CN109961212A - One kind is based on the visual construction speed dynamic management BIM system of work surface - Google Patents
One kind is based on the visual construction speed dynamic management BIM system of work surface Download PDFInfo
- Publication number
- CN109961212A CN109961212A CN201910082247.5A CN201910082247A CN109961212A CN 109961212 A CN109961212 A CN 109961212A CN 201910082247 A CN201910082247 A CN 201910082247A CN 109961212 A CN109961212 A CN 109961212A
- Authority
- CN
- China
- Prior art keywords
- module
- construction speed
- work surface
- progress
- option
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 65
- 230000000007 visual effect Effects 0.000 title claims abstract description 18
- 230000009471 action Effects 0.000 claims description 6
- 239000003973 paint Substances 0.000 claims description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 3
- 230000006399 behavior Effects 0.000 claims description 2
- 238000007726 management method Methods 0.000 description 19
- 238000000034 method Methods 0.000 description 3
- 238000012544 monitoring process Methods 0.000 description 3
- 238000004458 analytical method Methods 0.000 description 2
- 230000008901 benefit Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000037452 priming Effects 0.000 description 2
- 238000012800 visualization Methods 0.000 description 2
- 241001269238 Data Species 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010835 comparative analysis Methods 0.000 description 1
- 238000013523 data management Methods 0.000 description 1
- 238000000151 deposition Methods 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 230000001815 facial effect Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012913 prioritisation Methods 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063114—Status monitoring or status determination for a person or group
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- Theoretical Computer Science (AREA)
- Entrepreneurship & Innovation (AREA)
- General Physics & Mathematics (AREA)
- Marketing (AREA)
- General Business, Economics & Management (AREA)
- Physics & Mathematics (AREA)
- Educational Administration (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Game Theory and Decision Science (AREA)
- Development Economics (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses one kind to be connected with each other based on the visual construction speed dynamic management BIM system of work surface, including nucleus module and display module, nucleus module and display module by signal wire;The nucleus module includes the construction project time management module for managing construction plan progress, changing and actually accomplish progress, the construction speed recording module for typing construction speed, the historical information enquiry module for inquiring construction speed and the construction speed memory module for storing construction speed;Display module includes title module, selecting module, main operation module and menu module, and display module and nucleus module cooperate, and carries out display access and management correcting to construction speed.
Description
Technical field
The present invention relates to architecture information systems technology fields, specially a kind of to be based on the visual construction speed of work surface
Dynamic management BIM system.
Background technique
The progress monitoring of engineering project is the important content of three controls, and ultimately forming for building products is in construction rank
Section, therefore, carrying out stringent progress monitoring just in the construction stage seems increasingly important.Reinforcing construction progress control is standard construction
Behavior and guarantee construction realization of goal key, how organizing construction's schedule, how to find in time actual progress and plan
The difference of progress is simultaneously timely and effectively adjusted, and is not easy to for project scheduling management personnel.Although both at home and abroad to having
Some management tools of the control problem of degree of putting into, but facilitate tool also to lack construction stage progress monitoring visualized management,
And operability is not strong.Scientific management to construction speed is to establish corporate image to improve corporate reputation, obtains economic benefit
With the fundamental way of social benefit.
Progress msg is reflected by chart, and progress and being associated with for other information are more difficult.Particularly, progress and model close
Connection, existing software is less, and trivial operations, is not easy to site administrator's use, and cannot achieve dynamic and manage, and visualizes journey
It spends low.How BIM technology to be used effectively to organize progress and related information, to realize effective progress pipe of stages of design and construction
Reason and analysis, are applied by corporate decision maker, are current architecture information management problems to be solved.
Summary of the invention
The purpose of the present invention is to provide one kind to manage BIM system based on the visual construction speed dynamic of work surface, with
Solve the problems mentioned above in the background art.
To achieve the above object, the invention provides the following technical scheme: a kind of be based on the visual construction speed of work surface
Dynamic management BIM system, including nucleus module and display module, nucleus module and display module are connected with each other by signal wire;
The nucleus module includes construction project time management module, the use for managing construction plan progress, changing and actually accomplish progress
In the construction speed recording module of typing construction speed, the historical information enquiry module for inquiring construction speed and for depositing
Store up the construction speed memory module of construction speed;Display module includes title module, selecting module, main operation module and menu
Module, nucleus module and display module cooperate, and carry out display access and management correcting to construction speed.
Preferably, the title module shows master control option, project name option and batch option, and master control option is aobvious
Show that engineering master control progress display interface, project name option show that progress control dbase or project name, batch option are used
It is backed up in batch selection.
Preferably, the selecting module shows major selection option, selection of time option, work surface selection option.
Preferably, Engineering Speciality is selected in the major selection option, the profession can be defined as structure, electricity
Gas and water, HVAC wind, fire-fighting profession, also may be defined as bar bender, scaffolder, plasterer, painter, carpenter's work post, also can define
For plastering, priming paint, finishing coat, furred ceiling action;Show the work surface performance of related content.
Preferably, the selection of time option selects time point, period, shows that the time point or period are each
Work surface performance.
Preferably, the selection of work surface selection option do not start, start, carrying out in, milestone, completed state,
The state being partially completed can also be increased as needed, such as 60% be completed, 80% is completed;Show related content or profession or work
The time point or period that each work surface of kind is accordingly completed.
Preferably, the main operation module is provided with multiple grids arranged vertically and horizontally, and each grid is according to the position where it
It installs and is equipped with coordinate in length and breadth, coordinate respectively represents Lou Dong, floor or floor, region in length and breadth.
Preferably, the state of the grid is expressed by color, and the legend of color expression can be set with automatic or manual;Lattice
By numeral expression time point or period on son, pass through letter expression profession or work post or subpackage or action;Pass through choosing
Medium square, each work surface progress state corresponding to grid, profession and time are configured.
Preferably, the menu module includes actual progress, target advance, and the content of actual progress is all actually typing
Progress, the content of target advance are all progresses in the works.
Compared with prior art, the beneficial effects of the present invention are: the present invention is mentioned by 3D digitizing technique for field management
For dummy model, the progress relationship of each work surface is shown to visual pattern, and its relevant all engineering information are electronic
With it is integrated;Whole related datas of engineering site are integrated on the same threedimensional model platform simultaneously, make information
Express it is intuitive and accurate, due in project overall process use same set of information, enhance the uniformity of information, avoid information
Transmitting loss;Based on BIM model, by progress and spatial data management, display include engineering entity information, engineering environment information,
Engineering problem information etc. will provide database abundant for the service management of project operation, support progress dynamic and visual profession
Analysis;Progress control visualization view is automatically generated, is provided for field programs progress, actual progress and plan and actual comparison
Foundation, dynamic chek progress conflict, reduction scene is unordered, construction site dynamic management and prioritization scheme is formed, for business administration
Level, which is promoted, provides support.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention;
Figure label: 1, nucleus module;11, construction project time management module;12, construction speed recording module;13, history is believed
Cease enquiry module;14, construction speed memory module;2, display module;21, title module;22, selecting module;23, main operation mould
Block;24, menu module.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that the orientation of the instructions such as term "vertical", "upper", "lower", "horizontal"
Or positional relationship is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of description of the present invention and simplification of the description, and
It is not that the device of indication or suggestion meaning or element must have a particular orientation, be constructed and operated in a specific orientation, therefore
It is not considered as limiting the invention.
In the description of the present invention, it is also necessary to which explanation is unless specifically defined or limited otherwise, term " setting ",
" installation ", " connected ", " connection " shall be understood in a broad sense, for example, it may be fixedly connected, may be a detachable connection or one
Connect to body;It can be mechanical connection, be also possible to be electrically connected;It can be directly connected, it can also be indirect by intermediary
It is connected, can be the connection inside two elements.For the ordinary skill in the art, it can manage as the case may be
Solve the concrete meaning of above-mentioned term in the present invention.
Referring to Fig. 1, the present invention provides a kind of technical solution: one kind is managed based on the visual construction speed dynamic of work surface
BIM system, including nucleus module 1 and display module 2 are managed, nucleus module 1 and display module 2 are connected with each other by signal wire;Institute
Stating nucleus module 1 includes construction project time management module 11, the use for managing construction plan progress, changing and actually accomplish progress
In the construction speed recording module 12 of typing construction speed, the historical information enquiry module 13 for inquiring construction speed and use
In the construction speed memory module 14 of storage construction speed;Display module 2 includes title module 21, selecting module 22, main operation
Module 23 and menu module 24, nucleus module 1 and display module 2 cooperate, to construction speed carry out display access and
Management correcting.
Further, the title module 21 shows master control option, project name option and batch option, master control choosing
Item display engineering master control progress display interface, project name option show that progress control dbase or project name, batch select
Item is for backing up batch selection.
Further, the selecting module 22 shows major selection option, selection of time option, work surface selection choosing
?.
Further, Engineering Speciality is selected in the major selection option, the profession can be defined as structure,
Electric gas and water, HVAC wind, fire-fighting profession, also may be defined as bar bender, scaffolder, plasterer, painter, carpenter's work post, can also determine
Justice is plastering, priming paint, finishing coat, furred ceiling action;Show the work surface performance of related content.
Further, the selection of time option selects time point, period, shows the time point or period
Each work surface performance.
Further, the selection of work surface selection option do not start, start, carrying out in, milestone, completed shape
State can also increase the state being partially completed as needed, such as 60% be completed, 80% is completed;Show related content or profession
Or time point or period that each work surface of work post is accordingly completed.
Further, the main operation module 23 is provided with multiple grids arranged vertically and horizontally, and each grid is according to where it
Position be provided with coordinate in length and breadth, coordinate respectively represents Lou Dong, floor or floor, region in length and breadth.
Further, the state of the grid is expressed by color, and the legend of color expression can be set with automatic or manual;
By numeral expression time point or period on grid, pass through letter expression profession or work post or subpackage or action;Pass through
Grid is chosen, each work surface progress state corresponding to grid, profession and time are configured.
Further, the menu module 24 includes actual progress, target advance, and the content of actual progress is all practical record
The progress entered, the content of target advance are all progresses in the works.
Working principle: the present invention and existing progress control software are all different, be using work surface are carrier by work surface information
It is associated with progress msg, the information that progress msg and each professional workers are constructed is subjected to visualization presentation in three-dimensional work surface,
Intuitively reflect the field conditions such as the progress msg of each work surface.It solves gunter drawing and lacks field scene description, do not make
The problem of industry facial canal is managed, and solve BIM and live inconsistent puzzlement in conventional BIM5D displaying progress, it greatly improves
The efficiency of live project management.
Application scheme uses work surface and progress msg effectively combines, and solves the construction operation that scene occurs always
Face conflict, work surface are intersected that management is difficult, and actual progress record is difficult, and target advance and actual progress comparative analysis be not intuitive etc. and are asked
Topic.
Construction project time management module 11, construction speed recording module 12, historical information are respectively set in nucleus module 1 to look into
Module 13 and construction speed memory module 14 are ask, cooperation display module 2 is consulted and modified to construction speed.
Title module 21 is provided in display module 2, master control option, project name option in title module 21 and
Batch option is checked convenient for users to selection project and is backed up using batch option, progress msg is carried out standby
Part, it avoids losing;Selecting module 22 is set, respectively according to profession, time, work surface to examine;Main operation is set
Module 23 is operated for the grid in main operation module 23, to work surface representated by grid be arranged its state, profession,
Time;Menu module 24, inside setting actual progress, target advance, respectively theoretical progress and real progress, side are set simultaneously
Just compare.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with
A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding
And modification, the scope of the present invention is defined by the appended.
Claims (9)
1. one kind is based on the visual construction speed dynamic management BIM system of work surface, it is characterised in that: including nucleus module
(1) it is connected with each other with display module (2), nucleus module (1) and display module (2) by signal wire;Nucleus module (1) packet
It includes the construction project time management module (11) for managing construction plan progress, changing and actually accomplish progress, construct for typing
The construction speed recording module (12) of progress, the historical information enquiry module (13) for inquiring construction speed and for storing
The construction speed memory module (14) of construction speed;Display module (2) includes title module (21), selecting module (22), main behaviour
Make module (23) and menu module (24), nucleus module (1) and display module (2) cooperate, show to construction speed
Show access and management correcting.
2. according to claim 1 a kind of based on the visual construction speed dynamic management BIM system of work surface, feature
Be: the title module (21) shows master control option, project name option and batch option, and master control option shows engineering
Master control progress display interface, project name option show progress control dbase or project name, batch option be used for batch
Amount selection is backed up.
3. according to claim 1 a kind of based on the visual construction speed dynamic management BIM system of work surface, feature
Be: the selecting module (22) shows major selection option, selection of time option, work surface selection option.
4. according to claim 3 a kind of based on the visual construction speed dynamic management BIM system of work surface, feature
It is: Engineering Speciality is selected in the major selection option, the profession can be defined as structure, electric gas and water, HVAC
Wind, fire-fighting profession, also may be defined as bar bender, scaffolder, plasterer, painter, carpenter's work post, also may be defined as plastering, bottom
Paint, finishing coat, furred ceiling action;Show the work surface performance of related content.
5. according to claim 3 a kind of based on the visual construction speed dynamic management BIM system of work surface, feature
Be: the selection of time option selects time point, period, shows that the time point or period each work surface complete
Situation.
6. according to claim 3 a kind of based on the visual construction speed dynamic management BIM system of work surface, feature
Be: work surface selection option selection do not start, start, carrying out in, milestone, completed state, can also be according to need
Increase the state being partially completed, such as 60% is completed, 80% is completed;Show related content or profession or each work surface of work post
The time point or period accordingly completed.
7. according to claim 1 a kind of based on the visual construction speed dynamic management BIM system of work surface, feature
Be: the main operation module (23) is provided with multiple grids arranged vertically and horizontally, and each grid is arranged according to the position where it
There is coordinate in length and breadth, coordinate respectively represents Lou Dong, floor or floor, region in length and breadth.
8. according to claim 7 a kind of based on the visual construction speed dynamic management BIM system of work surface, feature
Be: the state of the grid is expressed by color, and the legend of color expression can be set with automatic or manual;Pass through number on grid
Word expression time point or period pass through letter expression profession or work post or subpackage or action;By choosing grid, other side
The corresponding each work surface progress state of lattice, profession and time are configured.
9. according to claim 7 a kind of based on the visual construction speed dynamic management BIM system of work surface, feature
Be: the menu module (24) includes actual progress, target advance, and the content of actual progress is all the progress being actually typing,
The content of target advance is all progress in the works.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910082247.5A CN109961212A (en) | 2019-01-28 | 2019-01-28 | One kind is based on the visual construction speed dynamic management BIM system of work surface |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910082247.5A CN109961212A (en) | 2019-01-28 | 2019-01-28 | One kind is based on the visual construction speed dynamic management BIM system of work surface |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109961212A true CN109961212A (en) | 2019-07-02 |
Family
ID=67023464
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910082247.5A Pending CN109961212A (en) | 2019-01-28 | 2019-01-28 | One kind is based on the visual construction speed dynamic management BIM system of work surface |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109961212A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111177305A (en) * | 2019-12-30 | 2020-05-19 | 广州骏伯网络科技有限公司 | Method, system, device and storage medium for time segment selection |
CN111539690A (en) * | 2020-04-28 | 2020-08-14 | 悉地(苏州)勘察设计顾问有限公司 | Construction project collaborative management method and system based on BIM |
CN112307548A (en) * | 2020-11-02 | 2021-02-02 | 中国电建集团华东勘测设计研究院有限公司 | BIM-based rail transit construction visualization progress management method and system |
-
2019
- 2019-01-28 CN CN201910082247.5A patent/CN109961212A/en active Pending
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111177305A (en) * | 2019-12-30 | 2020-05-19 | 广州骏伯网络科技有限公司 | Method, system, device and storage medium for time segment selection |
CN111177305B (en) * | 2019-12-30 | 2021-01-05 | 广州骏伯网络科技有限公司 | Method, system, device and storage medium for time segment selection |
CN111539690A (en) * | 2020-04-28 | 2020-08-14 | 悉地(苏州)勘察设计顾问有限公司 | Construction project collaborative management method and system based on BIM |
CN112307548A (en) * | 2020-11-02 | 2021-02-02 | 中国电建集团华东勘测设计研究院有限公司 | BIM-based rail transit construction visualization progress management method and system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109961212A (en) | One kind is based on the visual construction speed dynamic management BIM system of work surface | |
CN109375595A (en) | A kind of workshop method for visually monitoring, device and equipment | |
CN111898990A (en) | Building construction progress management method | |
CN106485784B (en) | Indoor design imaging processing method based on multi-terminal equipment data synchronization | |
CN103093007A (en) | Power transmission iron tower three-dimensional virtual assembly method | |
CA2257886A1 (en) | Real-time pricing control system and methods regarding same | |
CN104077653A (en) | Building construction supervision method based on BIM | |
KR101885692B1 (en) | Heavy equipment management system based on BIM and heavy equipment management method of the same | |
CN108665022A (en) | A kind of digitlization yard management system | |
CN111666619A (en) | BIM technology-based substation engineering implementation field digital management system | |
CN109035874A (en) | A kind of flat cluster airspace use monitoring method and system of multi-source | |
CN113557506B (en) | Quantifiable and programmable building construction group tower optimal arrangement method | |
CN108009332A (en) | Suspended ceiling member adding set, its method, electronic equipment and computer program | |
CN109949011A (en) | A kind of strip foundation pit construction system based on BIM | |
CN112506155A (en) | PC component production simulation and intelligent control system | |
CN106227431A (en) | The method and apparatus of management and monitoring members list on a kind of electronic chart | |
CN217467183U (en) | Digital display device for grid pipe arrangement engineering | |
CN115809287A (en) | Three-dimensional visual display method and platform for regulating and controlling running state of electric power system | |
CN102968926A (en) | Symbol configuration system of zonal statistical map and method thereof | |
CN110378670A (en) | A kind of spatial network technology model and its construction method and application | |
CN108197357A (en) | The automatic fenestration system of furred ceiling, boring method, electronic equipment and computer program | |
KR101082149B1 (en) | Optimizing drawing system for shipbuilding | |
CN113255034A (en) | Automatic layout system and generation method for equipment of convergence machine room | |
CN107832548A (en) | Circle logical furred ceiling design system, its method, electronic equipment and computer program | |
CN114466166A (en) | Method for remotely monitoring and accepting house decoration |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20190702 |
|
WD01 | Invention patent application deemed withdrawn after publication |