CN110093842A - Auxiliary device and its application method for interlocking segment construction - Google Patents
Auxiliary device and its application method for interlocking segment construction Download PDFInfo
- Publication number
- CN110093842A CN110093842A CN201910361146.1A CN201910361146A CN110093842A CN 110093842 A CN110093842 A CN 110093842A CN 201910361146 A CN201910361146 A CN 201910361146A CN 110093842 A CN110093842 A CN 110093842A
- Authority
- CN
- China
- Prior art keywords
- horizontal ruler
- horizontal
- supporting plate
- sliding block
- interlocking segment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C19/00—Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving
- E01C19/52—Apparatus for laying individual preformed surfacing elements, e.g. kerbstones
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
- E02D17/205—Securing of slopes or inclines with modular blocks, e.g. pre-fabricated
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Architecture (AREA)
- Revetment (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
The present invention relates to engineering construction field, specifically a kind of auxiliary device and its application method for interlocking segment construction;It is characterized in that: including sliding rail, sliding block, horizontal ruler, horizontal ruler supporting plate and snap ring, wherein sliding block is arranged on the slide rail, and horizontal ruler supporting plate is built up on sliding block, and horizontal ruler supporting plate is equipped with horizontal ruler, and horizontal ruler is equipped with snap ring;The horizontal ruler supporting plate includes column, half circular track and the horizontal shelf being arranged between column and half circular track, one end of the horizontal shelf and column are rotatablely connected, the other end is embedded in half circular track, so that horizontal shelf is rotated upwardly and downwardly along half circular track around column.The present apparatus assists the construction of interlock block using the combination of sliding rail, sliding block and horizontal ruler, thus, it is possible to which intuitively, accurately and rapidly the flatness of interlocking segment is checked and corrected.
Description
Technical field
The present invention relates to engineering construction field, specifically a kind of auxiliary device and its user for interlocking segment construction
Method.
Background technique
Traditional interlocking segment construction is typically all that construction personnel stands on ungraded sand bedding course, and sand bedding course paves one on one side
While paving interlocking segment, interlocking segment gently places blend rubber hammer or wooden mallet beats stabilization, paves the flat of interlocking segment by bracing wire control
Whole degree, flatness error are difficult control in tolerance range, be easy to cause secondary do over again.
Summary of the invention
It is an object of the invention to overcome drawbacks described above, providing one kind synchronous with interlocking segment Paving Construction can be carried out, with
When interlocking segment flatness can be carried out check correction auxiliary device and its application method.
In order to achieve the above object, the present invention is implemented as follows:
A kind of auxiliary device for interlocking segment construction, including sliding rail, sliding block, horizontal ruler, horizontal ruler supporting plate and snap ring, wherein
Sliding block is arranged on the slide rail, and horizontal ruler supporting plate is built up on sliding block, and horizontal ruler supporting plate is equipped with horizontal ruler, and horizontal ruler is equipped with card
Ring;The horizontal ruler supporting plate includes column, half circular track and the horizontal shelf being arranged between column and half circular track, institute
The one end and column for stating horizontal shelf are rotatablely connected, and the other end is embedded in half circular track, so that horizontal shelf is along semicircle
Shape guide rail and rotated upwardly and downwardly around column.
The application method of the auxiliary device for interlocking segment construction, including
Step 1, respectively in two plain concretes up and down of slope protection every placing auxiliary device on stalk;
Step 2, the angle that horizontal ruler is adjusted by horizontal ruler supporting plate, keep it parallel with interlocking segment slope surface;
Horizontal ruler and Paving Construction synchronous marching are made by the mobile sliding block of track when step 3, interlocking segment construction, at any time to interlocking segment
Flatness is checked and is corrected;Wherein, it when step 1, is checked using quadrangle of the level to sliding rail, sliding rail is leveled;
When step 2, horizontal ruler supporting plate is fixed by bolts on sliding block;The angle that two groups of horizontal ruler supporting plates up and down are adjusted when step 3 makes
Horizontal ruler is parallel with slope protection;Pass through the fixed horizontal ruler of horizontal ruler supporting plate upper snap ring;Repetition measurement horizontal ruler angle finely tunes supporting plate;Use water
Quasi- instrument repetition measurement bidirectional sliding rail, it is ensured that sliding rail levelness;It applies utilization of hour Steel Ruler control upper and lower ends sliding block and interlocking segment is constructed
Progress synchronous translational.
The present apparatus assists the construction of interlock block using the combination of sliding rail, sliding block and horizontal ruler, thus, it is possible to intuitively, it is quasi-
Really, rapidly the flatness of interlocking segment is checked and is corrected.
Detailed description of the invention
Fig. 1 is present apparatus use state diagram.
Fig. 2 is present apparatus structural schematic diagram.
Specific embodiment
The present invention is further illustrated below by way of specific embodiment.
As shown in Figure 1 and Figure 2, a kind of auxiliary device for interlocking segment construction, including sliding rail 1, sliding block 2, horizontal ruler 3, water
Leveling ruler supporting plate 4 and snap ring 5, wherein sliding block 2 is arranged on sliding rail 1, and horizontal ruler supporting plate 4 is built up on sliding block 2, horizontal ruler supporting plate 4
It is equipped with horizontal ruler 3, horizontal ruler 3 is equipped with snap ring 5;The horizontal ruler supporting plate 4 includes column 41, half circular track 42 and setting
Horizontal shelf 43 between column 41 and half circular track 42, one end of the horizontal shelf 43 and column 41 are rotatablely connected,
The other end is embedded in half circular track 42, so that horizontal shelf 42 turns along half circular track 42 around about 41 column
It is dynamic.
The application method of the auxiliary device for interlocking segment construction, including
Step 1, respectively in two plain concretes up and down of slope protection every placing auxiliary device on stalk;
Step 2, the angle that horizontal ruler is adjusted by horizontal ruler supporting plate, keep it parallel with interlocking segment slope surface;
Horizontal ruler and Paving Construction synchronous marching are made by the mobile sliding block of track when step 3, interlocking segment construction, at any time to interlocking segment
Flatness is checked and is corrected;Wherein, it when step 1, is checked using quadrangle of the level to sliding rail, sliding rail is leveled;
When step 2, horizontal ruler supporting plate is fixed by bolts on sliding block;The angle that two groups of horizontal ruler supporting plates up and down are adjusted when step 3 makes
Horizontal ruler is parallel with slope protection;Pass through the fixed horizontal ruler of horizontal ruler supporting plate upper snap ring;Repetition measurement horizontal ruler angle finely tunes supporting plate;Use water
Quasi- instrument repetition measurement bidirectional sliding rail, it is ensured that sliding rail levelness;It applies utilization of hour Steel Ruler control upper and lower ends sliding block and interlocking segment is constructed
Progress synchronous translational.
The present apparatus assists the construction of interlock block using the combination of sliding rail, sliding block and horizontal ruler, thus, it is possible to intuitively, it is quasi-
Really, rapidly the flatness of interlocking segment is checked and is corrected.
Claims (2)
1. a kind of auxiliary device for interlocking segment construction, it is characterized in that: including sliding rail, sliding block, horizontal ruler, horizontal ruler supporting plate
And snap ring, wherein sliding block is arranged on the slide rail, and horizontal ruler supporting plate is built up on sliding block, and horizontal ruler supporting plate is equipped with horizontal ruler, water
Leveling ruler is equipped with snap ring;The horizontal ruler supporting plate includes column, half circular track and setting between column and half circular track
Horizontal shelf, one end of the horizontal shelf and column be rotatablely connected, and the other end is embedded in half circular track, thus horizontal
Supporting plate is rotated upwardly and downwardly along half circular track around column.
2. the application method described in claim 1 for the auxiliary device of interlocking segment construction, it is characterized in that: including
Step 1, respectively in two plain concretes up and down of slope protection every placing auxiliary device on stalk;
Step 2, the angle that horizontal ruler is adjusted by horizontal ruler supporting plate, keep it parallel with interlocking segment slope surface;
Horizontal ruler and Paving Construction synchronous marching are made by the mobile sliding block of track when step 3, interlocking segment construction, at any time to interlocking segment
Flatness is checked and is corrected;
Wherein, it when step 1, is checked using quadrangle of the level to sliding rail, sliding rail is leveled;When step 2, by horizontal ruler support
Plate is fixed by bolts on sliding block;The angle that two groups of horizontal ruler supporting plates up and down are adjusted when step 3 keeps horizontal ruler parallel with slope protection;It is logical
Cross the fixed horizontal ruler of horizontal ruler supporting plate upper snap ring;Repetition measurement horizontal ruler angle finely tunes supporting plate;With level repetition measurement bidirectional sliding rail, really
Protect sliding rail levelness;Apply utilization of hour Steel Ruler control upper and lower ends sliding block and interlocking segment construction speed synchronous translational.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910361146.1A CN110093842B (en) | 2019-04-30 | 2019-04-30 | Auxiliary device for interlocking block construction and using method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910361146.1A CN110093842B (en) | 2019-04-30 | 2019-04-30 | Auxiliary device for interlocking block construction and using method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110093842A true CN110093842A (en) | 2019-08-06 |
CN110093842B CN110093842B (en) | 2021-12-07 |
Family
ID=67446515
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910361146.1A Active CN110093842B (en) | 2019-04-30 | 2019-04-30 | Auxiliary device for interlocking block construction and using method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110093842B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113215939A (en) * | 2021-06-03 | 2021-08-06 | 中铁二局集团有限公司 | Sidewalk brick laying auxiliary device and paving method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5633327U (en) * | 1979-08-20 | 1981-04-01 | ||
CN103669291A (en) * | 2013-12-06 | 2014-03-26 | 浙江水利水电学院 | Method for constructing slope through connected slope bricks |
KR200475868Y1 (en) * | 2014-05-21 | 2015-01-08 | 정영길 | Hoarstone construction device |
CN205804904U (en) * | 2016-07-05 | 2016-12-14 | 上海路港建设工程有限公司 | A kind of leveling unit |
CN205894626U (en) * | 2016-07-01 | 2017-01-18 | 湖南省沙坪建设有限公司 | Concrete floor roughness controlling means |
CN107675867A (en) * | 2017-11-29 | 2018-02-09 | 喻伟 | High-precision leveling unit for floor leveling |
CN108759799A (en) * | 2018-07-17 | 2018-11-06 | 中国水利水电第五工程局有限公司 | A kind of laser orientation system and application method for side slope sash beam setting-out |
-
2019
- 2019-04-30 CN CN201910361146.1A patent/CN110093842B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5633327U (en) * | 1979-08-20 | 1981-04-01 | ||
CN103669291A (en) * | 2013-12-06 | 2014-03-26 | 浙江水利水电学院 | Method for constructing slope through connected slope bricks |
KR200475868Y1 (en) * | 2014-05-21 | 2015-01-08 | 정영길 | Hoarstone construction device |
CN205894626U (en) * | 2016-07-01 | 2017-01-18 | 湖南省沙坪建设有限公司 | Concrete floor roughness controlling means |
CN205804904U (en) * | 2016-07-05 | 2016-12-14 | 上海路港建设工程有限公司 | A kind of leveling unit |
CN107675867A (en) * | 2017-11-29 | 2018-02-09 | 喻伟 | High-precision leveling unit for floor leveling |
CN108759799A (en) * | 2018-07-17 | 2018-11-06 | 中国水利水电第五工程局有限公司 | A kind of laser orientation system and application method for side slope sash beam setting-out |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113215939A (en) * | 2021-06-03 | 2021-08-06 | 中铁二局集团有限公司 | Sidewalk brick laying auxiliary device and paving method |
Also Published As
Publication number | Publication date |
---|---|
CN110093842B (en) | 2021-12-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104295862B (en) | A kind of power measuring instrument tripod | |
CN207280467U (en) | It is a kind of position, the cross horizon rule of leveling | |
CN103967041A (en) | Construction method of fan foundation ring | |
CN110093842A (en) | Auxiliary device and its application method for interlocking segment construction | |
CN208921129U (en) | A kind of contact network in tunnel trackless construction survey instrument | |
CN206862658U (en) | For testing the device of search and rescue robot performance | |
CN105672638A (en) | Scaffold with supporting and sliding functions and net rack mounting method | |
CN103967048B (en) | Fan foundation ring leveling method | |
CN207300237U (en) | The quick monitoring device of pier slope | |
JP2015175162A (en) | transfer method | |
CN203323740U (en) | Building settlement nondestructive measurement leveling rod bracket | |
CN210036717U (en) | Automatic leveling total powerstation base device | |
CN203792305U (en) | Device for leveling T-shaped groove ground rail quickly | |
CN208547487U (en) | Multi-angle vehicle ramp test device | |
CN105002790B (en) | A kind of section of track adjusting means | |
CN208105335U (en) | A kind of self-leveling gravity platform | |
CN103061216A (en) | monolithic rail bed and turnout lifting support arrangement structure of subway short sleeper | |
CN203440721U (en) | Right-angle line beam eccentricity and railway ballast thickness detection ruler | |
CN206095210U (en) | Chi pole is held up in measurement of absorption formula | |
CN104831643A (en) | Jacking device used for bridge construction | |
CN108842545B (en) | Railway removes and dials a way stake device | |
CN107988992B (en) | Sediment test device for experiments | |
CN206459649U (en) | A kind of absolute altitude copies survey device and copies survey system | |
RU134177U1 (en) | DEVICE FOR ADJUSTING THE RAILWAY | |
CN201891250U (en) | Flooring leveling device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||