CN109989350A - A kind of bridge Sarasota construction method - Google Patents

A kind of bridge Sarasota construction method Download PDF

Info

Publication number
CN109989350A
CN109989350A CN201910234350.7A CN201910234350A CN109989350A CN 109989350 A CN109989350 A CN 109989350A CN 201910234350 A CN201910234350 A CN 201910234350A CN 109989350 A CN109989350 A CN 109989350A
Authority
CN
China
Prior art keywords
king
construction method
bridge
tower
post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910234350.7A
Other languages
Chinese (zh)
Inventor
蔡仁杰
袁传军
刘重刚
梅军
王昌裕
柳细才
尚彩霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Engineering Co Ltd of China Railway Seventh Group Co Ltd
Original Assignee
China Railway Seventh Group Co Ltd
Wuhan Engineering Co Ltd of China Railway Seventh Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Seventh Group Co Ltd, Wuhan Engineering Co Ltd of China Railway Seventh Group Co Ltd filed Critical China Railway Seventh Group Co Ltd
Priority to CN201910234350.7A priority Critical patent/CN109989350A/en
Publication of CN109989350A publication Critical patent/CN109989350A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

A kind of bridge Sarasota construction method of the invention, including king-post is divided, determination pours segment, pours king-tower;Tower crane and elevator are configured outside two king-posts;Template system is set up, hydraulic climbing formwork is built;Layer-by-layer assembling reinforcement, embedded part fixed form, casting concrete construct king-tower.The present invention is divided into multiple segments by carrying out king-post, carries out paragraph by paragraph pouring, and cooperate tower crane, elevator and template system, assembling reinforcement is poured.A kind of bridge Sarasota construction method of the invention, construction technology is simple, it is high in machining efficiency, effectively improve the speed of application that the old rope of existing cable-stayed bridge is removed and new rope is set up, ensure the safety for changing rope process, it also solves because beam-ends operating space is limited, new rope is difficult to the problem of setting up caused by can not installing pulling equipment.

Description

A kind of bridge Sarasota construction method
Technical field
The present invention relates to pontic construction technologies, more particularly, to a kind of bridge Sarasota construction method.
Background technique
With the rapid economic development in our country, the construction of traffic infrastructure is also grown rapidly, occur at the same time More and more span bridge construction engineerings.
It is the most common construction method of Large Span Structure of Arch bridge construction that arch bridge cantilever button, which hangs method construction, is applied when using the method The lower end of working hour, usual knotted rope and anchor cable is anchored at arch section front end respectively and buckles at point and rear anchorage, the upper end of knotted rope and anchor cable It is anchored at the anchor beam both ends on knotted rope pylon.It is connected by screw bolts or welds between anchor beam and knotted rope pylon.
In the construction process, existing bridge Sarasota construction technology is cumbersome, it is difficult to meet needs of production, it is therefore, anxious A kind of bridge Sarasota construction method need to be invented.
Summary of the invention
The present invention provides a kind of bridge Sarasota construction method that construction technology is simple and convenient to operate, to solve upper existing bridge The technical issues of beam Sarasota complicated construction technique.
According to an aspect of the present invention, a kind of bridge Sarasota construction method is provided, comprising the following steps:
Step S1, divides king-post, and determination pours segment, pours king-tower;
Step S2 configures tower crane and elevator outside two king-posts;
Step S4 sets up template system, builds hydraulic climbing formwork;
Step S5, layer-by-layer assembling reinforcement, embedded part fixed form, casting concrete construct king-tower.
On the basis of above scheme preferably, in the step S1, the king-post is divided into 22 segments, the height of the segment Degree is 4.5m.
On the basis of above scheme preferably, it is 4.5m that the maximum of the creeping formwork, which pours height,.
On the basis of above scheme preferably, the outside of the king-post is arranged in the tower crane, and the brachium of the tower crane is extremely It is less 45m.
On the basis of above scheme preferably, template system is by panel, wooden frame, back cord and connector group in the step S4 At.
On the basis of above scheme preferably, the hydraulic climbing formwork builds step and includes:
Step S3.1 installs attached wall hanging seat, and lifts heavy duty tripod;
Step S3.2, installation template and rear moving device install upper frame, and pour upper layer concrete, with lift rail.
On the basis of above scheme preferably, when installing attached wall hanging seat, built-in fitting, the attached wall hanging seat are installed in attached wall It is installed on the built-in fitting by high-strength bolt.
A kind of bridge Sarasota construction method of the invention is divided into multiple segments by carrying out king-post, is poured paragraph by paragraph It builds, and cooperates tower crane, elevator and template system, carry out assembling reinforcement, poured.
A kind of bridge Sarasota construction method of the invention, construction technology is simple, and high in machining efficiency, the present invention effectively improves The speed of application that the old rope of existing cable-stayed bridge is removed and new rope is set up, it is ensured that the safety for changing rope process also solves because of beam-ends Operating space is limited, and new rope is difficult to the problem of setting up caused by can not installing pulling equipment.
Detailed description of the invention
Fig. 1 is the process flow chart of bridge Sarasota construction method of the invention.
Specific embodiment
With reference to the accompanying drawings and examples, specific embodiments of the present invention will be described in further detail.Implement below Example is not intended to limit the scope of the invention for illustrating the present invention.
Refering to Figure 1, the present invention provides a kind of bridge Sarasota construction methods, comprising the following steps:
Step S1, divides king-post, and determination pours segment, pours king-tower;
Step S2 configures tower crane and elevator outside two king-posts;
Step S4 sets up template system, builds hydraulic climbing formwork;
Step S5, layer-by-layer assembling reinforcement, embedded part fixed form, casting concrete construct king-tower.
Wherein, in step S1, the king-post is divided into 22 segments, and the height of segment is 4.5m.Carrying out king-post segment When division, buttress, three kinds of lower king-post strut intersections are comprehensively considered slowly.
In casting process, it is 4.5m that the maximum of creeping formwork of the present invention, which pours height, and the outside of king-post is arranged in tower crane, and The brachium of tower crane is at least 45m.Preferably, a Tai Zhonglianchong section TC7013-10 type tower crane is respectively configured on the outside of 2 king-posts, Downstream side tower crane brachium 60m, can cover steel bar meter field;Upstream side tower crane brachium 45m;To guarantee group towers work safety, 60m arm Long tower crane is set as high-order tower, and the safe height difference between 2 tower cranes is not less than 10m.Preferably, TC7013-10 type tower crane is most Big hoist 10t, can meet creeping formwork frame body and overarm brace lifting requirements.
The present invention respectively configures a construction elevator in each king-post, and elevator can be straight with king-post clear spacing 3m in big mileage side It connects and is docked with climbing formwork for construction platform, attachment is set between king-post, attachment spacing is not more than 9m.
Further, template system is made of panel, wooden frame, back cord and connector in step S4 of the invention.
Wherein, hydraulic climbing formwork builds step and includes:
Step S3.1 installs attached wall hanging seat, and lifts heavy duty tripod;
Step S3.2, installation template and rear moving device install upper frame, and pour upper layer concrete, with lift rail.
Wherein, the present invention should be noted following item when hydraulic climbing formwork is built:
(1) climbing form system attached wall bolt embedded part necessary position when embedded is accurate and on same absolute altitude, embedded ribs For high strength wire, overcurrent or oxygen is forbidden to cut during installation;
(2) template and climbing frame scaffold board are timber structure, and fire safety of the climbing form system in construction is particularly important, therefore It is required that climbing form system is in entire work progress, every layer of platform is respectively provided with no less than four fire extinguishers, high pressure water with climbing frame liter High heel into and purchase fire water box, while on platform be arranged sandbox for smoker use;
(3) climbing frame surrounding will hang close hole safety net, to prevent falling object from high altitude, and reserved measurement observation sight channel;
(4) lighting apparatus is installed on climbing frame, special messenger is responsible for keeping an eye on.
On the basis of above scheme preferably, when installing attached wall hanging seat, built-in fitting, the attached wall hanging seat are installed in attached wall It is installed on the built-in fitting by high-strength bolt.
A kind of bridge Sarasota construction method of the invention is divided into multiple segments by carrying out king-post, is poured paragraph by paragraph It builds, and cooperates tower crane, elevator and template system, carry out assembling reinforcement, poured.
A kind of bridge Sarasota construction method of the invention, construction technology is simple, and high in machining efficiency, the present invention effectively improves The speed of application that the old rope of existing cable-stayed bridge is removed and new rope is set up, it is ensured that the safety for changing rope process also solves because of beam-ends Operating space is limited, and new rope is difficult to the problem of setting up caused by can not installing pulling equipment.
Finally, the present processes are only preferable embodiment, it is not intended to limit the scope of the present invention.It is all Within the spirit and principles in the present invention, any modification, equivalent replacement, improvement and so on should be included in protection of the invention Within the scope of.

Claims (7)

1. a kind of bridge Sarasota construction method, which comprises the following steps:
Step S1, divides king-post, and determination pours segment, pours king-tower;
Step S2 configures tower crane and elevator outside two king-posts;
Step S4 sets up template system, builds hydraulic climbing formwork;
Step S5, layer-by-layer assembling reinforcement, embedded part fixed form, casting concrete construct king-tower.
2. a kind of bridge Sarasota construction method as described in claim 1, which is characterized in that in the step S1, the king-post 22 segments are divided into, the height of the segment is 4.5m.
3. a kind of bridge Sarasota construction method as described in claim 1, which is characterized in that the maximum of the creeping formwork pours height For 4.5m.
4. a kind of bridge Sarasota construction method as claimed in claim 3, which is characterized in that the tower crane is arranged in the king-post Outside, and the brachium of the tower crane is at least 45m.
5. a kind of bridge Sarasota construction method as claimed in claim 4, which is characterized in that in the step S4 template system by Panel, wooden frame, back cord and connector composition.
6. a kind of bridge Sarasota construction method as described in claim 1, which is characterized in that the hydraulic climbing formwork builds step packet It includes:
Step S3.1 installs attached wall hanging seat, and lifts heavy duty tripod;
Step S3.2, installation template and rear moving device install upper frame, and pour upper layer concrete, with lift rail.
7. a kind of bridge Sarasota construction method as claimed in claim 6, which is characterized in that when installing attached wall hanging seat, attached Built-in fitting is installed within the walls, the attached wall hanging seat is installed on the built-in fitting by high-strength bolt.
CN201910234350.7A 2019-03-26 2019-03-26 A kind of bridge Sarasota construction method Pending CN109989350A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910234350.7A CN109989350A (en) 2019-03-26 2019-03-26 A kind of bridge Sarasota construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910234350.7A CN109989350A (en) 2019-03-26 2019-03-26 A kind of bridge Sarasota construction method

Publications (1)

Publication Number Publication Date
CN109989350A true CN109989350A (en) 2019-07-09

Family

ID=67131631

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910234350.7A Pending CN109989350A (en) 2019-03-26 2019-03-26 A kind of bridge Sarasota construction method

Country Status (1)

Country Link
CN (1) CN109989350A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112942106A (en) * 2021-01-13 2021-06-11 中铁七局集团武汉工程有限公司 Construction method of portal cable tower
CN112942107A (en) * 2021-01-13 2021-06-11 中铁七局集团武汉工程有限公司 Hydraulic creeping formwork construction process in cable tower construction process
CN113684758A (en) * 2021-09-07 2021-11-23 中国铁建大桥工程局集团有限公司 Self-anchored suspension bridge construction auxiliary device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1912314A (en) * 2006-08-28 2007-02-14 杨秋利 Automatic hydraulic climbing shuttering
JP2010048060A (en) * 2008-08-25 2010-03-04 Shimizu Corp Construction method of structure
CN103741601A (en) * 2013-06-28 2014-04-23 中交第三航务工程局有限公司 Tower, beam and cable synchronous bridge forming technology
CN105839536A (en) * 2016-04-01 2016-08-10 中铁大桥局集团第五工程有限公司 Construction method of cable-stayed bridge pylon
CN106948267A (en) * 2017-04-13 2017-07-14 中铁四局集团市政工程有限公司 A kind of memorial archway bar formula bridge cable tower king-post method for synchronously constructing

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1912314A (en) * 2006-08-28 2007-02-14 杨秋利 Automatic hydraulic climbing shuttering
JP2010048060A (en) * 2008-08-25 2010-03-04 Shimizu Corp Construction method of structure
CN103741601A (en) * 2013-06-28 2014-04-23 中交第三航务工程局有限公司 Tower, beam and cable synchronous bridge forming technology
CN105839536A (en) * 2016-04-01 2016-08-10 中铁大桥局集团第五工程有限公司 Construction method of cable-stayed bridge pylon
CN106948267A (en) * 2017-04-13 2017-07-14 中铁四局集团市政工程有限公司 A kind of memorial archway bar formula bridge cable tower king-post method for synchronously constructing

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
谢喜峰: "洞庭湖特大桥斜拉桥主塔施工关键技术", 《科技创新与应用》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112942106A (en) * 2021-01-13 2021-06-11 中铁七局集团武汉工程有限公司 Construction method of portal cable tower
CN112942107A (en) * 2021-01-13 2021-06-11 中铁七局集团武汉工程有限公司 Hydraulic creeping formwork construction process in cable tower construction process
CN112942107B (en) * 2021-01-13 2023-02-17 中铁七局集团武汉工程有限公司 Hydraulic creeping formwork construction process in cable tower construction process
CN113684758A (en) * 2021-09-07 2021-11-23 中国铁建大桥工程局集团有限公司 Self-anchored suspension bridge construction auxiliary device
CN113684758B (en) * 2021-09-07 2023-12-05 中国铁建大桥工程局集团有限公司 Self-anchored suspension bridge construction auxiliary device

Similar Documents

Publication Publication Date Title
CN101476410B (en) Mounting and demounting method for roof plate formwork support platform of concrete silo
CN109989350A (en) A kind of bridge Sarasota construction method
CN201221193Y (en) High altitude packway ceiling construction operating platform
CN106012852B (en) Support integrally falls frame construction method
CN103375023A (en) Attached type lifting scaffold
CN104477736A (en) Shaft elevator installation method
CN205036072U (en) A shaped steel formwork support that encorbelments for high altitude structure of encorbelmenting
CN208088097U (en) A kind of three-tower suspension bridge erection of main beam constructing structure
CN202530769U (en) Large span steel structure high-altitude subsection hoisting support system
CN111021749A (en) Simple hoisting mechanism for bare concrete exterior wall cladding and construction method thereof
CN209873584U (en) Hang basket template and demolish device
CN109797649A (en) A kind of tool car Hoisting Program not influencing bridge deck traffic
CN207244452U (en) A kind of suspension bridge vice saddle adjusting apparatus in place
CN102733608B (en) Construction method for spray head layer of granulation tower
CN201176566Y (en) External tower type retractable construction platform at end of staying cable tower
CN109881585A (en) A kind of assembly flow shop platform for high pier construction
CN103288002A (en) Simple combination portal upper-air heavy-article hoisting device
CN106522541B (en) A kind of template suspension centre spandrel girder of steel platform and the hanging method of template system
CN111519545A (en) Pier and capping beam integrated construction platform and construction method thereof
CN104404888A (en) Large hoisting system allowing gradient to be adjusted in air and application
CN201714056U (en) Truss-type operating platform
CN204212065U (en) Bridge crossing anticollision barrier punching block erection equipment
CN110040632A (en) A kind of segmental hoisting construction method of large span section steel beam
CN202039299U (en) Totally-closed hanging basket
CN107119561A (en) A kind of basket-hanging bridge maintaining job platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20200814

Address after: 430000 6 Bridge Road, New Bridge District, Jiangxia District, Wuhan, Hubei

Applicant after: WUHAN ENGINEERING CO., LTD., CHINA RAILWAY 7TH BUREAU GROUP Co.,Ltd.

Address before: 450000 No. 1225 East navigation road, Henan, Zhengzhou

Applicant before: CHINA RAILWAY SEVENTH GROUP Co.,Ltd.

Applicant before: WUHAN ENGINEERING CO., LTD., CHINA RAILWAY 7TH BUREAU GROUP Co.,Ltd.

TA01 Transfer of patent application right