Summary of the invention
The present invention provides a kind of bridge Sarasota construction method that construction technology is simple and convenient to operate, to solve upper existing bridge
The technical issues of beam Sarasota complicated construction technique.
According to an aspect of the present invention, a kind of bridge Sarasota construction method is provided, comprising the following steps:
Step S1, divides king-post, and determination pours segment, pours king-tower;
Step S2 configures tower crane and elevator outside two king-posts;
Step S4 sets up template system, builds hydraulic climbing formwork;
Step S5, layer-by-layer assembling reinforcement, embedded part fixed form, casting concrete construct king-tower.
On the basis of above scheme preferably, in the step S1, the king-post is divided into 22 segments, the height of the segment
Degree is 4.5m.
On the basis of above scheme preferably, it is 4.5m that the maximum of the creeping formwork, which pours height,.
On the basis of above scheme preferably, the outside of the king-post is arranged in the tower crane, and the brachium of the tower crane is extremely
It is less 45m.
On the basis of above scheme preferably, template system is by panel, wooden frame, back cord and connector group in the step S4
At.
On the basis of above scheme preferably, the hydraulic climbing formwork builds step and includes:
Step S3.1 installs attached wall hanging seat, and lifts heavy duty tripod;
Step S3.2, installation template and rear moving device install upper frame, and pour upper layer concrete, with lift rail.
On the basis of above scheme preferably, when installing attached wall hanging seat, built-in fitting, the attached wall hanging seat are installed in attached wall
It is installed on the built-in fitting by high-strength bolt.
A kind of bridge Sarasota construction method of the invention is divided into multiple segments by carrying out king-post, is poured paragraph by paragraph
It builds, and cooperates tower crane, elevator and template system, carry out assembling reinforcement, poured.
A kind of bridge Sarasota construction method of the invention, construction technology is simple, and high in machining efficiency, the present invention effectively improves
The speed of application that the old rope of existing cable-stayed bridge is removed and new rope is set up, it is ensured that the safety for changing rope process also solves because of beam-ends
Operating space is limited, and new rope is difficult to the problem of setting up caused by can not installing pulling equipment.
Specific embodiment
With reference to the accompanying drawings and examples, specific embodiments of the present invention will be described in further detail.Implement below
Example is not intended to limit the scope of the invention for illustrating the present invention.
Refering to Figure 1, the present invention provides a kind of bridge Sarasota construction methods, comprising the following steps:
Step S1, divides king-post, and determination pours segment, pours king-tower;
Step S2 configures tower crane and elevator outside two king-posts;
Step S4 sets up template system, builds hydraulic climbing formwork;
Step S5, layer-by-layer assembling reinforcement, embedded part fixed form, casting concrete construct king-tower.
Wherein, in step S1, the king-post is divided into 22 segments, and the height of segment is 4.5m.Carrying out king-post segment
When division, buttress, three kinds of lower king-post strut intersections are comprehensively considered slowly.
In casting process, it is 4.5m that the maximum of creeping formwork of the present invention, which pours height, and the outside of king-post is arranged in tower crane, and
The brachium of tower crane is at least 45m.Preferably, a Tai Zhonglianchong section TC7013-10 type tower crane is respectively configured on the outside of 2 king-posts,
Downstream side tower crane brachium 60m, can cover steel bar meter field;Upstream side tower crane brachium 45m;To guarantee group towers work safety, 60m arm
Long tower crane is set as high-order tower, and the safe height difference between 2 tower cranes is not less than 10m.Preferably, TC7013-10 type tower crane is most
Big hoist 10t, can meet creeping formwork frame body and overarm brace lifting requirements.
The present invention respectively configures a construction elevator in each king-post, and elevator can be straight with king-post clear spacing 3m in big mileage side
It connects and is docked with climbing formwork for construction platform, attachment is set between king-post, attachment spacing is not more than 9m.
Further, template system is made of panel, wooden frame, back cord and connector in step S4 of the invention.
Wherein, hydraulic climbing formwork builds step and includes:
Step S3.1 installs attached wall hanging seat, and lifts heavy duty tripod;
Step S3.2, installation template and rear moving device install upper frame, and pour upper layer concrete, with lift rail.
Wherein, the present invention should be noted following item when hydraulic climbing formwork is built:
(1) climbing form system attached wall bolt embedded part necessary position when embedded is accurate and on same absolute altitude, embedded ribs
For high strength wire, overcurrent or oxygen is forbidden to cut during installation;
(2) template and climbing frame scaffold board are timber structure, and fire safety of the climbing form system in construction is particularly important, therefore
It is required that climbing form system is in entire work progress, every layer of platform is respectively provided with no less than four fire extinguishers, high pressure water with climbing frame liter
High heel into and purchase fire water box, while on platform be arranged sandbox for smoker use;
(3) climbing frame surrounding will hang close hole safety net, to prevent falling object from high altitude, and reserved measurement observation sight channel;
(4) lighting apparatus is installed on climbing frame, special messenger is responsible for keeping an eye on.
On the basis of above scheme preferably, when installing attached wall hanging seat, built-in fitting, the attached wall hanging seat are installed in attached wall
It is installed on the built-in fitting by high-strength bolt.
A kind of bridge Sarasota construction method of the invention is divided into multiple segments by carrying out king-post, is poured paragraph by paragraph
It builds, and cooperates tower crane, elevator and template system, carry out assembling reinforcement, poured.
A kind of bridge Sarasota construction method of the invention, construction technology is simple, and high in machining efficiency, the present invention effectively improves
The speed of application that the old rope of existing cable-stayed bridge is removed and new rope is set up, it is ensured that the safety for changing rope process also solves because of beam-ends
Operating space is limited, and new rope is difficult to the problem of setting up caused by can not installing pulling equipment.
Finally, the present processes are only preferable embodiment, it is not intended to limit the scope of the present invention.It is all
Within the spirit and principles in the present invention, any modification, equivalent replacement, improvement and so on should be included in protection of the invention
Within the scope of.