三维漫游,初步排查现场布置不合理之处,及时进行修改更正;
步骤四、应用BIM技术信息数据之间的共享功能,将创建的三维场布模型导入BIM5D软件中,进行各种仿真动画模拟,进一步排查现场塔吊布置、材料堆放位置是否合理,道路规划是否容易造成场地内交通不畅等等;
步骤五、及时解决发现的问题,进一步优化场地布置;
步骤六、依据优化后的三维场布指导施工现场三维布置。
进一步,步骤二中所述施工现场三维布置软件可以是BIM技术中所有能进行三维场布的软件,不单指某一具体软件,也可以是软件之间的相互协作链接整合进行施工现场三维场布。
进一步,步骤四中所述进行仿真动画模拟,不单指在某一具体软件中进行仿真动画模拟,可以是BIM技术中所有能进行仿真动画模拟的软件。
本发明包含以下有益成果:
本发明采用基于BIM技术的施工现场三维布置优化方法,利用BIM技术软件创建施工现场三维场布模型,进行三维漫游和各种仿真动画模拟,有效排查现场布置不合理之处,及时进行纠正和优化,提高施工场地的利用效率,给工程建设带来效益。
附图说明
为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。
图1为基于BIM技术的施工现场三维布置优化方法的流程图。
具体实施方式
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。
下面结合附图及具体实施例对本发明的应用原理作进一步描述。
实施例一
一种基于BIM技术的施工现场三维布置优化方法,包括以下步骤:
步骤一、仔细阅读并熟练掌握施工现场平面布置图纸并对图纸进行优化,以便场地布置三维模型的创建;
步骤二、将优化后的施工现场平面布置图纸导入广联达BIM施工现场三维布置软件中,依据图纸创建三维模型;
步骤三、对整个施工现场进行三维漫游,初步排查现场布置不合理之处,及时进行修改更正;
步骤四、应用BIM技术信息数据之间的共享功能,将创建的三维场布模型导入BIM5D软件中,进行各种仿真动画模拟,进一步排查现场塔吊布置、材料堆放位置是否合理,道路规划是否容易造成场地内交通不畅等等;
步骤五、及时解决发现的问题,进一步优化场地布置;
步骤六、依据优化后的三维场布指导施工现场三维布置。
进一步,步骤二中所述施工现场三维布置软件可以是BIM技术中所有能进行三维场布的软件,不单指某一具体软件,也可以是软件之间的相互协作链接整合进行施工现场三维场布。
进一步,步骤四中所述进行仿真动画模拟,不单指在某一具体软件中进行仿真动画模拟,可以是BIM技术中所有能进行仿真动画模拟的软件。
本发明提出了一种基于BIM技术的施工现场三维布置优化方法,首先,仔细阅读并熟练掌握施工现场平面布置图纸并对图纸进行优化,以便场地布置三维模型的创建,将优化后的施工现场平面布置图纸导入广联达BIM施工现场三维布置软件中,依据图纸创建三维模型;其次,对整个施工现场进行三维漫游,初步排查现场布置不合理之处,及时进行修改更正,然后应用BIM技术信息数据之间的共享功能,将创建的三维场布模型导入BIM5D软件中,进行各种仿真动画模拟,进一步排查现场塔吊布置、材料堆放位置是否合理,道路规划是否容易造成场地内交通不畅等等;最后,及时解决发现的问题,进一步优化场地布置,依据优化后的三维场布指导施工现场三维布置。
Claims (4)
1.一种基于BIM技术的施工现场三维布置优化方法,其特征在于,包含以下步骤:
步骤一、仔细阅读并熟练掌握施工现场平面布置图纸并对图纸进行优化,以便场地布置三维模型的创建;
步骤二、将优化后的施工现场平面布置图纸导入广联达BIM施工现场三维布置软件中,依据图纸创建三维模型;
步骤三、对整个施工现场进行三维漫游,初步排查现场布置不合理之处,及时进行修改更正;
步骤四、应用BIM技术信息数据之间的共享功能,将创建的三维场布模型导入BIM5D软件中,进行各种仿真动画模拟,进一步排查现场塔吊布置、材料堆放位置是否合理,道路规划是否容易造成场地内交通不畅等等;
步骤五、及时解决发现的问题,进一步优化场地布置;
步骤六、依据优化后的三维场布指导施工现场三维布置。
2.根据权利要求1所述的一种基于BIM技术的施工现场三维布置优化方法,其特征在于:步骤二中所述施工现场三维布置软件可以是BIM技术中所有能进行三维场布的软件,不单指某一具体软件,也可以是软件之间的相互协作链接整合进行施工现场三维场布。
3.根据权利要求1所述的一种基于BIM技术的施工现场三维布置优化方法,其特征在于:步骤二中所述施工现场三维布置软件为BIM5D软件。
4.根据权利要求1所述的一种基于BIM技术的施工现场三维布置优化方法,其特征在于步骤四中所述进行仿真动画模拟,不单指在某一具体软件中进行仿真动画模拟,可以是BIM技术中所有能进行仿真动画模拟的软件。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810562302.6A CN108875167A (zh) | 2018-06-04 | 2018-06-04 | 一种基于bim技术的施工现场三维布置优化方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810562302.6A CN108875167A (zh) | 2018-06-04 | 2018-06-04 | 一种基于bim技术的施工现场三维布置优化方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108875167A true CN108875167A (zh) | 2018-11-23 |
Family
ID=64336535
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810562302.6A Pending CN108875167A (zh) | 2018-06-04 | 2018-06-04 | 一种基于bim技术的施工现场三维布置优化方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108875167A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109711076A (zh) * | 2018-12-29 | 2019-05-03 | 江苏龙腾数字建造技术研究院有限公司 | Bim模型在施工过程中的应用方法 |
CN109920036A (zh) * | 2019-04-02 | 2019-06-21 | 中国十七冶集团有限公司 | 一种基于bim技术的弧形钢结构施工方法 |
CN109933900A (zh) * | 2019-03-13 | 2019-06-25 | 上海理工大学 | 一种基于bim技术的施工三维场布建模方法 |
CN111581818A (zh) * | 2020-05-06 | 2020-08-25 | 北方工业大学 | 一种基于bim技术的施工现场布置优化方法 |
CN112364414A (zh) * | 2020-10-26 | 2021-02-12 | 中国能源建设集团安徽电力建设第一工程有限公司 | 一种基于bim技术的三维施工场地布置方法 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6058778B1 (ja) * | 2015-12-14 | 2017-01-11 | 東芝エレベータ株式会社 | Bimシステム、方法およびプログラム |
CN107993000A (zh) * | 2017-11-27 | 2018-05-04 | 中国十九冶集团有限公司 | 基于bim的施工总平面动态协调管理的方法 |
-
2018
- 2018-06-04 CN CN201810562302.6A patent/CN108875167A/zh active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6058778B1 (ja) * | 2015-12-14 | 2017-01-11 | 東芝エレベータ株式会社 | Bimシステム、方法およびプログラム |
CN107993000A (zh) * | 2017-11-27 | 2018-05-04 | 中国十九冶集团有限公司 | 基于bim的施工总平面动态协调管理的方法 |
Non-Patent Citations (1)
Title |
---|
张志: ""基于BIM信息化技术的施工场地布置与优化"", 《天津建设科技》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109711076A (zh) * | 2018-12-29 | 2019-05-03 | 江苏龙腾数字建造技术研究院有限公司 | Bim模型在施工过程中的应用方法 |
CN109933900A (zh) * | 2019-03-13 | 2019-06-25 | 上海理工大学 | 一种基于bim技术的施工三维场布建模方法 |
CN109920036A (zh) * | 2019-04-02 | 2019-06-21 | 中国十七冶集团有限公司 | 一种基于bim技术的弧形钢结构施工方法 |
CN111581818A (zh) * | 2020-05-06 | 2020-08-25 | 北方工业大学 | 一种基于bim技术的施工现场布置优化方法 |
CN112364414A (zh) * | 2020-10-26 | 2021-02-12 | 中国能源建设集团安徽电力建设第一工程有限公司 | 一种基于bim技术的三维施工场地布置方法 |
CN112364414B (zh) * | 2020-10-26 | 2023-12-22 | 中能建建筑集团有限公司 | 一种基于bim技术的三维施工场地布置方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108875167A (zh) | 一种基于bim技术的施工现场三维布置优化方法 | |
CN109711052B (zh) | 基于Revit+Dynamo的隧道模型创建方法 | |
CN110851956B (zh) | 一种建设工程管道施工定位信息自动化计算、标注及出图方法 | |
CN105781064A (zh) | 基于bim的地砖铺设施工方法 | |
CN107862105A (zh) | 基于bim对构件施工工序进行技术交底的方法 | |
CN108563847B (zh) | 用catia软件将三维桥梁模型生成二维布置图的方法 | |
CN105975655B (zh) | 一种基于bim的仿唐宋古建异形屋面瓦参数化建模方法 | |
CN104631826A (zh) | 一种基于bim模型的施工总平面布置方法 | |
CN110688713B (zh) | 一种变电工程电气设备三维设计的线路连接系统 | |
CN110990928A (zh) | 一种跨软件平台的异形空间网格结构参数化设计方法 | |
CN105320012A (zh) | 一种多媒体动态舞台控制方法及系统 | |
CN112733230A (zh) | 一种基于bim技术的建筑机电管线综合优化方法 | |
CN110096268A (zh) | 将vr/ar/mr装置的可执行程序活态化二次编辑的系统及方法 | |
CN106844840B (zh) | 一种基于bim实现地铁车站快速建模的方法 | |
CN106780723B (zh) | 一种利用bim技术实现基坑快速参数化三维建模的方法 | |
CN114254238B (zh) | 一种基于数字孪生的三维Web建模平台 | |
CN111597625A (zh) | 一种基于bim的基坑支护开挖质量控制方法 | |
CN107679332A (zh) | 基于Tekla平台的输电铁塔BIM模型构建方法 | |
CN113505424B (zh) | 一种线性工程派生构件交互式建造方法 | |
CN103425844A (zh) | 基于数据流通信平台的cad/cae系统及集成方法 | |
CN115391856B (zh) | 一种基于bim的室外管网参数化建模方法及系统 | |
Li | Brief analysis of the application and limitation of BIM in project life cycle management | |
CN108549765B (zh) | 在Civil3D中利用要素线进行道路纵断设计的方法 | |
CN115587456A (zh) | 一种室外给排水管网bim正向设计方法及设计系统 | |
CN114297766A (zh) | 基于AutoCAD与DotNET的工程结构三视图联合设计的方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181123 |