CN110093936A - The isolated filling construction method of line side following formula railway station building roadbed side high roadbed - Google Patents

The isolated filling construction method of line side following formula railway station building roadbed side high roadbed Download PDF

Info

Publication number
CN110093936A
CN110093936A CN201910387271.XA CN201910387271A CN110093936A CN 110093936 A CN110093936 A CN 110093936A CN 201910387271 A CN201910387271 A CN 201910387271A CN 110093936 A CN110093936 A CN 110093936A
Authority
CN
China
Prior art keywords
roadbed
following formula
concrete
railway station
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910387271.XA
Other languages
Chinese (zh)
Inventor
裴健
岳庭
刘玲
韩毅
裴强
赵泽平
郝天坤
郭启龙
李树林
白进存
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Sixth Group Co Ltd
Construction and Installation Engineering Co Ltd of China Railway Sixth Group Co Ltd
Original Assignee
China Railway Sixth Group Co Ltd
Construction and Installation Engineering Co Ltd of China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixth Group Co Ltd, Construction and Installation Engineering Co Ltd of China Railway Sixth Group Co Ltd filed Critical China Railway Sixth Group Co Ltd
Priority to CN201910387271.XA priority Critical patent/CN110093936A/en
Publication of CN110093936A publication Critical patent/CN110093936A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/12Back-filling of foundation trenches or ditches

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Railway Tracks (AREA)

Abstract

The present invention relates to the backfill retaining wall foundation constructions of roadbed side high roadbed, the specially isolated filling construction method of line side following formula railway station building roadbed side high roadbed.This method takes isolation and safeguard measure to station exterior wall in construction, and construction finishes and need to remove quarantine measures, and fills husky processing.Using the isolated filling Construction Technique of line side following formula railway station building roadbed side high roadbed, eliminate the influence of high-fill roadbed and railroad train dynamic load to station main structure, optimize station structure design, reduce project cost, reduce station operation maintenance cost, efficiently solve the problems, such as railway station platform foundation settlement, economic and social benefit is significant.

