CN110067569A - Three arm rock drilling jumbo pipe shed construction methods - Google Patents

Three arm rock drilling jumbo pipe shed construction methods Download PDF

Info

Publication number
CN110067569A
CN110067569A CN201910243400.8A CN201910243400A CN110067569A CN 110067569 A CN110067569 A CN 110067569A CN 201910243400 A CN201910243400 A CN 201910243400A CN 110067569 A CN110067569 A CN 110067569A
Authority
CN
China
Prior art keywords
massif
hole
metal tube
drilling rod
knife
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910243400.8A
Other languages
Chinese (zh)
Other versions
CN110067569B (en
Inventor
廖建军
舒敏标
方晓成
叶德峰
傅建红
胡宇翔
曾嵘
肖珊珊
陈辉辉
吴江锋
陈品明
牛海波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Jiaogong Hongtu Transportation Construction Co Ltd
Original Assignee
Zhejiang Jiaogong Hongtu Transportation Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Jiaogong Hongtu Transportation Construction Co Ltd filed Critical Zhejiang Jiaogong Hongtu Transportation Construction Co Ltd
Priority to CN201910243400.8A priority Critical patent/CN110067569B/en
Publication of CN110067569A publication Critical patent/CN110067569A/en
Application granted granted Critical
Publication of CN110067569B publication Critical patent/CN110067569B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines
    • E21D9/1006Making by using boring or cutting machines with rotary cutting tools

Abstract

The present invention relates to a kind of three arm rock drilling jumbo pipe shed construction methods, the first step links together indicator light with power supply, separates knife;Second step drives drilling rod rotation by three arm rock drilling jumbos, and drilling rod driving drill bit goes band moving knife to rotate by axis of drilling rod, and knife forms hole on massif, and it is remaining that the part that massif enters in drill bit and drilling rod forms massif;Third step drives metal tube to be inserted into the hole and unclamps the pressing to normally opened push switch when drill bit enters and squeezes normally open push button switch to flanging in massif and cause indicator light bright, makes the hole perforation massif from multiple second step and third step;4th step removes massif remnants, makes drilling rod retreat to exit drill bit and drilling rod out of metal tube after collapsing knife, metal tube stays in hole the wall for constituting hole.The three arm rock drilling jumbo pipe shed construction methods punched are driven by three arm rock drilling jumbos the present invention provides a kind of, to punch for massif.

Description

Three arm rock drilling jumbo pipe shed construction methods
Technical field
The present invention relates to technical field of tunnel construction, more particularly to a kind of three arm rock drilling jumbo pipe shed construction methods.
Background technique
Tunnel specific gravity will be increasing in highway, railway and Construction for Hydroelectric Project;It is existing in tunnel excavation construction Some constructions have shallow hole drilling pipe roof construction and the construction of three arm rock drilling jumbos.There are environmental pollutions for shallow hole drilling pipe roof construction greatly, pore-forming The problems such as of poor quality, easy collapse hole, it is not able to satisfy environmental protection, low power consuming, the requirement of economy and high safety quality.Three arm drilling stagings The construction technology of vehicle is low in the pollution of the environment, and safety coefficient is higher, at low cost, little energy is consumed, than traditional tunnel shallow bore hole drilling pipe canopy Construction has significant advantage.Conventional drill jumbo, which excavates, uses electrical actuation power, does not generate dust, changes to air regime Less, cleanliness without any pollution, only a certain amount of noise can greatly reduce injury of the noise to human body, and pore-forming efficiency is high, matter Measure, pore-forming is once completed, meet quality requirement higher and higher now.
Summary of the invention
The three arm rock drilling jumbo pipe roof construction sides punched are driven by three arm rock drilling jumbos the present invention provides a kind of Method, to be punched for massif.
The above technical problem is solved through the following technical scheme: a kind of three arm rock drilling jumbo pipe shed construction methods, It is characterized in that, drives perforating mechanism to form hole, the perforating mechanism in massif according to the following steps by three arm rock drilling jumbos Including annular bit, the same drill bit tail end that is set in the metal tube of annular brick tail end and is threaded through in metal tube links together Pipe structure drilling rod, the tail end of the annular bit is equipped with flanging, and the front end of the metal tube is equipped with and can abut to In-flanges on flanging, the inner end of the in-flanges is equipped with to be connected by the indicator light series connection that conducting wire is located on metal tube rear end The normally opened push switch being connected together, the annular bit front end face are equipped with several can collapse together and before passing through drill bushing The knife in hole is formed when the use at end on massif;The first step links together indicator light with power supply, separates knife;Second step, Drilling rod rotation is driven by three arm rock drilling jumbos, drilling rod driving drill bit goes band moving knife to rotate by axis of drilling rod, knife shape on massif Pore-forming, it is remaining that the part that massif enters in drill bit and drilling rod forms massif;Third step is squeezed when drill bit enters in massif to flanging Driving metal tube is inserted into the hole and unclamps the pressing to normally opened push switch when pressure normally open push button switch causes indicator light bright, Make the hole perforation massif from multiple second step and third step;4th step removes massif remnants, after making drilling rod after gathering knife It moves back to exit drill bit and drilling rod out of metal tube, metal tube stays in hole the wall for constituting hole.The present invention can pass through change Drill bit gets the hole of response magnitude, and the hole wall that insertion metal tube constitutes hole can be synchronized after beating, and prevents from caving in hole and to brill Bar is protected, and can easily know whether need to promote metal tube in drill process.Metal tube does not pass through drill bit or drilling rod Driving, the drilling rod that the damage to drill bit drilling rod can be prevented and make same power drive bigger.
Preferably, inner tube is also equipped in the metal tube, shape type chamber between said inner tube, in-flanges and metal tube, The type chamber is open at one end far from drill bit, and said inner tube is equipped with the water seepage hole of several perforation type chambers, and the 4th step is divided into following Step: 4-1, that the mixture of sand cement through the opening of type chamber is filled into type is intracavitary;4-2, collapse knife after make drilling rod retreat from And drill bit and drilling rod are exited out of metal tube;4-3, by metal tube it is closed at both ends live and inner tube and massif remnants between shape At water storage cavity;4-4, to pouring water in water storage cavity, the water in water storage cavity is through the intracavitary water for making type intracavitary of the water seepage hole infitration type The sub- mixture of silt forms the concrete shield being covered on metal tube inner peripheral surface;4-5, massif remnants are removed.It being capable of shape At protective layer, the metal tube still aging corrosion damage for constituting hole wall is prevented.Inner tube, that is, structure forming cavity template can be regarded again The decorative surface layer of fireprotection layer is used.
Preferably, the conducting wire is located in the concrete shield, the normally opened push switch is located at the type chamber Outside, the guiding includes zero curve and firewire, is electrically connected with several fiery branch lines worn in inner tube on the firewire, described Several zero branch lines worn in inner tube are electrically connected on zero curve.Synchronous progress cloth concealed wire in hole can be synchronously completed, so that hole Subsequent installation lamp it is electrical when to connect electricity convenient.Form back a fiery branch line and a zero branch line with electrical connection Road, normally opened push switch can be used at this time as all electrical master switch are controlled.
Preferably, said inner tube links together with in-flanges, inner tube is driven to be inserted into institute by metal tube in third step It states in hole.Inner tube can be penetrated in hole when inner tube intensity is weaker.
Preferably, the hole is all stretched out at the both ends of said inner tube, pours and be supported on metal tube at the both ends of metal tube And prevent the massif at hole both ends from caving in the wall that massif is fixed together.It can prevent massif from caving at the both ends in hole, and And convenience when constructing wall.
Preferably, the front end face of the base tube is equipped with several notches circumferentially distributed along base tube, the knife is hinged on In the notch, the bottom wall of the notch, which is equipped with, enables knife to be maintained knife by towards when rotation far from base tube axis direction In the positioning region of separated position.Make knife towards the rotation i.e. inner rotation of base tube at the axis place of base tube when closing up knife.
Preferably, the diameter in hole of the drill bit formed in massif is bigger than the overall diameter of metal tube.Work progress Middle insertion metal tube is convenient and strength-saving.
Preferably, the diameter of the massif remnants in hole of the drill bit formed in massif is smaller than the interior diameter of drilling rod. It can reduce massif remnants drilling rod is carried out to pierce the inhibition generated when operation.
The present invention has an advantage that can synchronize the inner wall to form hole prevents from caving in hole to improve the drive degree in hole.
Detailed description of the invention
Fig. 1 is the schematic diagram when present invention just starts punching.
Fig. 2 is the schematic diagram of the perforating mechanism in the present invention.
Fig. 3 is that drill bit is fed to schematic diagram when flanging is expressed to normally opened push switch.
Fig. 4 is schematic diagram when massif just drills through.
Fig. 5 is schematic diagram of the drill bit drilling rod after taking out in hole.
In figure: annular bit 1, metal tube 2, drilling rod 3, flanging 4, in-flanges 5, inner tube 6, type chamber 7, opening 8, water seepage hole 9, indicator light 10, normally opened push switch 11, zero curve 12, firewire 13, fiery branch line 14, zero branch line 15, notch 16, hinged shaft 17, knife 18, Positioning region 19, hole 20, massif remnants 21, massif 22, concrete shield 23.
Specific embodiment
The present invention will be further described below with reference to the accompanying drawings and embodiments.
Embodiment one, referring to Fig. 1 and Fig. 2, a kind of three arm rock drilling jumbo pipe shed construction methods are driven by three arm rock drilling jumbos Dynamic perforating mechanism forms hole in massif according to the following steps, and perforating mechanism includes annular bit 1, is set in annular brick tail end Metal tube 2 and the drilling rod 3 of pipe structure that links together of the same drill bit tail end that is threaded through in metal tube.The tail of annular bit End is equipped with flanging 4.The front end of metal tube is equipped with the in-flanges 5 that can be abutted on flanging.In being also equipped in metal tube Pipe 6.Shape type chamber 7 between inner tube, in-flanges and metal tube.Type chamber all opens wide far from drill bit one end and forms opening 8.Inner tube is the same as interior Flange links together.Inner tube is equipped with the water seepage hole 9 of several through chambers.The inner end of in-flanges is equipped with and is located on by conducting wire The normally opened push switch 11 that the indicator light 10 of metal tube rear end is connected in series.Guiding includes zero curve 12 and firewire 13.Zero Line 12 and firewire 13 are all from the intracavitary extraction metal tube rear end of type.Normally opened push switch is located at the outside of type chamber.It is electrically connected on firewire There are several fiery branch lines 14 worn in inner tube.Several zero branch lines 15 worn in inner tube are electrically connected on zero curve.Base tube Front end face is equipped with several notches 16 circumferentially distributed along base tube.A bar shaped is hinged with by hinged shaft 17 in each notch Knife 18.The bottom wall of notch, which is equipped with, enables knife by towards knife maintained separated position when rotation far from base tube axis direction The positioning region 19 of (i.e. state in Fig. 2), knife is able to carry out aperture at this time.Detailed process is as follows for aperture;
The first step links together indicator light with power supply, and indicator light and normally opened push switch are to be connected on power supply, makes knife It separates.
Referring to Fig. 3, second step drives drilling rod rotation and holding to live metal tube by three arm rock drilling jumbos, and drilling rod driving is bored Head goes band moving knife to rotate by axis of drilling rod, and knife forms hole 20 on massif 22, and massif enters drill bit and formed with the part in drilling rod Massif remnants 21;Third step, the driving when drill bit enters causes indicator light bright in massif to flanging extruding normally open push button switch Metal tube inserts in the hole and unclamps the pressing to normally opened push switch, and metal inner pipe driving inner tube, which synchronizes, to insert in the hole.
Referring to fig. 4, hole 20 is made to penetrate through massif 22 from multiple second step and third step.Hole is all stretched out at the both ends of metal tube.
Referring to Fig. 5, the 4th step removes massif remnants, collapse retreat drilling rod after knife to by drill bit and drilling rod from gold Belong to and being exited in pipe, metal tube stays in hole the wall for constituting hole.4th step is divided into following steps: 4-1, by the mixture of sand cement It is intracavitary that opening through type chamber is filled into type;4-2, drilling rod is made to retreat to move back drill bit and drilling rod out of metal tube after collapsing knife Out;4-3, the closed at both ends of metal tube is formed into water storage cavity firmly and between inner tube and massif remnants;4-4, it is filled in water storage cavity Water, the water in water storage cavity are covered on metal through the intracavitary cement sand mixture formation for making type intracavitary of the water seepage hole infitration type Concrete shield 23 on pipe inner peripheral surface, zero curve 12 and firewire 13 are located in the concrete shield;It is 4-5, massif is residual Remaining removal.5th step pours at the both ends of metal tube and is supported on metal tube and prevents hole with the wall that massif is fixed together The massif at both ends caves in.

Claims (8)

1. a kind of three arm rock drilling jumbo pipe shed construction methods, which is characterized in that drive perforating mechanism to press by three arm rock drilling jumbos Hole is formed in massif according to following steps, the perforating mechanism includes annular bit, the metal tube for being set in annular brick tail end The drilling rod of the pipe structure to link together with the same drill bit tail end being threaded through in metal tube, the tail end of the annular bit are equipped with Flanging, the front end of the metal tube are equipped with the in-flanges that can be abutted on flanging, and the inner end of the in-flanges is equipped with The normally opened push switch being connected in series by the indicator light that conducting wire is located on metal tube rear end, the annular bit front end Face be equipped with it is several can collapse together and pass through drill bushing front end use when on massif formed hole knife;The first step, general Indicator light links together with power supply, separates knife;Second step drives drilling rod rotation, drilling rod driving by three arm rock drilling jumbos Drill bit goes band moving knife to rotate by axis of drilling rod, and knife forms hole on massif, and the part that massif enters in drill bit and drilling rod forms mountain Body is remaining;Third step causes to drive metal when indicator light is bright when drill bit enters in massif to flanging extruding normally open push button switch Pipe is inserted into the hole and unclamps the pressing to normally opened push switch, makes hole perforation mountain from multiple second step and third step Body;4th step removes massif remnants, makes drilling rod retreat to exit drill bit and drilling rod out of metal tube after collapsing knife, gold Belong to pipe and stays in hole the wall for constituting hole.
2. three arm rock drilling jumbos pipe shed construction method according to claim 1, which is characterized in that also worn in the metal tube Equipped with inner tube, shape type chamber between said inner tube, in-flanges and metal tube, the type chamber is open at one end far from drill bit, said inner tube Water seepage holes equipped with several perforations type chambers, the 4th step are divided into following steps: 4-1, by the mixture of sand cement through type chamber Opening to be filled into type intracavitary;4-2, drilling rod is made to retreat to exit drill bit and drilling rod out of metal tube after collapsing knife;4-3, Closed at both ends by metal tube forms water storage cavity firmly and between inner tube and massif remnants;4-4, to pouring water in water storage cavity, water storage Intracavitary water is covered on metal tube inner circumferential through the intracavitary cement sand mixture formation for making type intracavitary of the water seepage hole infitration type Concrete shield on face;4-5, massif remnants are removed.
3. three arm rock drilling jumbos pipe shed construction method according to claim 2, which is characterized in that the conducting wire is located at described In concrete shield, the normally opened push switch is located at the outside of the type chamber, and the guiding includes zero curve and firewire, described It is electrically connected with several fiery branch lines worn in inner tube on firewire, is electrically connected with several zero worn in inner tube on the zero curve Branch line.
4. three arm rock drilling jumbos pipe shed construction method according to claim 2, which is characterized in that the same in-flanges of said inner tube It links together, drives inner tube to be inserted into the hole by metal tube in third step.
5. three arm rock drilling jumbos pipe shed construction method according to claim 1, which is characterized in that make the two of the metal tube The hole is all stretched out at end, is poured at the both ends of metal tube and is supported on metal tube and prevents hole with the wall that massif is fixed together The massif at both ends caves in.
6. three arm rock drilling jumbos pipe shed construction method according to claim 1, which is characterized in that the front end face of the base tube Several notches circumferentially distributed along base tube are equipped with, the knife is hinged in the notch, and the bottom wall of the notch, which is equipped with, to be made Knife by towards can be maintained the positioning region of separated position when rotation far from base tube axis direction by knife.
7. three arm rock drilling jumbos pipe shed construction method according to claim 1, which is characterized in that the drill bit is in massif The diameter for being formed by hole is bigger than the overall diameter of metal tube.
8. three arm rock drilling jumbos pipe shed construction method according to claim 1, which is characterized in that the drill bit is in massif The diameter for being formed by the massif remnants in hole is smaller than the interior diameter of drilling rod.
CN201910243400.8A 2019-03-28 2019-03-28 Construction method of pipe shed of three-arm drill jumbo Active CN110067569B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910243400.8A CN110067569B (en) 2019-03-28 2019-03-28 Construction method of pipe shed of three-arm drill jumbo

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910243400.8A CN110067569B (en) 2019-03-28 2019-03-28 Construction method of pipe shed of three-arm drill jumbo

Publications (2)

Publication Number Publication Date
CN110067569A true CN110067569A (en) 2019-07-30
CN110067569B CN110067569B (en) 2020-09-15

Family

ID=67366922

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910243400.8A Active CN110067569B (en) 2019-03-28 2019-03-28 Construction method of pipe shed of three-arm drill jumbo

Country Status (1)

Country Link
CN (1) CN110067569B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101691842A (en) * 2009-07-15 2010-04-07 中铁隧道股份有限公司 Three-arm hydraulic wagon drill and tunnel drilling and grouting construction method
CN102174894A (en) * 2011-03-15 2011-09-07 中铁十二局集团第一工程有限公司 Follow-up pipe shed construction method
CN204436417U (en) * 2015-01-06 2015-07-01 辽宁省东水西调工程建设局 A kind of pipe canopy propulsion plant
CN107269303A (en) * 2017-07-10 2017-10-20 中铁十局集团第四工程有限公司 A kind of three arm rock drilling jumbo sets the fixing device and its application method of lock foot anchoring stock
CN107524407A (en) * 2017-08-21 2017-12-29 中国铁建重工集团有限公司 A kind of drill jumbo that dress function is pushed away with pipe canopy
CN108425688A (en) * 2018-05-28 2018-08-21 交通运输部公路科学研究所 A kind of groutable Shed-pipe Advanced Support propulsion device and its application method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101691842A (en) * 2009-07-15 2010-04-07 中铁隧道股份有限公司 Three-arm hydraulic wagon drill and tunnel drilling and grouting construction method
CN102174894A (en) * 2011-03-15 2011-09-07 中铁十二局集团第一工程有限公司 Follow-up pipe shed construction method
CN204436417U (en) * 2015-01-06 2015-07-01 辽宁省东水西调工程建设局 A kind of pipe canopy propulsion plant
CN107269303A (en) * 2017-07-10 2017-10-20 中铁十局集团第四工程有限公司 A kind of three arm rock drilling jumbo sets the fixing device and its application method of lock foot anchoring stock
CN107524407A (en) * 2017-08-21 2017-12-29 中国铁建重工集团有限公司 A kind of drill jumbo that dress function is pushed away with pipe canopy
CN108425688A (en) * 2018-05-28 2018-08-21 交通运输部公路科学研究所 A kind of groutable Shed-pipe Advanced Support propulsion device and its application method

Also Published As

Publication number Publication date
CN110067569B (en) 2020-09-15

Similar Documents

Publication Publication Date Title
US7004264B2 (en) Bore lining and drilling
CN108757000A (en) A kind of quick slot orientation fracturing system in underground based on drilling machine power and method
CN111255381A (en) Comprehensive permeability increasing device for coal bed mechanical reaming and hydraulic slotting
CN110306934A (en) The construction method and supporting drilling tool of double branch's top plate major diameter high position directional long boreholes
CN204877376U (en) Bridging plug for fracturing
CN110067569A (en) Three arm rock drilling jumbo pipe shed construction methods
CN109458148A (en) Three-layer pipe impacts core bit
CN215595491U (en) One-time pore-forming while-drilling casing device for soft coal seam
CN202673167U (en) Three-arris drill pipe special for coal mine underground gas drainage
CN109057712B (en) Anchor cable pore-forming two-stage sleeve construction method
CN104975859B (en) Collapse Accidents rescue skills and the horizontal excavator of dual pipe for relief
CN109236190A (en) Double-vane waterpower, which expands, rushes integration drills technique
CN113530448A (en) One-time pore-forming while-drilling casing device for soft coal seam
CN109667557A (en) A kind of standard coring device and construction method for fractured coal and rock sample
CN210217679U (en) Small well bore sleeve milling, making and buckling, fishing and well repairing tool
CN201439694U (en) Taking and changing sleeve cutting salvage device
CN210888945U (en) Punching mechanism
CN207879293U (en) Rotation make-up changes top of fish fishing integrated tool
CN211058732U (en) Anchor rod taking drill rod
CN209430144U (en) Three-layer pipe impacts core bit
CN111140177A (en) Reaming and casing pipe laying integrated complete drilling tool
CN110080681A (en) Lateral blind hole drilling method
CN211058722U (en) Remote control hole expanding drilling tool system
CN218265818U (en) Synchronous follow-up connecting structure of drill bit and sleeve in follow-up pipe drilling construction
CN207453975U (en) A kind of drilling pipe for the core that can break online

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant