CN110029763B - Indoor furred ceiling of fast-assembling building - Google Patents

Indoor furred ceiling of fast-assembling building Download PDF

Info

Publication number
CN110029763B
CN110029763B CN201910277310.0A CN201910277310A CN110029763B CN 110029763 B CN110029763 B CN 110029763B CN 201910277310 A CN201910277310 A CN 201910277310A CN 110029763 B CN110029763 B CN 110029763B
Authority
CN
China
Prior art keywords
rod
suspender
keel
groove
auxiliary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910277310.0A
Other languages
Chinese (zh)
Other versions
CN110029763A (en
Inventor
瞿永兴
张帆
滕玲英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenzhou Ruiying Construction Engineering Co ltd
Original Assignee
Wenzhou Ruiying Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenzhou Ruiying Construction Engineering Co ltd filed Critical Wenzhou Ruiying Construction Engineering Co ltd
Priority to CN201910277310.0A priority Critical patent/CN110029763B/en
Publication of CN110029763A publication Critical patent/CN110029763A/en
Application granted granted Critical
Publication of CN110029763B publication Critical patent/CN110029763B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/006Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation with means for hanging lighting fixtures or other appliances to the framework of the ceiling
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/06Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/06Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
    • E04B9/12Connections between non-parallel members of the supporting construction
    • E04B9/14Connections between non-parallel members of the supporting construction all the members being discontinuous and laying at least partly in the same plane
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/18Means for suspending the supporting construction

Abstract

The invention discloses a fast-assembled building indoor ceiling, which is characterized by comprising a main keel and an auxiliary keel, wherein the main keel and the auxiliary keel are transversely arranged, the main keel and the auxiliary keel are fixedly connected, an ejector rod is arranged on the auxiliary keel, the ejector rod penetrates through the auxiliary keel to be longitudinally arranged, a safety frame for preventing the ejector rod from being broken is arranged on the side surface of the auxiliary keel, the safety frame is sleeved outside the main keel, a connecting rod is arranged between the safety frame and the auxiliary keel, the connecting rod is used for connecting the safety frame with the main keel, the ceiling is arranged at the main keel, and the ceiling can realize fast assembly and is provided with a device for preventing the keel from falling.

Description

Indoor furred ceiling of fast-assembling building
Technical Field
The invention relates to the field of building decoration, in particular to a fast-assembled building indoor suspended ceiling.
Background
The home decoration suspended ceiling is a common link in home decoration; the suspended ceilings are classified differently according to different materials of the decorative plates; the ceiling finishing material is a main basis for distinguishing the names of the ceilings, and mainly comprises the following components: light steel joist gypsum board suspended ceiling, mineral wool board suspended ceiling, etc.; the decoration of the whole living room plays a very important role, and the top surface of the living room is properly decorated, so that the indoor environment can be beautified, and a rich and colorful indoor space artistic image can be created. The current furred ceiling mounting means mainly adopts the air nail to install furred ceiling and fossil fragments, though intensity is high, the installation is dismantled loaded down with trivial details, has certain damage to fossil fragments, furred ceiling to the furred ceiling among the prior art has not all set up the protection device that fossil fragments were broken.
Disclosure of Invention
Aiming at the defects of the prior art, the invention aims to provide a fast-assembling indoor suspended ceiling for a building, which can realize fast assembly and is provided with a device for preventing keels from falling.
In order to achieve the above purpose, the present invention provides the following technical solutions: the utility model provides an indoor furred ceiling of fast-assembling building, includes the main joist and the vertical auxiliary joist that set up of horizontal setting, fixed connection between main joist and the auxiliary joist, be provided with the ejector pin on the auxiliary joist, the ejector pin passes the auxiliary joist and is vertical setting, the auxiliary joist side is provided with the safety frame that is used for preventing the ejector pin to fall absolutely, the main joist is outside is located to the safety frame cover, be provided with the connecting rod between safety frame and the auxiliary joist, the connecting rod is used for linking together safety frame and main joist, the ceiling lamp sets up in main joist department.
As a further improvement of the invention, the ejector rod is divided into an upper suspender and a lower suspender, the upper suspender and the lower suspender are detachably connected, a fixed rod for being buried in the wall is arranged at one end of the upper suspender far away from the lower suspender, a support rod for being buried in the ceiling is arranged at one end of the lower suspender far away from the upper suspender, the fixed rod and the upper suspender are in a T-shaped structure, the fixed connection between the support rod and the lower suspender is in a T-shaped structure, and the fixed rod, the upper suspender, the support rod and the lower suspender are connected to form an I-shaped structure.
As a further development of the invention, the threaded connection between the upper boom and the lower boom is provided.
As a further improvement of the invention, a transversely arranged inlet groove and a longitudinally arranged fixing groove are formed in the ceiling, the inlet groove is used for the support rod to be inserted, the inlet groove and the fixing groove are vertically arranged, the upper end face of the inlet groove is attached to the lower end face of the fixing groove and are mutually communicated, a transversely arranged caulking groove and a longitudinally arranged inlet groove are formed in the wall, the caulking groove is used for the fixing rod to be inserted, the caulking groove and the inlet groove are vertically arranged, and the upper end face of the inlet groove is attached to the lower end face of the caulking groove and are mutually communicated.
As a further improvement of the invention, an opening is arranged on the side face of the safety frame, the opening is arranged below the safety frame, a sealing component is arranged at the opening, the sealing component comprises an inserting block and an auxiliary block matched with the inserting block, the inserting block and the auxiliary block are fixedly connected with the safety frame, the inserting block and the auxiliary block are oppositely arranged, an inserting piece used for being inserted into the auxiliary block is arranged on the inserting block, the inserting piece comprises an inserting rod and a ball arranged on the side face of the inserting rod, a circular groove matched with the inserting rod is arranged on the auxiliary block, and a clamping groove used for clamping the ball is arranged on the inner side wall of the circular groove.
The invention has the beneficial effects that:
1. the main joist and the auxiliary joist play a supporting role on the suspended ceiling, the suspended ceiling can be pulled to prevent the suspended ceiling from falling down through the arrangement of the ejector rods, safety is achieved, the side face of the auxiliary joist is provided with a safety frame, the safety frame is sleeved on the outer side of the main joist, the auxiliary joist can be prevented from falling down after being broken through the arrangement of the safety frame, and the auxiliary joist and the safety frame can be effectively connected through the arrangement of the connecting rod.
2. The ejector rod is divided into an upper suspender and a lower suspender, the upper end of the upper suspender is provided with a fixed rod, the fixed rod is connected with a wall body, the lower end of the lower suspender is provided with a supporting rod, the supporting rod is connected with a ceiling, the corresponding positions of the upper suspender and the lower suspender are connected in a matched mode, and the ceiling can be effectively fixed through the arrangement of the upper suspender, the lower suspender, the supporting rod and the fixed rod, so that the ceiling is prevented from falling and smashing a middle house owner when natural disasters such as earthquakes occur.
3. After the dead lever buries into the wall body inside, go up the position of jib and be fixed, screw in the one end that is equipped with the screw thread with lower jib and go up the jib and connect down fixedly to through going up jib and lower jib threaded connection's setting, can realize going up the ready-package between jib and the lower jib, thereby reduction in production cost.
4. The groove that advances of horizontal setting and the fixed slot that vertically set up are all offered inside the ceiling, lower jib and bracing piece fixed connection, transversely set up the caulking groove and vertically set up go into the groove and all offer inside the wall body, go up jib and dead lever fixed connection, in the installation, only need insert horizontal caulking groove with the dead lever in, it rotates to go up the jib again, make the dead lever card go into inside the groove, go up the jib installation after accomplishing and put into the inslot with lower jib, then with lower jib and last jib swivelling joint, make the bracing piece card go into inside the fixed slot at last, do not need to adopt screw fixed connection in the installation, and can realize quick installation, saving manufacturing cost.
5. The safety frame cover is established in the main joist outside, thereby the safety frame is used for being used for preventing the auxiliary joist to drop after collapsing and injures personnel by a smash, set up seal assembly at the safety frame downside, set up the opening at its downside the benefit lies in after the auxiliary joist fracture, the opening part can not stress and be opened, seal assembly includes the inserted block and with the auxiliary block of inserted block complex, inserted block and auxiliary block all are in safety frame fixed connection, set up the plug-in components in the inserted block, be used for inserting in the auxiliary block, the plug-in components include the inserted bar and set up the ball in the inserted bar side, set up on the auxiliary block and supply inserted bar male circular groove and supply the draw-in groove that the ball card was gone into, in the installation, outwards pull out the safety frame opening both sides, the cover is established on the main joist, when closing the opening again, only need insert the circular inslot with the inserted bar when getting into the circular groove, the ball is popped out into the card and is gone into the draw-in groove when the ball reaches the card slot position.
Drawings
FIG. 1 is a schematic perspective view of a suspended ceiling;
FIG. 2 is a side view of a suspended ceiling;
FIG. 3 is another angular side view of a suspended ceiling;
FIG. 4 is another perspective view of a suspended ceiling;
FIG. 5 is a schematic perspective view of a safety frame;
FIG. 6 is a schematic illustration of the structure of a caulking groove and an in-groove;
fig. 7 is a schematic view of the structure of the inlet groove and the fixing groove.
Reference numerals: 1. a main keel; 11. a secondary keel; 12. a push rod; 121. an upper boom; 122. a lower boom; 13. a safety frame; 14. a connecting rod; 15. pendant lamp; 2. a fixed rod; 21. a support rod; 3. feeding into a groove; 31. a fixing groove; 4. a caulking groove; 41. entering a groove; 5. an opening; 6. a closure assembly; 61. inserting blocks; 62. an auxiliary block; 7. an insert; 71. a rod; 72. a ball; 73. a circular groove; 74. a clamping groove.
Detailed Description
The invention will now be described in further detail with reference to the drawings and examples. Wherein like parts are designated by like reference numerals. It should be noted that the words "front", "back", "left", "right", "upper" and "lower" used in the following description refer to directions in the drawings, and the words "bottom" and "top", "inner" and "outer" refer to directions toward or away from, respectively, the geometric center of a particular component.
Referring to fig. 1 to 7, an indoor ceiling of a fast-assembling building of this embodiment, including the main joist 1 of horizontal setting and the vertical false keel 11 that sets up, fixed connection between main joist 1 and the false keel 11, be provided with ejector pin 12 on the false keel 11, ejector pin 12 passes the false keel 11 and is vertical setting, the false keel 11 side is provided with the safety frame 13 that is used for preventing ejector pin 12 to break down, safety frame 13 cover locates outside main joist 1, be provided with connecting rod 14 between safety frame 13 and the false keel 11, connecting rod 14 is used for linking together safety frame 13 and main joist 1, ceiling lamp 15 sets up in main joist 1 department.
The main joist 1 and the auxiliary joist 11 play a supporting role on a suspended ceiling, the suspended ceiling can be pulled to prevent the suspended ceiling from falling down through the arrangement of the ejector rods 12, safety is achieved, the side face of the auxiliary joist 11 is provided with the safety frame 13, the safety frame 13 is sleeved on the outer side of the main joist 1, the auxiliary joist 11 can be prevented from falling down after being broken through the arrangement of the safety frame 13, and the auxiliary joist 11 and the safety frame 13 can be effectively connected through the arrangement of the connecting rods 14.
As a specific implementation manner of improvement, the ejector rod 12 is divided into an upper boom 121 and a lower boom 122, the upper boom 121 and the lower boom 122 are detachably connected, one end of the upper boom 121 far away from the lower boom 122 is provided with a fixed rod 2 for being buried in a wall, one end of the lower boom 122 far away from the upper boom 121 is provided with a support rod 21 for being buried in a ceiling, the fixed rod 2 and the upper boom 121 are in a T-shaped structure, the fixed rod 21 and the lower boom 122 are fixedly connected to form a T-shaped structure, and the fixed rod 2, the upper boom 121, the support rod 21 and the lower boom 122 are connected to form an i-shaped structure.
The ejector rod 12 is divided into an upper suspender 121 and a lower suspender 122, the upper end of the upper suspender 121 is provided with a fixed rod 2, the fixed rod 2 is connected with a wall body, the lower end of the lower suspender 122 is provided with a supporting rod 21, the supporting rod 21 is connected with a ceiling, the corresponding positions of the upper suspender 121 and the lower suspender 122 are connected in a matched mode, and the ceiling can be effectively fixed through the arrangement of the upper suspender 121, the lower suspender 122, the supporting rod 21 and the fixed rod 2, so that the ceiling is prevented from falling and smashing a middle householder when natural disasters such as earthquakes occur.
As an improved embodiment, the upper boom 121 and the lower boom 122 are threadably connected.
After the fixing rod 2 is buried in the wall, the position of the upper boom 121 is fixed, one end of the lower boom 122 provided with threads is screwed into the upper boom 121, so that the upper boom 121 and the lower boom 122 are fixedly connected, and quick assembly between the upper boom 121 and the lower boom 122 can be realized through the arrangement of the threaded connection of the upper boom 121 and the lower boom 122, so that the production cost is reduced.
As a concrete implementation manner of improvement, a transversely arranged inlet groove 3 and a longitudinally arranged fixing groove 31 are formed in the ceiling, the inlet groove 3 is used for the support rod 21 to be inserted, the inlet groove 3 and the fixing groove 31 are vertically arranged, the upper end face of the inlet groove 3 is attached to the lower end face of the fixing groove 31 and are mutually conducted, a transversely arranged caulking groove 4 and a longitudinally arranged inlet groove 41 are formed in the wall, the caulking groove 4 is used for the fixing rod 2 to be inserted, the caulking groove 4 and the inlet groove 41 are vertically arranged, and the upper end face of the inlet groove 41 is attached to the lower end face of the caulking groove 4 and are mutually conducted.
The groove 3 that advances that transversely sets up and the fixed slot 31 that vertically set up are all offered in the ceiling inside, lower jib 122 and bracing piece 21 fixed connection, transversely set up caulking groove 4 and vertically set up go into groove 41 and all offer in the wall body inside, go up jib 121 and dead lever 2 fixed connection, in the installation, only need insert transverse caulking groove 4 with dead lever 2 in, it rotates again to go up jib 121, make dead lever 2 card go into inslot 41, go up jib 121 after the installation is accomplished and put into lower jib 122 into inslot 3, then with lower jib 122 and last jib 121 swivelling joint, make bracing piece 21 card go into inside fixed slot 31 at last, need not adopt screw fixed connection in the installation, and can realize quick installation, save manufacturing cost.
As a specific implementation manner of improvement, the side of the safety frame 13 is provided with an opening 5, the opening 5 is arranged below the safety frame 13, a sealing component 6 is arranged at the opening 5, the sealing component 6 comprises an inserting block 61 and an auxiliary block 62 matched with the inserting block 61, the inserting block 61 and the auxiliary block 62 are fixedly connected with the safety frame 13, the inserting block 61 and the auxiliary block 62 are oppositely arranged, an inserting piece 7 used for being inserted into the auxiliary block 62 is arranged on the inserting block 61, the inserting piece 7 comprises an inserting rod 71 and a ball 72 arranged on the side of the inserting rod 71, a circular groove 73 matched with the inserting rod 71 is arranged on the auxiliary block 62, and a clamping groove 74 used for clamping the ball 72 is arranged on the inner side wall of the circular groove 73.
The safety frame 13 is sleeved outside the main joist 1, the safety frame 13 is used for preventing the auxiliary joist 11 from falling after collapse and injuring personnel by smashing, the sealing component 6 is arranged on the lower side of the safety frame 13, the advantage of arranging the opening 5 on the lower side of the safety frame is that after the auxiliary joist 11 breaks, the opening 5 cannot be stressed and opened, the sealing component comprises an insert block 61 and an auxiliary block 62 matched with the insert block 61, the insert block 61 and the auxiliary block 62 are fixedly connected with each other in the safety frame 13, the insert block 61 is internally provided with an insert 7 for being inserted into the auxiliary block 62, the insert 7 comprises an insert rod 71 and a ball 72 arranged on the side face of the insert rod 71, the auxiliary block 62 is provided with a circular groove 73 for inserting the insert rod 71 and a clamping groove 74 for clamping the ball 72, in the mounting process, the two sides of the opening 5 of the safety frame 13 are outwards pulled out to be sleeved on the main joist 1, and when the opening 5 is closed, the insert rod 71 is only required to be inserted into the circular groove 73, the ball 72 is inserted into the ball 72 when the ball 72 enters the circular groove 73, and the ball 72 is ejected into the clamping groove 74 when the ball 72 reaches the clamping groove 74 position.
The above description is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above examples, and all technical solutions belonging to the concept of the present invention belong to the protection scope of the present invention. It should be noted that modifications and adaptations to the present invention may occur to one skilled in the art without departing from the principles of the present invention and are intended to be within the scope of the present invention.

