CN106684870B - Power supply plan formulating method and device - Google Patents

Power supply plan formulating method and device Download PDF

Info

Publication number
CN106684870B
CN106684870B CN201710189785.5A CN201710189785A CN106684870B CN 106684870 B CN106684870 B CN 106684870B CN 201710189785 A CN201710189785 A CN 201710189785A CN 106684870 B CN106684870 B CN 106684870B
Authority
CN
China
Prior art keywords
data
power grid
grid access
power supply
access way
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201710189785.5A
Other languages
Chinese (zh)
Other versions
CN106684870A (en
Inventor
韩振泉
栗新
张兴强
袁涛
王志强
张德金
王毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xiajin Power Supply Company State Grid Shandong Electric Power Co
State Grid Corp of China SGCC
Original Assignee
Xiajin Power Supply Company State Grid Shandong Electric Power Co
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiajin Power Supply Company State Grid Shandong Electric Power Co, State Grid Corp of China SGCC filed Critical Xiajin Power Supply Company State Grid Shandong Electric Power Co
Priority to CN201710189785.5A priority Critical patent/CN106684870B/en
Publication of CN106684870A publication Critical patent/CN106684870A/en
Application granted granted Critical
Publication of CN106684870B publication Critical patent/CN106684870B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention provides a kind of power supply plan formulating method and devices;Wherein, this method includes receiving the electricity consumption application information and data of job-site survey of user to be powered;The data of job-site survey includes the confirmation message to electricity consumption application information, power grid access demand information, by electricity demanding information and electricity consumption point distributed intelligence;Extract the parameter area of power supply plan corresponding with the electricity consumption application information after confirmation;According to power grid access demand information, by electricity demanding information and parameter area, generate the power grid access way data and electric means data of user to be powered;According to power grid access way data and electric means data, component locations distribution map and line alignment figure are generated;Power grid access way data, electric means data, component locations distribution map and line alignment figure are determined as to the power supply plan of user to be powered.The present invention improves the Accuracy and high efficiency for formulating power supply plan.

