CN110080556A - A kind of building moving is inverse to make formula constructing structure and construction method - Google Patents
A kind of building moving is inverse to make formula constructing structure and construction method Download PDFInfo
- Publication number
- CN110080556A CN110080556A CN201910384803.4A CN201910384803A CN110080556A CN 110080556 A CN110080556 A CN 110080556A CN 201910384803 A CN201910384803 A CN 201910384803A CN 110080556 A CN110080556 A CN 110080556A
- Authority
- CN
- China
- Prior art keywords
- top tray
- glide path
- anchor
- inverse
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/06—Separating, lifting, removing of buildings; Making a new sub-structure
Abstract
Make formula constructing structure and construction method the invention discloses a kind of building moving is inverse, which includes: S1, the transform beams range earthwork on excavations, until top tray beam beam absolute altitude, and no more than original base bottom absolute altitude;S2, construction top tray girder construction simultaneously conserve;S3, counter-force static pressure anchor rod static pressed pile is provided using top tray beam;S4, anchor jacked pile and top tray beam connect;S5, the earthwork for excavating glide path beam range, are excavated to glide path bottom elevation;S6, the construction of glide path beam;S7, installation shift unit;S8, cutting anchor jacked pile, prepare translation.Original shallow foundation is replaced using anchor rod static-pressing pile foundation, structure trunk load is transferred in deep soil, and when glide path beam range earth excavation is not disturbed by the soil body;Glide path bottom elevation is not limited by basic bottom absolute altitude;Each link has reliable stress and force path in work progress, greatly improves the safety of structure trunk in work progress.
Description
Technical field
Make formula constructing structure and apply the present invention relates to building moving technical field more particularly to a kind of building moving are inverse
Work method.
Background technique
Building moving preliminary construction work includes earth excavation, the construction of top tray beam, the construction of glide path beam, main purpose
To shift on glide path beam structure trunk load by top tray corbel, general main construction technology makees formula construction to be suitable
Technique is sequentially directly excavated to glide path beam bottom, construction glide path beam, construction top tray beam for the earthwork, underpins process as building
Object ontology load directly passes through top tray beam and disposably underpins to glide path beam.
Such suitable formula construction technology of making is suitable for the deeper building translation engineering of embedded depth of foundation, generally new building, such as
Fruit, which is applied to the shallower landmark displacement engineering with reserve value of embedded depth of foundation, can encounter following problem:
(1) substrate of glide path beam buries absolute altitude in the buried depth of basement of original building, and glide path beam of such as first constructing can disturb original and build
Build basis, at this time along the practice earth excavation when bring the security risks such as structure trunk differential settlement;
(2) guarantee that the substrate absolute altitude of glide path beam is higher than the buried depth of basement of original building, such case is needed top tray beam
Absolute altitude improves, and can be higher by indoor ± 0.00 absolute altitude, can destroy along the practice damage building for value ± 0.00 or more of withing a hook at the end at this time
Position is built, this does not allow from the point of view of protecting historical relic.
In conclusion such suitable disposable underpinning construction technique of formula of making is applied to meeting band when the landmark object of shallow foundation
Come the risk of structure trunk differential settlement or the damage to position more than indoor terrace is retained.
Summary of the invention
, construction of the remote past, with a hook at the end value landmark shallow for embedded depth of foundation, in order to guarantee in each construction ring
Section will have reliable stress and force path, guarantee the safety of structure trunk in work progress, the object of the present invention is to provide
It is a kind of inverse to make formula construction method based on what is repeatedly underpined.Guarantee the safety of work progress structure trunk and basis, and guarantees
The construction site of antique value can not be damaged in the construction process.
In order to solve the above-mentioned technical problem, the embodiment of the present invention provides that a kind of building moving is inverse to make formula constructing structure,
It is characterized in that, including structure trunk, top tray beam, anchor jacked pile, glide path beam, piling slot and carriage, it is described to build
It builds object body bottom portion and is fixedly connected with top tray beam, the top tray beam is equipped with piling slot, and it is quiet to be equipped with anchor pole in the piling slot
Piling, described anchor jacked pile one end are fixedly connected in the piling slot, and the anchor jacked pile other end anchors into soil, institute
It states and is equipped with glide path beam on the downside of top tray beam, carriage is equipped between the top tray beam and the glide path beam.
Preferably, the anchor rod static pressure pile material is piling bar.
Preferably, the anchor rod static pressure pile material is concrete-pile.
Preferably, the anchor jacked pile is rectangular or round.
Preferably, the piling slot is preformed groove.
Preferably, the anchor jacked pile is overlapped with the axis of the glide path beam.
Preferably, the axis of the anchor jacked pile and the glide path beam mutually staggers.
In order to solve the above-mentioned technical problem, the embodiment of the present invention, which provides, a kind of makees formula construction using above-mentioned building moving is inverse
The construction method of structure, which comprises the following steps:
The transform beams range earthwork on S1, excavation, until top tray beam beam absolute altitude, and it is no more than original base bottom absolute altitude;
S2, construction top tray girder construction are simultaneously conserved to design strength;
S3, counter-force static pressure anchor rod static pressed pile is provided using top tray beam;
S4, anchor jacked pile and top tray beam connect;
S5, the earthwork for excavating glide path beam range, are excavated to glide path bottom elevation;
S6, the construction of glide path beam;
S7, installation shift unit;
S8, cutting anchor jacked pile, prepare translation.
Preferably, anchor jacked pile is connect with top tray beam connection type for cementitious material in the step S4, or is spiral shell
It tethers and connects or for steel structure connection.
Beneficial effects of the present invention:
(1) original shallow foundation being replaced using anchor rod static-pressing pile foundation, structure trunk load is transferred in deep soil, under
It is not disturbed by the soil body when slipway beam range earth excavation;
(2) glide path bottom elevation is not limited by basic bottom absolute altitude;
(3) each link has reliable stress and force path in work progress, greatly improves in work progress and builds
The safety of object ontology.
Detailed description of the invention
Fig. 1 is top tray beam earth excavation schematic diagram of the invention.
Fig. 2 is top tray beam construction schematic diagram of the invention.
Fig. 3 is anchor rod static pressure pile driving construction schematic diagram of the invention.
Fig. 4 is anchor jacked pile and top tray beam connection schematic diagram of the invention.
Fig. 5 is glide path beam earth excavation schematic diagram of the invention.
Fig. 6 is glide path Liang Xiahuadaoliang construction schematic diagram of the invention.
Fig. 7 is shift unit scheme of installation of the invention.
Fig. 8 is anchor jacked pile cutting schematic diagram of the invention.
1- structure trunk;2- top tray beam;3- anchor jacked pile;4- glide path beam;5- piling slot;6- shift unit.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
As shown in Figures 1 to 8, the specific embodiment of the invention uses following technical scheme: a kind of building moving is inverse to be made
Formula constructing structure, it is characterised in that: including structure trunk 1, top tray beam 2, anchor jacked pile 3, glide path beam 4, piling slot 5
With shift unit 6,1 bottom of structure trunk is fixedly connected with top tray beam 2, and the top tray beam 2 is equipped with piling slot 5,
It is equipped with anchor jacked pile 3 in the piling slot 5, described 3 one end of anchor jacked pile is fixedly connected in the piling slot 5, described
3 other end of anchor jacked pile anchors into soil, on the downside of the top tray beam 2 be equipped with glide path beam 4, the top tray beam 2 with it is described
Shift unit 6 is equipped between glide path beam 4.
Wherein, it is preferred that 3 material of anchor jacked pile is piling bar.
Wherein, 3 material of anchor jacked pile is concrete-pile.
Wherein, the anchor jacked pile 3 is rectangular or round.
Wherein, the piling slot 5 is preformed groove.
Wherein, the anchor jacked pile 3 is overlapped with the axis of the glide path beam 4.
Wherein, the axis of the anchor jacked pile 3 and the glide path beam 4 mutually staggers.
It is a kind of to utilize the inverse construction method for making formula constructing structure of building moving described in claim 1, which is characterized in that packet
Include following steps:
The transform beams range earthwork on S1, excavation, until top tray beam beam absolute altitude, and it is no more than original base bottom absolute altitude;
S2, construction top tray girder construction are simultaneously conserved to design strength;
S3, counter-force static pressure anchor rod static pressed pile is provided using top tray beam;
S4, anchor jacked pile and top tray beam connect;
S5, the earthwork for excavating glide path beam range, are excavated to glide path bottom elevation;
S6, the construction of glide path beam;
S7, installation shift unit;
S8, cutting anchor jacked pile, prepare translation.
Wherein, anchor jacked pile is connect with top tray beam connection type for cementitious material in the step S4, or is bolt
Connection is steel structure connection.
Technical solution of the present invention is further illustrated with reference to the accompanying drawings and examples.
Embodiment one (pile foundation and glide path beam axis misalignment): incorporated by reference to shown in Fig. 1 to Fig. 8, shift unit 6 can be
Slidingtype, roller and wheel dynamic formula.For the present invention using the technique repeatedly underpined, top tray beam 2 of first constructing, this process is to complete knot
The first time of structure underpins, then using top tray beam 2 and the self weight static pressure anchor rod static pressed pile of structure trunk 1, by structure trunk 1
It is underpined by top tray beam 2 to anchor jacked pile 3, this process completes second underpinning, and then large area excavates transform beams or less soil
Side, glide path beam 4 of constructing, after cutting pile foundation, structure trunk 1 is underpined by top tray beam 2 to glide path beam 4, this mistake
Journey is completed third time and is underpined.Concrete measure method is as follows:
Described repeatedly underpins to be different from the upper transform beams 2 along the practice and directly underpining once underpining to glide path beam 4
Construction method, contrary sequence method are to underpin to underpin by top tray beam 2 to anchor jacked pile 3 for structure trunk 1 for the first time;Second
It underpins and changes 2 to glide path beam 4 by top tray corbel for structure trunk 1, increase anchor jacked pile 3 and temporarily underpin.
The contrary sequence method is the working procedure of construction glide path beam 4 after first construction translation top tray beam 2.
The glide path beam 4 is 1 vertical load of structure trunk and horizontal loading when undertaking translation;
The top tray beam 2 is coupled to be whole with structure trunk 1, and reserved piling slot 5, can provide anchor jacked pile
3 counter-force;
The anchor jacked pile 3 is temporarily to underpin measure, can be overlapped with 4 axis of glide path beam, can also be mutually wrong
It opens, purpose is to guarantee the stabilization and safety of the structure trunk 1 in lower layer's cubic metre of earth digging process, and material can also be with for piling bar
For concrete-pile, shape can be rectangular or circle;
Those of ordinary skill in the art it should be appreciated that more than embodiment be intended merely to illustrate the present invention,
And be not used as limitation of the invention, as long as the change in spirit of the invention, to embodiment described above
Change, modification will all be fallen within the scope of claims of the present invention.
Claims (9)
1. a kind of building moving is inverse to make formula constructing structure, which is characterized in that including structure trunk (1), top tray beam (2),
Anchor jacked pile (3), glide path beam (4), piling slot (5) and shift unit (6), structure trunk (1) bottom is fixed to be connected
It connects pallet beam (2), the top tray beam (2) is equipped with piling slot (5), and anchor jacked pile is equipped in the piling slot (5)
(3), described anchor jacked pile (3) one end is fixedly connected in the piling slot (5), anchor jacked pile (3) other end anchor
In burying, be equipped with glide path beam (4) on the downside of the top tray beam (2), the top tray beam (2) and the glide path beam (4) it
Between be equipped with shift unit (6).
2. a kind of building moving according to claim 1 is inverse to make formula constructing structure, it is characterised in that: the anchor rod static pressure
Stake (3) material is piling bar.
3. a kind of building moving according to claim 1 is inverse to make formula constructing structure, it is characterised in that: the anchor rod static pressure
Stake (3) material is concrete-pile.
4. a kind of building moving according to claim 1 is inverse to make formula constructing structure, it is characterised in that: the anchor rod static pressure
Stake (3) is rectangular or round.
5. a kind of building moving according to claim 1 is inverse to make formula constructing structure, it is characterised in that: the piling slot
It (5) is preformed groove.
6. a kind of building moving according to claim 1 is inverse to make formula constructing structure, it is characterised in that: the anchor rod static pressure
Stake (3) is overlapped with the axis of the glide path beam (4).
7. a kind of building moving according to claim 1 is inverse to make formula constructing structure, it is characterised in that: the anchor rod static pressure
Stake (3) and the axis of the glide path beam (4) mutually stagger.
8. a kind of utilize the inverse construction method for making formula constructing structure of building moving described in claim 1, which is characterized in that including
Following steps:
The transform beams range earthwork on S1, excavation, until top tray beam beam absolute altitude, and it is no more than original base bottom absolute altitude;
S2, construction top tray girder construction are simultaneously conserved to design strength;
S3, counter-force static pressure anchor rod static pressed pile is provided using top tray beam;
S4, anchor jacked pile and top tray beam connect;
S5, the earthwork for excavating glide path beam range, are excavated to glide path bottom elevation;
S6, the construction of glide path beam;
S7, installation shift unit;
S8, cutting anchor jacked pile, prepare translation.
9. construction method according to claim 8, it is characterised in that: anchor jacked pile and top tray beam in the step S4
Connection type is cementitious material connection, or to be bolted or being steel structure connection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910384803.4A CN110080556A (en) | 2019-05-09 | 2019-05-09 | A kind of building moving is inverse to make formula constructing structure and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910384803.4A CN110080556A (en) | 2019-05-09 | 2019-05-09 | A kind of building moving is inverse to make formula constructing structure and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110080556A true CN110080556A (en) | 2019-08-02 |
Family
ID=67419556
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910384803.4A Pending CN110080556A (en) | 2019-05-09 | 2019-05-09 | A kind of building moving is inverse to make formula constructing structure and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110080556A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102127974A (en) * | 2011-04-18 | 2011-07-20 | 上海现代建筑设计(集团)有限公司 | Design and construction method of additional cellar under existing building |
CN102220769A (en) * | 2011-04-15 | 2011-10-19 | 上海天演建筑物移位工程有限公司 | System and method for underpinning and jacking building and adding storeys downwards |
GB2495304A (en) * | 2011-10-05 | 2013-04-10 | Francis & Lewis Internat Ltd | Grillage installation apparatus and method |
KR101683080B1 (en) * | 2015-01-14 | 2016-12-08 | (주)골든엔지니어링 | Construction method for addition pile |
CN109680983A (en) * | 2019-01-24 | 2019-04-26 | 上海天演建筑物移位工程股份有限公司 | A kind of modular building underpinning device and method |
-
2019
- 2019-05-09 CN CN201910384803.4A patent/CN110080556A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102220769A (en) * | 2011-04-15 | 2011-10-19 | 上海天演建筑物移位工程有限公司 | System and method for underpinning and jacking building and adding storeys downwards |
CN102127974A (en) * | 2011-04-18 | 2011-07-20 | 上海现代建筑设计(集团)有限公司 | Design and construction method of additional cellar under existing building |
GB2495304A (en) * | 2011-10-05 | 2013-04-10 | Francis & Lewis Internat Ltd | Grillage installation apparatus and method |
KR101683080B1 (en) * | 2015-01-14 | 2016-12-08 | (주)골든엔지니어링 | Construction method for addition pile |
CN109680983A (en) * | 2019-01-24 | 2019-04-26 | 上海天演建筑物移位工程股份有限公司 | A kind of modular building underpinning device and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103758134B (en) | A kind of construction method combining Double-row Piles Support system | |
CN103774675B (en) | Combined double-row-pile combined vertical prestress anchor rod supporting system and construction method thereof | |
CN103452147B (en) | Self-balancing anchor counterweight broken pile forced-landing tilt correcting method | |
CN106150506B (en) | A kind of entrance open excavation section inverted side-wall construction method | |
CN203729308U (en) | Double-row pile supporting system of reinforced concrete pile combined structural steel cement mixing pile wall | |
CN210598987U (en) | Subway station based on single-layer four-guide-hole and middle-guide-hole inner pile foundation | |
CN104264683B (en) | Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition | |
CN102758458A (en) | Underground continuous wall repairing method | |
CN203716156U (en) | Pit-in-pit city gate hole type excavation construction structure in deep foundation pit | |
CN104846832A (en) | Construction method of circular deep foundation pit enclosure of discrete pile support | |
CN101793098B (en) | Coordinated interactive combined rectification method | |
US6948885B2 (en) | Method for constructing foundation | |
CN110080556A (en) | A kind of building moving is inverse to make formula constructing structure and construction method | |
CN103243721A (en) | Raft foundation and core tube excavation construction method of high-rise building under weak geological conditions | |
CN203625911U (en) | Soil discharging construction structure with pit-in-pit door opening arranged in deep foundation pit | |
CN105735335A (en) | Foundation pile construction method and foundation pile structure | |
JP6810411B2 (en) | Caisson construction method | |
JP2001132004A (en) | Earthquake resistant placing method for raising of building and settlement correction work | |
CN102966074B (en) | Artificial channel bank protection structure and method for constructing same | |
CN111593735A (en) | Vertical shaft structure and construction method thereof | |
JPH02108798A (en) | Underground large scale space structure and building method thereof | |
CN111305050A (en) | Protection process for existing piers on two sides in tunnel construction | |
CN204491627U (en) | A kind of building foundation pit quaternity circular section interlocking pile supporting and protection structure | |
CN110206041A (en) | A kind of multi-arch type fashioned iron cement-soil pile and construction method | |
CN113863285B (en) | Inclination stopping method for high-rise building with foundation side large-diameter pile and external box type structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190802 |
|
RJ01 | Rejection of invention patent application after publication |