CN110067581A - The arrangement and construction method of trouble or opening armored concrete branch sheath embedded hole are opened in tunnel or tunnel - Google Patents

The arrangement and construction method of trouble or opening armored concrete branch sheath embedded hole are opened in tunnel or tunnel Download PDF

Info

Publication number
CN110067581A
CN110067581A CN201910394706.3A CN201910394706A CN110067581A CN 110067581 A CN110067581 A CN 110067581A CN 201910394706 A CN201910394706 A CN 201910394706A CN 110067581 A CN110067581 A CN 110067581A
Authority
CN
China
Prior art keywords
embedded
pipe
tunnel
layer
ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910394706.3A
Other languages
Chinese (zh)
Other versions
CN110067581B (en
Inventor
叶建军
尹仲
程大春
杜晓莉
庄心善
陈智
刘一鸣
陈飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei University of Technology
Original Assignee
Hubei University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei University of Technology filed Critical Hubei University of Technology
Priority to CN201910394706.3A priority Critical patent/CN110067581B/en
Publication of CN110067581A publication Critical patent/CN110067581A/en
Application granted granted Critical
Publication of CN110067581B publication Critical patent/CN110067581B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

Trouble or opening armored concrete branch sheath embedded hole arrangement and construction method are opened in a kind of tunnel or tunnel, it is disclosed when the branch sheath construction of trouble or opening is opened in tunnel or tunnel, process by increasing the fixed several plastic tubes of steel ring, realizes that arrangement is used for the built-in pipe of demolition blasting blasthole.It is broken or the occasions such as cannot expose that the present invention is suitable for tunnel or roadway surrounding rock, avoids bore operation, shortens the duration, reduce construction cost, brings good economic and social benefit.

Description

隧道或巷道开岔或开口处钢筋混凝土支护层预埋孔的布置方 式及施工方法Arrangement of pre-buried holes in reinforced concrete supporting layers at tunnel or roadway forks or openings formula and construction method

技术领域technical field

本发明涉及爆破工程领域,具体涉及到一种隧道或巷道开岔或开口处钢筋混凝土支护层预埋孔布置及施工方法。The invention relates to the field of blasting engineering, in particular to an arrangement and construction method of pre-buried holes in a reinforced concrete supporting layer at a tunnel or a roadway fork or opening.

背景技术Background technique

在地下工程建设中,会设计一些交叉的隧道或巷道,在修建中为了方便与另一条隧道或巷道贯通,可以在修建的隧道或巷道需要开岔或开口处采取不支护,等另一条隧道或巷道修建过来一起支护。但有时隧道或巷道开挖中的围岩过于破碎或不能长时间暴露在空气中,就必须立即进行支护工作,不然隧道或巷道局部可能发生侧塌。所以要和另一条隧道或巷道贯通就要在已支护好的隧道或巷道侧壁上进行开岔或开口作业。通常爆破技术是隧道或巷道开岔或开口的高效手段,工程中常用的做法是:对已支护好的隧道在开叉或开口处进行钻孔作业,沿支护层表面法线方向布置多个炮孔,在炮孔里面装上炸药进行爆破开岔或开口。这个做法存在很多弊端:In the construction of underground engineering, some intersecting tunnels or roadways will be designed. In order to facilitate the connection with another tunnel or roadway during construction, it is possible to take no support at the tunnel or roadway that needs to be split or open, and wait for another tunnel or roadway. The roadway was built and supported together. However, sometimes the surrounding rock in tunnel or roadway excavation is too broken or cannot be exposed to the air for a long time, and support work must be carried out immediately, otherwise the tunnel or roadway may partially collapse. Therefore, in order to connect with another tunnel or roadway, it is necessary to carry out the fork or opening operation on the side wall of the well-supported tunnel or roadway. Usually blasting technology is an efficient method for tunnels or roadways to open forks or openings. The common practice in engineering is to drill holes at the forks or openings of the supported tunnels, and arrange more holes along the normal direction of the surface of the support layer. A gun hole, and explosives are installed in the gun hole to blast the fork or opening. There are many disadvantages to this approach:

1、由于隧道或巷道支护层中有钢筋网、钢拱架、连接筋、锚杆的存在,钻孔难度很大,而贯通爆破中需要较多炮孔,以致钻孔成本往往非常高。1. Due to the existence of steel mesh, steel arches, connecting bars, and bolts in the supporting layer of the tunnel or roadway, drilling is very difficult, and more blast holes are required in through blasting, so the drilling cost is often very high.

2、由于孔数较多,人工钻孔对炮孔位置的要求以及炮孔的角度把控不太精准,从而影响爆破效果。2. Due to the large number of holes, the requirements of manual drilling on the position of the blasthole and the angle control of the blasthole are not accurate, thus affecting the blasting effect.

3、孔数较多,人工钻孔非常费时,延长了工期,还有可能影响隧道结构的稳定性。3. The number of holes is large, and manual drilling is very time-consuming, prolonging the construction period and possibly affecting the stability of the tunnel structure.

4、钻孔产生的大量粉尘给环境造成了污染。4. A large amount of dust generated by drilling has caused pollution to the environment.

为了解决上述的问题,在设计之初就考虑以后的隧道或巷道开岔或开口处钢筋混凝土支护层预埋孔布置及施工方法,沿隧道或巷道支护层表面的法线方向预埋管道,实现为以后的隧道或巷道开岔或开口爆破提供炮孔的目的。In order to solve the above problems, at the beginning of the design, the arrangement and construction method of the pre-buried holes in the reinforced concrete supporting layer at the openings or openings of the tunnel or roadway should be considered, and the pipeline should be pre-buried along the normal direction of the surface of the supporting layer of the tunnel or roadway. , to achieve the purpose of providing blastholes for future tunnel or roadway switching or opening blasting.

发明内容SUMMARY OF THE INVENTION

本发明所要解决的问题是提供一种隧道或巷道开岔或开口处钢筋混凝土支护层预埋孔布置及施工方法,本发明在隧道或巷道支护之初就考虑到开岔或开口的问题,设计出开岔和开口处预埋孔的布置、支护施工时预埋管道的固定,预埋管道形成开岔或开口爆破开挖的炮孔,达到高效、低成本、绿色爆破开岔或开口的目的。The problem to be solved by the present invention is to provide an arrangement and construction method of the pre-buried holes in the reinforced concrete supporting layer at the opening or opening of the tunnel or roadway. , Design the layout of the fork and the pre-buried hole at the opening, fix the pre-buried pipeline during the support construction, and the pre-buried pipeline to form the fork or the blast hole for the opening blasting excavation, so as to achieve high efficiency, low cost, green blasting, Purpose of opening.

本发明的目的是这样实现的:一种隧道或巷道开岔或开口处钢筋混凝土支护层预埋孔布置及施工方法,隧道或巷道支护施工时,按所设计的每一圈炮孔的轮廓线制作相同形状的钢筋圈,在隧道壁上打入锚杆工序后,将两排平行钢筋圈与锚杆焊接固定,把预埋管在所对应的位置与钢筋圈绑扎固定,然后完成后面隧道支护的工作,形成预埋炮孔。The purpose of the present invention is to realize in this way: a kind of tunnel or roadway fork or opening place reinforced concrete supporting layer pre-buried hole layout and construction method, when tunnel or roadway supporting construction, according to the design of each circle of blastholes The contour lines are used to make steel bars of the same shape. After the bolting process is driven into the tunnel wall, two rows of parallel steel bars are welded and fixed to the bolts, and the embedded pipes are tied and fixed with the steel bars at the corresponding positions. Tunnel support work to form pre-buried blastholes.

所述的预埋管采用PVC塑料管。The pre-embedded pipe adopts PVC plastic pipe.