Description

Power supply plan formulating method and device
Technical field
The present invention relates to technical field of electric power, more particularly, to a kind of power supply plan formulating method and device.
Background technique
Power supply plan refers to electricity unit because newly-increased electricity consumption facility or existing power supply are not able to satisfy current and submit Electricity consumption application, after auditing the electricity consumption application by local power supply department, the scheme of formulation.Power supply plan by access system plan and by Electric system scheme composition.Wherein, access system plan include client power supply voltage class, power supply capacity, power supply position, Power supply number, current supply circuit number, path, outlet method and power supply line's laying etc.;It is included inlet wire side by electric system scheme Formula, power receiving device capacity, main electrical scheme, the method for operation, the means of relay protection, dispatching communication, security measures, way of energy measuring and The mode of connection, installation site, property right and responsibility of maintenance separation, electric equipments technical parameter etc..
Power supply department needs to carry out the various pieces in power supply plan by staff multiple when formulating power supply plan Audit, for example, audit access system plan, by electric system scheme, audit metered scheme, billing scheme etc.;It is repeatedly complicated Auditing flow undoubtedly extend period of power supply plan formulation, and in review process, be compareed by staff it is related Policy is audited, the subjectivity in review process be likely to result in final power supply plan reasonability and accuracy it is poor.
Problem poor for above-mentioned formulation power supply plan accuracy and that efficiency is lower not yet proposes effective solution at present Scheme.
Summary of the invention
In view of this, being supplied the purpose of the present invention is to provide a kind of power supply plan formulating method and device with improving to formulate The Accuracy and high efficiency of electric scheme.
In a first aspect, the embodiment of the invention provides a kind of power supply plan formulating methods, comprising: receive user's to be powered Electricity consumption application information and data of job-site survey;Wherein, which includes the affiliated industry of user to be powered, with electrical property Matter appraises and decides electricity capacity and drafts client's classification;Data of job-site survey includes connecing to the confirmation message of electricity consumption application information, power grid Enter demand information, by electricity demanding information and electricity consumption point distributed intelligence;Extract confession corresponding with the electricity consumption application information after confirmation The parameter area of electric scheme;Wherein, the parameter area of the power supply plan is arranged according to the supply standard pre-established;According to power grid Access demand information, by electricity demanding information and parameter area, generate the power grid access way data of user to be powered and by electricity side Formula data;According to power grid access way data and electric means data, component locations distribution map and line alignment figure are generated;Its In, it include the position distribution of power supply, distribution transformer and metering device of powering in component locations distribution map;Line alignment It include the path trend of power supply line and low-voltage cable in figure;By power grid access way data, electric means data, component position It sets distribution map and line alignment figure is determined as the power supply plan of user to be powered.
With reference to first aspect, the embodiment of the invention provides the first possible embodiments of first aspect, wherein on It states according to power grid access demand information, by electricity demanding information and parameter area, generates the power grid access way number of user to be powered According to, comprising: by power grid access demand information input into the power grid access way model pre-established, generate preliminary power grid access Mode data;Wherein, power grid access way model is according to power grid access demand information in historical data and power grid access way number According to matching relationship establish;Judge whether preliminary power grid access way data meet parameter area;If so, preliminary power grid is connect Enter the power grid access way data that mode data are determined as user to be powered;If not, adjusting preliminary power grid access way data Until meeting parameter area, preliminary power grid access way data adjusted are determined as to the power grid access way of user to be powered Data;Wherein, power grid access way data include power supply voltage level, the power supply capacity of power supply and connect with power supply The power supply capacity of the road Jie Mei inlet wire.
With reference to first aspect, the embodiment of the invention provides second of possible embodiments of first aspect, wherein on It states according to power grid access demand information, by electricity demanding information and parameter area, generates the electric means data of user to be powered, wrap It includes:, into the electric means model pre-established, preliminary electric means data will be generated by electricity demanding information input;Wherein, by Electric mode model is established according to the matching relationship of electricity consumption application information in historical data and electric means data;Judgement is tentatively by electricity Whether mode data meet parameter area;If so, preliminary electric means data to be determined as to the electric means of user to be powered Data;If not, preliminary electric means data adjusted are determined as by adjustment electric means data up to meeting parameter area The electric means data of user to be powered;Wherein, electric means data include power receiving device capacity, it is reactive compensation standard, electrical The main line mode of connection and the method for operation.
With reference to first aspect, the embodiment of the invention provides the third possible embodiments of first aspect, wherein on It states according to power grid access way data and electric means data, generates component locations distribution map and line alignment figure, comprising: from In pre-stored component data, the component class to match with power grid access way data and electric means data is screened Type;Wherein, component includes power supply, distribution transformer, power supply metering device, power supply line and low-voltage cable;With route The component filtered out is distributed by the minimum principle of total length according to electricity consumption point distributed intelligence, generates component locations point Butut and line alignment figure.
With reference to first aspect, the embodiment of the invention provides the 4th kind of possible embodiments of first aspect, wherein on State method further include: extract the parameter area for counting electric mode corresponding with the electricity consumption application information after confirmation;Wherein, Ji electricity Fang The parameter area of formula is arranged according to the meter electric standard pre-established;Using the method for machine learning, prediction and the electricity consumption after confirmation The primary charging mode data that application information matches;Primary charging mode data are adjusted, until meeting the parameter for counting electric mode Range;Primary charging mode data adjusted are determined as to the charging mode data of user to be powered.