Description

The isolated filling construction method of line side following formula railway station building roadbed side high roadbed
Technical field
The present invention relates to the backfill retaining wall foundation construction of roadbed side high roadbed, specially line side following formula railway station building roadbed side is high The isolated filling construction method of embankment.
Background technique
Line side following formula railway station building refers to that station is located at the side of yard, and station first layer ground is lower than platform floor.Station Basement side wall foundation pit backfill need to be first carried out when the main platform Retaining wall of roadbed side, retaining wall foundation design generally uses graded sand Stone is backfilled, and layering is tamped, and the structure that high roadbed directly affects station to the lateral pressure that station exterior wall is applied designs The load factor of consideration, the dynamic load of train is also that station structure design is in need of consideration heavy especially during railway operation Point.After the resting period for requiring roadbed filling not to be preferably less than 6 months after the completion according to " Design of High-speed Railway specification ", is to guarantee backfill Material settlement and flow meet track construction requirement, using graded sand and stone backfill the duration will not be able to satisfy specification in putting Time requirement is set, while because the self weight of platform barricade is larger, being easy to cause sedimentation and deformation, and then influence track profession and subsequent profession Construction.
Summary of the invention
In view of the above-mentioned problems, the present invention provides the line side following formula railway station building roadbed side isolated filling construction sides of high roadbed Method.
The present invention adopts the following technical scheme that realization: line side following formula railway station building roadbed side high roadbed is isolated to be filled out Construction method is built, is followed the steps below to implement:
(1) sundries in foundation pit should be cleared up before foundation pit backfill, it is ensured that foundation pit cleaning;
(2) falsework is set up towards the side of foundation pit on outer wall of basement, it is solid towards the side of foundation pit on falsework Solid plate, the height of falsework are the thickness of each casting concrete;
(3) casting concrete in foundation pit pours the falsework height set up with a thickness of exterior wall side;
(4) reach people in initial set to the layer concrete, by falsework and form removable and one layer of position on exterior wall can be promoted to Waiting concreting is set, by falsework and form removable and is promoted to upper one layer of position on exterior wall after concreting again Concreting is waited, is so successively poured until casting concrete pours completion in foundation pit;
(5) after the completion of fill concrete pours, the husky processing of filling is done in gap between outer wall of basement and fill concrete.
The above-mentioned isolated filling construction method of line side following formula railway station building roadbed side high roadbed, each casting concrete With a thickness of 0.5~1.0 m.
The above-mentioned isolated filling construction method of line side following formula railway station building roadbed side high roadbed divides long range foundation pit Construction flowing water section divides storehouse operation.
The above-mentioned isolated filling construction method of line side following formula railway station building roadbed side high roadbed, concrete freely incline drop height Degree must not exceed 2m, is poured when pouring height as more than 2m with string bucket or elephant trunk, prevents concrete disintegration.
The above-mentioned isolated filling construction method of line side following formula railway station building roadbed side high roadbed, in order to reduce concrete The heat of hydration should improve concrete mix by measures such as adding coal ashes.
The above-mentioned isolated filling construction method of line side following formula railway station building roadbed side high roadbed, in concreting process In uniformly put into clean piece stone material, reduce the heat of hydration of concrete while reducing engineering cost.
Using the isolated filling Construction Technique of line side following formula railway station building roadbed side high roadbed, eliminate high-fill roadbed and Influence of the railroad train dynamic load to station main structure optimizes station structure design, reduces project cost, reduce station Room operation maintenance cost, efficiently solves the problems, such as railway station platform foundation settlement, and economic and social benefit is significant.
Detailed description of the invention
Fig. 1, which is that line side following formula railway station building roadbed side high roadbed is isolated, fills schematic diagram.
In figure: 1- high roadbed concrete, 2- station exterior wall, 3- fill husky separation layer, 4- platform barricade.
Specific embodiment
The present invention using concrete crushing strength height, fast solidifying, and is moored using concrete substitution graded broken stone backfill Loose smaller (generally 0.1~0.22) is used as retaining wall foundation high roadbed backfilling material, settles after upper portion pressurized and compression is perpendicular Meet subgrade stability requirement to deformation.
It is flow regime before initial set when concreting, External Wall has lateral pressure, is converted into after concrete setting Internal force, if keeping apart between high roadbed concrete and station exterior wall, the lateral pressure of high roadbed is not transmitted to outside station Wall.Isolation and safeguard measure need to be taken when construction, construction finishes and need to remove quarantine measures, and fills husky processing.Technical requirements Sandwich concrete is answered to pour, in the template of station exterior wall dismounting easy for installation, every layer pours 0.5~1.0 m of thickness.It is mixed to the layer Solidifying soil reaches people in initial set, by form removable and can be promoted to the waiting concreting of previous step position.To long range foundation pit Answer classifying rationally construction flowing water section point storehouse operation.
Using the external series gap reserved between high roadbed under railroad platform side and wire type railway station building roadbed side exterior wall, subtract naturally The earthwork lateral pressure of few station side, plays the function of shock insulation to railway station building side wall wall.
Operation of the present invention main points
Sundries in foundation pit should be cleared up before foundation pit backfill, it is ensured that foundation pit cleaning.
Outer wall formwork of basement bracket should be noted that protection external wall waterproof protective layer when installing, must not destroy waterproof protective layer. Installing structure type is detachable form.
Outer wall of basement height of baffle plate is the thickness of each casting concrete, pours thickness and is generally 0.5~1.0 m. In order to reduce the heat of hydration of concrete, concrete mix should be improved by measures such as adding coal ashes.It can also be in concrete Clean piece stone material is uniformly put into casting process, while reducing engineering cost.
Casting concrete should be carried out continuously, and layering is vibrated.The concrete drop height degree that freely inclines must not exceed 2m, pour height such as It must take measures when more than 2m, with string bucket or elephant trunk etc., prevent concrete disintegration.Reinforce concrete curing, in order to ensure new The concrete poured has suitable curing condition, prevents from generating crack due to drying shrinkage in early stage, after concreting, and Shi Jinhang covering and heat insulating moisture-keeping maintaining.
Reach people in initial set to the layer concrete, by form removable and upper one layer of position can be promoted to concrete is waited to pour It builds.Classifying rationally construction flowing water section point storehouse operation is answered to long range foundation pit.After the completion of backfill construction, outer wall of basement and backfill are mixed The husky processing of filling is done in gap between solidifying soil.

Claims (6)

1. the isolated filling construction method of line side following formula railway station building roadbed side high roadbed, it is characterised in that real according to the following steps It applies:
(1) sundries in foundation pit should be cleared up before foundation pit backfill, it is ensured that foundation pit cleaning;
(2) falsework is set up in outer wall of basement side, the fixed form on falsework, the height of falsework is each The thickness of casting concrete;
(3) casting concrete in foundation pit pours the falsework height set up with a thickness of exterior wall side;
(4) reach people in initial set to the layer concrete, by falsework and form removable and upper one layer of position can be promoted to etc. To concreting, by falsework and form removable and it is promoted to one layer of position after concreting again and waits coagulation Soil pours, and so successively pours until casting concrete pours completion in foundation pit;
(5) after the completion of fill concrete pours, the husky processing of filling is done in gap between outer wall of basement and fill concrete.
2. the isolated filling construction method of line side following formula railway station building roadbed according to claim 1 side high roadbed, special Sign be each casting concrete with a thickness of 0.5~1.0 m.
3. the isolated filling construction method of line side following formula railway station building roadbed according to claim 1 or 2 side high roadbed, It is characterized in that dividing long range foundation pit construction flowing water section point storehouse operation.
4. the isolated filling construction method of line side following formula railway station building roadbed according to claim 1 or 2 side high roadbed, It is characterized in that the concrete drop height degree that freely inclines must not exceed 2m, with bucket is gone here and there or elephant trunk pours when pouring height as more than 2m, prevents Concrete disintegration.
5. the isolated filling construction method of line side following formula railway station building roadbed according to claim 1 or 2 side high roadbed, It is characterized in that in concrete that adding coal ash improves match ratio.
6. the isolated filling construction method of line side following formula railway station building roadbed according to claim 1 or 2 side high roadbed, It is characterized in that in concreting process uniformly putting into piece stone material.
CN201910387271.XA 2019-05-10 2019-05-10 The isolated filling construction method of line side following formula railway station building roadbed side high roadbed Pending CN110093936A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910387271.XA CN110093936A (en) 2019-05-10 2019-05-10 The isolated filling construction method of line side following formula railway station building roadbed side high roadbed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910387271.XA CN110093936A (en) 2019-05-10 2019-05-10 The isolated filling construction method of line side following formula railway station building roadbed side high roadbed

Publications (1)

Publication Number Publication Date
CN110093936A true CN110093936A (en) 2019-08-06

Family

ID=67447602

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910387271.XA Pending CN110093936A (en) 2019-05-10 2019-05-10 The isolated filling construction method of line side following formula railway station building roadbed side high roadbed

Country Status (1)

Country Link
CN (1) CN110093936A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110670436A (en) * 2019-09-26 2020-01-10 华蓝设计(集团)有限公司 Structure for preventing urban road subgrade from non-uniform settlement and construction method thereof
CN110761287A (en) * 2019-10-25 2020-02-07 北京城建集团有限责任公司 High-low span structure and construction method thereof
CN114606807A (en) * 2022-04-18 2022-06-10 武汉铁路职业技术学院 Vibration isolation structure for reducing railway vibration

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182202A (en) * 2011-03-23 2011-09-14 平湖市科学技术局 Closed constraint sand cushion shock isolation/absorption foundation of rural residential building and construction method thereof
CN108103871A (en) * 2017-12-19 2018-06-01 浙江大学城市学院 A kind of construction method of the roadbed foam concrete fill placement technique of neighbouring existing Subway Facilities

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182202A (en) * 2011-03-23 2011-09-14 平湖市科学技术局 Closed constraint sand cushion shock isolation/absorption foundation of rural residential building and construction method thereof
CN108103871A (en) * 2017-12-19 2018-06-01 浙江大学城市学院 A kind of construction method of the roadbed foam concrete fill placement technique of neighbouring existing Subway Facilities

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘莉萍等: "《土木工程施工与组织管理》", 31 March 2019, 合肥工业大学出版社 *
朱沪生等: "《上海市轨道交通2号线(中山公园站-徐泾东站)工程设计》", 31 July 2011, 上海科学技术出版社 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110670436A (en) * 2019-09-26 2020-01-10 华蓝设计(集团)有限公司 Structure for preventing urban road subgrade from non-uniform settlement and construction method thereof
CN110761287A (en) * 2019-10-25 2020-02-07 北京城建集团有限责任公司 High-low span structure and construction method thereof
CN114606807A (en) * 2022-04-18 2022-06-10 武汉铁路职业技术学院 Vibration isolation structure for reducing railway vibration

Similar Documents

Publication Publication Date Title
WO2017125028A1 (en) Rail support beam low track and viaduct transition section structure for medium-low-speed magnetic suspension traffic project
CN110093936A (en) The isolated filling construction method of line side following formula railway station building roadbed side high roadbed
CN105201011B (en) A kind of compound anchored plate retaining wall and its construction method
CN106759496B (en) Anti-settling inspection shaft changes the outfit technique
CN209227580U (en) The tower-crane foundation structure of raft foundation is placed under a kind of
CN105332380B (en) Strut changing structure and method for underground building
CN110409244B (en) Composite bearing prefabricated road slab and prefabricated pavement construction method
CN109882182A (en) A kind of extra small clear distance construction method in tunnel
CN104532754B (en) A kind of prestressed concrete box girder end-blocking template construction method
CN104060760B (en) High Rise Building Transfer Floor Structure concrete super large beam construction in layer method
CN106758637A (en) A kind of road and its construction method for having enough to meet the need quick-assembling
CN110565449A (en) Anti-uplift and anti-separation type pile plate structure of high-speed railway
CN107988921A (en) A kind of cross-line bridge single-point successively incremeantal launching method construction method of overcrossing railway, highway
CN109113068A (en) A kind of inverse construction joint structure for building construction of deep basal pit
CN103741651B (en) A kind of concrete teeth groove stiling basin and construction method thereof
CN108797842A (en) Seismic shear wall and its construction method
CN108166395A (en) A kind of construction method that beam bridge is built across Business Line
CN108867225B (en) Method for processing water falling hole in karst landform road subgrade range
CN101446072A (en) Construction method for pouring concrete within steel pipe of arch bridge
CN207567570U (en) A kind of Foam lightweight soil railway bed transition section structure
CN206428547U (en) A kind of road for having enough to meet the need quick-assembling
CN109653223A (en) River anti-floating weighting board construction method
CN104695315A (en) Frame structure of deep foundation pit under existing railway and layered jacking method for construction of frame structure
CN210194691U (en) Protective structure for post-cast strip of settlement of basic raft
CN106758852A (en) Across foundation pit enclosure to support beam trestle construction technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190806