一种隧道或巷道开岔或开口处钢筋混凝土支护层预埋孔的布置方式的施工方法,包括以下步骤:A construction method for arranging pre-buried holes in a reinforced concrete supporting layer at the fork or opening of a tunnel or roadway, comprising the following steps:

1)隧道或巷道断面开挖至开岔或开口处后,清除开岔或开口处的浮尘、岩屑后钻孔,在孔中插入中空锚杆,且使锚杆伸出长度小于支护层厚度,在尾部加垫片,拧上螺母后注浆,架立钢筋网并与锚杆绑扎,然后喷锚,形成喷锚层;1) After the tunnel or roadway section is excavated to the fork or opening, remove the floating dust and cuttings at the fork or opening, and then drill the hole, insert the hollow bolt into the hole, and make the extension of the bolt less than the supporting layer. Thickness, add a gasket at the tail, screw on the nut and then grouting, erect the steel mesh and bind it with the anchor rod, and then spray the anchor to form the spray anchor layer;

2)在喷锚层表面外架设与锚杆固定连接的预埋掏槽管钢筋圈、预埋辅助管钢筋圈、预埋周边管钢筋圈,三个钢筋圈的形状分别与开岔或开口处的预埋周边孔、预埋辅助孔、预埋掏槽孔轮廓线相同,垂直隧道中线方向每隔一定距离搭设钢拱架,然后与前一层钢筋圈间隔一定距离处布置一层同样的钢筋圈,钢筋圈包括预埋掏槽管钢筋圈、预埋辅助管钢筋圈、预埋周边管钢筋圈,且与锚杆焊接,使两层钢筋圈所在平面平行;2) On the surface of the shotcrete layer, erect the steel ring of the pre-embedded undercutting pipe, the steel ring of the pre-embedded auxiliary pipe, and the steel ring of the pre-embedded peripheral pipe, which are fixedly connected with the bolt. The outlines of the pre-embedded peripheral holes, pre-embedded auxiliary holes, and pre-embedded cut holes are the same, and steel arches are erected at certain distances in the direction of the vertical tunnel centerline, and then a layer of the same reinforcement is arranged at a certain distance from the previous layer of reinforcement circles. The steel ring includes the steel ring of the pre-embedded undercut pipe, the steel ring of the pre-embedded auxiliary pipe, and the steel ring of the embedded peripheral pipe, and is welded with the anchor rod so that the planes of the two layers of the steel ring are parallel;

3)将预埋周边管、外圈预埋辅助管和预埋掏槽管垂直于钢筋混凝土支护层表面布置,一端往支护层内部延伸,另一端延伸至支护层表面,预埋周边管、预埋辅助管的预埋深度小于支护层厚度,预埋掏槽管的预埋深度为支护层厚度,并用扎丝将预埋周边管、外圈预埋辅助管、预埋掏槽管两端依次分别绑扎在有一定间距的两层钢筋圈上;空预埋管的两端分别用扎丝捆绑并拉紧,扎丝的另一端垂直绑扎于预埋掏槽管钢筋圈的边上,单个内圈预埋辅助管的两端分别绑上扎丝,扎丝另一端与三个已固定的外圈预埋辅助管捆绑,将所有的预埋管用塑料薄膜封住其上下口;3) Arrange the pre-embedded peripheral pipes, the pre-embedded auxiliary pipes in the outer ring and the pre-embedded undercut pipes perpendicular to the surface of the reinforced concrete supporting layer, with one end extending to the inside of the supporting layer and the other end extending to the surface of the supporting layer. The pre-embedded depth of the pipe and the pre-embedded auxiliary pipe is less than the thickness of the supporting layer. The two ends of the grooved pipe are respectively bound on two layers of steel bars with a certain distance in turn; the two ends of the empty pre-embedded pipe are respectively bundled and tightened with a wire, and the other end of the wire is tied vertically to the steel ring of the pre-embedded cut pipe. On the side, the two ends of the single inner ring pre-embedded auxiliary pipe are respectively tied with tie wires, and the other end of the tie wire is bound with the three fixed outer ring pre-embedded auxiliary pipes, and all the pre-embedded pipes are sealed with plastic films. ;

4)再次喷射混凝土完全覆盖钢拱架,形成复喷层;4) Spray concrete again to completely cover the steel arch to form a respray layer;

5)在复喷层表面施工防水层,沿着边墙、拱部布置钢筋,用衬砌台车立模,浇筑混凝土并捣实。5) Construct a waterproof layer on the surface of the compound spray layer, arrange steel bars along the side walls and arches, use a lining trolley to form a vertical form, pour concrete and tamp it.

上述步骤1)有另一种施工方法,隧道或巷道断面开挖开岔或开口处后,在开岔或开口处用高压风吹净岩面的浮尘、岩屑,在净岩面进行初喷混凝土,凝固后用钻孔机械钻孔,插入中空锚杆,且使锚杆伸出长度小于支护层厚度,在尾部加垫片,拧上螺母后注浆,架立钢筋网与锚杆焊接或用铁丝绑扎。The above step 1) has another construction method. After the tunnel or roadway section is excavated at the fork or opening, high-pressure wind is used to clean the floating dust and cuttings on the rock surface at the fork or opening, and the initial spray is carried out on the clean rock surface. After the concrete is solidified, use a drilling machine to drill holes, insert the hollow anchor rod, and make the extension length of the anchor rod less than the thickness of the supporting layer, add a gasket at the tail, screw the nut and then grouting, erect the steel mesh and weld the anchor rod Or tied with wire.

步骤5)的另一种施工方法是在复喷层表面施工防水层,用衬砌台车沿着边墙、拱部立模,浇筑混凝土并捣实。Another construction method of step 5) is to construct a waterproof layer on the surface of the compound spray layer, and use a lining trolley to form a vertical form along the side wall and the arch, pour concrete and compact it.

步骤5)有另一种施工方法是开挖仰拱,并在处布置钢筋并立模浇筑混凝土,终凝后,在复喷层表面施工防水层,接着沿着边墙、拱顶布置钢筋,用衬砌台车立模,浇筑混凝土并捣实。Step 5) Another construction method is to excavate the inverted arch, and arrange steel bars at the place and pour concrete with vertical formwork. Lining the vertical form of the trolley, pouring concrete and tamping.

一种钢筋混凝土支护隧道或巷道开岔或开口预埋孔的布置方式的施工方法,包括以下步骤:A construction method for arranging a reinforced concrete supporting tunnel or roadway fork or opening pre-buried hole, comprising the following steps:

2)平行于喷锚层表面布置一层钢筋圈,其包括预埋掏槽管钢筋圈、预埋辅助管钢筋圈、预埋周边管钢筋圈,且与锚杆焊接,其形状分别与开岔或开口处的预埋周边孔、预埋辅助孔、预埋掏槽孔轮廓线相同,然后与前一层钢筋圈间隔一定距离处布置一层同样的钢筋圈,其包括预埋掏槽管钢筋圈、固定预埋辅助管钢筋圈、预埋周边管钢筋圈,且与锚杆焊接,使两层钢筋圈所在平面平行;2) A layer of reinforcement rings is arranged parallel to the surface of the shotcrete layer, which includes reinforcement rings for pre-embedded undercut pipes, reinforcement rings for pre-embedded auxiliary pipes, and reinforcement rings for pre-embedded peripheral pipes, which are welded to the anchor rod, and their shapes are respectively the same as those of the fork. Or the pre-embedded peripheral holes, pre-embedded auxiliary holes, and pre-embedded undercut holes at the opening have the same outline, and then arrange a layer of the same reinforcement ring at a certain distance from the previous layer of reinforcement circles, including the pre-embedded undercut pipe reinforcement. ring, fixed pre-embedded auxiliary pipe reinforcement ring, pre-embedded peripheral pipe reinforcement ring, and welded with the anchor rod, so that the planes of the two layers of reinforcement rings are parallel;

3)将预埋周边管、外圈预埋辅助管和预埋掏槽管垂直于钢筋混凝土支护层表面布置,一端往支护层内部延伸,另一端延伸至支护层表面,预埋周边管、预埋辅助管的预埋深度小于支护层厚度,预埋掏槽管的预埋深度为支护层厚度,并用扎丝将预埋周边管、外圈预埋辅助管、预埋掏槽管两端依次分别绑扎在两层钢筋圈上;空预埋管的两端分别用扎丝捆绑并拉紧,扎丝的另一端垂直绑扎于预埋掏槽管钢筋圈的边上,单个内圈预埋辅助管的两端分别绑上扎丝,扎丝另一端与三个已固定的外圈预埋辅助管捆绑,将所有的预埋管用塑料薄膜封住其上下口;3) Arrange the pre-embedded peripheral pipes, the pre-embedded auxiliary pipes in the outer ring and the pre-embedded undercut pipes perpendicular to the surface of the reinforced concrete supporting layer, with one end extending to the inside of the supporting layer and the other end extending to the surface of the supporting layer. The pre-embedded depth of the pipe and the pre-embedded auxiliary pipe is less than the thickness of the supporting layer. The two ends of the grooved pipe are respectively bound on the two layers of steel bars in turn; the two ends of the empty pre-embedded pipe are respectively tied and tightened with a wire, and the other end of the wire is tied vertically on the edge of the steel ring of the pre-embedded cut pipe. The two ends of the inner ring pre-embedded auxiliary pipes are respectively tied with ties, the other end of the ties is bound with the three fixed outer ring pre-embedded auxiliary pipes, and all the pre-embedded pipes are sealed with plastic films at their upper and lower openings;

4)在喷锚层表面施工防水层,接着沿边墙、拱部布置钢筋,用衬砌台车立模,浇筑混凝土并捣实。4) Construct a waterproof layer on the surface of the shotcrete layer, then arrange steel bars along the side walls and arches, use a lining trolley to form a vertical form, pour concrete and tamp it.

上述步骤1)有另一种施工方法,隧道或巷道断面开挖开岔或开口处后,在开岔或开口处用高压风吹净岩面的浮尘、岩屑,在净岩面进行初喷混凝土,凝固后用钻孔机械钻孔,插入中空锚杆,且使锚杆伸出长度小于支护层厚度,在尾部加垫片,拧上螺母后注浆,架立钢筋网与锚杆焊接或用铁丝绑扎。The above step 1) has another construction method. After the tunnel or roadway section is excavated at the fork or opening, high-pressure wind is used to clean the floating dust and cuttings on the rock surface at the fork or opening, and the initial spray is carried out on the clean rock surface. After the concrete is solidified, use a drilling machine to drill holes, insert the hollow anchor rod, and make the extension length of the anchor rod less than the thickness of the supporting layer, add a gasket at the tail, screw the nut and then grouting, erect the steel mesh and weld the anchor rod Or tied with wire.

步骤4)的另一种施工方法,在喷锚层表面施工防水层,用衬砌台车沿边墙、拱部立模,浇筑混凝土并捣实。Another construction method in step 4) is to construct a waterproof layer on the surface of the shotcrete layer, use a lining trolley to form a vertical form along the side wall and the arch, pour concrete and tamp it.

本发明具有以下有益效果:本发明提供一种隧道或巷道开岔或开口处钢筋混凝土支护层预埋孔布置及施工方法,在隧道或巷道支护施工时预埋PVC塑料管,在需要开岔或开口作业时只需要找到PVC塑料管,就可以进行爆破作业,避免了在隧道或巷道支护层钻孔的作业,节约了大量人力物力财力,也避免了钻孔施工中产生的噪音污染。The present invention has the following beneficial effects: the present invention provides an arrangement and a construction method of pre-buried holes in a reinforced concrete supporting layer at a tunnel or a roadway fork or opening, where PVC plastic pipes are pre-buried during the tunnel or roadway supporting construction, and when it needs to be opened For fork or opening operation, you only need to find the PVC plastic pipe, and then the blasting operation can be carried out, which avoids the drilling operation in the tunnel or roadway support layer, saves a lot of manpower, material and financial resources, and also avoids the noise pollution generated in the drilling construction. .

本发明在一种隧道或巷道开岔或开口处钢筋混凝土支护层预埋孔布置及施工方法,能轻易在支护层布置炮孔,所布置的预埋孔位置准确,避免了人工钻孔带来的诸多误差,从而提供以后爆破的效果,加快了开岔或开口的速度。The invention arranges pre-embedded holes in a reinforced concrete supporting layer at the fork or opening of a tunnel or a roadway and a construction method, which can easily arrange blast holes in the supporting layer, and the pre-buried holes are arranged in an accurate position, and manual drilling is avoided. Many errors brought about, thereby providing the effect of subsequent blasting, and speeding up the speed of opening forks or openings.

本发明提供的一种隧道或巷道开岔或开口处钢筋混凝土支护层预埋孔布置及施工方法,有利于钢筋网、钢拱架、混凝土的循环利用。The invention provides an arrangement and a construction method for pre-buried holes in a reinforced concrete supporting layer at a fork or opening of a tunnel or a roadway, which is beneficial to the recycling of reinforced mesh, steel arch and concrete.

本发明避免了钻空作业以及钻孔产生的粉尘,同时减少了对环境的影响。The invention avoids the drilling operation and the dust generated by the drilling, and reduces the impact on the environment at the same time.

附图说明Description of drawings

下面结合附图和实施例对本发明作进一步说明。The present invention will be further described below with reference to the accompanying drawings and embodiments.

图1是隧道或巷道开岔或开口预埋孔示意图。Figure 1 is a schematic diagram of a tunnel or roadway with a fork or an open pre-buried hole.

图2是衬砌层为钢筋混凝土的隧道或巷道预埋孔断面示意图。(图4中的B-B)Figure 2 is a schematic cross-sectional view of a tunnel or roadway embedded hole with a lining layer of reinforced concrete. (B-B in Figure 4)

图3是衬砌层为素混凝土的隧道或巷道预埋孔断面示意图。(图4中的B-B)Figure 3 is a schematic cross-sectional view of a tunnel or roadway pre-buried hole where the lining layer is plain concrete. (B-B in Figure 4)

图4是隧道或巷道预埋孔剖面示意图,即图2、3中的A-A向视图。FIG. 4 is a schematic cross-sectional view of a pre-buried hole in a tunnel or a roadway, that is, a view from the direction A-A in FIGS. 2 and 3 .

图5是无钢拱架且衬砌层为钢筋混凝土的隧道或巷道预埋孔断面示意图。Fig. 5 is a schematic cross-sectional view of a tunnel or roadway pre-buried hole without a steel arch and the lining layer is reinforced concrete.

图6是无钢拱架且衬砌层为素混凝土的隧道或巷道预埋孔断面示意图。Figure 6 is a schematic cross-sectional view of a tunnel or roadway pre-buried hole without a steel arch and the lining layer is plain concrete.

图7是预埋掏槽管固定示意图。Figure 7 is a schematic diagram of the fixing of the embedded undercut pipe.

图8是空预埋管固定示意图。Fig. 8 is a schematic diagram of fixing the empty pre-embedded pipe.

图9是外圈预埋辅助管固定示意图。Fig. 9 is a schematic diagram showing the fixing of the pre-embedded auxiliary pipe in the outer ring.

图10是内圈单个预埋辅助管固定示意图。Fig. 10 is a schematic diagram of fixing a single pre-embedded auxiliary pipe in the inner ring.

图11是预埋周边管辅助示意图。Figure 11 is an auxiliary schematic diagram of the pre-embedded peripheral pipe.

图中,预埋孔1,锚杆2,钢拱架3,钢筋网4,空预埋孔5,预埋掏槽孔6,外圈预埋辅助孔7,内圈单一预埋辅助孔 8,预埋周边孔9,空预埋管10,预埋掏槽管11,扎丝12,预埋掏槽管钢筋圈13,外圈预埋辅助管14,内圈预埋辅助管15,预埋辅助管钢筋圈16,预埋周边管17,预埋周边管钢筋圈18,喷锚层表面19,钢筋20,复喷层与二次衬砌层界线21。In the figure, pre-embedded hole 1, bolt 2, steel arch 3, steel mesh 4, empty pre-embedded hole 5, pre-embedded undercut hole 6, pre-embedded auxiliary hole 7 in the outer ring, and single pre-embedded auxiliary hole in the inner ring 8 , pre-embedded peripheral hole 9, empty pre-embedded pipe 10, pre-embedded undercut pipe 11, tie wire 12, pre-embedded undercut pipe reinforcement ring 13, outer ring pre-embedded auxiliary pipe 14, inner ring pre-embedded auxiliary pipe 15, pre-buried Buried auxiliary pipe reinforcement ring 16, pre-embedded peripheral pipe 17, pre-embedded peripheral pipe reinforcement ring 18, surface 19 of spray anchor layer, steel reinforcement 20, boundary line 21 of compound spray layer and secondary lining layer.

具体实施方式Detailed ways

具体实施方式,如图1-11所示,隧道或巷道开岔或开口处钢筋混凝土支护层预埋孔布置及施工方法包括隧道或巷道开岔或开口预埋孔示意图,衬砌层为钢筋混凝土的隧道或巷道预埋孔断面示意图,衬砌层为素混凝土的隧道或巷道预埋孔断面示意图,隧道或巷道预埋孔剖面示意图,无钢拱架且衬砌层为钢筋混凝土的隧道或巷道预埋孔断面示意图,无钢拱架且衬砌层为素混凝土的隧道或巷道预埋孔断面示意图,预埋掏槽管固定示意图,空预埋管固定示意图,外圈预埋辅助管固定示意图,内圈单个预埋辅助管固定示意图,预埋周边管辅助示意图。DETAILED DESCRIPTION As shown in Figures 1-11, the layout and construction method of the pre-buried holes in the reinforced concrete supporting layer at the switch or opening of the tunnel or roadway include a schematic diagram of the pre-buried hole at the switch or opening of the tunnel or roadway, and the lining layer is reinforced concrete. Schematic diagram of the pre-buried hole in the tunnel or roadway, schematic diagram of the pre-buried hole in the tunnel or roadway with the lining layer of plain concrete, schematic diagram of the pre-buried hole in the tunnel or roadway, without steel arch frame and the lining layer of the tunnel or roadway pre-buried with reinforced concrete Schematic diagram of hole section, schematic diagram of tunnel or roadway pre-buried hole without steel arch frame and lining layer of plain concrete, schematic diagram of pre-buried undercut pipe fixing, schematic diagram of empty pre-buried pipe fixing, outer ring pre-embedded auxiliary pipe fixing schematic diagram, inner ring A schematic diagram of fixing a single pre-embedded auxiliary pipe, and a schematic diagram of the auxiliary pre-embedded peripheral pipe.

实施例1:Example 1:

某隧道设计长2km,跨度6米,墙高2米,拱高1.5m,支护层厚度为55cm,在隧道中需要开岔或开口。A tunnel is designed with a length of 2km, a span of 6m, a wall height of 2m, an arch height of 1.5m, and the thickness of the support layer is 55cm. In the tunnel, a fork or opening is required.

根据上述的隧道或巷道开岔或开口处钢筋混凝土支护层预埋孔布置及施工方法,本发明的施工工序为:According to above-mentioned tunnel or roadway fork or opening place reinforced concrete supporting layer pre-buried hole arrangement and construction method, the construction process of the present invention is:

1)隧道或巷道断面开挖开岔或开口处后,在开岔或开口处用高压风吹净岩面的浮尘、岩屑,用钻孔机械钻孔,插入中空锚杆2,且使锚杆伸出长度小于支护层厚度5cm ,在尾部加垫片,拧上螺母后注浆,架立钢筋网并与锚杆焊接或用铁丝绑扎,然后混凝土喷射机组喷锚,喷锚层厚度为40mm;1) After excavating the fork or opening of the tunnel or roadway section, use high-pressure wind to blow off the floating dust and cuttings on the rock surface at the fork or opening, drill holes with a drilling machine, insert the hollow bolt 2, and make the anchor The extension length of the rod is less than 5cm of the thickness of the supporting layer, add a gasket at the tail, screw on the nut and then grouting, erect the steel mesh and weld it with the anchor rod or bind it with iron wire, and then spray the anchor with the concrete spray unit, and the thickness of the spray anchor layer is 40mm;

2)在离喷锚层表面10cm处架设三个与锚杆焊接的钢筋圈,即预埋掏槽管钢筋圈13、预埋辅助管钢筋圈16和预埋周边管钢筋圈18,三个钢筋圈的形状分别与开岔或开口处所设计的预埋周边孔、预埋辅助孔、预埋掏槽孔轮廓线相同,钢筋圈直径为8mm,垂直隧道中线方向每隔1.5m搭设钢拱架,钢拱架侧面与锚杆焊接,并在两相邻钢拱架焊上纵向连接筋;然后与前一层钢筋圈间隔一定距离处布置一层同样的钢筋圈,钢筋圈包括预埋掏槽管钢筋圈13、预埋辅助管钢筋圈16、预埋周边管钢筋圈18,且与锚杆2焊接,使两层钢筋圈所在平面平行;2) At 10cm away from the surface of the shotcrete layer, set up three reinforcement rings welded with the anchor rod, namely, the reinforcement ring 13 of the pre-embedded cutting pipe, the reinforcement ring 16 of the pre-embedded auxiliary pipe, and the reinforcement ring 18 of the pre-embedded peripheral pipe, three steel bars. The shape of the ring is the same as the contour lines of the pre-embedded peripheral holes, pre-embedded auxiliary holes and pre-embedded cut holes designed at the fork or opening, respectively. The diameter of the reinforcement ring is 8mm. The side of the steel arch frame is welded with the anchor rod, and longitudinal connecting ribs are welded on the two adjacent steel arch frames; then a layer of the same steel ring is arranged at a certain distance from the previous layer of steel ring, and the steel ring includes pre-buried undercut pipes. The reinforcement ring 13, the pre-embedded auxiliary pipe reinforcement ring 16, and the pre-embedded peripheral pipe reinforcement ring 18 are welded with the anchor rod 2 so that the planes of the two layers of reinforcement rings are parallel;

3)预埋管采用PVC塑料管,将预埋周边管、预埋辅助管、预埋掏槽管沿钢筋混凝土支护层表面的法线方向布置,一端往支护层内部延伸,另一端延伸至支护层表面。预埋周边管、预埋辅助管的预埋深度为45cm,直径为50mm,长度为55cm,预埋掏槽管和空预埋管的预埋深度为50cm,长度为60mm,预埋掏槽管直径为50mm,空预埋管直径为63mm,并用扎丝将预埋周边管、预埋辅助管、预埋掏槽管两端依次分别绑扎在有一定间距的两层钢筋圈上。空预埋管的两端分别扎丝捆绑并拉紧,扎丝的另一端分别绑扎于三角形钢筋圈的边上,内圈单个预埋辅助管的两端分别绑上扎丝,扎丝另一端与三个已固定预埋辅助管捆绑,将预埋管用塑料袋封住其上下口;3) The pre-embedded pipes are made of PVC plastic pipes. The pre-embedded peripheral pipes, pre-embedded auxiliary pipes and pre-embedded undercut pipes are arranged along the normal direction of the surface of the reinforced concrete supporting layer, with one end extending into the supporting layer and the other end extending to the surface of the support layer. The pre-embedded peripheral pipe and pre-embedded auxiliary pipe shall have a pre-embedded depth of 45cm, a diameter of 50mm and a length of 55cm. The diameter is 50mm, the diameter of the empty pre-embedded pipe is 63mm, and the two ends of the pre-embedded peripheral pipe, the pre-embedded auxiliary pipe, and the pre-embedded undercut pipe are respectively bound on two layers of steel bars with a certain distance with a wire tie. The two ends of the empty pre-embedded pipe are respectively tied with wires and tightened, and the other ends of the wires are tied to the edge of the triangular steel bar respectively. Bundle with three fixed pre-embedded auxiliary pipes, and seal the upper and lower openings of the pre-embedded pipes with plastic bags;

4)复喷混凝土覆盖钢拱架,复喷厚度为26cm;4) The re-sprayed concrete covers the steel arch, and the re-spray thickness is 26cm;

5)仰拱处布置钢筋立模浇筑混凝土,终凝后,在复喷层表面施工防水层,接着沿着边墙、拱顶布置钢筋,用衬砌台车立模,浇筑混凝土并捣实,厚度为25cm。5) Arrange reinforced vertical formwork at the inverted arch to cast concrete. After the final setting, construct a waterproof layer on the surface of the respray layer, then arrange reinforced steel along the side wall and the vault, use a lining trolley to form a vertical form, pour concrete and tamp it. Thickness is 25cm.

实施例2:Example 2:

某隧道设计长3km,跨度6.5米,墙高1.9米,拱高1.6m,支护层厚度为50cm,在隧道中需要开岔或开口。A tunnel is designed with a length of 3km, a span of 6.5m, a wall height of 1.9m, an arch height of 1.6m, and a supporting layer thickness of 50cm. Forks or openings are required in the tunnel.

根据上述的隧道或巷道开岔或开口处钢筋混凝土支护层预埋孔布置及施工方法,本发明的施工工序为:According to above-mentioned tunnel or roadway fork or opening place reinforced concrete supporting layer pre-buried hole arrangement and construction method, the construction process of the present invention is:

1)隧道或巷道断面开挖开岔或开口处后,在开岔或开口处用高压风吹净岩面的浮尘、岩屑,初喷混凝土厚度为50mm,凝固后用钻孔机械钻孔,插入中空锚杆,且使锚杆伸出长度小于支护层厚度10cm ,在尾部加垫片,拧上螺母后注浆,架立钢筋网与锚杆焊接或用铁丝绑扎;1) After excavating the fork or opening of the tunnel or roadway section, use high-pressure air to clean the floating dust and cuttings on the rock surface at the fork or opening. The thickness of the initial shotcrete is 50mm. Insert the hollow anchor rod, and make the extension length of the anchor rod less than 10cm of the thickness of the supporting layer, add a gasket at the tail, screw the nut and then grouting, erect the steel mesh and weld the anchor rod or bind it with iron wire;

2)在离所架的钢筋网面8cm处架设三个与锚杆焊接的钢筋圈,三个钢筋圈的形状分别与开岔或开口处所设计的预埋周边孔、预埋辅助孔、预埋掏槽孔轮廓线相同,且钢筋圈直径为6mm,垂直隧道中线方向每隔1m搭设钢拱架,钢拱架侧面与锚杆焊接,并在两相邻钢拱架焊上纵向连接筋,然后与第一排钢筋圈间隔一定距离处布置一层同样的钢筋圈,钢筋圈包括预埋掏槽管钢筋圈13、预埋辅助管钢筋圈16、预埋周边管钢筋圈18,且与锚杆2焊接,使两层钢筋圈所在平面平行;2) Set up three reinforcement rings welded to the anchor rod at a distance of 8cm from the surface of the reinforcement mesh to be erected. The shapes of the three reinforcement rings are respectively the same as the pre-embedded peripheral holes, pre-embedded auxiliary holes and pre-embedded holes designed at the fork or opening. The contour lines of the cut holes are the same, and the diameter of the steel ring is 6mm. Steel arches are erected at intervals of 1m in the direction of the vertical tunnel centerline. A layer of the same reinforcement ring is arranged at a certain distance from the first row of reinforcement rings. The reinforcement ring includes the reinforcement ring 13 of the pre-embedded cutting pipe, the reinforcement ring 16 of the pre-embedded auxiliary pipe, and the reinforcement ring 18 of the pre-embedded peripheral pipe. 2 Weld so that the planes of the two layers of steel bars are parallel;

3)预埋管采用PVC塑料管,将预埋周边管、预埋辅助管、预埋掏槽管沿钢筋混凝土支护层表面的法线方向布置,一端往支护层内部延伸,另一端延伸至支护层表面。预埋周边管、预埋辅助管的预埋深度为40cm,直径为50mm,长度为45cm,预埋掏槽管和空预埋管的预埋深度为45cm,长度为50mm,预埋掏槽管直径为50mm,空预埋管直径为63mm,并用扎丝将预埋周边管、预埋辅助管、预埋掏槽管两端依次分别绑扎在有一定间距的钢筋圈上。空预埋管的两端分别扎丝捆绑并拉紧,扎丝的另一端分别绑扎于三角形钢筋圈的边上,内圈单个预埋辅助管的两端分别绑上扎丝,扎丝另一端与三个已固定预埋辅助管捆绑,将预埋管用塑料袋封住其上下口;3) The pre-embedded pipes are made of PVC plastic pipes. The pre-embedded peripheral pipes, pre-embedded auxiliary pipes and pre-embedded undercut pipes are arranged along the normal direction of the surface of the reinforced concrete supporting layer, with one end extending into the supporting layer and the other end extending to the surface of the support layer. The pre-embedded peripheral pipes and pre-embedded auxiliary pipes shall have a pre-embedded depth of 40 cm, a diameter of 50 mm and a length of 45 cm. The diameter is 50mm, the diameter of the empty pre-embedded pipe is 63mm, and the two ends of the pre-embedded peripheral pipe, the pre-embedded auxiliary pipe, and the pre-embedded undercut pipe are respectively tied to the steel ring with a certain spacing with wire ties. The two ends of the empty pre-embedded pipe are respectively tied with wires and tightened, and the other ends of the wires are tied to the edge of the triangular steel bar respectively. Bundle with three fixed pre-embedded auxiliary pipes, and seal the upper and lower openings of the pre-embedded pipes with plastic bags;

4)复喷混凝土覆盖钢拱架,复喷厚度为25cm;4) The re-sprayed concrete covers the steel arch, and the re-spray thickness is 25cm;

5)在复喷层表面施工防水层,接着沿着边墙、拱顶布置钢筋,用衬砌台车立模,浇筑混凝土并捣实,厚度为20cm。5) A waterproof layer is constructed on the surface of the compound spray layer, and then the steel bars are arranged along the side wall and the vault, and the lining trolley is used to form the vertical form, and the concrete is poured and tamped, with a thickness of 20cm.

实施例3Example 3

某隧道设计长2.5km,跨度5.5米,墙高2.1米,拱高1.5m,支护层厚度为60cm,在隧道中需要开岔或开口。A tunnel is designed with a length of 2.5km, a span of 5.5m, a wall height of 2.1m, an arch height of 1.5m, and a supporting layer thickness of 60cm. A fork or opening is required in the tunnel.

1)隧道或巷道断面开挖开岔或开口处后,在开岔或开口处用高压风吹净岩面的浮尘、岩屑,用钻孔机械钻孔,插入中空锚杆2,且使锚杆伸出长度小于支护层厚度12cm ,在尾部加垫片,拧上螺母后注浆,架立钢筋网4与锚杆2固定连接,采用焊接或用铁丝绑扎均可,然后混凝土喷射机组喷锚,喷锚层厚度为40mm;1) After excavating the fork or opening of the tunnel or roadway section, use high-pressure wind to blow off the floating dust and cuttings on the rock surface at the fork or opening, drill holes with a drilling machine, insert the hollow bolt 2, and make the anchor The extension length of the rod is less than the thickness of the supporting layer 12cm, add a gasket at the tail, screw on the nut and then grouting, erect the steel mesh 4 and the anchor rod 2 to be fixedly connected, either welding or binding with iron wire can be used, and then the concrete spraying unit sprays Anchor, the thickness of the shotcrete layer is 40mm;

2)在离所架的钢筋网面15cm处架设三个与锚杆焊接的钢筋圈,即预埋掏槽管钢筋圈13、预埋辅助管钢筋圈16、预埋周边管钢筋圈18,三个钢筋圈的形状分别与开岔或开口处所设计的预埋周边孔、预埋辅助孔、预埋掏槽孔轮廓线相同,且钢筋圈直径为6mm,然后与第一排钢筋圈间隔一定距离且离支护层表面10cm处布置三个同样的钢筋圈并与锚杆焊接;2) Set up three reinforcement rings welded with the anchor rod at a distance of 15cm from the surface of the reinforcement mesh to be erected, namely the reinforcement ring 13 of the pre-embedded cutting pipe, the reinforcement ring of the pre-embedded auxiliary pipe 16, and the reinforcement ring of the pre-embedded peripheral pipe 18. The shapes of each steel ring are the same as the contour lines of the pre-embedded peripheral holes, pre-embedded auxiliary holes and pre-embedded cut holes designed at the fork or opening, and the diameter of the steel ring is 6mm, and then it is separated from the first row of steel rings by a certain distance. And three identical reinforcement rings are arranged 10cm away from the surface of the support layer and welded with the anchor rod;

3)预埋管采用PVC塑料管,将预埋周边管、预埋辅助管、预埋掏槽管沿钢筋混凝土支护层表面的法线方向布置,一端往支护层内部延伸,另一端延伸至支护层表面。预埋周边管、预埋辅助管的预埋深度为52cm,直径为50mm,长度为57cm,预埋掏槽管和空预埋管的预埋深度为56cm,长度为61mm,预埋掏槽管直径为50mm,空预埋管直径为63mm,并用扎丝将预埋周边管、预埋辅助管、预埋掏槽管两端依次分别绑扎在有一定间距的钢筋圈上。空预埋管的两端分别扎丝捆绑并拉紧,扎丝的另一端分别绑扎于预埋掏槽管钢筋圈13的边上,内圈单个预埋辅助管的两端分别绑上扎丝,扎丝另一端与三个已固定预埋辅助管捆绑,将预埋管用塑料袋封住其上下口;3) The pre-embedded pipes are made of PVC plastic pipes. The pre-embedded peripheral pipes, pre-embedded auxiliary pipes and pre-embedded undercut pipes are arranged along the normal direction of the surface of the reinforced concrete supporting layer, with one end extending into the supporting layer and the other end extending to the surface of the support layer. The pre-embedded peripheral pipes and pre-embedded auxiliary pipes shall have a pre-embedded depth of 52cm, a diameter of 50mm and a length of 57cm. The diameter is 50mm, the diameter of the empty pre-embedded pipe is 63mm, and the two ends of the pre-embedded peripheral pipe, the pre-embedded auxiliary pipe, and the pre-embedded undercut pipe are respectively tied to the steel ring with a certain spacing with wire ties. The two ends of the empty pre-embedded pipe are respectively tied with wires and tensioned, the other ends of the tied wires are respectively tied to the edge of the steel ring 13 of the embedded undercut pipe, and the two ends of the single pre-embedded auxiliary pipe in the inner ring are tied with the tied wires respectively. , the other end of the tie wire is bound with three fixed pre-embedded auxiliary pipes, and the upper and lower openings of the pre-embedded pipes are sealed with plastic bags;

4)在喷锚层表面施工防水层,用衬砌台车沿边墙和拱部立模,浇筑混凝土并捣实。厚底为56cm。4) Construct a waterproof layer on the surface of the shotcrete layer, use a lining trolley along the side walls and arches to form the vertical form, pour concrete and tamp it. The thick bottom is 56cm.

本发明中,预埋掏槽管钢筋圈13为三角形,预埋辅助管钢筋圈16,预埋周边管钢筋圈18与隧道截面形状相同,上部为弧形,下部为矩形。In the present invention, the pre-embedded undercut pipe reinforcement ring 13 is triangular, the pre-embedded auxiliary pipe reinforcement ring 16, and the pre-embedded peripheral pipe reinforcement ring 18 have the same cross-sectional shape as the tunnel, the upper part is arc-shaped, and the lower part is rectangular.

Claims (4)

1.一种隧道或巷道开岔或开口处钢筋混凝土支护层预埋孔的布置方式,其特征在于:包括预埋孔(1),所述预埋孔(1)包括预埋周边孔(9)、内圈单一预埋辅助孔(8)、外圈预埋辅助孔(7)、预埋掏槽孔(6)以及空预埋孔(5);空预埋孔(5)位于预埋掏槽孔(6)所围成的区域内;预埋孔(1)的长度方向与钢筋混凝土支护层表面垂直,一端往支护层内部延伸,另一端延伸至支护层表面;预埋周边孔(9)分布于隧道或巷道开岔或开口处轮廓线上,预埋周边孔(9)、内圈单一预埋辅助孔(8)深度小于支护层厚度;预埋掏槽孔(6)和空预埋孔(5)深度与支护层厚度相同,空预埋孔(5)直径大于或等于其它孔径。1. An arrangement of pre-embedded holes in reinforced concrete supporting layers at tunnel or roadway forks or openings, characterized in that: the pre-embedded holes (1) are included, and the pre-embedded holes (1) include pre-embedded peripheral holes ( 9), a single pre-embedded auxiliary hole (8) in the inner ring, a pre-embedded auxiliary hole (7) in the outer ring, a pre-embedded undercut hole (6) and an empty pre-buried hole (5); the empty pre-buried hole (5) is located in the pre-buried hole (5). In the area enclosed by the buried undercut hole (6); the length direction of the embedded hole (1) is perpendicular to the surface of the reinforced concrete supporting layer, one end extends to the inside of the supporting layer, and the other end extends to the surface of the supporting layer; The buried peripheral holes (9) are distributed on the contour line of the forks or openings of the tunnel or roadway, and the pre-embedded peripheral holes (9) and the inner ring single pre-embedded auxiliary hole (8) have a depth smaller than the thickness of the supporting layer; (6) The depth of the empty pre-buried hole (5) is the same as the thickness of the supporting layer, and the diameter of the empty pre-buried hole (5) is greater than or equal to other apertures. 2.根据权利要求1所述的一种隧道或巷道开岔或开口处钢筋混凝土支护层预埋孔的布置方式的施工方法,其特征在于,包括以下步骤:2. the construction method of the arrangement mode of a kind of tunnel or roadway switch or the pre-buried hole of reinforced concrete supporting layer at the opening according to claim 1, is characterized in that, comprises the following steps: 1)隧道或巷道断面开挖至开岔或开口处后,清除开岔或开口处的浮尘、岩屑后钻孔,在孔中插入中空锚杆(2),且使锚杆伸出长度小于支护层厚度,在尾部加垫片,拧上螺母后注浆,架立钢筋网(4)并与锚杆(2)绑扎,然后喷锚,形成喷锚层;1) After the tunnel or roadway section is excavated to the fork or opening, remove the floating dust and cuttings at the fork or opening, and then drill the hole, insert the hollow bolt (2) into the hole, and make the extension length of the bolt less than For the thickness of the support layer, add a gasket at the tail, screw on the nut and then grouting, erect the steel mesh (4) and bind it with the anchor rod (2), and then spray the anchor to form the spray anchor layer; 2)在喷锚层表面外架设与锚杆(2)固定连接的预埋掏槽管钢筋圈(13)、预埋辅助管钢筋圈(16)、预埋周边管钢筋圈(18),三个钢筋圈的形状分别与开岔或开口处的预埋周边孔(9)、预埋辅助孔(7)、预埋掏槽孔(6)轮廓线相同,垂直隧道中线方向每隔一定距离搭设钢拱架(3),然后与前一层钢筋圈间隔一定距离处布置一层同样的钢筋圈,钢筋圈包括预埋掏槽管钢筋圈(13)、预埋辅助管钢筋圈(16)、预埋周边管钢筋圈(18),且与锚杆(2)焊接,使两层钢筋圈所在平面平行;2) On the surface of the shotcrete layer, erect the reinforcement ring (13) for the pre-embedded undercut pipe, the reinforcement ring (16) for the pre-embedded auxiliary pipe, and the reinforcement ring (18) for the pre-embedded peripheral pipe, which are fixedly connected to the anchor rod (2). The shapes of each steel ring are the same as the contour lines of the pre-embedded peripheral holes (9), pre-embedded auxiliary holes (7) and pre-embedded undercut holes (6) at the fork or opening respectively, and are erected at certain distances in the direction perpendicular to the center line of the tunnel. Steel arch frame (3), and then arrange a layer of the same reinforcing steel ring at a certain distance from the previous layer of reinforcing steel ring. The reinforcement ring (18) of the peripheral pipe is embedded in advance and welded with the anchor rod (2), so that the planes of the two layers of reinforcement rings are parallel; 3)将预埋周边管(17)、外圈预埋辅助管(14)和预埋掏槽管(11)垂直于钢筋混凝土支护层表面布置,一端往支护层内部延伸,另一端延伸至支护层表面,预埋周边管(17)、预埋辅助管(14)的预埋深度小于支护层厚度,预埋掏槽管(11)的预埋深度为支护层厚度,并用扎丝(12)将预埋周边管(17)、外圈预埋辅助管(14)、预埋掏槽管(11)两端依次分别绑扎在有一定间距的两层钢筋圈上;空预埋管(10)的两端分别用扎丝(12)捆绑并拉紧,扎丝(12)的另一端垂直绑扎于预埋掏槽管钢筋圈(13)的边上,单个内圈预埋辅助管(15)的两端分别绑上扎丝,扎丝另一端与三个已固定的外圈预埋辅助管(14)捆绑,将所有的预埋管用塑料薄膜封住其上下口;3) Arrange the pre-embedded peripheral pipe (17), the outer ring pre-embedded auxiliary pipe (14) and the pre-embedded undercut pipe (11) perpendicular to the surface of the reinforced concrete supporting layer, with one end extending into the supporting layer and the other end extending To the surface of the supporting layer, the pre-embedded depth of the pre-embedded peripheral pipes (17) and the pre-embedded auxiliary pipes (14) is less than the thickness of the supporting layer, and the pre-embedded depth of the pre-embedded cutting pipes (11) is the thickness of the supporting layer, and the The wire ties (12) bind the pre-embedded peripheral pipe (17), the pre-embedded auxiliary pipe (14) in the outer ring, and the pre-embedded undercut pipe (11) on the two-layer reinforcement rings with a certain interval in turn; The two ends of the buried pipe (10) are respectively bundled and tensioned with the wire (12), and the other end of the wire (12) is tied vertically on the edge of the steel ring (13) of the pre-embedded cutting pipe, and a single inner ring is pre-buried Two ends of the auxiliary pipe (15) are respectively tied with tie wires, the other end of the tie wire is bound with the three fixed outer ring pre-embedded auxiliary pipes (14), and all the pre-embedded pipes are sealed with plastic films at their upper and lower openings; 4)再次喷射混凝土完全覆盖钢拱架(3),形成复喷层;4) Spray concrete again to completely cover the steel arch (3) to form a re-spray layer; 5)在复喷层表面施工防水层,沿着边墙、拱部布置钢筋(20),用衬砌台车立模,浇筑混凝土并捣实。5) Construct a waterproof layer on the surface of the compound spray layer, arrange steel bars (20) along the side walls and arches, use a lining trolley to form a vertical form, pour concrete and tamp it. 3.根据权利要求1所述的一种钢筋混凝土支护隧道或巷道开岔或开口预埋孔的布置方式的施工方法,其特征在于,包括以下步骤:3. the construction method of a kind of reinforced concrete supporting tunnel according to claim 1 or the arrangement of roadway fork or opening pre-buried hole, is characterized in that, comprises the following steps: 1)隧道或巷道断面开挖至开岔或开口处后,清除开岔或开口处的浮尘、岩屑后钻孔,在孔中插入中空锚杆(2),且使锚杆伸出长度小于支护层厚度,在尾部加垫片,拧上螺母后注浆,架立钢筋网(4)并与锚杆(2)绑扎,然后喷锚,形成喷锚层;1) After the tunnel or roadway section is excavated to the fork or opening, remove the floating dust and cuttings at the fork or opening, and then drill the hole, insert the hollow bolt (2) into the hole, and make the extension length of the bolt less than For the thickness of the support layer, add a gasket at the tail, screw on the nut and then grouting, erect the steel mesh (4) and bind it with the anchor rod (2), and then spray the anchor to form the spray anchor layer; 2)在喷锚层表面外架设与锚杆(2)固定连接的预埋掏槽管钢筋圈(13)、预埋辅助管钢筋圈(16)、预埋周边管钢筋圈(18),三个钢筋圈的形状分别与开岔或开口处的预埋周边孔(9)、预埋辅助孔(7)、预埋掏槽孔(6)轮廓线相同,垂直隧道中线方向每隔一定距离搭设钢拱架(3),然后与之前布置的预埋掏槽管钢筋圈(13)、预埋辅助管钢筋圈(16)、预埋周边管钢筋圈(18)间隔一定距离处布置三个相同的预埋掏槽管钢筋圈(13)、固定预埋辅助管钢筋圈(16)、预埋周边管钢筋圈(18),并使钢筋圈与锚杆(2)固定连接;2) On the surface of the shotcrete layer, erect the reinforcement ring (13) for the pre-embedded undercut pipe, the reinforcement ring (16) for the pre-embedded auxiliary pipe, and the reinforcement ring (18) for the pre-embedded peripheral pipe, which are fixedly connected to the anchor rod (2). The shapes of each steel ring are the same as the contour lines of the pre-embedded peripheral holes (9), pre-embedded auxiliary holes (7), and pre-embedded undercut holes (6) at the fork or opening, respectively, and are erected at certain distances in the direction perpendicular to the center line of the tunnel. Steel arch frame (3), and then three identical reinforcement rings (13), pre-embedded auxiliary pipe reinforcement rings (16) and pre-embedded peripheral pipe reinforcement rings (18) previously arranged at a certain distance The reinforcement ring (13) of the pre-embedded cutting pipe, the reinforcement ring (16) of the fixed pre-embedded auxiliary pipe, the reinforcement ring (18) of the pre-embedded peripheral pipe, and the reinforcement ring and the anchor rod (2) are fixedly connected; 3)将预埋周边管(17)、外圈预埋辅助管(14)和预埋掏槽管(11)垂直于钢筋混凝土支护层表面布置,一端往支护层内部延伸,另一端延伸至支护层表面,预埋周边管(17)、预埋辅助管(14)的预埋深度小于支护层厚度,预埋掏槽管(11)的预埋深度为支护层厚度,并用扎丝(12)将预埋周边管(17)、外圈预埋辅助管(14)、预埋掏槽管(11)两端依次分别绑扎在有一定间距的钢筋圈上;空预埋管(10)的两端分别用扎丝(12)捆绑并拉紧,扎丝(12)的另一端垂直绑扎于预埋掏槽管钢筋圈(13)的边上,单个内圈预埋辅助管(15)的两端分别绑上扎丝,扎丝另一端与三个已固定的外圈预埋辅助管(14)捆绑,将所有的预埋管用塑料薄膜封住其上下口;3) Arrange the pre-embedded peripheral pipe (17), the outer ring pre-embedded auxiliary pipe (14) and the pre-embedded undercut pipe (11) perpendicular to the surface of the reinforced concrete supporting layer, with one end extending into the supporting layer and the other end extending To the surface of the supporting layer, the pre-embedded depth of the pre-embedded peripheral pipes (17) and the pre-embedded auxiliary pipes (14) is less than the thickness of the supporting layer, and the pre-embedded depth of the pre-embedded cutting pipes (11) is the thickness of the supporting layer, and the The wire tie (12) binds the pre-embedded peripheral pipe (17), the outer ring pre-embedded auxiliary pipe (14), and the pre-embedded undercut pipe (11) on the steel ring with a certain interval in turn; the empty pre-embedded pipe The two ends of (10) are respectively bundled and tightened with the tie wire (12), and the other end of the tie wire (12) is bound vertically on the edge of the reinforcement ring (13) of the pre-embedded undercut pipe, and a single inner ring is pre-embedded with an auxiliary pipe. The two ends of (15) are tied with tie wires respectively, and the other end of the tie wires is bound with the three fixed outer ring pre-embedded auxiliary pipes (14), and all the pre-embedded pipes are sealed with plastic films at their upper and lower openings; 4)在喷锚层表面施工防水层,接着沿边墙、拱部布置钢筋(20),用衬砌台车立模,浇筑混凝土并捣实。4) A waterproof layer is constructed on the surface of the shotcrete layer, and then the steel bars (20) are arranged along the side wall and the arch, and the lining trolley is used to form the vertical form, and the concrete is poured and compacted. 4.根据权利要求2或 3所述的一种钢筋混凝土支护隧道或巷道开岔或开口预埋孔的布置方式的施工方法,其特征在于:步骤1)有另一种施工方法,隧道或巷道断面开挖开岔或开口处后,在开岔或开口处用高压风吹净岩面的浮尘、岩屑,在净岩面进行初喷混凝土,待混凝土厚凝固后用钻孔机械钻孔,插入中空锚杆(2),且使锚杆伸出长度小于支护层厚度,在尾部加垫片,拧上螺母后注浆,架立钢筋网(4)与锚杆(2)焊接或用铁丝绑扎。4. A construction method for the arrangement of reinforced concrete supporting tunnels or roadways fork or opening pre-buried holes according to claim 2 or 3, characterized in that: step 1) there is another construction method, tunnel or After excavating the fork or opening of the roadway section, blow the dust and debris on the rock surface with high-pressure air at the fork or opening, and spray concrete on the clean rock surface. After the concrete is thick and solidified, use a drilling machine to drill holes , insert the hollow anchor rod (2), and make the extension length of the anchor rod less than the thickness of the supporting layer, add a gasket at the tail, screw on the nut and then grouting, and erect the steel mesh (4) and the anchor rod (2) by welding or Tie with wire.
CN201910394706.3A 2019-05-13 2019-05-13 Arrangement and construction method of pre-buried holes in reinforced concrete supporting layers at tunnel or roadway forks or openings Active CN110067581B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910394706.3A CN110067581B (en) 2019-05-13 2019-05-13 Arrangement and construction method of pre-buried holes in reinforced concrete supporting layers at tunnel or roadway forks or openings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910394706.3A CN110067581B (en) 2019-05-13 2019-05-13 Arrangement and construction method of pre-buried holes in reinforced concrete supporting layers at tunnel or roadway forks or openings

Publications (2)

Publication Number Publication Date
CN110067581A true CN110067581A (en) 2019-07-30
CN110067581B CN110067581B (en) 2020-10-02

Family

ID=67370648

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910394706.3A Active CN110067581B (en) 2019-05-13 2019-05-13 Arrangement and construction method of pre-buried holes in reinforced concrete supporting layers at tunnel or roadway forks or openings

Country Status (1)

Country Link
CN (1) CN110067581B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111255464A (en) * 2020-03-03 2020-06-09 中国五冶集团有限公司 Shallow-buried underground excavation construction method for power tunnel in pebble stratum
CN114382510A (en) * 2021-12-10 2022-04-22 中交一公局集团有限公司 Tunnel support for combined drilling and blasting + TBM construction and its support method
CN116201574A (en) * 2023-05-06 2023-06-02 中国矿业大学(北京) Rock burst active prevention and control system

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196537A (en) * 2014-08-26 2014-12-10 广东省建筑工程机械施工有限公司 Construction method of three parallel metro tunnels with ultra-small clear distance
CN104457460A (en) * 2014-11-13 2015-03-25 山东科技大学 Roadway large empty hole parallel cut rapid blasting method
CN105587119A (en) * 2016-01-29 2016-05-18 武汉爆破有限公司 Cast-in-place concrete pre-buried hole forming device and cast-in-place concrete pre-buried shot hole forming method thereof
CN105973082A (en) * 2016-06-03 2016-09-28 武汉科技大学 Hole distribution method for blasting demolition of reinforced concrete support beam in foundation pit
CN106759526A (en) * 2016-12-16 2017-05-31 武汉科技大学 Purlin protection preprocess method is enclosed before a kind of Brace in Deep Footing Groove beam demolition blasting
CN207111118U (en) * 2017-08-15 2018-03-16 中国水利水电第五工程局有限公司 Pre-buried drilled grout hole is guide locating device provided on a kind of needle beam trolley
CN107843160A (en) * 2017-12-01 2018-03-27 武汉科技大学 A kind of initiation net of deep foundation pit reinforced concrete support beam demolition blasting
KR20180058439A (en) * 2016-11-24 2018-06-01 김효성 Excavation method for rock blasting having no-vibration
JP2018193678A (en) * 2017-05-12 2018-12-06 株式会社増岡組 Tunnel drilling method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196537A (en) * 2014-08-26 2014-12-10 广东省建筑工程机械施工有限公司 Construction method of three parallel metro tunnels with ultra-small clear distance
CN104457460A (en) * 2014-11-13 2015-03-25 山东科技大学 Roadway large empty hole parallel cut rapid blasting method
CN105587119A (en) * 2016-01-29 2016-05-18 武汉爆破有限公司 Cast-in-place concrete pre-buried hole forming device and cast-in-place concrete pre-buried shot hole forming method thereof
CN105973082A (en) * 2016-06-03 2016-09-28 武汉科技大学 Hole distribution method for blasting demolition of reinforced concrete support beam in foundation pit
KR20180058439A (en) * 2016-11-24 2018-06-01 김효성 Excavation method for rock blasting having no-vibration
CN106759526A (en) * 2016-12-16 2017-05-31 武汉科技大学 Purlin protection preprocess method is enclosed before a kind of Brace in Deep Footing Groove beam demolition blasting
JP2018193678A (en) * 2017-05-12 2018-12-06 株式会社増岡組 Tunnel drilling method
CN207111118U (en) * 2017-08-15 2018-03-16 中国水利水电第五工程局有限公司 Pre-buried drilled grout hole is guide locating device provided on a kind of needle beam trolley
CN107843160A (en) * 2017-12-01 2018-03-27 武汉科技大学 A kind of initiation net of deep foundation pit reinforced concrete support beam demolition blasting

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
叶建军等: "《基坑钢筋混凝土临时支撑梁绿色拆除爆破技术》", 《爆破》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111255464A (en) * 2020-03-03 2020-06-09 中国五冶集团有限公司 Shallow-buried underground excavation construction method for power tunnel in pebble stratum
CN111255464B (en) * 2020-03-03 2022-02-18 中国五冶集团有限公司 Shallow-buried underground excavation construction method for power tunnel in pebble stratum
CN114382510A (en) * 2021-12-10 2022-04-22 中交一公局集团有限公司 Tunnel support for combined drilling and blasting + TBM construction and its support method
CN116201574A (en) * 2023-05-06 2023-06-02 中国矿业大学(北京) Rock burst active prevention and control system
US12037904B1 (en) 2023-05-06 2024-07-16 China University Of Mining And Technology—Beijing Rock burst active prevention and control mechanism

Also Published As

Publication number Publication date
CN110067581B (en) 2020-10-02

Similar Documents

Publication Publication Date Title
US7530765B2 (en) Structure of intermediate wall of three arch excavated tunnel and method for constructing the same
JP4803429B2 (en) Construction method of underground cavity
JP4958035B2 (en) Shield roof construction method
CN107091101B (en) Superimposed joint structure of middle mine shield junction tunnel in sea area and construction method
CN110067581B (en) Arrangement and construction method of pre-buried holes in reinforced concrete supporting layers at tunnel or roadway forks or openings
CN105822313A (en) Method and device for removing obstacle foreign matter in shield section based on transverse channel
KR102136951B1 (en) Construction Method of Duplex Tunnel
CN114991810B (en) Composite supporting structure and construction method of wall rear mould bag grouting and high-strength support
KR101427812B1 (en) Open cut method for constructing an underground structure
CN109184752B (en) Supporting structure for coal mine to penetrate through old kiln goaf and supporting method thereof
CN210380191U (en) Lightweight power communication combination prefabricated cable channel
CN108590710A (en) Prefabricated tunnel and construction method in a kind of underground goaf to be filled
CN113062750A (en) A construction method of tunnel structure that penetrates underground structure uplift piles
JP5806576B2 (en) Pipe roof and pipe roof construction method
KR100217845B1 (en) Construction process of underground structure
JP5012149B2 (en) Ground support structure and ground support method
CN115949091A (en) A pile foundation structure and method suitable for pile foundation underpinning of stacked tunnels
CN109268032B (en) Tunnel crossing structure of large karst funnel and construction method
JP6019690B2 (en) Tunnel widening method
KR100941438B1 (en) Upper girder part waterproof method for 2 arch tunnel
JP6092359B1 (en) Large section lining body and large section tunnel construction method
JP6019689B2 (en) Tunnel widening method
KR200311976Y1 (en) Structure about center wall of three arch tunnel excavation method and steel sheeting
CN114382510B (en) Tunnel support and support method for combined drilling and blasting + TBM construction
CN214787406U (en) I-steel self-filling roadside support facility

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant