CN110042860A - The Construction Method of Metro Station of existing underpass intrusion - Google Patents

The Construction Method of Metro Station of existing underpass intrusion Download PDF

Info

Publication number
CN110042860A
CN110042860A CN201910317259.1A CN201910317259A CN110042860A CN 110042860 A CN110042860 A CN 110042860A CN 201910317259 A CN201910317259 A CN 201910317259A CN 110042860 A CN110042860 A CN 110042860A
Authority
CN
China
Prior art keywords
construction
existing
underpass
construction method
intrusion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910317259.1A
Other languages
Chinese (zh)
Inventor
赵海
刘军
陆海燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 5 Engineering Group Co Ltd
Chengdu Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
Chengdu Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical Chengdu Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority to CN201910317259.1A priority Critical patent/CN110042860A/en
Publication of CN110042860A publication Critical patent/CN110042860A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses the Construction Method of Metro Station of existing underpass intrusion, comprising the following steps: S1: reinforces existing underpass structure in advance;S2: using rope saw cut method, existing underpass structures are removed;S3: the transformation of existing underpass is encircled and hunted down;S4: pile driving construction is gone along with sb. to guard him within the scope of existing underpass intrusion station structure;S5: restore existing underpass.Construction method disclosed by the invention is suitable for the intrusion existing structure construction of subway station underground main body, using the preparatory construction method for reinforcing underpass structure, saw cut existing buildings of restricting, fully ensure that the stable structure in existing channel and the personnel safety of construction period, speed of application can be accelerated using rope saw cut method construction, shortened the construction period;The existing channel design of not large-scale damage, construction period ensure that the use function in existing channel;Solve existing channel can not overall pulling down, remove object can not bulk transport the problem of, saved time and mechanical, labour.

Description

The Construction Method of Metro Station of existing underpass intrusion
Technical field
The invention belongs to metro station construction technical field more particularly to a kind of subway stations of existing underpass intrusion Construction method.
Background technique
In recent years, with the sustainable growth of continuous improvement and the social demand of China's economic level, previous traditional cities The vehicles have been unable to meet the travel requirement of people, and urban track traffic is convenient, highly-safe with material benefit, comfort is good, The advantages that speed is fast, pollution level is small, has been to be concerned by more and more people.China carrys out the development of city track traffic engineering this year Rapidly, but since subway work is generally within city proper, usually intersect with existing building, complicated underground structure is direct Affect the safe mass, progress, benefit of subway work.And the existing channel flow of the people of hypogee is huge, how to guarantee to apply Between duration, the stable structure and personnel safety in the existing channel in underground become the key points and difficulties of construction.
Summary of the invention
The present invention provides a kind of Construction Method of Metro Station of existing underpass intrusion, it is intended to solve above-mentioned ask Topic.
The invention is realized in this way the Construction Method of Metro Station of existing underpass intrusion, comprising the following steps:
S1: existing underpass structure is reinforced in advance;
S2: using rope saw cut method, existing underpass structures are removed;
S3: the transformation of existing underpass is encircled and hunted down;
S4: pile driving construction is gone along with sb. to guard him within the scope of existing underpass intrusion station structure;
S5: restore existing underpass.
Further, the method for reinforcing existing underpass structure in advance includes: installation steel pipe post and building branch Buttress.
Further, the sequence of construction of the installation steel pipe post include: construction encircle and hunt down → surveying setting-out → pedestal is levelling → installing steel pipe support movable end → is installed steel pipe support → erector's beam → application prestressing force → column finishing → dismounting section by section and is enclosed Gear.
Further, the sequence of construction of the building knee wall includes: measurement and positioning → bar planting → reinforcing bar binding → bracket Set up → template installation straightening → concrete placings maintenance.
Further, the step S2 includes:
S21: the dismounting sideline of existing underpass structures is determined;
S22: carrying out lifting equipment configuration according to dismounting structure load, determines the concrete construction weight that monolithic is removed;
S23: drilling to the concrete structure of pre-demolition, and reeves in hole and carry out fall arrest reinforcing;
S24: using rope saw cut, the concrete structure of pre-demolition is removed.
Further, in step s 2, dismounting sequence according to ecto-entad, from top to bottom, it is main after first building enclosure The sequence of body structure carries out piecemeal dismounting.
Further, the step S2 further includes S25: cutting line edge trimming picks out original knot along cutting line edge Structure reinforcing bar does antirust treatment to reinforcing bar using antirust paint after the completion of picking out.
Further, further includes: existing structure is monitored in the construction process.
Further, the content of the monitoring includes ground settlement and horizontal displacement.
Further, the monitoring uses personal monitoring, and monitoring frequency is 1 times/day.
Compared with prior art, the beneficial effects of the present invention are: construction method disclosed by the invention is suitable for subway station Underground main body invades existing structure construction, using the preparatory construction party for reinforcing underpass structure, saw cut existing buildings of restricting Method fully ensures that the stable structure in existing channel and the personnel safety of construction period, can be accelerated using rope saw cut method construction Speed of application shortens the construction period;The existing channel design of not large-scale damage, construction period ensure that the use function in existing channel; Using rope saw cut, solve existing channel can not overall pulling down, remove object can not bulk transport the problem of, saved the time and Mechanical, labour.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to embodiments, to the present invention It is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not used to Limit the present invention.
In the description of the present invention, it is to be understood that, term " length ", " width ", "upper", "lower", "front", "rear", The orientation or positional relationship of the instructions such as "left", "right", "vertical", "horizontal", "top", "bottom" "inner", "outside", is merely for convenience of The description present invention and simplified description, rather than the device or element of indication or suggestion meaning must have a particular orientation, with spy Fixed orientation construction and operation, therefore be not considered as limiting the invention.In addition, in the description of the present invention, " multiple " It is meant that two or more, unless otherwise specifically defined.
The present invention provides a kind of technical solution: the Construction Method of Metro Station of existing underpass intrusion, including following step It is rapid:
S1: existing underpass structure is reinforced in advance;
S2: using rope saw cut method, existing underpass structures are removed;
S3: the transformation of existing underpass is encircled and hunted down;
S4: pile driving construction is gone along with sb. to guard him within the scope of existing underpass intrusion station structure;
S5: restore existing underpass.
Specifically, first being reinforced to existing underpass, channel is removed using rope sawing, then to underpass Transformation is encircled and hunted down, and the fender post finally constructed within the scope of existing underpass intrusion station structure is carried out according to process sequence of construction Each road working procedure is gone along with sb. to guard him pile driving construction until station and is completed, restore existing underpass, meet code requirement, technical standard, protects Station main body construction progress, safety requirements are demonstrate,proved.
Wherein, it needs to reinforce channel design existing in coverage before removing underpass, first according to design requirement In the channel portion construction encircle and hunt down after interim steel pipe post is installed, after the completion enclosing bevelling to need removal position create concrete partition wall into The interim protection of row;
Before construction, first construction area is encircled and hunted down, interim steel pipe post uses finished product bracing members, determines often according to height is reinforced The length of root temporary support, length will deduct the height of jack and steel plate;Material, thickness equidimension to temporary support of marching into the arena It is checked, all machine and appliance in scene is checked, it is ensured that all gone well, the steel pipe support and accessory into scene are answered Classification is stacked, and is kept properly;
After completion underpass is encircled and hunted down, point unwrapping wire is carried out to interim stud, starts that column, column are installed after levelling It is supported using 609 fished pipe of φ, is attached at the top of column using Two bors d's oeuveres 20a I-steel, apply prestressing force after connecting in place It holds out against;Sequence of construction are as follows: construction encircles and hunts down → and surveying setting-out → pedestal levelling → installation steel pipe support movable end → installs steel pipe section by section Support → erector's beam → application prestressing force → column is fitted up → removes enclosing.
After completing the interim steel pipe post of underpass, start Construction Support wall, knee wall is using 250 thick reinforced concrete walls, wall Body reinforcing bar anchors into underpass bottom plate and top plate, and wall uses C30 microdilatancy concrete, reduces concrete and shrinks bring influence;Construction Sequentially are as follows: measurement and positioning → bar planting → reinforcing bar binding → bracket sets up → template installation straightening → concrete placings (maintenance).
Concrete knee wall pour finish reach design strength after start carry out underpass structural demolition, for reduce construction disturbance Existing structure is had an impact safely, removes mode using rope saw cut.
It removes according to ecto-entad, from top to bottom, the sequence of main structure carries out piecemeal dismounting after first building enclosure, and presses Lifting equipment configuration is carried out according to dismounting structure load, is no more than 0.5t on every piece of cutting size principle, when site operation, according to showing Field actual conditions appropriate adjustment monolithic concrete cuts size;Diameter is first used to concrete structure in part to be removed before rope saw cut The drilling of 5cm water drilling, reeves and carries out fall arrest reinforcing, start to cut after hanging device is in place, operation is hung after cutting Face.
After concrete integral cutting is completed, before concrete block pulls out construction, waste and old wheel is laid on the bottom plate of pull-out direction Tire makees cushion;For side wall, concrete block is pulled out using 5T fork truck, for top plate, is hung out concrete block using 25T crane, concrete block It carries out abolishing construction after hanging out boundary of works area.
After the completion of cutting, survey crew discharges cut-sytle pollination line in cut edge position, is returned out and is cut according to measurement control line Cut edge line is first advisable with not injuring original structure main reinforcement along line joint-cutting, joint-cutting depth is rejected with cutting machine before rejecting, meets side along cutting Edge picks out original structure reinforcing bar using pneumatic pick, and doing antirust treatment using antirust paint after the completion of picking out makes steel so that the later period restores structure Muscle welding.
It is encircled and hunted down in channel and is divided into the progress of two phases, the first phase encircles and hunts down channel north half range range, and construction content is northern half range steel Column;Remove enclosing after construction, carrying out the second phase encircles and hunts down, and encloses and covers channel south half range region and construct concrete partition wall in the region, applies Northern half range normal pass between duration;Concrete partition wall and steel pipe post remove enclosing in channel after all constructing in channel.Start Progress ground, which is encircled and hunted down, carries out dismounting and rebuilding construction.
Start carry out ground encircle and hunt down carry out remove and rebuilding construction after, first constructing is not influenced fender post by existing structure, with This is completed at the same time reinforcing and rebuilding construction in channel, carries out 1:1 slope excavation by the outside of channel and top and (reserves 2m wide operation horizontal Platform), underpass fender post is carried out while excavating and structure is abolished, and place cleaning after abolishing backfills out revolve again Drilling machine construction platform (berm width is not less than 8m) is dug, invasive channel part is carried out by aforementioned building enclosure construction technology and goes along with sb. to guard him knot Structure construction.
Construction period is monitored underground connecting pipeline structure, and monitoring content is ground settlement and horizontal displacement. It goes along with sb. to guard him pile driving construction to the part from reinforcing channel to complete, using personal monitoring, monitoring frequency is 1 times/day;
With it is traditional artificial abolish construction compared with, rope saw construction method reduce artificial investment, saved manpower, improve Construction efficiency accelerates construction progress, and shortens the duration, reduces construction cost, achieves good economic benefit, using rope sawing Engineering method is cut up to 12 ㎡/day, and it is traditional artificial abolish engineering method only 6 ㎡/day daily, 6 ㎡/day, overall pulling down work can be shortened the construction period Phase shortens half;
Meanwhile saw engineering method operation of restricting is driven by electronic or hydraulic device, construction noise is extremely low, and is wet work, can be compared with Good control dustiness dye, influences surrounding enviroment smaller;
And need operator few, and labor intensity is reduced, it is easy to operate safe and reliable, have overload protection etc. is automatic to protect Protective function can maximally reduce the generation of personal injury accident, and the component after cutting is regular, can be disposable with crane Entrucking transhipment appears on the scene.
Notch is linear incision, and construction section can be made more neat, the point-device dismounting part-structure of energy, while It is convenient when structure need to be restored or be transformed that a series of processing such as reinforcing bar rejecting, dabbing, bar planting are carried out to section;Saw cut equipment of restricting is dynamic Power is powerful, and operating efficiency is high, can significantly improve operating rate compared to other dismounting modes to shorten construction period, further Reduce labor cost;The safe and reliable and stability of hydraulic system itself, greatly reduces the cost depletions of construction equipment; The disturbance of diamond rope saw cutting operation is extremely low, can save the stability and safety of existing structure to the full extent.
The above is merely preferred embodiments of the present invention, be not intended to limit the invention, it is all in spirit of the invention and Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within principle.

Claims (10)

1. the Construction Method of Metro Station of existing underpass intrusion, which comprises the following steps:
S1: existing underpass structure is reinforced in advance;
S2: using rope saw cut method, existing underpass structures are removed;
S3: the transformation of existing underpass is encircled and hunted down;
S4: pile driving construction is gone along with sb. to guard him within the scope of existing underpass intrusion station structure;
S5: restore existing underpass.
2. construction method according to claim 1, which is characterized in that the side for reinforcing existing underpass structure in advance Method includes: installation steel pipe post and building knee wall.
3. construction method according to claim 2, which is characterized in that it is described installation steel pipe post sequence of construction include: Construction encircles and hunts down → surveying setting-out → pedestal levelling → installation steel pipe support movable end → install section by section steel pipe support → erector's beam → Apply prestressing force → column is fitted up → and removes enclosing.
4. construction method according to claim 2, which is characterized in that the sequence of construction of the building knee wall includes: to survey Amount positioning → bar planting → reinforcing bar binding → bracket sets up → template installation straightening → concrete placings maintenance.
5. construction method according to claim 1, which is characterized in that the step S2 includes:
S21: the dismounting sideline of existing underpass structures is determined;
S22: carrying out lifting equipment configuration according to dismounting structure load, determines the concrete construction weight that monolithic is removed;
S23: drilling to the concrete structure of pre-demolition, and reeves in hole and carry out fall arrest reinforcing;
S24: using rope saw cut, the concrete structure of pre-demolition is removed.
6. construction method according to claim 5, it is characterised in that: in step s 2, the dismounting sequence is according to by outer Inwardly, from top to bottom, after first building enclosure the sequence of main structure carries out piecemeal dismounting.
7. construction method according to claim 5, which is characterized in that the step S2 further includes S25: cutting line edge Finishing, picks out original structure reinforcing bar along cutting line edge, does antirust treatment to reinforcing bar using antirust paint after the completion of picking out.
8. construction method according to claim 1, which is characterized in that further include: in the construction process to existing structure into Row monitoring.
9. construction method according to claim 8, it is characterised in that: the content of the monitoring includes ground settlement and structure Horizontal displacement.
10. construction method according to claim 8, it is characterised in that: the monitoring uses personal monitoring, and monitoring frequency is 1 times/day.
CN201910317259.1A 2019-04-19 2019-04-19 The Construction Method of Metro Station of existing underpass intrusion Pending CN110042860A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910317259.1A CN110042860A (en) 2019-04-19 2019-04-19 The Construction Method of Metro Station of existing underpass intrusion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910317259.1A CN110042860A (en) 2019-04-19 2019-04-19 The Construction Method of Metro Station of existing underpass intrusion

Publications (1)

Publication Number Publication Date
CN110042860A true CN110042860A (en) 2019-07-23

Family

ID=67277973

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910317259.1A Pending CN110042860A (en) 2019-04-19 2019-04-19 The Construction Method of Metro Station of existing underpass intrusion

Country Status (1)

Country Link
CN (1) CN110042860A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110965584A (en) * 2019-12-23 2020-04-07 中铁十二局集团第二工程有限公司 Access and exit earthwork excavation and passage opening concrete breaking synchronous construction method
CN112482809A (en) * 2020-11-24 2021-03-12 中铁四局集团第二工程有限公司 In-situ rapid reconstruction and upgrade construction method for existing operation railway station
CN113279295A (en) * 2021-05-13 2021-08-20 中铁五局集团成都工程有限责任公司 Construction traffic fluffing method for narrow urban road station in famous-region tourist area
CN114961336A (en) * 2022-07-06 2022-08-30 中铁四局集团有限公司 Protective demolition construction method for basement pile foundation next to existing subway line

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102943678B (en) * 2012-11-28 2015-01-07 北京市市政工程设计研究总院有限公司 Arched subway station old and new building connection structure and construction method
CN105155579A (en) * 2015-08-11 2015-12-16 中铁建大桥工程局集团第五工程有限公司 Construction method for penetrating existing underground passage in open cutting of subway foundation pit
WO2017203326A1 (en) * 2016-05-25 2017-11-30 Arun Kumar Pedestrian subway
CN107654234A (en) * 2017-07-24 2018-02-02 广州地铁设计研究院有限公司 A kind of construction method of subway tunnel crossing subway station diaphram wall
CN108396778A (en) * 2018-01-25 2018-08-14 成都城投建筑科技投资管理集团有限公司 A kind of construction method in precast assembly tunnel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102943678B (en) * 2012-11-28 2015-01-07 北京市市政工程设计研究总院有限公司 Arched subway station old and new building connection structure and construction method
CN105155579A (en) * 2015-08-11 2015-12-16 中铁建大桥工程局集团第五工程有限公司 Construction method for penetrating existing underground passage in open cutting of subway foundation pit
WO2017203326A1 (en) * 2016-05-25 2017-11-30 Arun Kumar Pedestrian subway
CN107654234A (en) * 2017-07-24 2018-02-02 广州地铁设计研究院有限公司 A kind of construction method of subway tunnel crossing subway station diaphram wall
CN108396778A (en) * 2018-01-25 2018-08-14 成都城投建筑科技投资管理集团有限公司 A kind of construction method in precast assembly tunnel

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110965584A (en) * 2019-12-23 2020-04-07 中铁十二局集团第二工程有限公司 Access and exit earthwork excavation and passage opening concrete breaking synchronous construction method
CN112482809A (en) * 2020-11-24 2021-03-12 中铁四局集团第二工程有限公司 In-situ rapid reconstruction and upgrade construction method for existing operation railway station
CN112482809B (en) * 2020-11-24 2022-05-17 中铁四局集团第二工程有限公司 In-situ rapid reconstruction and upgrade construction method for existing operation railway station
CN113279295A (en) * 2021-05-13 2021-08-20 中铁五局集团成都工程有限责任公司 Construction traffic fluffing method for narrow urban road station in famous-region tourist area
CN114961336A (en) * 2022-07-06 2022-08-30 中铁四局集团有限公司 Protective demolition construction method for basement pile foundation next to existing subway line
CN114961336B (en) * 2022-07-06 2023-10-10 中铁四局集团有限公司 Protective demolition construction method for foundation pile of basement close to existing subway line

Similar Documents

Publication Publication Date Title
CN110042860A (en) The Construction Method of Metro Station of existing underpass intrusion
CN105926669B (en) A kind of Construction Method of Metro Station
CN105220894B (en) Inner support rope saws lossless cutting disassembling structure and construction thereof
CN206722852U (en) A kind of mobile inverted arch trestle of growing up for carrying inverted arch template
CN103939114B (en) A kind of outstanding rail chassis lining construction method
CN107795749A (en) A kind of precast spliced pipe fitting jacking system and its construction method
CN101158153A (en) Construction method for manual digging pile
CN105155579A (en) Construction method for penetrating existing underground passage in open cutting of subway foundation pit
CN106979021B (en) Large-section loess tunnel excavates and preliminary bracing quick closure cyclization method
CN110043269A (en) A kind of excavation construction process of freeway tunnel barrel
CN104480868A (en) Beam detaching method for road bridge overpassing operation railway
CN110863841A (en) Two-lining three-step construction method for large-span shallow-buried underground excavation tunnel
CN103821523A (en) Excavating method for extending existing single-hole two-driveway tunnel into four-driveway tunnel
CN108678751A (en) The shield cutter inspection-pit assembly construction method excavated after first jacking
CN102758458A (en) Underground continuous wall repairing method
CN107035383A (en) The supporting construction of extra-large cross-section loess tunnel and its excavation method
CN102296964B (en) Method for enlarging and digging soft surrounding rock primarily-supported section of large-section tunnel
CN109488347A (en) A kind of excavation construction method for special formation chamber
CN110158609A (en) A kind of mechanization demolition reduction method of reinforced concrete brace in foundation pit
CN109736591A (en) A kind of ruggedized construction and reinforcement means suitable for building hoist basement roof
CN109629576A (en) Cross foundation pit feed pipe suspension protection system and construction method
CN105862897A (en) Original-groove casting construction method for shallow foundation of sandy mudstone foundation
CN108708727A (en) The shield cutter inspection-pit assembly construction method of jacking after half excavation
JP3864377B2 (en) Existing tunnel widening method
CN203891047U (en) Equipment equipped with steel platform for foundation construction of land bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20200715

Address after: Office building of China Railway No.5 Bureau, No.309, Shaoshan North Road, Changsha City, Hunan Province

Applicant after: CHINA RAILWAY NO.5 ENGINEERING GROUP Co.,Ltd.

Applicant after: CHINA RAILWAY NO.5 ENGINEERING GROUP CHENGDU ENGINEERING Co.,Ltd.

Address before: 610091 No. 2 Building, Area E, Industrial Headquarters Base, Qingyang District, Chengdu City, Sichuan Province (No. 51 Tengfei Avenue)

Applicant before: CHINA RAILWAY NO.5 ENGINEERING GROUP CHENGDU ENGINEERING Co.,Ltd.

TA01 Transfer of patent application right
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190723

WD01 Invention patent application deemed withdrawn after publication