Second aspect, the embodiment of the invention provides a kind of power supply plan making devices, comprising: receiving module, for connecing Receive the electricity consumption application information and data of job-site survey of user to be powered;Wherein, electricity consumption application information includes the institute of user to be powered Belong to industry, load nature of electricity consumed, appraise and decide electricity capacity and drafts client's classification;Data of job-site survey include to electricity consumption application information really Recognize information, power grid access demand information, by electricity demanding information and electricity consumption point distributed intelligence;First extraction module, for extract with The parameter area of the corresponding power supply plan of electricity consumption application information after confirmation;Wherein, the parameter area of power supply plan is according to pre- The supply standard setting first formulated;First generation module is used for according to power grid access demand information, by electricity demanding information and parameter Range generates the power grid access way data and electric means data of user to be powered;Second generation module, for according to power grid Access way data and electric means data generate component locations distribution map and line alignment figure;Wherein, component locations point It include the position distribution of power supply, distribution transformer and metering device of powering in Butut;It include supply lines in line alignment figure Road and the path of low-voltage cable trend;Power supply plan determining module, for by power grid access way data, electric means data, Component locations distribution map and line alignment figure are determined as the power supply plan of user to be powered.
In conjunction with second aspect, the embodiment of the invention provides the first possible embodiments of second aspect, wherein on Stating the first generation module includes: the first generation unit, for connecing power grid access demand information input to the power grid pre-established Enter in mode model, generates preliminary power grid access way data;Wherein, power grid access way model is according to power grid in historical data The matching relationship of access demand information and power grid access way data is established;First judging unit, for judging that preliminary power grid connects Enter whether mode data meet parameter area;First determination unit, if meeting parameter for preliminary power grid access way data Preliminary power grid access way data are determined as the power grid access way data of user to be powered by range;The first adjustment unit is used If being unsatisfactory for parameter area in preliminary power grid access way data, preliminary power grid access way data are adjusted until meeting parameter Preliminary power grid access way data adjusted are determined as the power grid access way data of user to be powered by range;Wherein, electric Net access way data include power supply voltage level, the power supply capacity of power supply and every road inlet wire for connecting with power supply Power supply capacity.
In conjunction with second aspect, the embodiment of the invention provides second of possible embodiments of second aspect, wherein on Stating the first generation module includes: the second generation unit, for will be by electricity demanding information input to the electric means mould pre-established In type, preliminary electric means data are generated;Wherein, electric means model is according to electricity consumption application information in historical data and by electricity side The matching relationship of formula data is established;Second judgment unit, for judging whether preliminary electric means data meet parameter area;The Preliminary electric means data are determined as wait supply by two determination units if meeting parameter area for preliminary electric means data The electric means data of electric user;Second adjustment unit adjusts if being unsatisfactory for parameter area for preliminary electric means data Electric means data until meet parameter area, by preliminary electric means data adjusted be determined as user to be powered by electricity Mode data;Wherein, electric means data include power receiving device capacity, reactive compensation standard, the electrical main line mode of connection and fortune Line mode.
In conjunction with second aspect, the embodiment of the invention provides the third possible embodiments of second aspect, wherein on Stating the second generation module includes: screening unit, for screening and power grid access way number from pre-stored component data According to the component type to match with electric means data;Wherein, component includes power supply, distribution transformer, power supply meter Measure device, power supply line and low-voltage cable;Component distribution unit is used for the minimum principle of total line length, according to electricity consumption The component filtered out is distributed by point distributed intelligence, generates component locations distribution map and line alignment figure.
In conjunction with second aspect, the embodiment of the invention provides the 4th kind of possible embodiments of second aspect, wherein on State device further include: the second extraction module, by extract with confirm after electricity consumption application information it is corresponding based on electric mode ginseng Number range;Wherein, the parameter area for counting electric mode is arranged according to the meter electric standard pre-established;Prediction module, for using machine The method of device study, the primary charging mode data that prediction matches with the electricity consumption application information after confirmation;Module is adjusted, is used for Primary charging mode data are adjusted, until meeting the parameter area for counting electric mode;Charging mode data determining module, for that will adjust Primary charging mode data after whole are determined as the charging mode data of user to be powered.
The embodiment of the present invention bring it is following the utility model has the advantages that
A kind of power supply plan formulating method and device provided in an embodiment of the present invention, according to the electricity consumption application of user to be powered The parameter area of information, data of job-site survey and the corresponding power supply plan of electricity consumption application information, can be generated use to be powered The power grid access way data and electric means data at family;And then according to the power grid access way data and electric means data, Component locations distribution map and line alignment figure can be generated;Finally by power grid access way data, electric means data, first device Part location map and line alignment figure are determined as the power supply plan of user to be powered.This method can accurately and efficiently be made The power supply plan of user to be powered, avoid through the caused Review Cycle manually audited layer by layer long, heavy workload and Error-prone defect improves the Accuracy and high efficiency for formulating power supply plan.
Other features and advantages of the present invention will illustrate in the following description, also, partly become from specification It obtains it is clear that understand through the implementation of the invention.The objectives and other advantages of the invention are in specification, claims And specifically noted structure is achieved and obtained in attached drawing.
To enable the above objects, features and advantages of the present invention to be clearer and more comprehensible, preferred embodiment is cited below particularly, and cooperate Appended attached drawing, is described in detail below.
Detailed description of the invention
It, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution in the prior art Embodiment or attached drawing needed to be used in the description of the prior art be briefly described, it should be apparent that, it is described below Attached drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not making the creative labor It puts, is also possible to obtain other drawings based on these drawings.
Fig. 1 is a kind of flow chart of power supply plan formulating method provided in an embodiment of the present invention;
Fig. 2 is in a kind of power supply plan formulating method provided in an embodiment of the present invention, according to power grid access demand information, by Electricity demanding information and parameter area generate the specific flow chart of the power grid access way data of user to be powered;
Fig. 3 is a kind of structural schematic diagram of power supply plan making device provided in an embodiment of the present invention;
Fig. 4 is the specific structure of the first generation module in a kind of power supply plan making device provided in an embodiment of the present invention Schematic diagram.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with attached drawing to the present invention Technical solution be clearly and completely described, it is clear that described embodiments are some of the embodiments of the present invention, rather than Whole embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art are not making creative work premise Under every other embodiment obtained, shall fall within the protection scope of the present invention.
For the problem that power supply plan accuracy is poor and efficiency is lower is formulated, the embodiment of the invention provides a kind of power supplies Solution formulation method and apparatus;The technology can be applied to power generation department or power operation administrative department and power to application During user is powered solution formulation, the mistake to the audit of power supply customer power supply scheme later period, revision also can be applied to Cheng Zhong;The technology can use corresponding software or hardware realization, be described below by embodiment.
Embodiment one:
A kind of flow chart of power supply plan formulating method shown in Figure 1, this method comprises the following steps:
Step S102 receives the electricity consumption application information and data of job-site survey of user to be powered;Wherein, the electricity consumption letter of application Breath includes the affiliated industry of user to be powered, load nature of electricity consumed, appraises and decides electricity capacity and draft client's classification;The data of job-site survey Including to electricity consumption application information confirmation message, power grid access demand information, by electricity demanding information and electricity consumption point distributed intelligence;
In general, correlation can be organized after power supply plan formulates the electricity consumption application information that unit recipient is submitted to user to be powered Staff goes to the address of user to be powered to carry out the inspection of the scene of a crime, can confirm that user to be powered submits during reconnoitring at the scene Whether electricity consumption application information true, and according to the practical load nature of electricity consumed of user to be powered, building structure, the distribution of electricity consumption point, should be to The factors such as the grid condition on power supply station address periphery are submitted the power grid access demand information of the user to be powered, are believed by electricity demanding Breath and the distributed intelligence of electricity consumption point.
Step S104 extracts the parameter area of power supply plan corresponding with the electricity consumption application information after confirmation;Wherein, should The parameter area of power supply plan is arranged according to the supply standard pre-established;
Specifically, above-mentioned supply standard can be the user the country in which it is located to be powered or the unified power supply mark of provinces and regions formulation Standard, for example, industry expands the related supply standards such as power supply plan establishment directive/guide, power consumer power supply monitor configured management opinion; Data relevant to power supply plan formulation process are extracted from above-mentioned supply standard, to generate the parameter model of above-mentioned power supply plan It encloses;The parameter area of the power supply plan can specification power supply plan formulate in specific data, improve the reasonability of power supply plan And safety.
Step S106 generates user's to be powered according to power grid access demand information, by electricity demanding information and parameter area Power grid access way data and electric means data;
Specifically, above-mentioned power grid access way data include the power supply of power supply voltage level, power supply and every road inlet wire Capacity, power supply line and system of laying requirement etc.;Above-mentioned electric means data include the capacity of power receiving device, reactive compensation mark Standard, consumer electrical main wiring mode, the method for operation, main power receiving device electric parameter, and clear emergency power supply and security measures Configuration, harmonic wave control, relay protection, dispatching communication requirement etc..
Step S108 generates component locations distribution map and line according to power grid access way data and electric means data Move towards figure in road;It wherein, include the position of power supply, distribution transformer and metering device of powering in the component locations distribution map Distribution;It include the path trend of power supply line and low-voltage cable in the line alignment figure;
Step S110, by power grid access way data, electric means data, component locations distribution map and line alignment figure It is determined as the power supply plan of user to be powered.
A kind of power supply plan formulating method provided in an embodiment of the present invention, according to the electricity consumption application information of user to be powered, The parameter area of data of job-site survey and the corresponding power supply plan of electricity consumption application information, can be generated the electricity of user to be powered Net access way data and electric means data;And then according to the power grid access way data and electric means data, Ke Yisheng At component locations distribution map and line alignment figure;Finally by power grid access way data, electric means data, component locations Distribution map and line alignment figure are determined as the power supply plan of user to be powered.This method can accurately and efficiently be made to be powered The power supply plan of user avoids through Review Cycle caused by manually being audited layer by layer long, heavy workload and error-prone Defect improves the Accuracy and high efficiency for formulating power supply plan.
In a kind of power supply plan formulating method shown in Figure 2, according to power grid access demand information, by electricity demanding information And parameter area, the specific flow chart of the power grid access way data of user to be powered is generated, this method comprises the following steps:
Step S202 is generated just by power grid access demand information input into the power grid access way model pre-established Walk power grid access way data;Wherein, the power grid access way model is according to power grid access demand information in historical data and electricity The matching relationship of net access way data is established;
In actual implementation, historical data can be handled by way of machine learning training, finds power grid and connects Enter the matching relationship of demand information Yu power grid access way data, and then establishes power grid access way model;It is new when receiving When power grid access demand information, preliminary power grid access way data can be obtained by the power grid access way model.
In view of preliminary power grid access way data not only need to meet the power grid access demand information of user to be powered, also Need to meet the related data in supply standard, therefore, it is necessary to carry out by following step to preliminary power grid access way data Reprocessing.
Step S204, judges whether preliminary power grid access way data meet parameter area;If so, executing step S206;If not, executing step S208;
Preliminary power grid access way data are determined as the power grid access way data of user to be powered by step S206;
Step S208 adjusts preliminary power grid access way data until meeting parameter area, by preliminary power grid adjusted Access way data are determined as the power grid access way data of user to be powered;Wherein, which includes supplying The power supply capacity of piezoelectric voltage grade, the power supply capacity of power supply and the every road inlet wire being connect with power supply.
The power grid access demand information for both having met user to be powered can be obtained through the above way, also meet supply standard In related data power grid access way data, improve the accuracy and reliability of power grid access way data.
In order to improve the accuracy and reliability of electric means data, it is above-mentioned according to power grid access demand information, by electric need Information and parameter area are asked, the electric means data of user to be powered is generated, includes the following steps:
(1), into the electric means model pre-established, preliminary electric means data will be generated by electricity demanding information input; Wherein, which establishes according to the matching relationship of electricity consumption application information in historical data and electric means data;
In actual implementation, historical data can be handled by way of machine learning training, finding is needed by electricity The matching relationship of information Yu electric means data is sought, and then establishes electric means model;It is new by electricity demanding information when receiving When, preliminary electric means data can be obtained by the electric means model.
In view of preliminary electric means data not only need to meet user to be powered by electricity demanding information, it is also necessary to meet Related data in supply standard, therefore, it is necessary to be reprocessed by following step to preliminary electric means data.
(2) judge whether preliminary electric means data meet parameter area;
(3) if so, preliminary electric means data to be determined as to the electric means data of user to be powered;
(4) if not, adjustment electric means data are until meet parameter area, by preliminary electric means data adjusted It is determined as the electric means data of user to be powered;Wherein, which includes power receiving device capacity, reactive compensation mark Quasi-, the electrical main line mode of connection and the method for operation.
Can obtain through the above way both met user to be powered by electricity demanding information, also meet in supply standard The electric means data of related data, improve the accuracy and reliability of electric means data.
Further, above-mentioned according to power grid access way data and electric means data, generate component locations distribution map With line alignment figure, include the following steps: that (1) from pre-stored component data, is screened and power grid access way data The component type to match with electric means data;Wherein, which includes power supply, distribution transformer, power supply meter Measure device, power supply line and low-voltage cable;(2) it with the minimum principle of total line length, will be screened according to the distributed intelligence of electricity consumption point Component out is distributed, and component locations distribution map and line alignment figure are generated.
In actual implementation, staff can carry out power grid line attachment according to line alignment figure and at the scene by electric The laying on road;Carry out the installation of component at the scene according to component locations distribution map.Aforesaid way substantially increases supplier of electricity The practicability of case improves the reliability and safety of power supply line's laying.
In view of power supply plan is when formulating, it is also necessary to determine the meter electricity mode of user to be powered, thus, above-mentioned supplier of electricity Case formulating method further includes following steps: (1) extracting the parameter for counting electric mode corresponding with the electricity consumption application information after confirmation Range;Wherein, the parameter area of the meter electricity mode is arranged according to the meter electric standard pre-established;(2) side of machine learning is used Method, the primary charging mode data that prediction matches with the electricity consumption application information after confirmation;(3) primary charging mode number is adjusted According to until meeting the parameter area for counting electric mode;(4) primary charging mode data adjusted are determined as user's to be powered Charging mode data.Aforesaid way can rapidly make the charging mode of reasonable user to be powered, avoid and pass through people Work formulate audit caused charging mode is unreasonable and period longer defect.
Embodiment two:
Corresponding to above method embodiment, a kind of structural schematic diagram of power supply plan making device shown in Figure 3 should Device includes following part:
Receiving module 302, for receiving the electricity consumption application information and data of job-site survey of user to be powered;Wherein, the use Electric application information includes the affiliated industry of user to be powered, load nature of electricity consumed, appraises and decides electricity capacity and draft client's classification;The scene Survey data includes the confirmation message to electricity consumption application information, power grid access demand information, by electricity demanding information and electricity consumption point minute Cloth information;
First extraction module 304, for extract with confirm after the corresponding power supply plan of electricity consumption application information parameter Range;Wherein, the parameter area of the power supply plan is arranged according to the supply standard pre-established;
First generation module 306 is used to generate according to power grid access demand information, by electricity demanding information and parameter area The power grid access way data and electric means data of user to be powered;
Second generation module 308, for generating component locations according to power grid access way data and electric means data Distribution map and line alignment figure;It wherein, include power supply, distribution transformer and power supply metering in the component locations distribution map The position distribution of device;It include the path trend of power supply line and low-voltage cable in the line alignment figure;
Power supply plan determining module 310, for dividing power grid access way data, electric means data, component locations Butut and line alignment figure are determined as the power supply plan of user to be powered.
A kind of power supply plan making device provided in an embodiment of the present invention, according to the electricity consumption application information of user to be powered, The parameter area of data of job-site survey and the corresponding power supply plan of electricity consumption application information, can be generated the electricity of user to be powered Net access way data and electric means data;And then according to the power grid access way data and electric means data, Ke Yisheng At component locations distribution map and line alignment figure;Finally by power grid access way data, electric means data, component locations Distribution map and line alignment figure are determined as the power supply plan of user to be powered.This method can accurately and efficiently be made to be powered The power supply plan of user avoids through Review Cycle caused by manually being audited layer by layer long, heavy workload and error-prone Defect improves the Accuracy and high efficiency for formulating power supply plan.
In a kind of power supply plan making device shown in Figure 4, the concrete structure schematic diagram of the first generation module, the mould Block includes following part:
First generation unit 402, for by power grid access demand information input to the power grid access way mould pre-established In type, preliminary power grid access way data are generated;Wherein, which accesses need according to power grid in historical data The matching relationship of information and power grid access way data is asked to establish;
First judging unit 404, for judging whether preliminary power grid access way data meet parameter area;
First determination unit 406 connects preliminary power grid if meeting parameter area for preliminary power grid access way data Enter the power grid access way data that mode data are determined as user to be powered;
The first adjustment unit 408 adjusts preliminary electricity if being unsatisfactory for parameter area for preliminary power grid access way data Preliminary power grid access way data adjusted are determined as user to be powered up to meeting parameter area by net access way data Power grid access way data;Wherein, which includes the power supply capacity of power supply voltage level, power supply And the power supply capacity for the every road inlet wire being connect with power supply.
The power grid access demand information for both having met user to be powered can be obtained through the above way, also meet supply standard In related data power grid access way data, improve the accuracy and reliability of power grid access way data.
In order to improve the accuracy and reliability of electric means data, above-mentioned first generation module includes: (1) second generation Unit, for preliminary electric means data will to be generated by electricity demanding information input into the electric means model pre-established;Its In, which establishes according to the matching relationship of electricity consumption application information in historical data and electric means data;(2) Two judging units, for judging whether preliminary electric means data meet parameter area;(3) second determination units, if for Preliminary electric means data meet parameter area, and preliminary electric means data are determined as to the electric means number of user to be powered According to;(4) second adjustment unit, if being unsatisfactory for parameter area for preliminary electric means data, adjustment electric means data are straight To parameter area is met, preliminary electric means data adjusted are determined as to the electric means data of user to be powered;Wherein, The electric means data include power receiving device capacity, reactive compensation standard, the electrical main line mode of connection and the method for operation.By upper The mode of stating can obtain both met user to be powered by electricity demanding information, also meet the related data in supply standard by electricity Mode data improve the accuracy and reliability of electric means data.
Further, above-mentioned second generation module includes following part: (1) screening unit, is used for from pre-stored member In device data, the component type to match with power grid access way data and electric means data is screened;Wherein, this yuan of device Part includes power supply, distribution transformer, power supply metering device, power supply line and low-voltage cable;(2) component distribution unit, For being distributed the component filtered out according to electricity consumption point distributed intelligence with the minimum principle of total line length, member is generated Device position distribution map and line alignment figure.In actual implementation, staff can carry out at the scene according to line alignment figure The laying of power grid line attachment and power receiving circuit;Carry out the installation of component at the scene according to component locations distribution map.It is above-mentioned Mode substantially increases the practicability of power supply plan, improves the reliability and safety of power supply line's laying.
In view of power supply plan is when formulating, it is also necessary to determine the meter electricity mode of user to be powered, thus, above-mentioned supplier of electricity Case making device also includes the following: (1) second extraction module, corresponding with the electricity consumption application information after confirming for extracting The electric mode of meter parameter area;Wherein, the parameter area of the meter electricity mode is arranged according to the meter electric standard pre-established;(2) Prediction module predicts the primary charging side to match with the electricity consumption application information after confirmation for the method using machine learning Formula data;(3) module is adjusted, for adjusting primary charging mode data, until meeting the parameter area for counting electric mode;(4) it counts Take mode data determining module, for primary charging mode data adjusted to be determined as to the charging mode number of user to be powered According to.Aforesaid way can rapidly make the charging mode of reasonable user to be powered, avoid by manually being formulated Audit caused charging mode is unreasonable and period longer defect.
A kind of computer program product of power supply plan formulating method and device provided by the embodiment of the present invention, including deposit The computer readable storage medium of program code is stored up, the instruction that said program code includes can be used for executing previous methods implementation Method described in example, specific implementation can be found in embodiment of the method, and details are not described herein.
It, can be with if the function is realized in the form of SFU software functional unit and when sold or used as an independent product It is stored in a computer readable storage medium.Based on this understanding, technical solution of the present invention is substantially in other words The part of the part that contributes to existing technology or the technical solution can be embodied in the form of software products, the meter Calculation machine software product is stored in a storage medium, including some instructions are used so that a computer equipment (can be a People's computer, server or network equipment etc.) it performs all or part of the steps of the method described in the various embodiments of the present invention. And storage medium above-mentioned includes: that USB flash disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), arbitrary access are deposited The various media that can store program code such as reservoir (RAM, Random Access Memory), magnetic or disk.
Finally, it should be noted that embodiment described above, only a specific embodiment of the invention, to illustrate the present invention Technical solution, rather than its limitations, scope of protection of the present invention is not limited thereto, although with reference to the foregoing embodiments to this hair It is bright to be described in detail, those skilled in the art should understand that: anyone skilled in the art In the technical scope disclosed by the present invention, it can still modify to technical solution documented by previous embodiment or can be light It is readily conceivable that variation or equivalent replacement of some of the technical features;And these modifications, variation or replacement, do not make The essence of corresponding technical solution is detached from the spirit and scope of technical solution of the embodiment of the present invention, should all cover in protection of the invention Within the scope of.Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (8)

1. a kind of power supply plan formulating method characterized by comprising
Receive the electricity consumption application information and data of job-site survey of user to be powered;Wherein, the electricity consumption application information includes described The affiliated industry of user to be powered, appraises and decides electricity capacity and drafts client's classification load nature of electricity consumed;The data of job-site survey includes To the confirmation message of the electricity consumption application information, power grid access demand information, by electricity demanding information and electricity consumption point distributed intelligence;
Extract the parameter area of power supply plan corresponding with the electricity consumption application information after confirmation;Wherein, the supplier of electricity The parameter area of case is arranged according to the supply standard pre-established;
According to the power grid access demand information, described by electricity demanding information and the parameter area, the use to be powered is generated The power grid access way data and electric means data at family;
According to the power grid access way data and the electric means data, component locations distribution map and line alignment are generated Figure;It wherein, include the position point of power supply, distribution transformer and metering device of powering in the component locations distribution map Cloth;It include the path trend of power supply line and low-voltage cable in the line alignment figure;
The power grid access way data, the electric means data, the component locations distribution map and the route are walked It is determined as the power supply plan of the user to be powered to figure;
It is described according to the power grid access demand information, it is described by electricity demanding information and the parameter area, generate described wait supply The power grid access way data of electric user, comprising:
By the power grid access demand information input into the power grid access way model pre-established, preliminary power grid access is generated Mode data;Wherein, the power grid access way model is according to power grid access demand information in historical data and power grid access side The matching relationship of formula data is established;
Judge whether the preliminary power grid access way data meet the parameter area;
If so, the preliminary power grid access way data to be determined as to the power grid access way data of the user to be powered;
If not, the adjustment preliminary power grid access way data are until meet the parameter area, will it is adjusted it is described at the beginning of Step power grid access way data are determined as the power grid access way data of the user to be powered;Wherein, the power grid access side Formula data include the confession of power supply voltage level, the power supply capacity of power supply and the every road inlet wire connecting with the power supply Capacitance.
2. the method according to claim 1, wherein it is described according to the power grid access demand information, it is described by Electricity demanding information and the parameter area generate the electric means data of the user to be powered, comprising:
By it is described by electricity demanding information input into the electric means model pre-established, generate preliminary electric means data;Its In, the electric means model is established according to the matching relationship of electricity consumption application information in historical data and electric means data;
Judge whether the preliminary electric means data meet the parameter area;
If so, the preliminary electric means data to be determined as to the electric means data of the user to be powered;
If not, adjust the electric means data until meet the parameter area, it will be adjusted described tentatively by electricity side Formula data are determined as the electric means data of the user to be powered;Wherein, the electric means data include that power receiving device holds Amount, reactive compensation standard, the electrical main line mode of connection and the method for operation.
3. the method according to claim 1, wherein it is described according to the power grid access way data and it is described by Electric mode data generate component locations distribution map and line alignment figure, comprising:
From pre-stored component data, screening and the power grid access way data and the electric means data phase The component type matched;Wherein, the component include power supply, distribution transformer, power supply metering device, power supply line and Low-voltage cable;
With the minimum principle of total line length, the component filtered out is distributed according to the electricity consumption point distributed intelligence, it is raw At component locations distribution map and line alignment figure.
4. the method according to claim 1, wherein the method also includes:
Extract the parameter area for counting electric mode corresponding with the electricity consumption application information after confirmation;Wherein, the meter electricity side The parameter area of formula is arranged according to the meter electric standard pre-established;
Using the method for machine learning, the primary charging mode number to match with the electricity consumption application information after confirmation is predicted According to;
The primary charging mode data are adjusted, until meeting the parameter area for counting electric mode;
The primary charging mode data adjusted are determined as to the charging mode data of the user to be powered.
5. a kind of power supply plan making device characterized by comprising
Receiving module, for receiving the electricity consumption application information and data of job-site survey of user to be powered;Wherein, the electricity consumption application Information includes the affiliated industry of the user to be powered, load nature of electricity consumed, appraises and decides electricity capacity and draft client's classification;The scene Survey data includes the confirmation message to the electricity consumption application information, power grid access demand information, by electricity demanding information and electricity consumption Point distributed intelligence;
First extraction module, for extract with confirm after the corresponding power supply plan of the electricity consumption application information parameter model It encloses;Wherein, the parameter area of the power supply plan is arranged according to the supply standard pre-established;
First generation module, for according to the power grid access demand information, described by electricity demanding information and the parameter area, Generate the power grid access way data and electric means data of the user to be powered;
Second generation module, for generating component position according to the power grid access way data and the electric means data Set distribution map and line alignment figure;It wherein, include power supply, distribution transformer and power supply in the component locations distribution map The position distribution of metering device;It include the path trend of power supply line and low-voltage cable in the line alignment figure;
Power supply plan determining module is used for the power grid access way data, the electric means data, the component position It sets distribution map and the line alignment figure is determined as the power supply plan of the user to be powered;
First generation module includes:
First generation unit, for by the power grid access demand information input to the power grid access way model pre-established In, generate preliminary power grid access way data;Wherein, the power grid access way model accesses need according to power grid in historical data The matching relationship of information and power grid access way data is asked to establish;
First judging unit, for judging whether the preliminary power grid access way data meet the parameter area;
First determination unit will be described preliminary if meeting the parameter area for the preliminary power grid access way data Power grid access way data are determined as the power grid access way data of the user to be powered;
The first adjustment unit, if being unsatisfactory for the parameter area for the preliminary power grid access way data, described in adjustment Preliminary power grid access way data are true by the preliminary power grid access way data adjusted up to meeting the parameter area It is set to the power grid access way data of the user to be powered;Wherein, the power grid access way data include supply voltage etc. The power supply capacity of grade, the power supply capacity of power supply and the every road inlet wire being connect with the power supply.
6. device according to claim 5, which is characterized in that first generation module includes:
Second generation unit, for by it is described by electricity demanding information input into the electric means model pre-established, generate just Walk electric means data;Wherein, the electric means model is according to electricity consumption application information in historical data and electric means data Matching relationship establish;
Second judgment unit, for judging whether the preliminary electric means data meet the parameter area;
Second determination unit, if meeting the parameter area for the preliminary electric means data, by described tentatively by electricity Mode data are determined as the electric means data of the user to be powered;
Second adjustment unit, if being unsatisfactory for the parameter area for the preliminary electric means data, adjustment is described by electricity The preliminary electric means data adjusted are determined as the use to be powered up to meeting the parameter area by mode data The electric means data at family;Wherein, the electric means data include power receiving device capacity, reactive compensation standard, electrical main line The mode of connection and the method for operation.
7. device according to claim 5, which is characterized in that second generation module includes:
Screening unit, for from pre-stored component data, screening and the power grid access way data and it is described by The component type that electric mode data match;Wherein, the component includes power supply, distribution transformer, power supply metering Device, power supply line and low-voltage cable;
Component distribution unit, for that will be filtered out according to the electricity consumption point distributed intelligence with the minimum principle of total line length Component be distributed, generate component locations distribution map and line alignment figure.
8. device according to claim 5, which is characterized in that described device further include:
Second extraction module, by extract with confirm after the electricity consumption application information it is corresponding based on electric mode parameter model It encloses;Wherein, the parameter area for counting electric mode is arranged according to the meter electric standard pre-established;
Prediction module, for the method using machine learning, prediction matches first with the electricity consumption application information after confirmation Walk charging mode data;
Module is adjusted, for adjusting the primary charging mode data, until meeting the parameter area for counting electric mode;
Charging mode data determining module, for the primary charging mode data adjusted to be determined as the use to be powered The charging mode data at family.
CN201710189785.5A 2017-03-27 2017-03-27 Power supply plan formulating method and device Expired - Fee Related CN106684870B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710189785.5A CN106684870B (en) 2017-03-27 2017-03-27 Power supply plan formulating method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710189785.5A CN106684870B (en) 2017-03-27 2017-03-27 Power supply plan formulating method and device

Publications (2)

Publication Number Publication Date
CN106684870A CN106684870A (en) 2017-05-17
CN106684870B true CN106684870B (en) 2019-03-19

Family

ID=58826385

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710189785.5A Expired - Fee Related CN106684870B (en) 2017-03-27 2017-03-27 Power supply plan formulating method and device

Country Status (1)

Country Link
CN (1) CN106684870B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109583766A (en) * 2018-12-03 2019-04-05 国网湖南省电力有限公司 Decontrol power grid enterprises' ancillary investment decision-making technique under increment distribution business background
CN112950027A (en) * 2021-03-02 2021-06-11 国网河北省电力有限公司保定供电分公司 Power grid working method and device and power grid working system
CN114137331B (en) * 2021-10-25 2023-09-08 四川蓉信开工程设计有限公司 BIM-based power substation design method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104573876A (en) * 2015-01-28 2015-04-29 华北电力大学(保定) Wind power plant short-period wind speed prediction method based on time sequence long memory model
CN104701888A (en) * 2015-02-28 2015-06-10 华中电网有限公司 Real-time load regulating method for power grid using hydro-thermal power working condition self-matching mode
CN105373972A (en) * 2015-12-04 2016-03-02 福建亿榕信息技术有限公司 Low-voltage client power supply scheme generation method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012162570A1 (en) * 2011-05-24 2012-11-29 Cameron D Kevin System and method for integrating and managing demand/response between alternative energy sources, grid power, and loads

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104573876A (en) * 2015-01-28 2015-04-29 华北电力大学(保定) Wind power plant short-period wind speed prediction method based on time sequence long memory model
CN104701888A (en) * 2015-02-28 2015-06-10 华中电网有限公司 Real-time load regulating method for power grid using hydro-thermal power working condition self-matching mode
CN105373972A (en) * 2015-12-04 2016-03-02 福建亿榕信息技术有限公司 Low-voltage client power supply scheme generation method

Also Published As

Publication number Publication date
CN106684870A (en) 2017-05-17

Similar Documents

Publication Publication Date Title
Varela et al. The IGREENGrid project: Increasing hosting capacity in distribution grids
CN106684870B (en) Power supply plan formulating method and device
CN110264015A (en) It opposes electricity-stealing and checks monitoring method and platform
CN109615427A (en) A kind of energy interactive system and method based on chain structure
CN108122068A (en) A kind of power distribution network risk-averse retailer method and system
CN102116857B (en) Method for checking electric quantity at power grid gate
CN108428045A (en) A kind of distribution network operation health state evaluation method
CN104538958B (en) The intelligent analysis method of Electricity customers electrical network access point and system
CN105356461B (en) A kind of accounting method of the load unbalanced administration project carbon emission reduction amount of low voltage electric network
CN107167704A (en) Fault Diagnosis of Distribution Network system and method based on CIM
CN105989546A (en) Power transmission and transformation construction cost basic data collection and analysis system
CN106056481A (en) Distribution power multi-source data system and multi-source data processing method
CN102495850A (en) Method for splicing multi-stage multi-region interconnected power grid relay protection model
CN102244677A (en) Green energy Cloud computing method and system
CN103473602A (en) Theoretical line loss data prediction system and prediction method of power grid
CN104103018A (en) Quality-based electric energy pricing method of distributed power generation system and microgrid
CN103903103A (en) Online model parameter collection method based on process cross-region power grid running method
CN105225162A (en) A kind of harmonizing ways method of distribution system operational efficiency
JP2014192981A (en) Server device and energy distribution system
Xiang et al. A traffic flow based planning strategy for optimal siting and sizing of charging stations
CN108199370A (en) A kind of electric energy managing and control system and method based on big data analysis
CN104077730A (en) Comprehensive quantization evaluation method, device and system for power grid dispatching and operating
CN106296464A (en) Big data multiple spot load forecasting method
CN104599090A (en) Interactive power supply service system
CN107832408A (en) It is a kind of that method is recommended based on the grounding grid defect of data label and entropy assessment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190319

Termination date: 20200327