CN110067581A - The arrangement and construction method of trouble or opening armored concrete branch sheath embedded hole are opened in tunnel or tunnel - Google Patents

The arrangement and construction method of trouble or opening armored concrete branch sheath embedded hole are opened in tunnel or tunnel Download PDF

Info

Publication number
CN110067581A
CN110067581A CN201910394706.3A CN201910394706A CN110067581A CN 110067581 A CN110067581 A CN 110067581A CN 201910394706 A CN201910394706 A CN 201910394706A CN 110067581 A CN110067581 A CN 110067581A
Authority
CN
China
Prior art keywords
buried
tunnel
opening
trouble
steel ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910394706.3A
Other languages
Chinese (zh)
Other versions
CN110067581B (en
Inventor
叶建军
尹仲
程大春
杜晓莉
庄心善
陈智
刘一鸣
陈飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei University of Technology
Original Assignee
Hubei University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei University of Technology filed Critical Hubei University of Technology
Priority to CN201910394706.3A priority Critical patent/CN110067581B/en
Publication of CN110067581A publication Critical patent/CN110067581A/en
Application granted granted Critical
Publication of CN110067581B publication Critical patent/CN110067581B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting

Abstract

Trouble or opening armored concrete branch sheath embedded hole arrangement and construction method are opened in a kind of tunnel or tunnel, it is disclosed when the branch sheath construction of trouble or opening is opened in tunnel or tunnel, process by increasing the fixed several plastic tubes of steel ring, realizes that arrangement is used for the built-in pipe of demolition blasting blasthole.It is broken or the occasions such as cannot expose that the present invention is suitable for tunnel or roadway surrounding rock, avoids bore operation, shortens the duration, reduce construction cost, brings good economic and social benefit.

Description

The arrangement side of trouble or opening armored concrete branch sheath embedded hole is opened in tunnel or tunnel Formula and construction method
Technical field
The present invention relates to blasting engineering fields, and in particular to opens trouble or opening armored concrete to a kind of tunnel or tunnel Branch sheath embedded hole arrangement and construction method.
Background technique
In underground engineering construction, the tunnel or tunnel of some intersections can be designed, in building for convenience with another Tunnel or roadway linking can need open trouble or opening to take not supporting, wait another tunnel in the tunnel or tunnel built Or supporting together is built in tunnel.But the country rock in tunnel or roadway excavation is excessively broken sometimes or cannot be exposed to for a long time In air, support work must be just carried out immediately, and not so tunnel or tunnel may locally occur side and collapse.So will be with another tunnel Road or roadway linking will carry out open trouble or opening operation on the good tunnel of supporting or tunnel side wall.Usual blasting technique is The efficient means of trouble or opening are opened in tunnel or tunnel, and common way is in engineering: in jag or being opened to the good tunnel of supporting Bore operation is carried out at mouthful, arranges multiple blastholes along supporting layer surface normal direction, and explosive is loaded onto inside blasthole and carries out explosion Open trouble or opening.There are many drawbacks for this way:
1, due to there is the presence of steel mesh, steel arch-shelf, dowel, anchor pole in tunnel or roadway support layer, it is difficult to drill, and More blasthole is needed in perforation explosion, so that drilling cost is often very high.
2, since hole count is more, the angle control of requirement and blasthole of the artificial drilling to blasthole position is less accurate, from And influence demolition effect.
3, hole count is more, and artificial drilling is very time-consuming, extends the duration, it is also possible to influence the stability of tunnel structure.
4, a large amount of dust that drilling generates causes pollution to environment.
In order to solve the problem above-mentioned, trouble is opened in tunnel or tunnel after just considering at the beginning of design or opening reinforcing bar is mixed Solidifying soil branch sheath embedded hole arrangement and construction method, the pre-buried pipeline of normal direction along tunnel or roadway support layer surface are realized Trouble is opened for later tunnel or tunnel or opening explosion provides the purpose of blasthole.
Summary of the invention
The problem to be solved by the invention is to provide a kind of tunnels or tunnel to open trouble or opening armored concrete branch sheath Embedded hole arrangement and construction method, the present invention just consider the problem of opening trouble or opening, design at the beginning of tunnel or roadway support The fixation of pre-buried pipeline when arrangement, the supporting construction of trouble and opening embedded hole is opened out, and trouble is opened in pre-buried pipeline formation or opening is quick-fried The blasthole for breaking digging achievees the purpose that trouble or opening are opened in efficient, inexpensive, green explosion.
The object of the present invention is achieved like this: a kind of tunnel or trouble is opened in tunnel or opening armored concrete branch sheath is pre- It is identical by the contour line production of designed each circle blasthole when buried via hole arrangement and construction method, tunnel or roadway support are constructed The steel ring of shape after squeezing into anchor pole process in tunnel wall, two rows of parallel rebar circles is welded and fixed with anchor pole, built-in pipe In corresponding position and steel ring binding and fixing, the work of tunnel support below is then completed, pre-buried blasthole is formed.
The built-in pipe uses PVC plastic pipe.
The construction method of the arrangement of trouble or opening armored concrete branch sheath embedded hole is opened in a kind of tunnel or tunnel, The following steps are included:
1) it after tunnel or drift section are excavated to out trouble or opening, drills after removing the floating dust for opening trouble or opening, landwaste, It is inserted into hollow bolt in hole, and anchor pole extension elongation is made to be less than branch covering thickness, is added gasket in tail portion, screws on nut grouting behind shaft or drift lining, Cableway net is simultaneously bound with anchor pole, is then sprayed anchor, is formed spray anchor layer;
2) spray anchor layer surface outside set up be fixedly connected with anchor pole pre-buried slotting pipe steel ring, pre-buried auxiliary tube steel ring, in advance Bury peripheral tubes steel ring, the shape of three steel rings respectively with open the pre-buried periphery hole of trouble or opening, pre-buried via hole, pre-buried Keyhole contour line is identical, and steel arch-shelf is set up in Vertical tunnel middle line direction at a certain distance, then between preceding layer steel ring At a certain distance place arrangement one layer of same steel ring, steel ring include pre-buried slotting pipe steel ring, pre-buried auxiliary tube steel ring, Pre-buried peripheral tubes steel ring, and welded with anchor pole, keep plane where two layers of steel ring parallel;
3) pre-buried peripheral tubes, the pre-buried auxiliary tube in outer ring and pre-buried slotting pipe are arranged perpendicular to armored concrete supporting layer surface, Toward branch sheath internal stretch, the other end extends to supporting layer surface for one end, and pre-buried peripheral tubes, the pre-buried depth of pre-buried auxiliary tube are small In branch covering thickness, the pre-buried depth of pre-buried slotting pipe is branch covering thickness, and with tied silk that pre-buried peripheral tubes, outer ring is pre-buried auxiliary Pipe, pre-buried slotting pipe both ends is helped successively to bind respectively on two layers of steel ring at regular intervals;Distinguish at the both ends of empty built-in pipe It is bundled and is tensed with tied silk, the other end of tied silk is vertically bound on the side of pre-buried slotting pipe steel ring, and single inner ring is pre-buried auxiliary The both ends of pipe are helped to bind tied silk respectively, the pre-buried auxiliary tube of the tied silk other end and three outer rings fixed bundlees, will be all pre- Pipe laying seals its upper and lower opening with plastic film;
4) steel arch-shelf is completely covered in gunite concrete again, forms multiple spray-up;
5) in multiple spray-up surface construction waterproof layer, reinforcing bar is arranged along abutment wall, arch, with lining trolley formwork erection, casting concrete And it consolidates.
Above-mentioned steps 1) there is another construction method, tunnel or drift section to open trouble or opening after, open trouble or Opening blows off the floating dust of scar, landwaste with high-pressure blast, carries out just pneumatically placed concrete in net scar, is bored after solidification with drilling machine Hollow bolt is inserted into hole, and anchor pole extension elongation is made to be less than branch covering thickness, is added gasket in tail portion, is screwed on nut grouting behind shaft or drift lining, frame Vertical steel mesh is welded with anchor pole or is bound with iron wire.
Another construction method of step 5) is in multiple spray-up surface construction waterproof layer, with lining trolley along abutment wall, arch Portion's formwork erection, casting concrete simultaneously consolidate.
It is to excavate inverted arch, and arrange reinforcing bar and formwork erection casting concrete, final set at place that step 5), which has another construction method, Afterwards, in multiple spray-up surface construction waterproof layer, reinforcing bar is arranged then along abutment wall, vault, with lining trolley formwork erection, casting concrete And it consolidates.
The construction method of the arrangement of trouble or the embedded hole that is open is opened in a kind of armored concrete supporting tunnel or tunnel, including Following steps:
2) be parallel to spray anchor layer surface arrange one layer of steel ring comprising pre-buried slotting pipe steel ring, pre-buried auxiliary tube steel ring, Pre-buried peripheral tubes steel ring, and with anchor pole weld, shape respectively with the pre-buried periphery hole for opening trouble or opening, pre-buried auxiliary Hole, pre-buried keyhole contour line are identical, then arrange one layer of same steel ring with preceding layer steel ring place spaced apart, It includes pre-buried slotting pipe steel ring, fixed pre-buried auxiliary tube steel ring, pre-buried peripheral tubes steel ring, and is welded with anchor pole, is made Plane where two layers of steel ring is parallel;
3) pre-buried peripheral tubes, the pre-buried auxiliary tube in outer ring and pre-buried slotting pipe are arranged perpendicular to armored concrete supporting layer surface, Toward branch sheath internal stretch, the other end extends to supporting layer surface for one end, and pre-buried peripheral tubes, the pre-buried depth of pre-buried auxiliary tube are small In branch covering thickness, the pre-buried depth of pre-buried slotting pipe is branch covering thickness, and with tied silk that pre-buried peripheral tubes, outer ring is pre-buried auxiliary Pipe, pre-buried slotting pipe both ends is helped successively to be bound on two layers of steel ring respectively;The both ends of empty built-in pipe are bundled simultaneously with tied silk respectively It tenses, the other end of tied silk is vertically bound on the side of pre-buried slotting pipe steel ring, and the both ends of the single pre-buried auxiliary tube of inner ring are divided Tied silk is not bound, and the pre-buried auxiliary tube of the tied silk other end and three outer rings fixed bundlees, and all pre-buried pipe plastics is thin Film seals its upper and lower opening;
4) in spray anchor layer surface construction waterproof layer, coagulation then is poured with lining trolley formwork erection along abutment wall, arch arrangement reinforcing bar Soil simultaneously consolidates.
Above-mentioned steps 1) there is another construction method, tunnel or drift section to open trouble or opening after, open trouble or Opening blows off the floating dust of scar, landwaste with high-pressure blast, carries out just pneumatically placed concrete in net scar, is bored after solidification with drilling machine Hollow bolt is inserted into hole, and anchor pole extension elongation is made to be less than branch covering thickness, is added gasket in tail portion, is screwed on nut grouting behind shaft or drift lining, frame Vertical steel mesh is welded with anchor pole or is bound with iron wire.
Another construction method of step 4), it is vertical along abutment wall, arch with lining trolley in spray anchor layer surface construction waterproof layer Mould, casting concrete simultaneously consolidate.
The invention has the following advantages: the present invention provides a kind of tunnel or trouble or opening armored concrete are opened in tunnel Branch sheath embedded hole arrangement and construction method, the pre-buried PVC plastic pipe when tunnel or roadway support are constructed are needing to open trouble or are opening It only needs to find PVC plastic pipe when mouthful operation, so that it may carry out bursting work, avoid in tunnel or the drilling of roadway support layer A large amount of manpower, material resources and financial resources have been saved in operation, also avoid the noise pollution generated in drilling construction.
The present invention opens trouble or opening armored concrete branch sheath embedded hole arrangement and construction party in a kind of tunnel or tunnel Method, can be easily in supporting layer arrangement blasthole, and the pre-buried hole site arranged is accurate, avoids the artificial drilling many mistakes of bring Difference accelerates out the speed of trouble or opening to provide the effect of explosion later.
A kind of tunnel or tunnel provided by the invention are opened trouble or opening armored concrete branch sheath embedded hole arrangement and are applied Work method is conducive to steel mesh, steel arch-shelf, concrete and recycles.
The invention avoids the dust for boring idle job and drilling generation, while reducing the influence to environment.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples.
Fig. 1 is tunnel or trouble or opening embedded hole schematic diagram are opened in tunnel.
Fig. 2 is the tunnel or tunnel embedded hole sectional schematic diagram that lining cutting layer is armored concrete.(B-B in Fig. 4)
Fig. 3 is the tunnel or tunnel embedded hole sectional schematic diagram that lining cutting layer is plain concrete.(B-B in Fig. 4)
Fig. 4 is tunnel or tunnel embedded hole diagrammatic cross-section, i.e. Fig. 2, the A-A direction view in 3.
Fig. 5 is no steel arch-shelf and lining cutting layer is the tunnel or tunnel embedded hole sectional schematic diagram of armored concrete.
Fig. 6 is no steel arch-shelf and lining cutting layer is the tunnel or tunnel embedded hole sectional schematic diagram of plain concrete.
Fig. 7 is the fixed schematic diagram of pre-buried slotting pipe.
Fig. 8 is the fixed schematic diagram of sky built-in pipe.
Fig. 9 is the fixed schematic diagram of the pre-buried auxiliary tube in outer ring.
Figure 10 is the inner ring individually fixed schematic diagram of pre-buried auxiliary tube.
Figure 11 is pre-buried peripheral tubes auxiliary schematic diagram.
In figure, embedded hole 1, anchor pole 2, steel arch-shelf 3, steel mesh 4, empty embedded hole 5, pre-buried keyhole 6, the pre-buried auxiliary in outer ring Hole 7, the single pre-buried via hole 8 of inner ring, pre-buried periphery hole 9, empty built-in pipe 10, pre-buried slotting pipe 11, tied silk 12, pre-buried slotting Pipe steel ring 13, the pre-buried auxiliary tube 14 in outer ring, the pre-buried auxiliary tube 15 of inner ring, pre-buried auxiliary tube steel ring 16, pre-buried peripheral tubes 17, Pre-buried peripheral tubes steel ring 18 sprays anchor layer surface 19, reinforcing bar 20, multiple spray-up and secondary lining stratum boundary line 21.
Specific embodiment
Specific embodiment, as shown in figs. 1-11, tunnel or trouble is opened in tunnel or opening armored concrete branch sheath is pre-buried Hole arrangement and construction method include tunnel or trouble or opening embedded hole schematic diagram are opened in tunnel, and lining cutting layer is the tunnel of armored concrete Or tunnel embedded hole sectional schematic diagram, lining cutting layer are the tunnel or tunnel embedded hole sectional schematic diagram, tunnel or lane of plain concrete Road embedded hole diagrammatic cross-section, no steel arch-shelf and lining cutting layer are the tunnel or tunnel embedded hole sectional schematic diagram of armored concrete, No steel arch-shelf and lining cutting layer are the tunnel or tunnel embedded hole sectional schematic diagram of plain concrete, and pre-buried slotting pipe fixes schematic diagram, The fixed schematic diagram of empty built-in pipe, the fixed schematic diagram of the pre-buried auxiliary tube in outer ring, individually pre-buried auxiliary tube fixes schematic diagram to inner ring, pre-buried Peripheral tubes assist schematic diagram.
Embodiment 1:
The long 2km of certain Tunnel Design, 6 meters of span, wall is 2 meters high, sagitta 1.5m, and branch covering thickness is 55cm, needs out in tunnel Trouble or opening.
Trouble or opening armored concrete branch sheath embedded hole arrangement and construction method are opened according to above-mentioned tunnel or tunnel, Working procedure of the invention are as follows:
1) after tunnel or drift section open trouble or opening, open trouble or opening with high-pressure blast blow off scar floating dust, Landwaste is drilled with drilling machine, is inserted into hollow bolt 2, and anchor pole extension elongation is made to be less than branch covering thickness 5cm, in tail portion plus Gasket screws on nut grouting behind shaft or drift lining, and cableway net is simultaneously welded with anchor pole or bound with iron wire, and then concrete ejection unit sprays Anchor sprays anchor layer with a thickness of 40mm;
2) from spray anchor layer surface 10cm place set up three with anchor pole weld steel rings, i.e., pre-buried slotting pipe steel ring 13, in advance Bury auxiliary tube steel ring 16 and pre-buried peripheral tubes steel ring 18, the shape of three steel rings respectively with open designed by trouble or opening Pre-buried periphery hole, pre-buried via hole, pre-buried keyhole contour line it is identical, reinforcing bar loop diameter is 8mm, Vertical tunnel middle line direction Steel arch-shelf is set up every 1.5m, and steel arch-shelf side and anchor pole weld, and burn-on longitudinally connected muscle in two adjacent steel arch-shelfs;Then with Preceding layer steel ring place spaced apart arranges one layer of same steel ring, steel ring include pre-buried slotting pipe steel ring 13, Pre-buried auxiliary tube steel ring 16, pre-buried peripheral tubes steel ring 18, and welded with anchor pole 2, keep plane where two layers of steel ring parallel;
3) built-in pipe uses PVC plastic pipe, by pre-buried peripheral tubes, pre-buried auxiliary tube, pre-buried slotting pipe along armored concrete supporting The normal direction of layer surface arranges that one end extends to supporting layer surface toward branch sheath internal stretch, the other end.Pre-buried peripheral tubes, The pre-buried depth of pre-buried auxiliary tube is 45cm, diameter 50mm, length 55cm, the pre- buried depth of pre-buried slotting pipe and empty built-in pipe Degree is 50cm, and length 60mm, pre-buried slotting pipe diameter is 50mm, and empty pre-buried pipe diameter is 63mm, and with tied silk by pre-buried week Bian Guan, pre-buried auxiliary tube, pre-buried slotting pipe both ends are successively bound respectively on two layers of steel ring at regular intervals.Empty built-in pipe Both ends distinguish tied silk and bundle and tense, the other end of tied silk is bound respectively on the side of triangle steel rib ring, and inner ring is individually pre- Tied silk is bound at the both ends for burying auxiliary tube respectively, and the tied silk other end and three have fixed pre-buried auxiliary tube binding, by pre-buried effective modeling Material bag seals its upper and lower opening;
4) multiple pneumatically placed concrete covers steel arch-shelf, and multiple spray is with a thickness of 26cm;
5) reinforcing bar formwork erection casting concrete is arranged at inverted arch, after final set, in multiple spray-up surface construction waterproof layer, then along side Wall, vault arrange reinforcing bar, and with lining trolley formwork erection, casting concrete is simultaneously consolidated, with a thickness of 25cm.
Embodiment 2:
The long 3km of certain Tunnel Design, 6.5 meters of span, wall is 1.9 meters high, sagitta 1.6m, and branch covering thickness is 50cm, needs in tunnel Open trouble or opening.
Trouble or opening armored concrete branch sheath embedded hole arrangement and construction method are opened according to above-mentioned tunnel or tunnel, Working procedure of the invention are as follows:
1) after tunnel or drift section open trouble or opening, open trouble or opening with high-pressure blast blow off scar floating dust, Landwaste, first thickness of shotcrete are 50mm, are drilled after solidification with drilling machine, are inserted into hollow bolt, and make anchor pole extension elongation It less than branch covering thickness 10cm, is added gasket in tail portion, screws on nut grouting behind shaft or drift lining, cableway net and anchor pole weld or use iron wire Binding;
2) steel ring of three with anchor pole welding, the shape difference of three steel rings are set up at the reinforcing bar wire side 8cm from institute's frame It is identical as pre-buried periphery hole, pre-buried via hole designed by trouble or opening, pre-buried keyhole contour line is opened, and reinforcing bar loop diameter For 6mm, steel arch-shelf is set up every 1m in Vertical tunnel middle line direction, and steel arch-shelf side and anchor pole weld, and in two adjacent steel arch-shelfs It burn-ons longitudinally connected muscle, then arranges one layer of same steel ring, steel ring packet with first row steel ring place spaced apart Pre-buried slotting pipe steel ring 13, pre-buried auxiliary tube steel ring 16, pre-buried peripheral tubes steel ring 18 are included, and is welded with anchor pole 2, makes two Plane where layer steel ring is parallel;
3) built-in pipe uses PVC plastic pipe, by pre-buried peripheral tubes, pre-buried auxiliary tube, pre-buried slotting pipe along armored concrete supporting The normal direction of layer surface arranges that one end extends to supporting layer surface toward branch sheath internal stretch, the other end.Pre-buried peripheral tubes, The pre-buried depth of pre-buried auxiliary tube is 40cm, diameter 50mm, length 45cm, the pre- buried depth of pre-buried slotting pipe and empty built-in pipe Degree is 45cm, and length 50mm, pre-buried slotting pipe diameter is 50mm, and empty pre-buried pipe diameter is 63mm, and with tied silk by pre-buried week Bian Guan, pre-buried auxiliary tube, pre-buried slotting pipe both ends are successively bound on steel ring at regular intervals respectively.The two of empty built-in pipe Tied silk is bundled and is tensed respectively at end, and the other end of tied silk is bound respectively on the side of triangle steel rib ring, and inner ring is single pre-buried auxiliary The both ends of pipe are helped to bind tied silk respectively, the tied silk other end and three have fixed pre-buried auxiliary tube binding, by pre-buried effective polybag Seal its upper and lower opening;
4) multiple pneumatically placed concrete covers steel arch-shelf, and multiple spray is with a thickness of 25cm;
5) it in multiple spray-up surface construction waterproof layer, is poured mixed then along abutment wall, vault arrangement reinforcing bar with lining trolley formwork erection Solidifying soil simultaneously consolidates, with a thickness of 20cm.
Embodiment 3
The long 2.5km of certain Tunnel Design, 5.5 meters of span, wall is 2.1 meters high, sagitta 1.5m, and branch covering thickness is 60cm, in tunnel Need out trouble or opening.
1) after tunnel or drift section open trouble or opening, the floating of scar is blown off with high-pressure blast opening trouble or opening Dirt, landwaste, are drilled with drilling machine, are inserted into hollow bolt 2, and anchor pole extension elongation is made to be less than branch covering thickness 12cm, in tail Portion's shimming, screws on nut grouting behind shaft or drift lining, and cableway net 4 is fixedly connected with anchor pole 2, binds using welding or with iron wire, Then concrete ejection unit sprays anchor, sprays anchor layer with a thickness of 40mm;
2) steel ring of three with anchor pole welding, i.e., pre-buried slotting pipe steel ring are set up at the reinforcing bar wire side 15cm from institute's frame 13, pre-buried auxiliary tube steel ring 16, pre-buried peripheral tubes steel ring 18, the shape of three steel rings respectively with open trouble or opening place Pre-buried periphery hole, pre-buried via hole, the pre-buried keyhole contour line of design are identical, and reinforcing bar loop diameter is 6mm, then with first Placing of reinforcement circle is spaced apart and welds from three same steel rings of arrangement at supporting layer surface 10cm and with anchor pole;
3) built-in pipe uses PVC plastic pipe, by pre-buried peripheral tubes, pre-buried auxiliary tube, pre-buried slotting pipe along armored concrete supporting The normal direction of layer surface arranges that one end extends to supporting layer surface toward branch sheath internal stretch, the other end.Pre-buried peripheral tubes, The pre-buried depth of pre-buried auxiliary tube is 52cm, diameter 50mm, length 57cm, the pre- buried depth of pre-buried slotting pipe and empty built-in pipe Degree is 56cm, and length 61mm, pre-buried slotting pipe diameter is 50mm, and empty pre-buried pipe diameter is 63mm, and with tied silk by pre-buried week Bian Guan, pre-buried auxiliary tube, pre-buried slotting pipe both ends are successively bound on steel ring at regular intervals respectively.The two of empty built-in pipe Tied silk is bundled and is tensed respectively at end, and the other end of tied silk is bound respectively on the side of pre-buried slotting pipe steel ring 13, and inner ring is single Tied silk is bound at the both ends of pre-buried auxiliary tube respectively, and the tied silk other end and three have fixed pre-buried auxiliary tube binding, will be pre-buried effective Polybag seals its upper and lower opening;
4) in spray anchor layer surface construction waterproof layer, with lining trolley along abutment wall and arch formwork erection, casting concrete is simultaneously consolidated.Thick bottom For 56cm.
In the present invention, pre-buried slotting pipe steel ring 13 is triangle, pre-buried auxiliary tube steel ring 16, pre-buried peripheral tubes reinforcing bar Circle 18 is identical as tunnel cross sectional shape, and top is arc, and lower part is rectangle.

Claims (4)

1. the arrangement that trouble or opening armored concrete branch sheath embedded hole are opened in a kind of tunnel or tunnel, it is characterised in that: Including embedded hole (1), the embedded hole (1) includes that pre-buried periphery hole (9), the single pre-buried via hole (8) of inner ring, outer ring are pre-buried auxiliary Help hole (7), pre-buried keyhole (6) and empty embedded hole (5);Empty embedded hole (5) is located at pre-buried keyhole (6) area defined It is interior;The length direction of embedded hole (1) is vertical with armored concrete supporting layer surface, and one end is toward branch sheath internal stretch, the other end Extend to supporting layer surface;Pre-buried periphery hole (9) is distributed in tunnel or tunnel and opens on trouble or opening contour line, pre-buried periphery hole (9), single pre-buried via hole (8) depth of inner ring is less than branch covering thickness;Pre-buried keyhole (6) and empty embedded hole (5) depth with Branch covering thickness is identical, and empty embedded hole (5) diameter is greater than or equal to other apertures.
2. the cloth that trouble or opening armored concrete branch sheath embedded hole are opened in a kind of tunnel according to claim 1 or tunnel Set the construction method of mode, which comprises the following steps:
1) it after tunnel or drift section are excavated to out trouble or opening, drills after removing the floating dust for opening trouble or opening, landwaste, Hollow bolt (2) are inserted into hole, and anchor pole extension elongation is made to be less than branch covering thickness, is added gasket in tail portion, is infused after screwing on nut Slurry, cableway net (4) simultaneously bind with anchor pole (2), then spray anchor, form spray anchor layer;
2) the pre-buried slotting pipe steel ring (13) being fixedly connected with anchor pole (2), pre-buried auxiliary tube steel are set up outside spray anchor layer surface Rib ring (16), pre-buried peripheral tubes steel ring (18), the shape of three steel rings respectively with the pre-buried periphery hole of opening trouble or opening (9), pre-buried via hole (7), pre-buried keyhole (6) contour line are identical, and steel is set up in Vertical tunnel middle line direction at a certain distance Arch (3) then arranges one layer of same steel ring with preceding layer steel ring place spaced apart, and steel ring includes pre-buried draws Barrel steel ring (13), pre-buried auxiliary tube steel ring (16), pre-buried peripheral tubes steel ring (18), and welded with anchor pole (2), make two Plane where layer steel ring is parallel;
3) by pre-buried peripheral tubes (17), the pre-buried auxiliary tube in outer ring (14) and pre-buried slotting pipe (11) perpendicular to armored concrete supporting Layer surface arrangement, toward branch sheath internal stretch, the other end extends to supporting layer surface for one end, pre-buried peripheral tubes (17), pre-buried auxiliary The pre-buried depth of pipe (14) is helped to be less than branch covering thickness, the pre-buried depth of pre-buried slotting pipe (11) is branch covering thickness, and with bundle Silk (12) by pre-buried peripheral tubes (17), the pre-buried auxiliary tube in outer ring (14), pre-buried slotting pipe (11) both ends are successively bound respectively is having On two layers of steel ring of one fixed spacing;The both ends of empty built-in pipe (10) are used tied silk (12) to bundle respectively and are tensed, tied silk (12) The other end is vertically bound on the side of pre-buried slotting pipe steel ring (13), and the both ends of the single pre-buried auxiliary tube of inner ring (15) are tied up respectively Upper tied silk, the tied silk other end and three pre-buried auxiliary tubes in the outer ring fixed (14) bundle, and all pre-buried pipe plastics is thin Film seals its upper and lower opening;
4) gunite concrete is completely covered steel arch-shelf (3) again, forms multiple spray-up;
5) it in multiple spray-up surface construction waterproof layer, is poured mixed along abutment wall, arch arrangement reinforcing bar (20) with lining trolley formwork erection Solidifying soil simultaneously consolidates.
3. the arrangement side that trouble or the embedded hole that is open are opened in a kind of armored concrete supporting tunnel according to claim 1 or tunnel The construction method of formula, which comprises the following steps:
1) it after tunnel or drift section are excavated to out trouble or opening, drills after removing the floating dust for opening trouble or opening, landwaste, Hollow bolt (2) are inserted into hole, and anchor pole extension elongation is made to be less than branch covering thickness, is added gasket in tail portion, is infused after screwing on nut Slurry, cableway net (4) simultaneously bind with anchor pole (2), then spray anchor, form spray anchor layer;
2) the pre-buried slotting pipe steel ring (13) being fixedly connected with anchor pole (2), pre-buried auxiliary tube steel are set up outside spray anchor layer surface Rib ring (16), pre-buried peripheral tubes steel ring (18), the shape of three steel rings respectively with the pre-buried periphery hole of opening trouble or opening (9), pre-buried via hole (7), pre-buried keyhole (6) contour line are identical, and steel is set up in Vertical tunnel middle line direction at a certain distance Arch (3), then with arrange before pre-buried slotting pipe steel ring (13), pre-buried auxiliary tube steel ring (16), pre-buried peripheral tubes Steel ring (18) place spaced apart arranges three identical pre-buried slotting pipe steel rings (13), fixed pre-buried auxiliary tube reinforcing bar (16), pre-buried peripheral tubes steel ring (18) are enclosed, and are fixedly connected with steel ring with anchor pole (2);
3) by pre-buried peripheral tubes (17), the pre-buried auxiliary tube in outer ring (14) and pre-buried slotting pipe (11) perpendicular to armored concrete supporting Layer surface arrangement, toward branch sheath internal stretch, the other end extends to supporting layer surface for one end, pre-buried peripheral tubes (17), pre-buried auxiliary The pre-buried depth of pipe (14) is helped to be less than branch covering thickness, the pre-buried depth of pre-buried slotting pipe (11) is branch covering thickness, and with bundle Silk (12) by pre-buried peripheral tubes (17), the pre-buried auxiliary tube in outer ring (14), pre-buried slotting pipe (11) both ends are successively bound respectively is having On the steel ring of one fixed spacing;The both ends of empty built-in pipe (10) use respectively tied silk (12) bundle and tense, tied silk (12) it is another For the vertical binding in end on the side of pre-buried slotting pipe steel ring (13), bundle is bound at the both ends of the single pre-buried auxiliary tube of inner ring (15) respectively Silk, the tied silk other end and three pre-buried auxiliary tubes in the outer ring fixed (14) bundle, and all pre-buried effective plastic films are sealed Firmly its upper and lower opening;
4) it in spray anchor layer surface construction waterproof layer, is then poured along abutment wall, arch arrangement reinforcing bar (20) with lining trolley formwork erection Concrete simultaneously consolidates.
4. the cloth that trouble or the embedded hole that is open are opened in a kind of armored concrete supporting tunnel according to claim 2 or 3 or tunnel Set the construction method of mode, it is characterised in that: step 1) has another construction method, and tunnel or drift section are opened trouble or opened After at mouthful, in floating dust, the landwaste for opening trouble or opening with high-pressure blast and blowing off scar, just pneumatically placed concrete is carried out in net scar, to mixed It is drilled, is inserted into hollow bolt (2), and anchor pole extension elongation is made to be less than branch covering thickness with drilling machine after the solidifying thick solidification of soil, Tail portion shimming, screws on nut grouting behind shaft or drift lining, and cableway net (4) is welded with anchor pole (2) or bound with iron wire.
CN201910394706.3A 2019-05-13 2019-05-13 Arrangement mode and construction method of reinforced concrete support layer pre-buried holes at turnout or opening of tunnel or roadway Active CN110067581B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910394706.3A CN110067581B (en) 2019-05-13 2019-05-13 Arrangement mode and construction method of reinforced concrete support layer pre-buried holes at turnout or opening of tunnel or roadway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910394706.3A CN110067581B (en) 2019-05-13 2019-05-13 Arrangement mode and construction method of reinforced concrete support layer pre-buried holes at turnout or opening of tunnel or roadway

Publications (2)

Publication Number Publication Date
CN110067581A true CN110067581A (en) 2019-07-30
CN110067581B CN110067581B (en) 2020-10-02

Family

ID=67370648

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910394706.3A Active CN110067581B (en) 2019-05-13 2019-05-13 Arrangement mode and construction method of reinforced concrete support layer pre-buried holes at turnout or opening of tunnel or roadway

Country Status (1)

Country Link
CN (1) CN110067581B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111255464A (en) * 2020-03-03 2020-06-09 中国五冶集团有限公司 Shallow-buried underground excavation construction method for power tunnel in pebble stratum
CN116201574A (en) * 2023-05-06 2023-06-02 中国矿业大学(北京) Rock burst active prevention and control system

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196537A (en) * 2014-08-26 2014-12-10 广东省建筑工程机械施工有限公司 Construction method of three parallel metro tunnels with ultra-small clear distance
CN104457460A (en) * 2014-11-13 2015-03-25 山东科技大学 Roadway large empty hole parallel cut rapid blasting method
CN105587119A (en) * 2016-01-29 2016-05-18 武汉爆破有限公司 Cast-in-place concrete pre-buried hole forming device and cast-in-place concrete pre-buried shot hole forming method thereof
CN105973082A (en) * 2016-06-03 2016-09-28 武汉科技大学 Hole distribution method for blasting demolition of reinforced concrete support beam in foundation pit
CN106759526A (en) * 2016-12-16 2017-05-31 武汉科技大学 Purlin protection preprocess method is enclosed before a kind of Brace in Deep Footing Groove beam demolition blasting
CN207111118U (en) * 2017-08-15 2018-03-16 中国水利水电第五工程局有限公司 Pre-buried drilled grout hole is guide locating device provided on a kind of needle beam trolley
CN107843160A (en) * 2017-12-01 2018-03-27 武汉科技大学 A kind of initiation net of deep foundation pit reinforced concrete support beam demolition blasting
KR20180058439A (en) * 2016-11-24 2018-06-01 김효성 Excavation method for rock blasting having no-vibration
JP2018193678A (en) * 2017-05-12 2018-12-06 株式会社増岡組 Tunnel drilling method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196537A (en) * 2014-08-26 2014-12-10 广东省建筑工程机械施工有限公司 Construction method of three parallel metro tunnels with ultra-small clear distance
CN104457460A (en) * 2014-11-13 2015-03-25 山东科技大学 Roadway large empty hole parallel cut rapid blasting method
CN105587119A (en) * 2016-01-29 2016-05-18 武汉爆破有限公司 Cast-in-place concrete pre-buried hole forming device and cast-in-place concrete pre-buried shot hole forming method thereof
CN105973082A (en) * 2016-06-03 2016-09-28 武汉科技大学 Hole distribution method for blasting demolition of reinforced concrete support beam in foundation pit
KR20180058439A (en) * 2016-11-24 2018-06-01 김효성 Excavation method for rock blasting having no-vibration
CN106759526A (en) * 2016-12-16 2017-05-31 武汉科技大学 Purlin protection preprocess method is enclosed before a kind of Brace in Deep Footing Groove beam demolition blasting
JP2018193678A (en) * 2017-05-12 2018-12-06 株式会社増岡組 Tunnel drilling method
CN207111118U (en) * 2017-08-15 2018-03-16 中国水利水电第五工程局有限公司 Pre-buried drilled grout hole is guide locating device provided on a kind of needle beam trolley
CN107843160A (en) * 2017-12-01 2018-03-27 武汉科技大学 A kind of initiation net of deep foundation pit reinforced concrete support beam demolition blasting

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
叶建军等: "《基坑钢筋混凝土临时支撑梁绿色拆除爆破技术》", 《爆破》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111255464A (en) * 2020-03-03 2020-06-09 中国五冶集团有限公司 Shallow-buried underground excavation construction method for power tunnel in pebble stratum
CN111255464B (en) * 2020-03-03 2022-02-18 中国五冶集团有限公司 Shallow-buried underground excavation construction method for power tunnel in pebble stratum
CN116201574A (en) * 2023-05-06 2023-06-02 中国矿业大学(北京) Rock burst active prevention and control system

Also Published As

Publication number Publication date
CN110067581B (en) 2020-10-02

Similar Documents

Publication Publication Date Title
JP7125550B2 (en) SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH
JP4958035B2 (en) Shield roof construction method
CN109723443B (en) Tunnel construction method
CN106703814A (en) Mined metro station hole pile construction method
CN104196537A (en) Construction method of three parallel metro tunnels with ultra-small clear distance
JP3824114B2 (en) Whale bone method for large section tunnel
CN104763435B (en) Construction method of shallow-buried excavation type large cross section of tunnel in tail slag filling area
JP2007217911A (en) Construction method of underground cavity and tunnel construction method
KR101244257B1 (en) Method for digging tunnel
CN107905814B (en) Large span loess tunnel top bar CD construction method
CN109026026A (en) Under wear existing piping lane the multi-thread more arcading bored tunnel groups of big cross section construction method
CN110486036B (en) Construction method for expanding arch foot primary support arch cover method
CN106884665B (en) A kind of Double Multi-Arch start tunneling method based on arch set arch
CN111997639B (en) Method for getting rid of trouble and reinforcing and improving geology of TBM construction tunnel bad geology section card machine
WO2000032906A1 (en) Sardine-bone construction method for large-section tunnel
CN104831733A (en) Arch bridge abutment tunnel type large-angle inclined pile construction method
CN110439590A (en) Method for tunnel construction
CN110067581A (en) The arrangement and construction method of trouble or opening armored concrete branch sheath embedded hole are opened in tunnel or tunnel
CN110700860B (en) Construction method of soil-stone boundary tunnel crossing loess valley
CN110985003B (en) Tunnel construction method for penetrating through earth-rock boundary stratum
JPH0765455B2 (en) Construction method for branch / joint of shield tunnel and temporary bulkhead construction device for branch / joint
CN107514266A (en) Shield export & import bolt anchorage soil body construction method
CN104863183A (en) Isolation damping pile structure used for construction of large cross-section tunnel closed-spaced building and construction method of isolation damping pile structure
CN107165641A (en) High inclination-angle ladder way opposite direction excavating construction method in thin layer breaking up hard rock stratum
KR20050020451A (en) Shield tunneling construction method and tunnel structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant