CN110055853A - A kind of honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge and mounting arrangements method - Google Patents

A kind of honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge and mounting arrangements method Download PDF

Info

Publication number
CN110055853A
CN110055853A CN201810051177.2A CN201810051177A CN110055853A CN 110055853 A CN110055853 A CN 110055853A CN 201810051177 A CN201810051177 A CN 201810051177A CN 110055853 A CN110055853 A CN 110055853A
Authority
CN
China
Prior art keywords
heat pipe
bridge
inorganic medium
medium heat
snow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810051177.2A
Other languages
Chinese (zh)
Inventor
宋杰
毕玉峰
徐润
王甲勇
柳尚
丁婷婷
马霞
李琳
姚晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Provincial Communications Planning and Design Institute Co Ltd
Original Assignee
Shandong Provincial Communications Planning and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Provincial Communications Planning and Design Institute Co Ltd filed Critical Shandong Provincial Communications Planning and Design Institute Co Ltd
Priority to CN201810051177.2A priority Critical patent/CN110055853A/en
Publication of CN110055853A publication Critical patent/CN110055853A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/24Methods or arrangements for preventing slipperiness or protecting against influences of the weather
    • E01C11/26Permanently installed heating or blowing devices ; Mounting thereof
    • E01C11/265Embedded electrical heating elements ; Mounting thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Road Paving Structures (AREA)
  • Cleaning Of Streets, Tracks, Or Beaches (AREA)

Abstract

The invention discloses a kind of honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge and mounting arrangements methods, including bridge bed course and bridge pier, it is characterized in that, inorganic medium heat pipe heat radiation section is set on the bridge bed course, inorganic medium heat pipe insulation section is set in the bridge pier, the inorganic medium heat pipe insulation section is connected with the inorganic medium heat pipe heat-absorbing section of insert into stratum thermostat layer, and the inorganic medium heat pipe is arranged on Bracket for steel bar, and spring is equipped between the inorganic heat tube and Bracket for steel bar.Working principle and efficient heat transfer efficiency of the present invention using inorganic medium heat pipe, ground temperature, which is adequately utilized, can save the energy, improve efficiency of energy utilization;By the arrangement of reasonable heat pipe heat-absorbing section, the snow melt effect of heat pipe is optimized, ground temperature, which is adequately utilized, there can be environmental protection.

Description

A kind of honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge and mounting arrangements method
Technical field
The present invention relates to a kind of honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge and mounting arrangements methods, belong to mechanical system It makes and field of civil engineering.
Background technique
Long Span Bridge in highway is easy a large amount of accumulated snow in northern winter Snowfall, and the accumulated snow of bridge floor section is An important factor for leading to traffic accidents, especially prolonged rain and snow weather, bridge floor accumulated snow can not use machine substantially Tool formula snow removing means and chemicals snow melt, automobile sharply decline in road traveling coefficient of friction, vehicle navigability and brake Effect is deteriorated, and eventually leads to vehicle driving and skids on the way out of control, leads to major traffic accidents.Meanwhile using deicing salt snow melt pair Serious corrosion failure is brought on road surface, while deicing salt melts Yu Shuizhong, generates greatly harm to the ecological environment on periphery, and Mechanical snow removing then generates great execution to bridge deck structure.Long range bridge is as the special road in highway system Section is the multiple section of traffic accident, and it is the effective ways for guaranteeing that traffic trip is unobstructed that effective safe snow melt is carried out to it.
Summary of the invention
The present invention in order to solve the problems, such as it is above-mentioned exist in the prior art, a kind of honest formula bridge floor inorganic medium heat pipe of bridge is provided and is melted Snow system and mounting arrangements method cause the technical issues of greatly damaging to solve prior art snow removing meeting road pavement.
The technical solution adopted by the present invention to solve the technical problems is:
The present invention provides a kind of honest formula bridge floor inorganic medium heat pipe snow-melting systems of bridge, including bridge bed course and bridge pier, special Sign is, inorganic medium heat pipe heat radiation section is arranged on the bridge bed course, inorganic medium heat pipe insulation section, institute is arranged in the bridge pier It states inorganic medium heat pipe insulation section to be connected with the inorganic medium heat pipe heat-absorbing section of insert into stratum thermostat layer, the inorganic medium heat pipe It is arranged on Bracket for steel bar, spring is equipped between the inorganic heat tube and Bracket for steel bar.
In this way, being mentioned by using the deicing or snow melting that the honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge of the invention is bridge floor Implementation method is supplied;Working principle and efficient heat transfer efficiency using inorganic medium heat pipe, ground temperature, which is adequately utilized, to be saved The about energy, improves efficiency of energy utilization;By the arrangement of reasonable heat pipe heat-absorbing section, the snow melt effect of heat pipe is optimized, Ground temperature energy is adequately utilized;The heat pipe of design installs radiating segment layout drawing, according to the relationship of bridge pier and the influence area of heat pipe, It is arranged using relative type motor, the heat that heat pipe absorbs effectively is transmitted in bridge floor and realizes the molten snow of bridge floor.
In addition, the honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge according to an embodiment of the present invention can also have it is following attached Add technical characteristic:
Preferably, the inorganic medium heat pipe heat-absorbing section of the thermostat layer located underground, the stepped distribution of lowest depth.
Preferably, it is equipped in the bridge pier and pays steel pipe in advance, it is earnestly interior that the inorganic medium heat pipe insulation section is evenly arranged in bridge Portion is paid in advance in steel pipe, and paying in advance for inorganic medium heat pipe insulation section backfills heat-insulating material in steel pipe.
Preferably, the inorganic medium heat pipe heat radiation section of the bridge floor layer is at radial distribution.
Preferably, the two adjacent bridge piers that are set as of the inorganic medium heat pipe heat radiation section are combined into arrangement unit, inorganic Jie Matter heat pipe heat radiation section is radial arrangement, and two bridge piers are interregional to be arranged for cross-like, and bridge floor region covers comprehensively between two bridges are honest.
Preferably, the heat pipe heat-absorbing section position for being set as bridge pier peripheral disposition of the inorganic medium endotherm section is deeper than bridge pier The heat pipe heat-absorbing section of inside arrangement.
The application method of the honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge of the present invention the following steps are included:
(1) the heat dissipation effective area for passing through inorganic medium heat pipe, calculates the work area of effective snow melt of heat pipe, determines two Spacing in heat exhausting pipe.
(2) the prefabricated steel pipe in bridge pier places heat pipe vertical section, and backfills the fixed heat pipe of heat-insulating material.
(3) horizontal segment of heat pipe is placed on Bracket for steel bar, places the damage that fractures.
(4) bed course, bridge floor layer are backfilled, and guarantees the stabilization of heat pipe horizontal segment.
(5) installation is completed, and determines that function is intact, and pavement temperature is kept to realize bridge floor snow melt.
Detailed description of the invention
Above-mentioned and/or additional aspect of the invention and advantage will become from the description of the embodiment in conjunction with the following figures Obviously and it is readily appreciated that, in which:
Fig. 1 is the cross section knot that the bridge floor of the honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge of the embodiment of the present invention uses Structure
Schematic diagram;
Fig. 2 is heat pipe part at the bridge pier of the honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge of the embodiment of the present invention
Structural schematic diagram;
Fig. 3 is the knot of the honest formula bridge floor inorganic medium heat pipe snow-melting system bridge floor heat-pipe apparatus arrangement of bridge of the embodiment of the present invention Structure schematic diagram.
Description of symbols:
In Fig. 1-Fig. 3, underground constant zone of subsurface temperature 1;Troposphere 2;Bridge pier 3;Bridge bed course 4;Inorganic medium heat pipe heat radiation section 5;Nothing Machine medium heat pipe insulation section 6;Inorganic medium heat pipe heat-absorbing section 7;Bridge floor layer 8.
Specific embodiment
The embodiment of the present invention is described below in detail, examples of the embodiments are shown in the accompanying drawings, wherein from beginning to end Same or similar label indicates same or similar element or element with the same or similar functions.Below with reference to The embodiment of attached drawing description is exemplary, and for explaining only the invention, and is not considered as limiting the invention.It ties below Attached drawing is closed to further illustrate.
As shown in Figure 1-Figure 3, bridge pier type bridge floor inorganic medium heat pipe snow-melting system of the invention, including bridge bed course 4 and bridge Pier 3, which is characterized in that inorganic medium heat pipe heat radiation section 5 is set on the bridge bed course 4, setting inorganic medium heat in the bridge pier 3 Pipe adiabatic section 6, the inorganic medium heat pipe insulation section 6 are connected with the inorganic medium heat pipe heat-absorbing section 7 of insert into stratum thermostat layer 1, The inorganic medium heat pipe is arranged on Bracket for steel bar, and spring is equipped between the inorganic heat tube and Bracket for steel bar.
Specifically, it is serious for current long range bridge floor accumulated snow phenomenon, serious bridge floor and bridge are easily caused using deicing salt The problem of structure erosion.A kind of bridge pier type bridge floor inorganic medium heat pipe snow-melting system, including bridge pier 3, bridge bed course 4, inorganic medium Heat pipe, bridge floor layer 8.Inorganic medium heat pipe includes inorganic medium heat pipe heat-absorbing section 7, inorganic medium heat pipe heat radiation section 5, inorganic medium Heat pipe insulation section 6 fills inorganic heat-conducting medium in inorganic medium heat pipe;The thermostat layer located underground of inorganic medium heat pipe heat-absorbing section 7 1, it is placed in bridge pier 3, is uniformly distributed along bridge pier 3;Inorganic heat tube radiating segment 5 is located at bridge deck concrete layer.Inorganic medium heat pipe The heating conduction of the no temperature difference conducts ground temperature to bridge floor, improves bridge deck temperature, realizes the thawing that bridge floor accumulated snow freezes.
Specifically, a kind of bridge pier type bridge floor inorganic medium heat pipe snow-melting system, including more inorganic medium heat pipes, inorganic Jie Matter heat pipe is evenly arranged inside bridge pier 3, endotherm section is placed in the constant temperature soil layer below of bridge pier 3, insulation end is evenly arranged in bridge In pier 3, radiating segment is arranged in bridge floor supercrust.
Specifically, a kind of bridge pier type bridge floor inorganic medium heat pipe snow-melting system, it is main include transmission ground heating tube system and Heat pipe arranges installation method system two large divisions, realizes and the heat of deep layer constant temperature soil layer is passed through heat by the heat transfer of heat pipe Working media inside pipe is transmitted to bridge floor layer 8, and bridge pavement temperature is made to be increased to zero degree or more.In the actual process, heat pipe without Method is uniformly distributed buried depth as pavement snow melting.In order to which effective opposite heat tube is protected, the arrangement of bridge floor heat pipe snow-melting system It must be by fixed inside bridge pier 3.
Specifically, method for fixing hot pipe is that a diameter is greater than heat pipe diameter to be formed in advance inside bridge pier 3, and corresponding Region carries out the drilling of the embedding position of heat pipe, by the embedding depth with formulation of heat pipe, backfills corresponding coagulation in heat pipe heat-absorbing section Soil guarantees the fixation of heat pipe.Heat pipe heat-insulating material is backfilled in steel pipe, forms the adiabatic section in hot-pipe system.
It specifically, heat pipe heat-absorbing section is embedded in underground constant zone of subsurface temperature, and is that range is arranged into a ladder with bridge pier 3, in bridge pier 3 Middle part, due to the coverage superposition of the mutual endotherm section of the heat pipe by surrounding, the hot arc depth arranged is maximum, is located at Heat pipe around bridge pier 3 require arrangement according to general, and arranged at staggeredly depth dimensions.
Specifically, heat pipe heat radiation section is embedded in bridge floor surface layer, heat pipe is arranged centered on bridge pier 3 at diversity, quantity with Reaching effectively dissolution bridge floor ice and snow is standard, and two connected bridge piers 3 are arrangement unit, two-phase crossover pier to radiating segment arrangement form 3 intermediate region heat pipe arrange by alternant.
A kind of bridge pier type bridge floor inorganic medium heat pipe snow-melting system that the embodiment of the present invention provides has below beneficial to effect Fruit:
Specifically, a kind of bridge pier type bridge floor inorganic medium heat pipe snow-melting system that the embodiment of the present invention provides is bridge floor Deicing or snow melting provides implementation method;Working principle and efficient heat transfer efficiency using inorganic medium heat pipe adequately utilize Ground temperature can save the energy, improve efficiency of energy utilization;By the arrangement of reasonable heat pipe heat-absorbing section, heat pipe is optimized Ground temperature energy is adequately utilized in snow melt effect;The heat pipe of design installs radiating segment layout drawing, according to the relationship and heat pipe of bridge pier 3 Influence area, arranged using relative type motor, by heat pipe absorb heat be effectively transmitted in bridge floor realize the molten snow of bridge floor.
The application method of the present embodiment bridge pier type bridge floor inorganic medium heat pipe snow-melting system is as follows:
(1) the heat dissipation effective area for passing through inorganic medium heat pipe, calculates the work area of effective snow melt of heat pipe, determines two Spacing in heat exhausting pipe.
(2) the prefabricated steel pipe in bridge pier 3 places heat pipe vertical section, and backfills the fixed heat pipe of heat-insulating material.
(3) horizontal segment of heat pipe is placed on Bracket for steel bar, places the damage that fractures.
(4) bed course, bridge floor layer 8 are backfilled, and guarantees the stabilization of heat pipe horizontal segment.
(5) installation is completed, and determines that function is intact, and pavement temperature is kept to realize bridge floor snow melt.
Although an embodiment of the present invention has been shown and described, it will be understood by those skilled in the art that: not A variety of change, modification, replacement and modification can be carried out to these embodiments in the case where being detached from the principle of the present invention and objective, this The range of invention is defined by the claims and their equivalents.

Claims (7)

1. a kind of honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge, including bridge bed course and bridge pier, which is characterized in that the bridge pad Inorganic medium heat pipe heat radiation section is set on layer, inorganic medium heat pipe insulation section, the inorganic medium heat pipe are set in the bridge pier Adiabatic section is connected with the inorganic medium heat pipe heat-absorbing section of insert into stratum thermostat layer, and the inorganic medium heat pipe is arranged in Bracket for steel bar On, spring is equipped between the inorganic heat tube and Bracket for steel bar.
2. the honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge according to claim 1, which is characterized in that described to be located at ground The inorganic medium heat pipe heat-absorbing section of lower thermostat layer, the stepped distribution of lowest depth.
3. the honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge according to claim 1, which is characterized in that in the bridge pier Equipped with steel pipe is paid in advance, the inorganic medium heat pipe insulation section is evenly arranged in the honest inside of bridge and pays in advance in steel pipe, inorganic medium heat pipe Paying in advance for adiabatic section backfills heat-insulating material in steel pipe.
4. the honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge according to claim 1, which is characterized in that the bridge floor layer Inorganic medium heat pipe heat radiation section at radial distribution.
5. the honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge according to claim 1, which is characterized in that inorganic Jie The two adjacent bridge piers that are set as of matter heat pipe heat radiation section are combined into arrangement unit, and inorganic medium heat pipe heat radiation section is radial arrangement, Two bridge piers are interregional to be arranged for cross-like, and bridge floor region covers comprehensively between two bridges are honest.
6. the honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge according to claim 1, which is characterized in that inorganic Jie The heat pipe heat-absorbing section position for being set as bridge pier peripheral disposition of matter endotherm section is deeper than the heat pipe heat-absorbing section arranged inside bridge pier.
7. the application method of the honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge described in claim 1, which is characterized in that including Following steps:
(1) the heat dissipation effective area for passing through inorganic medium heat pipe, calculates the work area of effective snow melt of heat pipe, determines two heat extractions Spacing in pipe;
(2) the prefabricated steel pipe in bridge pier places heat pipe vertical section, and backfills the fixed heat pipe of heat-insulating material;
(3) horizontal segment of heat pipe is placed on Bracket for steel bar, places the damage that fractures;
(4) bed course, bridge floor layer are backfilled, and guarantees the stabilization of heat pipe horizontal segment;
(5) installation is completed, and determines that function is intact, and pavement temperature is kept to realize bridge floor snow melt.
CN201810051177.2A 2018-01-19 2018-01-19 A kind of honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge and mounting arrangements method Pending CN110055853A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810051177.2A CN110055853A (en) 2018-01-19 2018-01-19 A kind of honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge and mounting arrangements method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810051177.2A CN110055853A (en) 2018-01-19 2018-01-19 A kind of honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge and mounting arrangements method

Publications (1)

Publication Number Publication Date
CN110055853A true CN110055853A (en) 2019-07-26

Family

ID=67315731

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810051177.2A Pending CN110055853A (en) 2018-01-19 2018-01-19 A kind of honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge and mounting arrangements method

Country Status (1)

Country Link
CN (1) CN110055853A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111979966A (en) * 2020-08-28 2020-11-24 山东省交通规划设计院有限公司 Plug-in type road ice and snow melting heat pipe and construction method

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103147376A (en) * 2013-02-28 2013-06-12 天津百思特环保能源开发有限公司 Solar snow melting system
CN103205932A (en) * 2013-04-23 2013-07-17 长沙理工大学 Pile-type anti-freezing system for bridge
CN103574170A (en) * 2013-11-12 2014-02-12 成都科盛石油科技有限公司 Adjustable pipeline support
CN204491357U (en) * 2015-03-25 2015-07-22 河南城建学院 Road and bridge two-way heat tube snow removing cooling system
CN105442432A (en) * 2015-12-18 2016-03-30 黑龙江建筑职业技术学院 Novel bridge for melting snow through waste heat of power plant and construction method
CN205559984U (en) * 2016-03-31 2016-09-07 孟如苗 Heat supply pipeline fixing base
CN105937861A (en) * 2016-06-02 2016-09-14 南京工业大学 Overlong flexible heat pipe and geothermal snow melting and deicing method thereof
CN205841992U (en) * 2016-05-28 2016-12-28 许昌东方热力有限公司 A kind of support means of heat distribution pipeline
CN206359994U (en) * 2016-12-22 2017-07-28 安徽建筑大学 A kind of spacing power consumption protection device of existing section assembling bridge pier
CN206468902U (en) * 2017-02-14 2017-09-05 奉新县大华燃气有限公司 A kind of gas supply pipe lays protector
CN208235256U (en) * 2018-01-19 2018-12-14 山东省交通规划设计院 A kind of honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103147376A (en) * 2013-02-28 2013-06-12 天津百思特环保能源开发有限公司 Solar snow melting system
CN103205932A (en) * 2013-04-23 2013-07-17 长沙理工大学 Pile-type anti-freezing system for bridge
CN103574170A (en) * 2013-11-12 2014-02-12 成都科盛石油科技有限公司 Adjustable pipeline support
CN204491357U (en) * 2015-03-25 2015-07-22 河南城建学院 Road and bridge two-way heat tube snow removing cooling system
CN105442432A (en) * 2015-12-18 2016-03-30 黑龙江建筑职业技术学院 Novel bridge for melting snow through waste heat of power plant and construction method
CN205559984U (en) * 2016-03-31 2016-09-07 孟如苗 Heat supply pipeline fixing base
CN205841992U (en) * 2016-05-28 2016-12-28 许昌东方热力有限公司 A kind of support means of heat distribution pipeline
CN105937861A (en) * 2016-06-02 2016-09-14 南京工业大学 Overlong flexible heat pipe and geothermal snow melting and deicing method thereof
CN206359994U (en) * 2016-12-22 2017-07-28 安徽建筑大学 A kind of spacing power consumption protection device of existing section assembling bridge pier
CN206468902U (en) * 2017-02-14 2017-09-05 奉新县大华燃气有限公司 A kind of gas supply pipe lays protector
CN208235256U (en) * 2018-01-19 2018-12-14 山东省交通规划设计院 A kind of honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111979966A (en) * 2020-08-28 2020-11-24 山东省交通规划设计院有限公司 Plug-in type road ice and snow melting heat pipe and construction method

Similar Documents

Publication Publication Date Title
Yu et al. State of the art and practice of pavement anti-icing and de-icing techniques
CN208201566U (en) Active ground source-air-source snow melt deicing device
KR101877843B1 (en) Power-saving typed snow melting system for road
KR20150009795A (en) Snow melting apparatus on paved road and installing mehod thereof
CN208235256U (en) A kind of honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge
CN108004863A (en) A kind of ground temperature and solar energy gravity type heat pipe road snow-melting system and its application method
CN110055853A (en) A kind of honest formula bridge floor inorganic medium heat pipe snow-melting system of bridge and mounting arrangements method
KR100987790B1 (en) Device of freezing of the road surface using earth heat
KR102001529B1 (en) Road Snow melting System and Connecting Installation Method Thereof
KR20080066507A (en) The road which equipped heat rail to be able to melt freezing prevention and an snow
KR101513532B1 (en) Road Snow melting System and Connecting Installation Method Thereof
KR101488416B1 (en) Facilities utilizing new and renewable sources of geothermal cooling and heating systems in combination with snowmelt road
JP2689400B2 (en) Solar heat storage type road surface snow melting device
CN201933383U (en) Low-temperature heat pipe road surface snow melting device
JP2015078597A (en) Antifreeze structure of road surface
KR100969985B1 (en) Device of freezing of the road surface using earth heat
Tanaka et al. Snow melting using heat pipes
KR20110113793A (en) Snow melting apparatus on paved road and mehod for paving road
KR101727154B1 (en) Snow melting block with enhanced water permeable
CN108611950B (en) Road snow melting system for old road reconstruction of inorganic medium heat pipe and construction method
JP6560706B2 (en) Snow extinguishing equipment and snow extinguishing method
Yu et al. Geothermal energy for bridge deck and pavement deicing—a brief review
KR101987464B1 (en) Apparatus for Preventing Freezing of Road and Bridge
JP2015203234A (en) Snow-melting system and steel pipe part
WO2014033475A1 (en) A ground source energy system for an outdoor traffic-bearing surface

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 250031 No. 576 Wushanxi Road, Tianqiao District, Jinan City, Shandong Province

Applicant after: Shandong transportation planning and Design Institute Group Co.,Ltd.

Address before: 250031 No. 576 Wushanxi Road, Tianqiao District, Jinan City, Shandong Province

Applicant before: Shandong transportation planning and Design Institute Co.,Ltd.

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20210611

Address after: 250031 No. 576 Wushanxi Road, Tianqiao District, Jinan City, Shandong Province

Applicant after: Shandong transportation planning and Design Institute Co.,Ltd.

Address before: No.576 WuYingShan Road, Tianqiao District, Jinan City, Shandong Province, 250031

Applicant before: SHANDONG PROVINCIAL COMMUNICATIONS PLANNING AND DESIGN INSTITUTE

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190726