Claims (1)

1. The utility model provides a furred ceiling in fast-assembling building, includes main joist (1) and the longitudinal set false keel (11) of horizontal setting, fixed connection between main joist (1) and the false keel (11), its characterized in that: the auxiliary keel (11) is provided with an ejector rod (12), the ejector rod (12) penetrates through the auxiliary keel (11) to be longitudinally arranged, the side face of the auxiliary keel (11) is provided with a safety frame (13) for preventing the ejector rod (12) from being broken, the safety frame (13) is sleeved outside the main keel (1), a connecting rod (14) is arranged between the safety frame (13) and the auxiliary keel (11), and the connecting rod (14) is used for connecting the safety frame (13) with the main keel (1), and a pendant lamp (15) is arranged at the main keel (1);
the ejector rod (12) is divided into an upper suspender (121) and a lower suspender (122), the upper suspender (121) and the lower suspender (122) are detachably connected, one end of the upper suspender (121) far away from the lower suspender (122) is provided with a fixing rod (2) which is buried in a wall, one end of the lower suspender (122) far away from the upper suspender (121) is provided with a supporting rod (21) which is buried in a ceiling, the fixing rod (2) and the upper suspender (121) are in a T-shaped structure, the fixing rod (21) and the lower suspender (122) are fixedly connected to form a T-shaped structure, and the fixing rod (2), the upper suspender (121), the supporting rod (21) and the lower suspender (122) are connected to form an I-shaped structure; the upper suspender (121) and the lower suspender (122) are connected through threads;
the ceiling is internally provided with a transversely arranged inlet groove (3) and a longitudinally arranged fixing groove (31), the inlet groove (3) is used for inserting a supporting rod (21), the inlet groove (3) and the fixing groove (31) are vertically arranged, the upper end face of the inlet groove (3) is attached to the lower end face of the fixing groove (31) and communicated with each other, the wall is internally provided with a transversely arranged caulking groove (4) and a longitudinally arranged inlet groove (41), the caulking groove (4) is used for inserting a fixing rod (2), the caulking groove (4) and the inlet groove (41) are vertically arranged, and the upper end face of the inlet groove (41) is communicated with the caulking groove;
the safety box is characterized in that an opening (5) is formed in the side face of the safety box (13), the opening (5) is formed in the lower portion of the safety box (13), a sealing component (6) is arranged at the opening (5), the sealing component (6) comprises an inserting block (61) and an auxiliary block (62) matched with the inserting block (61), the inserting block (61) and the auxiliary block (62) are fixedly connected with the safety box (13), the inserting block (61) and the auxiliary block (62) are oppositely arranged, an inserting piece (7) used for being inserted into the auxiliary block (62) is arranged on the inserting piece (61), the inserting piece (7) comprises an inserting rod (71) and balls (72) arranged on the side face of the inserting rod (71), circular grooves (73) matched with the inserting rod (71) are formed in the auxiliary block (62), and clamping grooves (74) used for clamping the balls (72) are formed in the inner side walls of the circular grooves (73).
CN201910277310.0A 2019-04-08 2019-04-08 Indoor furred ceiling of fast-assembling building Active CN110029763B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910277310.0A CN110029763B (en) 2019-04-08 2019-04-08 Indoor furred ceiling of fast-assembling building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910277310.0A CN110029763B (en) 2019-04-08 2019-04-08 Indoor furred ceiling of fast-assembling building

Publications (2)

Publication Number Publication Date
CN110029763A CN110029763A (en) 2019-07-19
CN110029763B true CN110029763B (en) 2024-04-09

Family

ID=67237744

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910277310.0A Active CN110029763B (en) 2019-04-08 2019-04-08 Indoor furred ceiling of fast-assembling building

Country Status (1)

Country Link
CN (1) CN110029763B (en)

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6317915B1 (en) * 1998-10-30 2001-11-20 Multuloc International Systems Energy efficient deck framing system and method
KR20100008928A (en) * 2008-07-17 2010-01-27 송우용 Ceiling panel structure with locking device
CN202181639U (en) * 2011-06-02 2012-04-04 浙江华光电器集团有限公司 Novel ceiling keel installation structure
CN204139418U (en) * 2014-09-03 2015-02-04 上海西蒙幕墙吊顶板有限公司 Corrugation PLASTIC LAMINATED suspended ceiling mounting structure
CN206408815U (en) * 2017-01-06 2017-08-15 深圳众志成城装修工程有限公司 A kind of main joist and the ceiling board mounting structure with the main joist
CN107130725A (en) * 2016-02-26 2017-09-05 上海七环实业有限公司 Mineral wool board keel ceiling structure
CN207419816U (en) * 2017-11-08 2018-05-29 深圳市建信装饰工程有限公司 A kind of ceiling joist mounting structure with pendant
CN207620196U (en) * 2017-12-16 2018-07-17 深圳市中鑫建筑装饰工程集团有限公司 A kind of furred ceiling structure of disturbance rejection
CN207686109U (en) * 2018-01-03 2018-08-03 河南农业大学 A kind of antidetonation ceiling structure
CN207739490U (en) * 2017-12-27 2018-08-17 品格卫厨(浙江)有限公司 A kind of mounting connection structure between Integral ceiling c-type main joist and triangle false keel
CN207863271U (en) * 2018-02-08 2018-09-14 深圳市雅度空间装饰设计工程有限公司 Indoor keel ceiling system
CN108532815A (en) * 2018-06-27 2018-09-14 成都言行果科技有限公司 A kind of simple plug-in type ceiling structure
CN208441330U (en) * 2018-05-29 2019-01-29 浙江尚都建设有限公司 Build ceiling component
CN210216863U (en) * 2019-04-08 2020-03-31 温州睿鹰建设工程有限公司 Fast-assembling building indoor suspended ceiling

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6317915B1 (en) * 1998-10-30 2001-11-20 Multuloc International Systems Energy efficient deck framing system and method
KR20100008928A (en) * 2008-07-17 2010-01-27 송우용 Ceiling panel structure with locking device
CN202181639U (en) * 2011-06-02 2012-04-04 浙江华光电器集团有限公司 Novel ceiling keel installation structure
CN204139418U (en) * 2014-09-03 2015-02-04 上海西蒙幕墙吊顶板有限公司 Corrugation PLASTIC LAMINATED suspended ceiling mounting structure
CN107130725A (en) * 2016-02-26 2017-09-05 上海七环实业有限公司 Mineral wool board keel ceiling structure
CN206408815U (en) * 2017-01-06 2017-08-15 深圳众志成城装修工程有限公司 A kind of main joist and the ceiling board mounting structure with the main joist
CN207419816U (en) * 2017-11-08 2018-05-29 深圳市建信装饰工程有限公司 A kind of ceiling joist mounting structure with pendant
CN207620196U (en) * 2017-12-16 2018-07-17 深圳市中鑫建筑装饰工程集团有限公司 A kind of furred ceiling structure of disturbance rejection
CN207739490U (en) * 2017-12-27 2018-08-17 品格卫厨(浙江)有限公司 A kind of mounting connection structure between Integral ceiling c-type main joist and triangle false keel
CN207686109U (en) * 2018-01-03 2018-08-03 河南农业大学 A kind of antidetonation ceiling structure
CN207863271U (en) * 2018-02-08 2018-09-14 深圳市雅度空间装饰设计工程有限公司 Indoor keel ceiling system
CN208441330U (en) * 2018-05-29 2019-01-29 浙江尚都建设有限公司 Build ceiling component
CN108532815A (en) * 2018-06-27 2018-09-14 成都言行果科技有限公司 A kind of simple plug-in type ceiling structure
CN210216863U (en) * 2019-04-08 2020-03-31 温州睿鹰建设工程有限公司 Fast-assembling building indoor suspended ceiling

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张永平.《建筑与装饰施工工艺》.北京理工大学出版社,第313-315页. *

Also Published As

Publication number Publication date
CN110029763A (en) 2019-07-19

Similar Documents

Publication Publication Date Title
CN110029763B (en) Indoor furred ceiling of fast-assembling building
CN207436409U (en) A kind of easy-to-dismount glass-fiber-fabric secretly inserts wallboard
CN210216863U (en) Fast-assembling building indoor suspended ceiling
CN109898731A (en) A kind of light weight type environmental protection calcium silicate board
CN206016029U (en) A kind of c-type buckle furred ceiling
CN205913226U (en) Pelmet light gauge steel framework
CN206174265U (en) A furred ceiling fixing device for gypsum board
CN205531132U (en) A activity combination formula decoration wallboard for indoor decoration
CN107514088A (en) Integrated modular flat-top and its construction method
CN206928498U (en) A kind of furred ceiling
CN204343521U (en) A kind of decoration panel connector of dark keel furred ceiling
CN206707070U (en) A kind of sheet material Combined hanger installation system
CN206667565U (en) A kind of ceiling structure
CN207405849U (en) Integrated modular flat-top
CN209568599U (en) A kind of adjustable integrated suspended ceiling pinch plate
CN203867112U (en) Dry-hanging wall tile structure
CN209194824U (en) A kind of half-cell ceiling structure
CN206607739U (en) A kind of V-type hang type furred ceiling
CN208329181U (en) A kind of easy-to-mount adjustable emergency building construction
CN206205245U (en) The T bone attachment structures of bright frame keel
CN212026800U (en) Decorative column molding suspended ceiling
CN210421590U (en) Keel for suspended ceiling
CN219992857U (en) Assembled furred ceiling structure
CN203867131U (en) Wall dry-hanging tile structure
CN215290935U (en) Architectural decoration furred ceiling based on BIM technique

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant