CN109973125A - A kind of seabed tunnel laying equipment - Google Patents

A kind of seabed tunnel laying equipment Download PDF

Info

Publication number
CN109973125A
CN109973125A CN201910292739.7A CN201910292739A CN109973125A CN 109973125 A CN109973125 A CN 109973125A CN 201910292739 A CN201910292739 A CN 201910292739A CN 109973125 A CN109973125 A CN 109973125A
Authority
CN
China
Prior art keywords
sea bed
immersed tube
running track
assembly
wheel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910292739.7A
Other languages
Chinese (zh)
Other versions
CN109973125B (en
Inventor
蔡佳恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910292739.7A priority Critical patent/CN109973125B/en
Publication of CN109973125A publication Critical patent/CN109973125A/en
Application granted granted Critical
Publication of CN109973125B publication Critical patent/CN109973125B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention relates to seabed tunnel technical fields, especially a kind of seabed tunnel is laid with equipment, calm down mechanism and mechanism running track including immersed tube assembly, equipment conveying mechanism assembly, two elevating mechanism assemblies, sea bed walking mechanism, sea bed, the equipment conveying mechanism assembly is located at the top of immersed tube assembly, the mechanism running track is installed on the top of equipment conveying mechanism assembly, the sea bed calms down the right end that mechanism is installed on mechanism running track, and the elevating mechanism assembly is installed on the upper surface of mechanism running track.The present invention uses rail mounted immersed tube tunnel, the track of track fixed equipment operation, prevent seabed ocean current from causing device shifting, the installation equipment for carrying immersed tube to be installed can be run on having installed the immersed tube that do not bury, such installation method accelerates transport, so that installation is rapider, sea bed calms down mechanism, for calming down sea bed, so that sea bed meets municipal administration and is laid with requirement.

Description

A kind of seabed tunnel laying equipment
Technical field
The present invention relates to seabed tunnel technical fields more particularly to a kind of seabed tunnel to be laid with equipment.
Background technique
Traditional immersed tube tunnel laying method needs to excavate sea bed with dredger, is dragged to Submersed type tunnel component with towboat Predetermined position is deposited on ground, and with locking material consolidating component, material is backfilled around Submersed type tunnel component, places and protects It protects rock layers and protects component, repair sea bed, in order to keep the process of deployment of immersed tube tunnel easier, a kind of seabed tunnel of bespoke design Road is laid with equipment, enables the device to that more quickly, while the heavy of intermediate damage can be directed in submarine laying immersed tube tunnel The repair and replacement in pipe tunnel.
Summary of the invention
The purpose of the present invention is to solve disadvantages existing in the prior art, and a kind of seabed tunnel proposed is laid with dress It is standby.
To achieve the goals above, present invention employs following technical solutions:
Design a kind of seabed tunnel and be laid with equipment, including immersed tube assembly, equipment conveying mechanism assembly, two elevating mechanism assemblies, Sea bed walking mechanism, sea bed calm down mechanism and mechanism running track, which is characterized in that the equipment conveying mechanism assembly is located at heavy The top of pipe assembly, the mechanism running track are installed on the top of equipment conveying mechanism assembly, and the sea bed calms down mechanism peace Right end loaded on mechanism running track, the sea bed walking mechanism is installed on the right end of mechanism running track, and sea bed is walked Mechanism is located at the left side that sea bed calms down mechanism, and the elevating mechanism assembly is installed on the upper surface of mechanism running track;
The immersed tube assembly includes pouring immersed tube main body, and the upper surface two sides for pouring immersed tube main body are mounted on rail, institute It states and water blocking tape is installed on the outside of the one end for pouring immersed tube main body, fixing bolt is installed on the outside of described one end for pouring immersed tube main body, One end two sides for pouring immersed tube main body are mounted on water fender, and the middle part of the water fender, which is equipped with, connects place's drainage hole;
The equipment conveying mechanism assembly includes two skeletons, and the lower end of two skeletons is equipped with mounting platform jointly, institute The lower surface for stating mounting platform is equipped with multiple support frames, and the two sides of each support frame as described above are mounted on axle, the axle Both ends be mounted on steel wheel, the mechanism running track is installed on the upper end of two skeletons, and the steel wheel is located at rail Upper surface;
The elevating mechanism assembly includes horizontal support, and the two sides of the horizontal support are symmetrically installed with fixed bracket, described Support bracket fastened side, which is mounted on, moves up and down wheel, moves up and down described in two and is equipped between wheel and moves up and down bar, described Two side lower parts for moving up and down bar are mounted on tightening wheel, two side lower parts for moving up and down bar be separately installed with interior catching and Outer catching, two side lower parts of the horizontal support are mounted on rotation wheel support, and the lower part of the rotation wheel support is mounted on The rotating wheel engaged with mechanism running track, two side lower parts of the horizontal support are symmetrically installed with movable pulley;
It includes the upper holder fixed with mechanism running track that the sea bed, which calms down mechanism, and the lower part of fixed frame passes through solid Fixed-axis rotation is equipped with rolling stand, and the opposite side of the rolling stand, which is equipped with, calms down roller, the phase of the rolling stand It is mounted on excretion wheel to side, the side of the rolling stand is rotatably equipped with telescoping cylinder, one end of the telescoping cylinder and machine The rotation connection of structure running track.
Preferably, the sea bed walking mechanism includes the walking fixed frame fixed with mechanism running track, and the walking is solid The two sides for determining frame are fixedly installed with Athey wheel fixed frame, and the lower end of the Athey wheel fixed frame is equipped with Athey wheel.
Preferably, the side of fixed frame is equipped with fixed frame.
A kind of seabed tunnel proposed by the present invention is laid with equipment, and beneficial effect is: the present invention uses rail mounted immersed tube tunnel Road, the track of track fixed equipment operation, prevents seabed ocean current from causing device shifting, carries the installation equipment energy of immersed tube to be installed Enough to run on having installed the immersed tube that do not bury, such installation method accelerates transport, so that installation is rapider, sea Bed calms down mechanism, for calming down sea bed, so that sea bed meets municipal administration and is laid with requirement.
Detailed description of the invention
Fig. 1 is that a kind of seabed tunnel proposed by the present invention is laid with equipment configuration schematic diagram;
Fig. 2 is the immersed tube assembly structure schematic diagram that a kind of seabed tunnel proposed by the present invention is laid with equipment;
Fig. 3 is the immersed tube assembly structure schematic diagram that a kind of seabed tunnel proposed by the present invention is laid with equipment;
Fig. 4 is the equipment conveying mechanism assembly structural schematic diagram that a kind of seabed tunnel proposed by the present invention is laid with equipment;
Fig. 5 is the elevating mechanism assembly structure schematic diagram that a kind of seabed tunnel proposed by the present invention is laid with equipment;
Fig. 6 is that the sea bed that a kind of seabed tunnel proposed by the present invention is laid with equipment calms down mechanism structure schematic diagram;
Fig. 7 is the sea bed walking mechanism structural schematic diagram that a kind of seabed tunnel proposed by the present invention is laid with equipment.
In figure: immersed tube assembly 1, equipment conveying mechanism assembly 2, elevating mechanism assembly 3, sea bed walking mechanism 4, sea bed calm down Mechanism 5, mechanism running track 6 pour immersed tube main body 7, rail 8, water blocking tape 9, fixing bolt 10, connect place drainage hole 11, water fender 12, steel wheel 13, axle 14, skeleton 15, mounting platform 16, interior catching 17, outer catching 18, tightening wheel 19, rotating wheel 20, movable pulley 21, horizontal support 22, rotation wheel support 23, move up and down wheel 24, fixed bracket 25, move up and down bar 26, is telescoping cylinder 27, upper solid Determine that frame 28, fixed frame 29, rolling stand 30, excretion wheel 31, to calm down roller 32, fixing axle 33, walking fixed frame 34, Athey wheel solid Determine frame 35, Athey wheel 36, support frame 37.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.
Referring to Fig.1-7, a kind of seabed tunnel is laid with equipment, including immersed tube assembly 1, equipment conveying mechanism assembly 2, two rise Descending mechanism assembly 3, sea bed walking mechanism 4, sea bed calm down mechanism 5 and mechanism running track 6, and sea bed walking mechanism 4 includes and machine The two sides of the fixed walking fixed frame 34 of structure running track 6, walking fixed frame 34 are fixedly installed with Athey wheel fixed frame 35, carry out The lower end of belt wheel fixed frame 35 is equipped with Athey wheel 36, and structure is simple, easy to use, can play the role of support, and raising is set The standby stability used.
Equipment conveying mechanism assembly 2 is located at the top of immersed tube assembly 1, and mechanism running track 6 is installed on equipment conveying mechanism The top of assembly 2, sea bed calm down the right end that mechanism 5 is installed on mechanism running track 6, and sea bed walking mechanism 4 is installed on mechanism The right end of running track 6, and sea bed walking mechanism 4 is located at the left side that sea bed calms down mechanism 5, elevating mechanism assembly 3 is installed on machine The upper surface of structure running track 6;
Immersed tube assembly 1 includes pouring immersed tube main body 7, and the upper surface two sides for pouring immersed tube main body 7 are mounted on rail 8, and it is heavy to pour Water blocking tape 9 is installed on the outside of one end of pipe main body 7, pours and fixing bolt 10, fixing bolt 10 is installed on the outside of one end of immersed tube main body 7 For fix it is adjacent pour immersed tube main body 7, one end two sides for pouring immersed tube main body 7 are mounted on water fender 12, water fender 12 Middle part, which is equipped with, connects place's drainage hole 11, for extracting the adjacent water poured between immersed tube main body 7 out;
Equipment conveying mechanism assembly 2 includes two skeletons 15, and the lower end of two skeletons 15 is equipped with mounting platform 16 jointly, is installed The lower surface of platform 16 is equipped with multiple support frames 37, and the two sides of each support frame 37 are mounted on axle 14, and the two of axle 14 End is mounted on steel wheel 13, and mechanism running track 6 is installed on the upper end of two skeletons 15, and steel wheel 13 is located at the upper surface of rail 8;
Elevating mechanism assembly 3 includes horizontal support 22, and the two sides of horizontal support 22 are symmetrically installed with fixed bracket 25, fixed branch The side of frame 25, which is mounted on, moves up and down wheel 24, and two move up and down and are equipped between wheel 24 and move up and down bar 26, above moves down Two side lower parts of lever 26 are mounted on tightening wheel 19, and two side lower parts for moving up and down bar 26 are separately installed with interior catching 17 and outer Catching 18, two side lower parts of horizontal support 22 be mounted on rotation wheel support 23, rotation wheel support 23 lower part be mounted on The rotating wheel 20 that mechanism running track 6 engages, two side lower parts of horizontal support 22 are symmetrically installed with movable pulley 21;
It includes the upper holder 28 fixed with mechanism running track 6 that sea bed, which calms down mechanism 5, and the side of upper holder 28 is equipped with solid Determine frame 29, in order to improve connective stability, enhances using effect.
The lower part of upper holder 28 is rotatably equipped with rolling stand 30, the opposite side of rolling stand 30 by fixing axle 33 It is equipped with and calms down roller 32, the opposite side of rolling stand 30 is mounted on excretion wheel 31, and the side of rolling stand 30 rotates peace Equipped with telescoping cylinder 27, one end of telescoping cylinder 27 and mechanism running track 6 are rotatablely connected.
Working principle: in use, equipment transports immersed tube assembly 1, equipment conveying mechanism assembly 2 passes through installed immersed tube Rail 8, steel wheel 13 on assembly 1 cooperate realization to transport with it, and elevating mechanism assembly 3 realizes the up and down motion of immersed tube assembly 1, sea Bed walking mechanism 4 is walked in immersed tube two sides, affects equipment to advance, sea bed, which calms down mechanism 5, can flatten sea bed, so that immersed tube assembly 1 placement meets installation requirement, and the elevating mechanism assembly 3 installed in mechanism running track 6, which can be realized, to move forward and backward.It carries wait pacify The installation equipment of dress immersed tube can be run on having installed the immersed tube that do not bury, and such installation method accelerates transport, So that installation is rapider.Sea bed calms down mechanism 5, for calming down sea bed, so that sea bed meets immersed tube and is laid with requirement.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.

Claims (3)

  1. It is equipped 1. a kind of seabed tunnel is laid with, including immersed tube assembly (1), equipment conveying mechanism assembly (2), two elevating mechanisms are total Calm down mechanism (5) and mechanism running track (6) at (3), sea bed walking mechanism (4), sea bed, which is characterized in that the equipment fortune Transfer mechanism assembly (2) is located at the top of immersed tube assembly (1), and the mechanism running track (6) is installed on equipment conveying mechanism assembly (2) top, the sea bed calm down the right end that mechanism (5) is installed on mechanism running track (6), the sea bed walking mechanism (4) it is installed on the right end of mechanism running track (6), and sea bed walking mechanism (4) is located at the left side that sea bed calms down mechanism (5), institute State the upper surface that elevating mechanism assembly (3) is installed on mechanism running track (6);
    The immersed tube assembly (1) includes pouring immersed tube main body (7), and the upper surface two sides for pouring immersed tube main body (7) are respectively mounted Have rail (8), is equipped with water blocking tape (9) on the outside of described one end for pouring immersed tube main body (7), the immersed tube main body (7) of pouring It is equipped with fixing bolt (10) on the outside of one end, one end two sides for pouring immersed tube main body (7) are mounted on water fender (12), described The middle part of water fender (12), which is equipped with, meets place drainage hole (11);
    The equipment conveying mechanism assembly (2) includes two skeletons (15), and the lower end of two skeletons (15) is equipped with jointly The lower surface of mounting platform (16), the mounting platform (16) is equipped with multiple support frames (37), each support frame as described above (37) Two sides be mounted on axle (14), the both ends of the axle (14) are mounted on steel wheel (13), the mechanism running track (6) It is installed on the upper end of two skeletons (15), the steel wheel (13) is located at the upper surface of rail (8);
    The elevating mechanism assembly (3) includes horizontal support (22), and the two sides of the horizontal support (22) are symmetrically installed with solid Fixed rack (25), the side of the fixed bracket (25), which is mounted on, moves up and down wheel (24), and wheel is moved up and down described in two (24) it being equipped with and moves up and down bar (26) between, two side lower parts for moving up and down bar (26) are mounted on tightening wheel (19), Two side lower parts for moving up and down bar (26) are separately installed with interior catching (17) and outer catching (18), the horizontal support (22) Two side lower parts be mounted on rotation wheel support (23), it is described rotation wheel support (23) lower part be mounted on and mechanism operation rail The rotating wheel (20) of road (6) engaging, two side lower parts of the horizontal support (22) are symmetrically installed with movable pulley (21);
    It includes the upper holder (28) fixed with mechanism running track (6), fixed frame that the sea bed, which calms down mechanism (5), (28) lower part is rotatably equipped with rolling stand (30) by fixing axle (33), the opposite side installation of the rolling stand (30) Have and calm down roller (32), the opposite side of the rolling stand (30) is mounted on excretion wheel (31), the rolling stand (30) Side be rotatably equipped with telescoping cylinder (27), one end of the telescoping cylinder (27) and mechanism running track (6) are rotatablely connected.
  2. 2. seabed tunnel according to claim 1 is laid with equipment, which is characterized in that the sea bed walking mechanism (4) includes The two sides of the fixed walking fixed frame (34) with mechanism running track (6), walking fixed frame (34) are fixedly installed with shoe The lower end of belt wheel fixed frame (35), the Athey wheel fixed frame (35) is equipped with Athey wheel (36).
  3. 3. seabed tunnel according to claim 1 is laid with equipment, which is characterized in that the side of fixed frame (28) Fixed frame (29) are installed.
CN201910292739.7A 2019-04-12 2019-04-12 Submarine tunnel lays and equips Active CN109973125B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910292739.7A CN109973125B (en) 2019-04-12 2019-04-12 Submarine tunnel lays and equips

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910292739.7A CN109973125B (en) 2019-04-12 2019-04-12 Submarine tunnel lays and equips

Publications (2)

Publication Number Publication Date
CN109973125A true CN109973125A (en) 2019-07-05
CN109973125B CN109973125B (en) 2021-03-26

Family

ID=67084252

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910292739.7A Active CN109973125B (en) 2019-04-12 2019-04-12 Submarine tunnel lays and equips

Country Status (1)

Country Link
CN (1) CN109973125B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2534610A1 (en) * 1982-10-18 1984-04-20 Tron Roger Aerial bridge on a stabilised submerged tunnel.
JPH1082062A (en) * 1996-09-10 1998-03-31 Kumagai Gumi Co Ltd Immersion device of immersed tube
CN203270611U (en) * 2012-12-31 2013-11-06 中交第一航务工程局有限公司 Pipe joint hoisting and immersing system
CN104652482A (en) * 2015-02-16 2015-05-27 中交一航局第二工程有限公司 Immersed tube joint mounting and dismounting device for sea bottom immersed tube tunnel
CN107676104A (en) * 2017-11-03 2018-02-09 中交公路规划设计院有限公司 Integrated immersed tube tube coupling and its installation method, the installation closure method of immersed tube tube coupling
CN108222068A (en) * 2017-10-18 2018-06-29 北京九州动脉隧道技术有限公司 A kind of underwater immersed tube Bridge Erector and its construction technology
CN208395859U (en) * 2018-07-02 2019-01-18 江苏科技大学 A kind of novel sink tubular type seabed tunnel

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2534610A1 (en) * 1982-10-18 1984-04-20 Tron Roger Aerial bridge on a stabilised submerged tunnel.
JPH1082062A (en) * 1996-09-10 1998-03-31 Kumagai Gumi Co Ltd Immersion device of immersed tube
CN203270611U (en) * 2012-12-31 2013-11-06 中交第一航务工程局有限公司 Pipe joint hoisting and immersing system
CN104652482A (en) * 2015-02-16 2015-05-27 中交一航局第二工程有限公司 Immersed tube joint mounting and dismounting device for sea bottom immersed tube tunnel
CN108222068A (en) * 2017-10-18 2018-06-29 北京九州动脉隧道技术有限公司 A kind of underwater immersed tube Bridge Erector and its construction technology
CN107676104A (en) * 2017-11-03 2018-02-09 中交公路规划设计院有限公司 Integrated immersed tube tube coupling and its installation method, the installation closure method of immersed tube tube coupling
CN208395859U (en) * 2018-07-02 2019-01-18 江苏科技大学 A kind of novel sink tubular type seabed tunnel

Also Published As

Publication number Publication date
CN109973125B (en) 2021-03-26

Similar Documents

Publication Publication Date Title
CN108149929B (en) Crawler-type floor concrete distribution system and construction method thereof
CN102242632A (en) System and method for walking type shield structure translation to transit
CN107387870A (en) A kind of automatic pipe-laying equipment
CN108116998A (en) A kind of tributary sediment sampling stent
CN105620566A (en) River network mire crawler-type carrier vehicle
CN109973125A (en) A kind of seabed tunnel laying equipment
CN106437847A (en) Supporting frame for underground pipeline system building
CN102094412A (en) Mud-water amphibious plate-inserting device for soft foundation
CN201362850Y (en) Fixed cantilever-type telescopic bidirectional distributor for concrete storehouse surface
CN207861773U (en) A kind of tributary sediment sampling holder
WO2016033707A1 (en) Walker-type traveling rotary drilling rig
CN207362978U (en) Position pipelayer attachment
JP5469524B2 (en) Installation method and moving method of scaffold device
CN201924338U (en) Mud-water amphibious soft foundation spile device
CN108708397A (en) The paving frame method of underground pipe gallery standard knot
CN212837866U (en) Split type section of jurisdiction dolly
CN108590676A (en) A kind of shield machine front carriage track platform
CN108163582A (en) A kind of mobile dress ore deposit platform and its dress ore deposit method
CN211252836U (en) Tire mechanism for tunnel traveling vehicle and tunnel traveling vehicle
CN204570690U (en) Pontoon pile driving plant
CN209195303U (en) A kind of drill string guiding manipulator
CN107237609A (en) Marine riser cat road
CN202578710U (en) Hydraulic self-propelled heavy gradient concrete pouring trolley
CN106368727A (en) Underground self-moving device of coal mine
CN107448211A (en) Tunnel efficient construction method and its automatically walk shifting formwork transposition framework trestle used

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: Room 2102, building g, shuxiangyuan, Yuhua Yuxiu community, Chenggong District, Kunming City, Yunnan Province

Applicant after: Cai Jiaheng

Address before: 250014 China Railway Yidu International Phase I 7-2-602 of Jinan High-tech Zone Tourist Road, Shandong Province

Applicant before: Cai Jiaheng

GR01 Patent grant
GR01 Patent grant