CN110147949A - A method of power supply plan power supply point is expanded based on weighted score selection industry - Google Patents

A method of power supply plan power supply point is expanded based on weighted score selection industry Download PDF

Info

Publication number
CN110147949A
CN110147949A CN201910392552.4A CN201910392552A CN110147949A CN 110147949 A CN110147949 A CN 110147949A CN 201910392552 A CN201910392552 A CN 201910392552A CN 110147949 A CN110147949 A CN 110147949A
Authority
CN
China
Prior art keywords
power supply
point
power source
install
parameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910392552.4A
Other languages
Chinese (zh)
Inventor
赵伟
孙其芳
李雪清
万强
田治博
牛延明
林晓乐
郭婉琳
戎士敏
刘保安
赵昆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Shijiazhuang Power Supply Co of State Grid Hebei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Shijiazhuang Power Supply Co of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Hebei Electric Power Co Ltd, Shijiazhuang Power Supply Co of State Grid Hebei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201910392552.4A priority Critical patent/CN110147949A/en
Publication of CN110147949A publication Critical patent/CN110147949A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06315Needs-based resource requirements planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Educational Administration (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of methods for expanding power supply plan power supply point based on weighted score selection industry, are related to power supply plan and formulate technical field;It include S1 determine the basic condition for applying to install user and apply to install element, the power supply parameter of S2 analysis alternative power source point and supply path, S3 establish calculate factor matching matrix, S4 calculates the matrix numerical value and S5 selection alternative power source point of alternative power source point;Its by for user power utilization classification, in conjunction with power distribution network grid structure, comprehensively consider the influence factors such as economy, safety, scalability, realize the formulation of power supply technical solution.

Description

A method of power supply plan power supply point is expanded based on weighted score selection industry
Technical field
The present invention relates to power supply plans to formulate technical field, more particularly to a kind of based on weighted score selection industry expansion supplier of electricity The method of case power supply point.
Background technique
Business Process System be electric power enterprise be directed to Electricity customers propose electricity consumption application, according to customer electricity specific requirements, Safe, economically and reasonably power supply plan overall process is formulated in conjunction with the situation of supply network.Wherein Business Process System scheme power supply point Selection be power supply plan formulate important evidence.How according to existing all kinds of power network resources data, rapidly and accurately select automatically Power supply point is selected, the important link for influencing Business Process System progress is had become.Present power supply point selection mode, typically Using manually or automatically distance measuring method, the power supply point nearest from user is selected, but since various factors influences, is selected in this way Power supply point feasibility, safety, in terms of there are different problems.
Above-mentioned influence will bring completely new choose to the scalability of user's economy, power distribution network safe operation and Electric Power Network Planning War, how to ensure the power supply point of selection, can economical and effective access power grid under the premise of, so that it is farthest applied to install electricity Net safe and stable operation state, and certain scalability is kept, it is that reality one is urgently to be resolved during current power supply plan is formulated Difficult point.
Summary of the invention
Technical problem to be solved by the invention is to provide one kind to expand power supply plan power supply point based on weighted score selection industry Method, by for user power utilization classification, in conjunction with power distribution network grid structure, comprehensively consider economy, safety, can expand The influence factors such as malleability realize the formulation of power supply technical solution.
In order to solve the above technical problems, use is applied to install in S1 determination the technical solution used in the present invention is: including the following steps The basic condition at family and apply to install element;S2 inquiry applies to install user region interior power point situation and as alternative power source Point analyzes the power supply parameter and available supply path of each alternative power source point;S3, which is established, calculates factor matching matrix;S4 will be every The power supply parameter of one alternative power source point substitute into calculate factor matching matrix and obtain each alternative power source point molecular group, Then formula (1) is substituted into, calculates the matrix numerical value of the weight score of each alternative power source point,
Wherein, F is matrix numerical value, and Qj is weight score value, and Mj is the parameter factors of power data, and Ni is the ginseng of user data The number factor;Matrix numerical value of the S5 according to the weight score of alternative power source point, the preferential alternative power source point for selecting high score.
A further technical solution lies in: in the S2 step, apply to install user region be with this with applying to install user The regional scope that circle obtains is drawn by radius of distance to a declared goal centered on point.
A further technical solution lies in: the distance to a declared goal is 1 kilometer~10 kilometers.
A further technical solution lies in: the distance to a declared goal is 1.5 kilometers.
A further technical solution lies in: it further include following steps, S6 determines the power supply point quantity that power supply plan needs, weight Multiple S1 step~S5 step, obtains the plant-grid connection point and supply path of user's whole.
A further technical solution lies in: basic condition and phase by applying to install user described in intelligent terminal output display The power data and matrix numerical value answered.
A further technical solution lies in: the intelligent terminal is laptop, tablet computer or smart phone.
A further technical solution lies in: by applied to install described in printer output user basic condition and corresponding electricity Source data and matrix numerical value.
A further technical solution lies in: the printer is laser printer.
A further technical solution lies in: above-mentioned steps are run based on server and internet platform.
The beneficial effects of adopting the technical scheme are that
First, which realizes the formulation of power supply technical solution, solves and how to formulate power supply skill The technical issues of art scheme, work efficiency is high, and effect is good.
Second, in the S2 step, apply to install user region be by this apply to install user locations centered on it is specified away from The regional scope that circle obtains is drawn from for radius.The technical solution specifies specific distance with actual effect according to the usage requirement, Using more convenient, select more flexible.
Third, the distance to a declared goal are 1 kilometer~10 kilometers.The technical solution in the case where meeting using needing, is applicable in Property is preferable.
4th, the distance to a declared goal is 1.5 kilometers.The technical solution, meet using need in the case where, working efficiency compared with Height, effect are preferable.
5th, it further include following steps, S6 determines the power supply point quantity that power supply plan needs, and repeats S1 step~S5 step Suddenly, the plant-grid connection point and supply path of user's whole are obtained.The technical solution, preferably meets needs, and applicability is more preferable.
6th, the basic condition that user is applied to install described in display and corresponding power data and square are exported by intelligent terminal Battle array numerical value.The technical solution is easy to use or checks, using more convenient.
7th, the intelligent terminal is laptop, tablet computer or smart phone.The technical solution, convenient for making With operation, using more convenient.
8th, by the basic condition and corresponding power data and matrix function of applying to install user described in printer output Value.The technical solution is easy to use or checks, using more convenient.
9th, the printer is laser printer.The technical solution, cost performance is more preferable, is easy to use or checks, uses It is more convenient.
Tenth, above-mentioned steps are run based on server and internet platform.The technical solution is shared convenient for team, uses It is more convenient.
It is detailed in specific embodiment part description.
Detailed description of the invention
Fig. 1 is flow chart of the invention;
Fig. 2 is user and power supply point calculating parameter comparative diagram in the present invention;
Fig. 3 is calculating factor matching matrix figure in the present invention.
Specific embodiment
Below in conjunction with the attached drawing in the embodiment of the present application, technical solutions in the embodiments of the present application carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of embodiments of the present application, instead of all the embodiments.Below Description only actually at least one exemplary embodiment be it is illustrative, never as to the application and its application or making Any restrictions.Based on the embodiment in the application, those of ordinary skill in the art are not making creative work premise Under every other embodiment obtained, shall fall in the protection scope of this application.
Many details are explained in the following description in order to fully understand the application, but the application can be with Implemented using other than the one described here other way, those skilled in the art can be without prejudice to the application intension In the case of do similar popularization, therefore the application is not limited by the specific embodiments disclosed below.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singular Also it is intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " packet Include " when, indicate existing characteristics, step, operation, device, component and/or their combination.
Unless specifically stated otherwise, positioned opposite, the digital table of the component and step that otherwise illustrate in these embodiments Up to the unlimited scope of the present application processed of formula and numerical value.Simultaneously, it should be appreciated that for ease of description, each portion shown in attached drawing The size divided not is to draw according to actual proportionate relationship.For technology, side known to person of ordinary skill in the relevant Method and equipment may be not discussed in detail, but in the appropriate case, and the technology, method and apparatus should be considered as authorizing explanation A part of book.In shown here and discussion all examples, any occurrence should be construed as merely illustratively, and Not by way of limitation.Therefore, the other examples of exemplary embodiment can have different values.It should also be noted that similar label Similar terms are indicated in following attached drawing with letter, therefore, once it is defined in a certain Xiang Yi attached drawing, then subsequent attached It does not need that it is further discussed in figure.
In the description of the present application, it is to be understood that the noun of locality such as " front, rear, top, and bottom, left and right ", " laterally, vertical, Vertically, orientation or positional relationship indicated by level " and " top, bottom " etc. is normally based on orientation or position shown in the drawings and closes System is merely for convenience of description the application and simplifies description, and in the absence of explanation to the contrary, these nouns of locality do not indicate that It must have a particular orientation or be constructed and operated in a specific orientation with the device or element for implying signified, therefore cannot manage Solution is the limitation to the application protection scope;The noun of locality " inside and outside " refers to inside and outside the profile relative to each component itself.
For ease of description, spatially relative term can be used herein, as " ... on ", " ... top ", " ... upper surface ", " above " etc., for describing such as a device shown in the figure or feature and other devices or spy The spatial relation of sign.It should be understood that spatially relative term is intended to comprising the orientation in addition to device described in figure Except different direction in use or operation.For example, being described as if the device in attached drawing is squeezed " in other devices It will be positioned as " under other devices or construction after part or construction top " or the device of " on other devices or construction " Side " or " under other devices or construction ".Thus, exemplary term " ... top " may include " ... top " and " in ... lower section " two kinds of orientation.The device can also be positioned with other different modes and (is rotated by 90 ° or in other orientation), and And respective explanations are made to the opposite description in space used herein above.
In addition, it should be noted that, limiting components using the words such as " first ", " second ", it is only for be convenient for Corresponding components are distinguished, do not have Stated otherwise such as, there is no particular meanings for above-mentioned word, therefore should not be understood as to this Apply for the limitation of protection scope.
Embodiment 1:
As shown in Figure 1-Figure 3, the invention discloses a kind of sides for expanding power supply plan power supply point based on weighted score selection industry Method includes the following steps,
S1 determines the basic condition for applying to install user and applies to install element
It determines the basic condition for applying to install user and applies to install element, and be decomposed into and apply to install basic parameter.
The power supply parameter and supply path of S2 analysis alternative power source point
Understand the three kilometer range interior power point situations for applying to install user region and as alternative power source point, analysis The power supply parameter and available supply path of each alternative power source point.
As shown in Fig. 2, the contrast relationship table and weight score value of two kinds of parameters in matrix are determined, according to where applying to install user The three kilometer range interior power point situations in region inquire the related of each power supply point and supply according to power network resources basic data Electrical parameter, and according to the concrete meaning of each relevant parameter, convert parameter to the calculating factor of each power supply point.
The determination of weighted value therein can be set according to importance rate of all kinds of parameters in power supply plan formulation Fixed and adjustment.
Judge the matching degree of each parameter, if parameter meets matching condition, otherwise it is 0 that numerical value, which is 1, in matrix.
S3, which is established, calculates factor matching matrix
Factor matching matrix is calculated as shown in figure 3, establishing.
Two classes calculate the factor in matrix, and one kind is that user applies to install parameter factors, and one kind is power supply point parameter factors.When two kinds When factor parameter matches, numerical value is just 1 in matrix, is otherwise just 0.
The matrix numerical value of S4 calculating alternative power source point
The power supply parameter of each alternative power source point is substituted into and calculates factor matching matrix and obtains each alternative power source Point obtains molecular group, then substitutes into formula 1, calculates the matrix numerical value of the weight score of each alternative power source point.
Wherein, F is matrix numerical value, and Qj is weight score value, and Mj is the parameter factors of power data, and Ni is the ginseng of user data The number factor.
S5 selects alternative power source point
According to the matrix numerical value of the weight score of alternative power source point, the preferential alternative power source point for selecting high score.I.e. according to confession Each power supply point calculates score in electric range, selects the power supply point of highest scoring.
The plant-grid connection point and supply path of S6 acquisition user's whole
It determines the power supply point quantity that power supply plan needs, repeats S1 step~S5 step, the power supply for obtaining user's whole connects Access point and supply path.
Example is as follows:
Certain customer power supply applies to install scheme, and it is as follows that user applies to install parameter:
Electricity consumption type: business;
Voltage class: 10kV;
Importance rate: common;
Apply to install capacity: 800.
Power supply point A, parameter are respectively:
Route basic load type: business;
Line voltage distribution grade: 10kV;
Power supply vertex type: switching station;
Route can open capacity: 1000;
Power supply point position: 500 meters;
Power supply point availability interval: have.
Parameter is substituted into and calculates factor matching matrix, matrix numerical value is obtained, then substitutes into calculation formula, obtain F=2.83.
Power supply point B, parameter are respectively:
Route basic load type: industry;
Power supply vertex type: switching station;
Route can open capacity: 500;
Power supply point position: 200 meters;
Power supply point availability interval: have.
Parameter is substituted into and calculates factor matching matrix, matrix numerical value is obtained, then substitutes into calculation formula, obtain F=2.24.
Power supply point C, parameter are respectively:
Route basic load type: industry;
Power supply vertex type: switching station;
Route can open capacity: 1000;
Power supply point position: 1000 meters;
Power supply point availability interval: nothing.
Parameter is substituted into and calculates factor matching matrix, matrix numerical value is obtained, then substitutes into calculation formula, obtain F=2.45.
The power supply point for selecting highest scoring, draws a conclusion using power supply point A.
Using the power supply point choosing method of power supply plan of the invention, the formulation of power supply technical solution is realized.Energy It is enough under the premise of ensuring user's effectively access power grid on time, meet client in the recent period, long term to electric power the needs of, while guaranteeing electricity The safe operation of net and power grid construction, transformation and development plan requirement.Work efficiency is high, and effect is good.
Embodiment 2:
Embodiment 2 is similar to Example 1, the difference is that, the distance to a declared goal is 1 kilometer.
The method of power supply plan power supply point is expanded based on weighted score selection industry the invention discloses a kind of, including is walked as follows Suddenly,
S1 determines the basic condition for applying to install user and applies to install element
It determines the basic condition for applying to install user and applies to install element, and be decomposed into and apply to install basic parameter.
The power supply parameter and supply path of S2 analysis alternative power source point
Understand the two kilometer range interior power point situations for applying to install user region and as alternative power source point, analysis The power supply parameter and available supply path of each alternative power source point.
The contrast relationship table and weight score value for determining two kinds of parameters in matrix, it is public according to apply to install user region two In range interior power point situation the related power supply parameter of each power supply point, and root inquired according to power network resources basic data According to the concrete meaning of each relevant parameter, it converts parameter to the calculating factor of each power supply point.
The determination of weighted value therein can be set according to importance rate of all kinds of parameters in power supply plan formulation Fixed and adjustment.
Judge the matching degree of each parameter, if parameter meets matching condition, otherwise it is 0 that numerical value, which is 1, in matrix.
S3, which is established, calculates factor matching matrix
It establishes and calculates factor matching matrix.
Two classes calculate the factor in matrix, and one kind is that user applies to install parameter factors, and one kind is power supply point parameter factors.When two kinds When factor parameter matches, numerical value is just 1 in matrix, is otherwise just 0.
The matrix numerical value of S4 calculating alternative power source point
The power supply parameter of each alternative power source point is substituted into and calculates factor matching matrix and obtains each alternative power source Point obtains molecular group, then substitutes into formula 1, calculates the matrix numerical value of the weight score of each alternative power source point.
Wherein, F is matrix numerical value, and Qj is weight score value, and Mj is the parameter factors of power data, and Ni is the ginseng of user data The number factor.
S5 selects alternative power source point
According to the matrix numerical value of the weight score of alternative power source point, the preferential alternative power source point for selecting high score.I.e. according to confession Each power supply point calculates score in electric range, selects the power supply point of highest scoring.
The plant-grid connection point and supply path of S6 acquisition user's whole
It determines the power supply point quantity that power supply plan needs, repeats S1 step~S5 step, the power supply for obtaining user's whole connects Access point and supply path.
Embodiment 3:
Embodiment 3 is similar to Example 1, the difference is that, the distance to a declared goal is 5 kilometers.
The method of power supply plan power supply point is expanded based on weighted score selection industry the invention discloses a kind of, including is walked as follows Suddenly,
S1 determines the basic condition for applying to install user and applies to install element
It determines the basic condition for applying to install user and applies to install element, and be decomposed into and apply to install basic parameter.
The power supply parameter and supply path of S2 analysis alternative power source point
Understand the ten kilometer range interior power point situations for applying to install user region and as alternative power source point, analysis The power supply parameter and available supply path of each alternative power source point.
The contrast relationship table and weight score value for determining two kinds of parameters in matrix, it is public according to apply to install user region ten In range interior power point situation the related power supply parameter of each power supply point, and root inquired according to power network resources basic data According to the concrete meaning of each relevant parameter, it converts parameter to the calculating factor of each power supply point.
The determination of weighted value therein can be set according to importance rate of all kinds of parameters in power supply plan formulation Fixed and adjustment.
Judge the matching degree of each parameter, if parameter meets matching condition, otherwise it is 0 that numerical value, which is 1, in matrix.
S3, which is established, calculates factor matching matrix
It establishes and calculates factor matching matrix.
Two classes calculate the factor in matrix, and one kind is that user applies to install parameter factors, and one kind is power supply point parameter factors.When two kinds When factor parameter matches, numerical value is just 1 in matrix, is otherwise just 0.
The matrix numerical value of S4 calculating alternative power source point
The power supply parameter of each alternative power source point is substituted into and calculates factor matching matrix and obtains each alternative power source Point obtains molecular group, then substitutes into formula 1, calculates the matrix numerical value of the weight score of each alternative power source point.
Wherein, F is matrix numerical value, and Qj is weight score value, and Mj is the parameter factors of power data, and Ni is the ginseng of user data The number factor.
S5 selects alternative power source point
According to the matrix numerical value of the weight score of alternative power source point, the preferential alternative power source point for selecting high score.I.e. according to confession Each power supply point calculates score in electric range, selects the power supply point of highest scoring.
The plant-grid connection point and supply path of S6 acquisition user's whole
It determines the power supply point quantity that power supply plan needs, repeats S1 step~S5 step, the power supply for obtaining user's whole connects Access point and supply path.
Embodiment 4:
Embodiment 4 is similar to Example 1, the difference is that, the distance to a declared goal is 10 kilometers.
The method of power supply plan power supply point is expanded based on weighted score selection industry the invention discloses a kind of, including is walked as follows Suddenly,
S1 determines the basic condition for applying to install user and applies to install element
It determines the basic condition for applying to install user and applies to install element, and be decomposed into and apply to install basic parameter.
The power supply parameter and supply path of S2 analysis alternative power source point
Understanding applies to install 20 kilometer range interior power point situations of user region and as alternative power source point, divides Analyse the power supply parameter and available supply path of each alternative power source point.
The contrast relationship table and weight score value for determining two kinds of parameters in matrix, according to applying to install the 20 of user region Kilometer range interior power point situation inquires the related power supply parameter of each power supply point according to power network resources basic data, and According to the concrete meaning of each relevant parameter, it converts parameter to the calculating factor of each power supply point.
The determination of weighted value therein can be set according to importance rate of all kinds of parameters in power supply plan formulation Fixed and adjustment.
Judge the matching degree of each parameter, if parameter meets matching condition, otherwise it is 0 that numerical value, which is 1, in matrix.
S3, which is established, calculates factor matching matrix
It establishes and calculates factor matching matrix.
Two classes calculate the factor in matrix, and one kind is that user applies to install parameter factors, and one kind is power supply point parameter factors.When two kinds When factor parameter matches, numerical value is just 1 in matrix, is otherwise just 0.
The matrix numerical value of S4 calculating alternative power source point
The power supply parameter of each alternative power source point is substituted into and calculates factor matching matrix and obtains each alternative power source Point obtains molecular group, then substitutes into formula 1, calculates the matrix numerical value of the weight score of each alternative power source point.
Wherein, F is matrix numerical value, and Qj is weight score value, and Mj is the parameter factors of power data, and Ni is the ginseng of user data The number factor.
S5 selects alternative power source point
According to the matrix numerical value of the weight score of alternative power source point, the preferential alternative power source point for selecting high score.I.e. according to confession Each power supply point calculates score in electric range, selects the power supply point of highest scoring.
The plant-grid connection point and supply path of S6 acquisition user's whole
It determines the power supply point quantity that power supply plan needs, repeats S1 step~S5 step, the power supply for obtaining user's whole connects Access point and supply path.
Relative to above-described embodiment, the basic condition and phase that user is applied to install described in display can be exported by intelligent terminal The power data and matrix numerical value answered.
Relative to above-described embodiment, the intelligent terminal is laptop, tablet computer or smart phone.
Relative to above-described embodiment, can by applied to install described in printer output user basic condition and corresponding electricity Source data and matrix numerical value.
Relative to above-described embodiment, the printer is laser printer.
Relative to above-described embodiment, above-mentioned steps can be run based on server and internet platform.

Claims (10)

1. a kind of method for expanding power supply plan power supply point based on weighted score selection industry, it is characterised in that: include the following steps, S1 It determines the basic condition for applying to install user and applies to install element;S2 inquiry apply to install user region interior power point situation and as Alternative power source point analyzes the power supply parameter and available supply path of each alternative power source point;S3, which is established, calculates factor matching square Battle array;S4, which substitutes into the power supply parameter of each alternative power source point, to be calculated factor matching matrix and obtains each alternative power source point Molecular group is obtained, then formula (1) is substituted into, calculates the matrix numerical value of the weight score of each alternative power source point,
Wherein, F be matrix numerical value, Qj be weight score value, Mj be power data parameter factors, Ni be user data parameter because Son;Matrix numerical value of the S5 according to the weight score of alternative power source point, the preferential alternative power source point for selecting high score.
2. a kind of method for expanding power supply plan power supply point based on weighted score selection industry according to claim 1, feature Be: in the S2 step, apply to install user region be by this apply to install user locations centered on using distance to a declared goal as radius Draw the regional scope that circle obtains.
3. a kind of method for expanding power supply plan power supply point based on weighted score selection industry according to claim 2, feature Be: the distance to a declared goal is 1 kilometer~10 kilometers.
4. a kind of method for expanding power supply plan power supply point based on weighted score selection industry according to claim 3, feature Be: the distance to a declared goal is 1.5 kilometers.
5. a kind of method for expanding power supply plan power supply point based on weighted score selection industry according to claim 1, feature It is: further includes following steps, S6 determines the power supply point quantity that power supply plan needs, and repeats S1 step~S5 step, is used The plant-grid connection point and supply path of family whole.
6. a kind of method for expanding power supply plan power supply point based on weighted score selection industry according to claim 1, feature It is: exports the basic condition for applying to install user described in display and corresponding power data and matrix numerical value by intelligent terminal.
7. a kind of method for expanding power supply plan power supply point based on weighted score selection industry according to claim 6, feature Be: the intelligent terminal is laptop, tablet computer or smart phone.
8. a kind of method for expanding power supply plan power supply point based on weighted score selection industry according to claim 1, feature It is: basic condition and corresponding power data and matrix numerical value by applying to install user described in printer output.
9. a kind of method for expanding power supply plan power supply point based on weighted score selection industry according to claim 8, feature Be: the printer is laser printer.
10. one kind described in any one of -9 is based on weighted score selection industry expansion power supply plan power supply point according to claim 1 Method, it is characterised in that: above-mentioned steps are run based on server and internet platform.
CN201910392552.4A 2019-05-13 2019-05-13 A method of power supply plan power supply point is expanded based on weighted score selection industry Pending CN110147949A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910392552.4A CN110147949A (en) 2019-05-13 2019-05-13 A method of power supply plan power supply point is expanded based on weighted score selection industry

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910392552.4A CN110147949A (en) 2019-05-13 2019-05-13 A method of power supply plan power supply point is expanded based on weighted score selection industry

Publications (1)

Publication Number Publication Date
CN110147949A true CN110147949A (en) 2019-08-20

Family

ID=67594227

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910392552.4A Pending CN110147949A (en) 2019-05-13 2019-05-13 A method of power supply plan power supply point is expanded based on weighted score selection industry

Country Status (1)

Country Link
CN (1) CN110147949A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105046398A (en) * 2015-05-29 2015-11-11 中国南方电网有限责任公司 System and method for intelligently carrying out business expansion aided installation
CN105844418A (en) * 2016-03-28 2016-08-10 国家电网公司 Business expansion intelligent mobile terminal
US20180114167A1 (en) * 2016-10-21 2018-04-26 International Business Machines Corporation Energy supplier strategy based on supplier confidence scoring

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105046398A (en) * 2015-05-29 2015-11-11 中国南方电网有限责任公司 System and method for intelligently carrying out business expansion aided installation
CN105844418A (en) * 2016-03-28 2016-08-10 国家电网公司 Business expansion intelligent mobile terminal
US20180114167A1 (en) * 2016-10-21 2018-04-26 International Business Machines Corporation Energy supplier strategy based on supplier confidence scoring

Similar Documents

Publication Publication Date Title
CN103970887B (en) A kind of information flow display system and method based on GIS power distribution network figures
CN102725933B (en) Dynamic distributed grid control system
US10090704B2 (en) Display device and display method of electric power system information
CN109670675B (en) Method and device for evaluating running state of charging pile
CN104538958B (en) The intelligent analysis method of Electricity customers electrical network access point and system
CN108228296A (en) A kind of light show visualizes system and method
CN110443499A (en) A kind of inventory project amount automatic generation method and system
CN108520362A (en) A kind of integrated evaluating method of rural area intelligent grid level
CN103996147A (en) Comprehensive evaluation method for power distribution network
CN110348674A (en) A kind of power grid risk assessment method, system and computer readable storage medium
CN103093007A (en) Power transmission iron tower three-dimensional virtual assembly method
CN108717473A (en) A kind of UHV transmission line digitlization electrical design method
CN107069801B (en) A kind of power distribution network isolated island division methods based on minimum Custom interruption cost
CN107609794A (en) A kind of technology maturity evaluation information processing unit
Sanchis et al. The Corridors of Power: A Pan-European\" Electricity Highway\" System for 2050
CN105139712B (en) On-line scheduling person's training system and its method based on real-time simulation
Nowak et al. Cloud-based DERMS test platform using real-time power system simulation
KR20150028436A (en) Apparatus and method for calculating connection possible capacity of distributed generator
CN105790256A (en) Multi-agent technology-based identification method for critical paths of distributed power generation units accessed to power distribution network
CN106684870B (en) Power supply plan formulating method and device
CN102647022A (en) Power distribution network intelligent operation and maintenance center based on enterprise service bus
CN110147949A (en) A method of power supply plan power supply point is expanded based on weighted score selection industry
CN102479359A (en) Power grid overhauling plan compilation method based on graphic operations
CN109599895A (en) A kind of distributed photovoltaic cut-in method based on clustering
Dutrieux et al. Assessing the impacts of distribution grid planning rules on the integration of renewable energy sources

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190820