CN109978355A - A kind of wisdom building site patrolling and checking management system - Google Patents

A kind of wisdom building site patrolling and checking management system Download PDF

Info

Publication number
CN109978355A
CN109978355A CN201910198197.7A CN201910198197A CN109978355A CN 109978355 A CN109978355 A CN 109978355A CN 201910198197 A CN201910198197 A CN 201910198197A CN 109978355 A CN109978355 A CN 109978355A
Authority
CN
China
Prior art keywords
management
unit
building site
patrolling
checking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910198197.7A
Other languages
Chinese (zh)
Inventor
蔡婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Wishbuild Information Technology Co Ltd
Original Assignee
Shanghai Wishbuild Information Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Wishbuild Information Technology Co Ltd filed Critical Shanghai Wishbuild Information Technology Co Ltd
Priority to CN201910198197.7A priority Critical patent/CN109978355A/en
Publication of CN109978355A publication Critical patent/CN109978355A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Marketing (AREA)
  • Educational Administration (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to a kind of wisdom building site patrolling and checking management systems, including background server interconnected and mobile client, background server is further connected with foreground control terminal, the background server includes class administrative unit, SIM system information management unit, district management unit, structure managing unit, work management unit, role management unit and data record unit, and the mobile client includes the building site inspection management application program with the transmission of background service end data;The system further includes the video monitor unit that building-site is arranged in, and the video monitor unit is connect with background server.Compared with prior art, the present invention is by carrying out integration for each management module, it solves the disadvantages of conventional items building site management is time-consuming and laborious, at high cost, result is inaccurate, and can preferably meet the demand of user in schemes generation, obtain more targeted data information.

Description

A kind of wisdom building site patrolling and checking management system
Technical field
The present invention relates to project management technique fields, more particularly, to a kind of wisdom building site patrolling and checking management system.
Background technique
Wisdom building site refers to information-based means, carries out careful design to engineering project by three dimensional design platform and applies Work simulation, while work progress management is surrounded, establish the project under construction information metaplasia of interconnection collaboration, intelligence production, scientific management State circle realizes the management of engineering construction visual intelligent, to improve project management information level and realize green construction and ecology It builds.
At present in terms of the inspection management of building site, usually staff carries out the project data carried out using file The characteristics of filing, the later period is according to new projects, finds similar project by manually pressing from both sides in data bank in archive file, by project The existing data of middle all or part is returned in a file to be used for reference.This way is handwork under pure line, cannot The intuitive design for carrying out scheme, data are not standardized in-depth without product line or item types concept, data in advance, so that Project building site management is time-consuming and laborious, at high cost, result is inaccurate.
Summary of the invention
It is an object of the present invention to overcome the above-mentioned drawbacks of the prior art and provide a kind of inspections of wisdom building site Management system.
The purpose of the present invention can be achieved through the following technical solutions:
A kind of wisdom building site patrolling and checking management system, including background server interconnected and mobile client, backstage take Business end is further connected with foreground control terminal, and the background server includes class administrative unit, SIM system information management unit, district management list Member, structure managing unit, work management unit, role management unit and data record unit, the mobile client include with The building site inspection management application program of background service end data transmission;The system further includes the video monitoring that building-site is arranged in Unit, the video monitor unit are connect with background server.
Preferably, the class administrative unit is for creating and managing process, equipment, worker, material, component, component process Data content.
Preferably, the SIM system information management unit for management module, department, user, system log, acess control, The data information of access address statistics.
Preferably, the district management unit includes architectural control module and workshop section's management module.
Preferably, the structure managing unit includes component groups management module and component management module.
Preferably, the work management unit is for managing WBS structure, key job chain, work relationship figure, job information Table.
Preferably, the role management unit is used for management role relational graph, mission bit stream table, task component groups relationship Table.
Preferably, the data record unit is for storing and managing building-site photo, inspection content, inspection log.
Compared with prior art, the invention has the following advantages that
1, this system by by each management module carry out integration, solve conventional items building site management it is time-consuming, it is laborious, At high cost, the disadvantages of result is inaccurate, and can preferably meet in schemes generation the demand of user, it obtains more targeted Data information.
2, it by integrating precision data, expert team, professional service in identical platform, is provided in the form of centralization for client Software, that is, service formula omnibearing management auxiliary experience;By diversified forms such as wechat, webpages, stays indoors and realize strange land project Long-range easily control, experiences specialized management ancillary service.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of present system;
Fig. 2 is the process for using figure of present system.
Specific embodiment
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.The present embodiment is with technical solution of the present invention Premised on implemented, the detailed implementation method and specific operation process are given, but protection scope of the present invention is not limited to Following embodiments.
Embodiment
As shown in Figure 1, the application proposes a kind of wisdom building site patrolling and checking management system, by project scene true progress, people Machine material puts into each management module such as situation, duration planning, quality safety data, monitoring and carries out integration, eliminates management Information island in the process;Project informationization management database is established based on live truthful data, provides number for big data analysis According to basis.
This system includes background server and mobile client interconnected, and background server is further connected with foreground control terminal And video monitor unit, video monitor unit are arranged in building-site.
Background server includes:
Class administrative unit: for creating and managing the data content of process, equipment, worker, material, component, component process;
SIM system information management unit: for management module, department, user, system log, acess control, access address system The data information of meter;
District management unit: including architectural control module and workshop section's management module;
Structure managing unit: including component groups management module and component management module;
Work management unit: for managing WBS structure, key job chain, work relationship figure, job information table;
Role management unit: management role relational graph, mission bit stream table, task component groups relation table are used for;
Data record unit: for storing and managing building-site photo, inspection content, inspection log.
It further include quality information table, safety information table and subcontracting entity information table in background server.
Foreground control terminal includes project general-circumstances, fine-grained management, intelligent management, safety problem, quality problems, video prison The function selecting modules such as control, labor management.Foreground control terminal avoids the delay of crucial duration by construction project time management and control, mentions High efficiency;It is managed by construction project resource, artificial, mechanical, material distribution of making rational planning for is accomplished to make the best use of everything;It is logical The control of construction project quality safety is crossed, confrontation peace problem carries out overall process tracking, accomplishes to find the problem in time, feedback problem, solution Certainly problem;
Mobile client includes the building site inspection management application program with the transmission of background service end data.
In the present embodiment, database uses MYSQL database server.File system uses mogilefs distributed document System.Search engine uses solr distributed full-text search system.Core system, WebServer, gateway interface, data scrubbing Service arrangement is in (SuSE) Linux OS.System uses all on-line online interaction mode, avoids data caused by off line business inaccurate Really, not in real time;Using sensitive data and critical data (SHA-256) algorithm for encryption, file transmission carries out (MAC) verification, guarantees The reliability of data transmission.
The process for using of this system is as shown in Fig. 2, include following sections:
1, safety problem process
1) site safety problem uploads: for site safety problem, by mobile client by the specifying information of problem and Image data typing uploads to background server;
2) safety problem delivery responsibility people: user is distributed to responsible person concerned to the safety problem of upload and reminds rectification;
3) rectification is handled: person liable goes to scene to rectify and improve after receiving distribution instruction, and scene is taken pictures after rectification And upload rectification achievement;
4) rectify and improve results review: user audits achievement after rectification, and by then being passed through, audit does not pass through for audit Delivery responsibility people time limit is rectified and improved again.
2, quality problems process
1) quality in site problem uploads: for quality in site problem, by mobile client by the specifying information of problem and Image data typing uploads to background server;
2) quality problems delivery responsibility people: user is distributed to responsible person concerned to the quality problems of upload and reminds rectification;
3) rectification is handled: person liable goes to scene to rectify and improve after receiving distribution instruction, and scene is taken pictures after rectification And upload rectification achievement;
4) rectify and improve results review: user audits achievement after rectification, and by then being passed through, audit does not pass through for audit Delivery responsibility people time limit is rectified and improved again.
3, task workflow
1) user splits project schedule plan according to WBS job analysis logic on backstage;
2) by project work input system, and the acquisition module of mobile client is combined to record project scene actual progress Enter;The progress msg of the project general-circumstances modules exhibit project entirety of control terminal on foreground, including it is planned time, the real time, pre- Between timing and progress percentage information;
3) in the progress msg of each level of fine-grained management modules exhibit project (branch's subitem) work, including when plan Between, real time, scheduled time and progress percentage information;
4) delay correction plan, resource and cost needed for calculating correction according to existing production efficiency parameter, Added Management Personnel's decision;
5) work arrangement has been completed, as unit of construction unit, " completion " Shipping Options Page has been clicked, is being moved according to user The project scene actual progress situation of dynamic client acquisition is shown the subdivisional work work completed.

Claims (8)

1. a kind of wisdom building site patrolling and checking management system, including background server interconnected and mobile client, background service End be further connected with foreground control terminal, which is characterized in that the background server include class administrative unit, SIM system information management unit, District management unit, structure managing unit, work management unit, role management unit and data record unit, the mobile visitor Family end includes the building site inspection management application program with the transmission of background service end data;The system further includes being arranged in building-site Video monitor unit, the video monitor unit connect with background server.
2. a kind of wisdom building site patrolling and checking management system according to claim 1, which is characterized in that the class administrative unit is used In the data content for creating and managing process, equipment, worker, material, component, component process.
3. a kind of wisdom building site patrolling and checking management system according to claim 1, which is characterized in that the SIM system information management The data information that unit is counted for management module, department, user, system log, acess control, access address.
4. a kind of wisdom building site patrolling and checking management system according to claim 1, which is characterized in that the district management unit Including architectural control module and workshop section's management module.
5. a kind of wisdom building site patrolling and checking management system according to claim 1, which is characterized in that the structure managing unit Including component groups management module and component management module.
6. a kind of wisdom building site patrolling and checking management system according to claim 1, which is characterized in that the work management unit For managing WBS structure, key job chain, work relationship figure, job information table.
7. a kind of wisdom building site patrolling and checking management system according to claim 1, which is characterized in that the role management unit For management role relational graph, mission bit stream table, task component groups relation table.
8. a kind of wisdom building site patrolling and checking management system according to claim 1, which is characterized in that the data record unit For storing and managing building-site photo, inspection content, inspection log.
CN201910198197.7A 2019-03-15 2019-03-15 A kind of wisdom building site patrolling and checking management system Pending CN109978355A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910198197.7A CN109978355A (en) 2019-03-15 2019-03-15 A kind of wisdom building site patrolling and checking management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910198197.7A CN109978355A (en) 2019-03-15 2019-03-15 A kind of wisdom building site patrolling and checking management system

Publications (1)

Publication Number Publication Date
CN109978355A true CN109978355A (en) 2019-07-05

Family

ID=67079074

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910198197.7A Pending CN109978355A (en) 2019-03-15 2019-03-15 A kind of wisdom building site patrolling and checking management system

Country Status (1)

Country Link
CN (1) CN109978355A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112200535A (en) * 2020-09-27 2021-01-08 河南省交通规划设计研究院股份有限公司 Highway engineering project engineering system of patrolling and examining based on BIM technique

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107622355A (en) * 2017-09-30 2018-01-23 长江勘测规划设计研究有限责任公司 Project cluster work progress digital management system and method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107622355A (en) * 2017-09-30 2018-01-23 长江勘测规划设计研究有限责任公司 Project cluster work progress digital management system and method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨晓毅 等: "基于BIM技术的特大型多方协作智慧管理", 《土木建筑工程信息技术》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112200535A (en) * 2020-09-27 2021-01-08 河南省交通规划设计研究院股份有限公司 Highway engineering project engineering system of patrolling and examining based on BIM technique

Similar Documents

Publication Publication Date Title
US10860861B2 (en) Data transmission system of safety patrol on construction project site based on “internet plus”
CN108009758B (en) BIM-based intelligent management method for field construction materials
Liu et al. Automatically updating maintenance information from a BIM database
CN104951905A (en) Equipment dynamic ledger management system
Zhong et al. Towards Physical Internet-enabled prefabricated housing construction in Hong Kong
CN102646220A (en) Multi-network-based manufacturing data real-time process management system and management method in ship manufacturing industry
CN113065756A (en) BIM-based project supervision informatization management system
CN106845834A (en) Transmission line of electricity hidden danger management method and system based on mobile phone A PP
EP3933744A1 (en) Blockchain-based industrial manufacturing resource sharing method, device and system
CN108154340A (en) Prefabricated component informationization management system based on BIM cloud platforms
CN105023117A (en) Electrified detection standardized operation management system based on mobile and cloud computing technologies
CN102142108A (en) Information processing method of corresponding relationship among materials and equipment suitable for power system
CN105184519A (en) Standardized safety operation tracing management system
CN110991886A (en) Community task processing method, device, equipment and medium
CN109978355A (en) A kind of wisdom building site patrolling and checking management system
CN105447613A (en) Enterprise intelligent information system
CN114819511A (en) Enterprise strategic object landing execution and performance management system and method
CN109360291A (en) A kind of construction machinery equipment inspection service system
Ying et al. Survey of the research of ICT applications in the AEC industry: A view from two mainstream journals
CN110097247A (en) A kind of cost data gathering system based on Internet technology
Fuqiang et al. Research on MES system based on production management of railway vehicle reducer
TWI703519B (en) Green building engineering mechanical and electrical equipment performance inspection management system
Wang et al. Design and Implementation of Mobile Workflow Function Based on Power Grid Inspection Scenario
CN114253744A (en) System and method for seamless data butt joint based on ERP and MES
KASHIRIPOOR et al. PROPER AUTOMATED MONITORING METHODOLOGY IN PROGRESS OF CONSTRUCTION

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination