CN110020753A - A kind of optimization of sewage network working sources and Project Schedule Risk Analysis method - Google Patents

A kind of optimization of sewage network working sources and Project Schedule Risk Analysis method Download PDF

Info

Publication number
CN110020753A
CN110020753A CN201910277262.5A CN201910277262A CN110020753A CN 110020753 A CN110020753 A CN 110020753A CN 201910277262 A CN201910277262 A CN 201910277262A CN 110020753 A CN110020753 A CN 110020753A
Authority
CN
China
Prior art keywords
duration
cost
teams
groups
expense
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910277262.5A
Other languages
Chinese (zh)
Inventor
李新
袁明国
李吉明
朱先杰
罗宁
南云朋
马涛
邓彦博
孟帅
刘亮亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Institute of Architectural Technology
Original Assignee
Jiangsu Institute of Architectural Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Institute of Architectural Technology filed Critical Jiangsu Institute of Architectural Technology
Priority to CN201910277262.5A priority Critical patent/CN110020753A/en
Priority to CN202311578386.XA priority patent/CN117557052A/en
Publication of CN110020753A publication Critical patent/CN110020753A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06315Needs-based resource requirements planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2113/00Details relating to the application field
    • G06F2113/14Pipes

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Operations Research (AREA)
  • Marketing (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Game Theory and Decision Science (AREA)
  • General Business, Economics & Management (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of optimization of sewage network working sources and Project Schedule Risk Analysis methods, first establish overhead cost, flat cost, total cost mathematical model;Secondly, establishing restrictive condition;Teams and groups' quantitative expression is calculated to total cost mathematical model again;Then the reasonable sex determination of calculated result is carried out, solution in next step is transferred to if rationally if result and obtains optimal teams and groups' quantity;Influence of the Outer risks factor to construction when finally assessing different month operations, and obtain the actually required duration.The present invention is according to influencing teams and groups' quantity, duration and cost function relationship and the moon number of days, utilize number of days, usage factor, monthly average usage factor, expense accounting, which can be obtained, from teams and groups quantitative relation curves, duration and expense relation curve, teams and groups-duration and expense relation curve and different months to be influenced number of days, utilizes number of days, usage factor distribution curve, required actual construction time, have many advantages, such as that method for solving is simple, solves object and be illustrated.

Description

A kind of optimization of sewage network working sources and Project Schedule Risk Analysis method
Technical field
The present invention relates to a kind of optimization of sewage network working sources and Project Schedule Risk Analysis methods, belong to pipeline network construction technology Field.
Background technique
Important component of the pipe-networks engineering as villages within the city's pollution treatment, construction speed directly influence the effect of waste water control Fruit.Since villages within the city tunnel is narrow, underground utilities are intricate, septic tank arranges unordered, wagon flow and flow of the people is big, pipeline construction Have the characteristics that difficulty is big, restraining factors are more, Schedule schema is big.How to organize to complete production task within a short period of time, effectively Various risks are eliminated and dissolved, realize the optimization of engineering cost, resource input, to reach pair of economic benefit and social benefit To income, there is stronger realistic meaning.
Currently, mainly carrying out around engineering cost, duration etc., in engineering construction optimization and progress analysis by building Vertical Optimized model, thus find Optimal Project Duration and expense, and be mainly used in road, bridge, highway etc., it congratulates such as high based on mould Paste mathematical theory studies road engineering optimum duration, Liu Nannan (engineering project schedule -expense optimizing research --- with The Xi'an [D] for science of bridge building project: Xi'an University of Architecture and Technology, 2013) use adaptivity genetic algorithm to science of bridge building Research, Yang Panpan (the expressway construction project multi-objective Optimization based on genetic algorithm is optimized in progress, expense The Tianjin [D]: Tianjin Polytechnic University, 2013.) expressway construction project multiple-objection optimization is ground based on genetic algorithm Study carefully;For the construction optimization and Project Schedule Risk Analysis of pipe network project, it is more from design angle that correlative study and application are less It accounts for, such as (Tian Jiandong, Cheng Jilin, Gong Yi municipal sewage transportation system Study on method of optimization [J] gives Tian Jiandong 2017,43 (4): water draining 115~121) carries out municipal sewage transportation system optimum design method using discrete enumerative technique Research, (Liu Shuming, Wang Huanhuan believe the Kunlun town water supply pipe network Algorithm for multiobjective optimization and give using [J] Liu Shuming etc. Water drains, 2014,30 (1): it is excellent 52~60.) to have carried out multiple target to town water supply pipe network using non-dominated sorted genetic algorithm Change, (Wang Guangyu, Xie Jiancang, Zhang Jianlong calculate [J] northwest agricultural based on the water supply network optimization for improving ant group algorithm to Wang Guangyu University of Science and Technology's journal (natural science edition), 2014,42 (1): 228~234.) based on improved ant group algorithm to water supply network into Optimization of having gone calculates, Chen Shengbing (Chen Shengbing, Lou Jinsheng, Huangping, the municipal sewage pipe network that Tian Hongdong is constructed based on topological relation 2007,33 (5): optimization design [J] water supply and drainage 189~121.) has carried out municipal sewage pipe network based on topological relation excellent Change design.
For an engineering, since job content and total amount are fixed, investment resource more more then durations it is shorter, resource more it is few then Duration is longer.The number of resource input will have a direct impact on the flat cost of engineering, and the engineering that the length of duration will affect Overhead cost.Overhead cost, which refers to, is not used to directly be included in engineering object, but to carry out the expense that engineering construction is occurred, including management Personnel's wage, assets usage charges, insurance premium etc..Flat cost includes labour cost, fee of material, mechanical stage student contributions pooled to pay for class activities, measure expense etc..Generally For, there are a normal durations for project, mean that engineering is delayed more than the normal duration, overhead cost can be increase accordingly, flat cost It reduces;Compressing the normal duration then means that the duration shifts to an earlier date, and overhead cost can be reduced accordingly, and flat cost increases.
Under normal conditions, overhead cost and duration are (direct proportion) linear functional relation, and flat cost and duration are quadratic function Relationship.Indirect expense mathematical formulae can be expressed as:
CI=β t (1)
In formula, CI --- overhead cost, Wan Yuan;
β --- indirect rate, β=(C`2-C`1)/(t2-t1);
t1--- minimum duration, day;
C`1——t1Corresponding indirect expense, Wan Yuan;
t2--- normal duration, day;
C`2——t2Corresponding indirect expense, Wan Yuan.
Indirect expense mathematical formulae can be expressed as:
CD=at2+bt+c (2)
In formula, CD --- flat cost, Wan Yuan;
B=2 (C2-C1)/(t2-t1);
C1——t1Corresponding direct cost;
C2——t2Corresponding direct cost.
Therefore, total cost can be expressed as lower array function:
C (t)=CI (t)+CD (t) (3)
The sum of flat cost CD and overhead cost CI are the total cost C of engineering.When total cost minimum, the corresponding duration is Optimum duration, resource input at this time are optimal resource input.
For sewage network project, the optimizing research to working sources investment and Schedule schema research are also lacked, it is specific next It says, lacks using the resource of pipeline network construction, duration, expense as optimizing index, using Outer risks factor as the tool of evaluation object Body method, therefore establish a kind of sewage network working sources optimization analysis and Project Schedule Risk Analysis method there is relatively strong application meaning Justice.
Summary of the invention
In view of the above existing problems in the prior art, the present invention provides a kind of optimization of sewage network working sources and progress wind Dangerous analysis method.
To achieve the goals above, a kind of optimization of sewage network working sources and Project Schedule Risk Analysis side that the present invention uses Method first establishes overhead cost, flat cost, total cost mathematical model;
Secondly, establishing restrictive condition;
Teams and groups' quantitative expression is calculated to total cost mathematical model again;
Then the reasonable sex determination of calculated result is carried out, is transferred to if rationally if result and solves optimal teams and groups' quantity in next step;
Influence of the Outer risks factor to construction when finally assessing different month operations, and obtain the actually required duration.
As an improvement, sewage network working sources optimization and Project Schedule Risk Analysis method, specifically includes the following steps:
Step 1: establishing the expense mathematical model in sewage network construction:
Indirect expense model is CI=β [L/ (ld·x)+11] (1);
Direct cost model is CD=a [L/ (ld·x)+11]2+b·[L/(ld·x)+11]+c (2);
Total cost mathematical model is C (x, ld)=a [L/ (ld·x)+11]2+(β+b)·[L/(ld·x)+11]+c (3);
Wherein: L --- pipe network total length is;X --- teams and groups' quantity;ld--- the pipe network that each teams and groups complete daily is long Degree;
B=2 (C2-C1)/(t2-t1);
t1--- minimum duration, day;
t2--- normal duration, day;
C1——t1Corresponding direct cost;
C2——t2Corresponding direct cost;
β --- indirect rate, β=(C`2-C`1)/(t2-t1);
C`1——t1Corresponding indirect expense, Wan Yuan;
C`2——t2Corresponding indirect expense, Wan Yuan;
Step 2: setting up the restrictive condition of investment teams and groups' quantity:
2000≤L/x≤10000 (4);
Step 3: the function factor that solving model is related to:
If very big, the minimum teams and groups quantity of investment is respectively x1、x3, the corresponding duration is respectively minimum duration t1, greatly Duration t3;Normal teams and groups' quantity is x2, the corresponding duration is normal duration t2;x1、x2Corresponding indirect expense is respectively C `1、C`2;Enable t2=(t1+t3)/2, then have:
x2=2x1·x3/(x1+x3) (5);
For indirect expense, can obtain:
CI=Cdj·t (6);
In formula, CI --- overhead cost, Wan Yuan;
Cdj--- the indirect expense occurred daily, Wan Yuan;
Know β=Cdj
Then have:
C`1=Cdj·t1(7);
C`2=Cdj·t2(8);
For daily flat cost, the functional relation of teams and groups' quantity and expense can be established:
Cdz=Kxld·Cd0(9);
In formula, Cdz--- daily direct cost, Wan Yuan;
Cd0--- it is the expense of every linear meter(lin.m.), Wan Yuan;
K --- direct cost coefficient related with compression duration size, is herein direct cost related with teams and groups' quantity Coefficient takes 1.0, x when teams and groups' quantity is 11、x2Corresponding cost coefficient is respectively K1、K2
Formula (9) are substituted into direct cost relational expression:
CD=Cdz·t (10);
In formula, CD --- flat cost, Wan Yuan;
Very big flat cost can be obtained, normal flat cost is respectively as follows:
C1=K1·x1·ld·Cd0·t1(11);
C2=K1·x2·ld·Cd0·t2(12);
Step 4: calculating optimal resource input expression formula:
To the x derivation that formula (3) includes, C` (x, l are enabledd)x=0, it obtains:
X=-2aL/ [ld·(22a+b+β)] (13);
Step 5: the reasonable sex determination of calculated result:
The second dervative to formula (3) comprising x is sought, and (13) formula, function factor are substituted into, if C`` (x, ld)xx> 0 is set up, Then (13) formula is optimal resource input, is transferred to and solves in next step;
Step 6: optimal resource input solves:
Function factor substitution (13) formula that model is related to is corresponding to get optimal resource input (optimal teams and groups' quantity) Duration be the optimal absolute duration;
Step 7: Project Schedule Risk Analysis:
Assuming that moon number of days is dm, the moon is d by external action number of days0, the moon can be d using construction days1, the moon usage factor be ε, monthly average usage factor areOptimal teams and groups' quantity corresponding absolute duration is t, and the actually required duration is T, then has:
d1=dm-d0(14);
ε=(dm-d0)/dm(15);
d1=ε dm(16);
Month usage factor is smaller illustrates that Schedule schema is bigger, the moon usage factor bigger illustrate that Schedule schema is lower.
Compared with prior art, the present invention is using the resource of pipeline network construction, duration, expense as optimizing index, by external wind Dangerous factor acquires pipeline network construction overhead cost, flat cost, the mathematical model of total cost and moon usage factor etc. as evaluation object Parameter.According to teams and groups' quantity, duration and cost function relationship and moon influence number of days, number of days, usage factor, monthly average is utilized to utilize Coefficient, can obtain expense accounting and teams and groups' quantitative relation curve, duration and expense relation curve, teams and groups-duration and expense relationship are bent Line and different months influence number of days, using number of days, usage factor distribution curve, required actual construction time, have method for solving simple, Solve the advantages that object is illustrated.
Detailed description of the invention
Fig. 1 is that the process stages of sewage network construction divide schematic diagram;
Fig. 2 is expense accounting and teams and groups' Figure of the quantitative relationship in sewage network construction;
Fig. 3 is duration and expense relational graph in sewage network construction;
Fig. 4 is teams and groups-duration, expense relational graph in sewage network construction;
Fig. 5 is to influence number of days different months, utilize number of days, usage factor figure.
Specific embodiment
In order to make the objectives, technical solutions and advantages of the present invention clearer, the present invention is carried out below further detailed It describes in detail bright.However, it should be understood that the specific embodiments described herein are merely illustrative of the present invention, it is not limited to this hair Bright range.
Unless otherwise defined, all technical terms and scientific terms used herein are led with technology of the invention is belonged to The normally understood meaning of the technical staff in domain is identical, and term as used herein in the specification of the present invention is intended merely to retouch State the purpose of specific embodiment, it is not intended that in the limitation present invention.
A kind of sewage network working sources method for optimization analysis, comprising the following steps:
Firstly, carrying out procedure analysis.
For pipe-networks engineering, working procedure mainly include surveying setting-out, road surface abolish, supporting, excavation, ground and base Plinth, pipe laying build well, closed-water test, encapsulating concrete and backfill, road surface recovery.In general, each process is that the flowing water constantly recycled is made Industry.Each process to be classified, divided stages are shown in Fig. 1 convenient for analysis.As seen from Figure 1, process 1. → 2. for preparation of construction, Startup stage (first stage);Process 2. → 5. for implement (circulation) stage (second stage);Process 5. → 6. for construction ending Stage (phase III).Second stage plays a crucial role to the duration, and first stage, phase III are mainly according to second stage Progress carries out operation.
If certain project pipe network total length is L, teams and groups' quantity (working face quantity) is x, and each teams and groups' (each working face) are every The pipe network length (cyclic advance) that day completes is ld, then there is the duration:
T=L/ (ldX)+1+2+8=L/ (ld·x)+11 (1);
Step 1: establishing model:
Indirect expense mathematical model are as follows:
CI=β [L/ (ld·x)+11] (2);
Direct cost mathematical model are as follows:
CD=a [L/ (ld·x)+11]2+b·[L/(ld·x)+11]+c (3);
Total cost mathematical model are as follows:
C (x, ld)=a [L/ (ld·x)+11]2+(β+b)·[L/(ld·x)+11]+c (4);
Wherein:
L --- pipe network total length is;
X --- teams and groups' quantity (working face quantity);
ld--- the pipe network length (cyclic advance) that each teams and groups' (each working face) are completed daily;
B=2 (C2-C1)/(t2-t1);
t1--- minimum duration, day;
t2--- normal duration, day;
C1——t1Corresponding direct cost;
C2——t2Corresponding direct cost.
β --- indirect rate, β=(C`2-C`1)/(t2-t1);
C`1——t1Corresponding indirect expense, Wan Yuan;
C`2——t2Corresponding indirect expense, Wan Yuan;
Step 2: establishing restrictive condition:
To ensure the duration in the reasonable scope, investment teams and groups' quantity must be limited in a certain range, the pact that the present invention establishes Beam condition are as follows:
2000≤L/x≤10000 (5);
Step 3: the correlation function factor that solving model is related to:
Very big, the minimum teams and groups quantity of facility work investment is respectively x1、x3, the corresponding duration is respectively minimum duration t1、 Very big duration t3;Normal teams and groups' quantity is x2, the corresponding duration is normal duration t2;x1、x2Corresponding indirect expense point It Wei not C`1、C`2;Enable t2=(t1+t3)/2, then have:
x2=2x1·x3/(x1+x3) (6);
For indirect expense, can obtain:
CI=Cdj·t (7);
In formula, CI --- overhead cost, Wan Yuan;
Cdj--- the indirect expense occurred daily, Wan Yuan.
Know β=Cdj
Then have:
C`1=Cdj·t1(8);
C`2=Cdj·t2(9);
For daily flat cost, the functional relation of teams and groups' quantity and expense can be established:
Cdz=Kxld·Cd0(10);
In formula, Cdz--- daily direct cost, Wan Yuan;
Cd0--- it is the expense of every linear meter(lin.m.), Wan Yuan;
K --- direct cost coefficient related with compression duration size, is herein direct cost related with teams and groups' quantity Coefficient takes 1.0, x when teams and groups' quantity is 11、x2Corresponding cost coefficient is respectively K1、K2
Formula (10) are substituted into direct cost relational expression:
CD=Cdz·t (11);
In formula, CD --- flat cost, Wan Yuan;
Very big flat cost can be obtained, normal flat cost is respectively as follows:
C1=K1·x1·ld·Cd0·t1(12);
C2=K1·x2·ld·Cd0·t2(13);
Step 4: calculating optimal resource input expression formula:
To the x derivation that formula (4) includes, C` (x, l are enabledd)x=0, it obtains:
X=-2aL/ [ld·(22a+b+β)] (14);
Step 5: the reasonable sex determination of calculated result:
The second dervative to formula (4) comprising x is sought, and (14) formula, function factor are substituted into, if C`` (x, ld)xx> 0 is set up, Then (14) formula is optimal resource input, is transferred to and solves in next step;
Step 6: optimal resource input solves:
Function factor substitution (14) formula that model is related to is corresponding to get optimal resource input (optimal teams and groups' quantity) Duration be the optimal absolute duration;
Step 7: Project Schedule Risk Analysis: assuming that moon number of days is dm, the moon is d by external action number of days0, construction day can be utilized by the moon Number is d1, moon usage factor is ε, and monthly average usage factor isOptimal teams and groups' quantity corresponding absolute duration is t, actually required Duration is T, then has:
d1=dm-d0 (15)
ε=(dm-d0)/dm (16)
d1=ε dm (17)
Month usage factor is smaller illustrates that Schedule schema is bigger, the moon usage factor bigger illustrate that Schedule schema is lower.
Embodiment 1
By taking the transformation of certain villages within the city's sewage as an example, sewage network project amount is shown in Table 1.
Certain the villages within the city's sewage network project amount of table 1
Serial number Project Specification Unit Quantity
1 UPVC drainpipe DN150 m 12698
2 UPVC drainpipe DN200 m 9004
3 HDPE hollow wall winding arrangement pipe DN300 m 5823
4 II grades of reinforced concrete sewage pipes d300 m 1831
5 II grades of reinforced concrete sewage pipes d400 m 957
6 II grades of reinforced concrete sewage pipes d500 m 380
It is total 30693
Through the ginseng such as direct cost of average daily cyclic advance, every working face can be obtained to construction effect, fee calculating and analysis Number, see Table 2 for details.
2 correlative charges parameter of table
Indirect expense, the direct cost correlation function factor can be calculated, see Table 3 for details.
As pipe network total length L=30693m, after reasonability determines, it can solve to obtain optimal teams and groups' number to be 7.80, take 8 A, corresponding optimal project duration is 118 days.
The 3 correlation function factor of table and optimum results
The parameters such as corresponding duration, expense under different teams and groups' quantity, see Table 4 for details.
Correlative charges parameter under the different teams and groups' quantity of table 4
According to the functional relation of teams and groups' quantity, duration and expense, expense accounting and teams and groups' quantitative relation curve, duration can be obtained With expense, teams and groups-duration, expense relation curve, Fig. 2-Fig. 4 is seen.
After different factors influence number of days is summarized, can obtain the moon influences number of days, the moon using number of days, moon usage factor, is shown in Table 5.
It influences number of days table May, summarized using number of days, the moon usage factor moon
Note: rainfall is greater than 5 millimeters (08:00-20:00 precipitation) in rainfall statistics 12 hours and rainfall is greater than in 24 hours 10 millimeters of number of days takes wherein the larger value.
It influences number of days in different months, see Fig. 5 using number of days, usage factor distribution curve.As seen from Figure 5 around the Spring Festival 1, The rainy season of 2 months and the 4-9 month can be less using number of days, and minimum usage factor is 0.37, and average value 0.55, Schedule schema is larger; The 10-12 month and March usage factor it is larger, maximum usage factor be 0.84, average value 0.81, Schedule schema is smaller.To Mr. Yu When the absolute duration is 118 days, if going into operation respectively at October 1 and March 1, reality can be calculated in villages within the city's pipe-networks engineering The required duration is respectively 159 days and 211 days.
The present invention is first according to pipe network total length L, teams and groups' quantity (working face quantity) x, each teams and groups (each working face) Pipe network length (cyclic advance) l completed dailydThree parameters establish overhead cost, flat cost, total cost mathematical model;Secondly Restrictive condition is established, the correlation function factor involved in expense mathematical model is solved;Again in total cost mathematical model The x derivation for including, obtains teams and groups' quantity;Then the reasonable sex determination of calculated result is carried out, if comprising x in total cost mathematical model Second dervative is greater than 0, then resulting teams and groups' quantity is optimal resource input (optimal teams and groups' number) after derivation, and optimal teams and groups' number institute is right The duration answered is the optimal absolute duration;Outer risks factor is to applying when finally assessing different month operations using moon usage factor Work influence (moon usage factor it is smaller illustrate that Schedule schema is bigger, the moon usage factor bigger illustrate that Schedule schema is lower), and adopt The actually required duration is calculated with monthly average usage factor.
The present invention is using the resource of pipeline network construction, duration, expense as optimizing index, using Outer risks factor as evaluation pair As acquiring the parameters such as pipeline network construction overhead cost, flat cost, the mathematical model of total cost and moon usage factor.According to teams and groups' number Amount, duration and cost function relationship and the moon influence number of days, using number of days, usage factor, monthly average usage factor, and the expense that can obtain accounts for Than being influenced from teams and groups quantitative relation curves, duration and expense relation curve, teams and groups-duration and expense relation curve and different months Number of days, using number of days, usage factor distribution curve, required actual construction time, have method for solving simple, solve object be illustrated etc. it is excellent Point.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modification, equivalent replacement or improvement etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (2)

1. a kind of sewage network working sources optimization and Project Schedule Risk Analysis method, it is characterised in that:
First establish overhead cost, flat cost, total cost mathematical model;
Secondly, establishing restrictive condition;
Teams and groups' quantitative expression is calculated to total cost mathematical model again;
Then the reasonable sex determination of calculated result is carried out, is transferred to if rationally if result and solves in next step;
Influence of the Outer risks factor to construction when finally assessing different month operations, and obtain the actually required duration.
2. a kind of sewage network working sources optimization according to claim 1 and Project Schedule Risk Analysis method, feature exist In: the following steps are included:
Step 1: establishing the expense mathematical model in sewage network construction:
Indirect expense model is CI=β [L/ (ld·x)+11] (1);
Direct cost model is CD=a [L/ (ld·x)+11]2+b·[L/(ld·x)+11]+c (2);
Total cost mathematical model is C (x, ld)=a [L/ (ld·x)+11]2+(β+b)·[L/(ld·x)+11]+c (3);
Wherein: L --- pipe network total length is;X --- teams and groups' quantity;ld--- the pipe network length that each teams and groups complete daily;
B=2 (C2-C1)/(t2-t1);
t1--- minimum duration, day;
t2--- normal duration, day;
C1——t1Corresponding direct cost;
C2——t2Corresponding direct cost;
β --- indirect rate, β=(C`2-C`1)/(t2-t1);
C`1——t1Corresponding indirect expense, Wan Yuan;
C`2——t2Corresponding indirect expense, Wan Yuan;
Step 2: setting up the restrictive condition of investment teams and groups' quantity:
2000≤L/x≤10000 (4);
Step 3: the function factor that solving model is related to:
If very big, the minimum teams and groups quantity of investment is respectively x1、x3, the corresponding duration is respectively minimum duration t1, very big duration t3;Normal teams and groups' quantity is x2, the corresponding duration is normal duration t2;x1、x2Corresponding indirect expense is respectively C`1、C `2;Enable t2=(t1+t3)/2, then have:
x2=2x1·x3/(x1+x3) (5);
For indirect expense, can obtain:
CI=Cdj·t (6);
In formula, CI --- overhead cost, Wan Yuan;
Cdj--- the indirect expense occurred daily, Wan Yuan;
Know β=Cdj
Then have:
C`1=Cdj·t1(7);
C`2=Cdj·t2(8);
For daily flat cost, the functional relation of teams and groups' quantity and expense can be established:
Cdz=Kxld·Cd0(9);
In formula, Cdz--- daily direct cost, Wan Yuan;
Cd0--- it is the expense of every linear meter(lin.m.), Wan Yuan;
K --- direct cost coefficient related with compression duration size, is herein direct cost coefficient related with teams and groups' quantity, 1.0, x are taken when teams and groups' quantity is 11、x2Corresponding cost coefficient is respectively K1、K2
Formula (9) are substituted into direct cost relational expression:
CD=Cdz·t (10);
In formula, CD --- flat cost, Wan Yuan;
Very big flat cost can be obtained, normal flat cost is respectively as follows:
C1=K1·x1·ld·Cd0·t1(11);
C2=K1·x2·ld·Cd0·t2(12);
Step 4: calculating optimal resource input expression formula:
To the x derivation that formula (3) includes, C` (x, l are enabledd)x=0, it obtains:
X=-2aL/ [ld·(22a+b+β)] (13);
Step 5: the reasonable sex determination of calculated result:
The second dervative to formula (3) comprising x is sought, and (13) formula, function factor are substituted into, if C`` (x, ld)xx> 0 is set up, then (13) formula is optimal resource input, is transferred to and solves in next step;
Step 6: optimal resource input solves:
The function factor that model is related to substitutes into (13) formula to get optimal resource input, and the corresponding duration is optimal absolute Duration;
Step 7: Project Schedule Risk Analysis:
Assuming that moon number of days is dm, the moon is d by external action number of days0, the moon can be d using construction days1, moon usage factor is ε, the moon Mean utilization isOptimal teams and groups' quantity corresponding absolute duration is t, and the actually required duration is T, then has:
d1=dm-d0(14);
ε=(dm-d0)/dm(15);
d1=ε dm(16);
Month usage factor is smaller illustrates that Schedule schema is bigger, the moon usage factor bigger illustrate that Schedule schema is lower.
CN201910277262.5A 2019-04-08 2019-04-08 A kind of optimization of sewage network working sources and Project Schedule Risk Analysis method Pending CN110020753A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201910277262.5A CN110020753A (en) 2019-04-08 2019-04-08 A kind of optimization of sewage network working sources and Project Schedule Risk Analysis method
CN202311578386.XA CN117557052A (en) 2019-04-08 2019-04-08 Sewage pipe network construction resource investment optimization analysis method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910277262.5A CN110020753A (en) 2019-04-08 2019-04-08 A kind of optimization of sewage network working sources and Project Schedule Risk Analysis method

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN202311578386.XA Division CN117557052A (en) 2019-04-08 2019-04-08 Sewage pipe network construction resource investment optimization analysis method

Publications (1)

Publication Number Publication Date
CN110020753A true CN110020753A (en) 2019-07-16

Family

ID=67190770

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201910277262.5A Pending CN110020753A (en) 2019-04-08 2019-04-08 A kind of optimization of sewage network working sources and Project Schedule Risk Analysis method
CN202311578386.XA Pending CN117557052A (en) 2019-04-08 2019-04-08 Sewage pipe network construction resource investment optimization analysis method

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN202311578386.XA Pending CN117557052A (en) 2019-04-08 2019-04-08 Sewage pipe network construction resource investment optimization analysis method

Country Status (1)

Country Link
CN (2) CN110020753A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112257977A (en) * 2020-09-15 2021-01-22 合肥工业大学 Logistics project construction period optimization method and system with resource limitation under fuzzy man-hour

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112257977A (en) * 2020-09-15 2021-01-22 合肥工业大学 Logistics project construction period optimization method and system with resource limitation under fuzzy man-hour
CN112257977B (en) * 2020-09-15 2022-11-08 合肥工业大学 Logistics project construction period optimization method and system with resource limitation under fuzzy man-hour

Also Published As

Publication number Publication date
CN117557052A (en) 2024-02-13

Similar Documents

Publication Publication Date Title
CN103544533B (en) A kind of water diversion project water resource optimal allocation dynamic model constructing system
Meng et al. Fuzzy comprehensive evaluation model for water resources carrying capacity in Tarim River Basin, Xinjiang, China
CN104809516B (en) Irrigation areas Programming for Multiobjective Water Resources Optimal Allocation Model and its method for solving
Lv et al. Quantitative assessment of ecological compensation for groundwater overexploitation based on emergy theory
CN104050515A (en) Water resource allocation method based on annual sequential decision
Qiao et al. Assessing current and future soil erosion under changing land use based on InVEST and FLUS models in the Yihe River Basin, North China
Jiang et al. Study on the sediment and phosphorus flux processes under the effects of mega dams upstream of Yangtze River
CN110020753A (en) A kind of optimization of sewage network working sources and Project Schedule Risk Analysis method
CN103614997A (en) Earth borrowing method in process of highway construction
CN106934659A (en) Highway engineering material cost difference method of adjustment and system
CN106599560A (en) GIS-based slope collapse distribution statistical method
CN110378611A (en) Sponge control index based on GIS examines and appraisal procedure and system
Sun et al. Estimating water pollution and economic cost embodied in the mining industry: An interprovincial analysis in China
CN106021850A (en) Entropy weight TOPSIS method based earth excavation machine combination analysis method
CN115660456A (en) Ecological damage assessment accounting system method for mineral resource development
CN114897233A (en) Rural domestic sewage treatment mode optimization method based on spatial clustering improved algorithm
CN111539596A (en) Storage regulation capability evaluation method for drainage basin grey infrastructure
CN104217102A (en) Integrated method for calculating volume and load capacity of low pollution water in lake basin
CN109992904A (en) A kind of depression of karst area-spring system water equilibrium calculation method
Yang The Method and Basis of Dam Location Selection
Xu et al. The Effects of Water Resource Restrictions on Sustainable Development in Semi-Arid Regions: A Case Study of Tongliao City, Inner Mongolia
Mills Construction cost forecast model: model documentation and technical notes.
Rao et al. Research on Resettlement and Resettlement of Water Conservancy Projects
Yang et al. An improved index system of regional water ecological carrying capacity evaluation: a case study of Tieling City, China
Lin et al. Surface water quality assessment using hybrid multivariate statistical analysis and geographic information system based on integrated water quality index model for Maozhou River Basin, Guangdong, China

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination