CN109898665A - Steel corridor bracket support adjusts steel plate system and its installation method - Google Patents

Steel corridor bracket support adjusts steel plate system and its installation method Download PDF

Info

Publication number
CN109898665A
CN109898665A CN201910195454.1A CN201910195454A CN109898665A CN 109898665 A CN109898665 A CN 109898665A CN 201910195454 A CN201910195454 A CN 201910195454A CN 109898665 A CN109898665 A CN 109898665A
Authority
CN
China
Prior art keywords
steel
adjustment
steel plate
corridor
embedded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910195454.1A
Other languages
Chinese (zh)
Inventor
金翔鹰
邓伟
杨志民
孙韩盛
展慧华
张辉
谭江
陈忠良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai No 7 Construction Co Ltd
Original Assignee
Shanghai No 7 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai No 7 Construction Co Ltd filed Critical Shanghai No 7 Construction Co Ltd
Priority to CN201910195454.1A priority Critical patent/CN109898665A/en
Publication of CN109898665A publication Critical patent/CN109898665A/en
Pending legal-status Critical Current

Links

Abstract

The present invention provides a kind of Steel corridor bracket support adjustment steel plate system and its installation methods, adjustment steel plate of the invention is only used under support, backing plate adjustment ensure that the horizontal absolute altitude of same layer support and different layers support height difference, in four angles of shock-proof ball shaped steel bearing and intermediate position and one week pad adjustment plate, each adjustment steel plate thickness is according to each self-adjusting of structural elevation, ensure final precision, improves the absolute altitude control quality of support;Meanwhile reducing repetition and promoting unloading adjustment in place for several times, it improves efficiency, reduces risk, can allow Steel corridor in place on shock-proof ball shaped steel bearing as early as possible, reduce the security risk for being repeatedly lifted up bring risk and construction site.

Description

Steel corridor bracket support adjusts steel plate system and its installation method
Technical field
The present invention relates to a kind of Steel corridor bracket support adjustment steel plate system and its installation methods.
Background technique
Multilayer support Steel corridor promoted it is in place before, in order to avoid multilayer support is marked vertically and transversely and horizontally in space Steel construction error of the Gao Yin in specification allowed band is excessive, causes each Bearing Seat Force unbalanced, according to Construction of Steel Structure specification It is required that needs should carry out on steel concrete bracket, structure is levelling, and back-grouting places monolith steel after the completion of being typically employed in bracket structure The levelling method of plate.
However, bracket planar dimension is larger, steel plate heavier-weight, manual operation upper air installing can not be completely secured steel plate and exist After installation, the horizontal absolute altitude error of multilayer bracket is in controlled range, and support installation region is only positioned at one of entire bracket Point, so needing to carry out levelling to standoff region, the absolute altitude of support is adjusted by the way that multiple control points are arranged in standoff region, If padding monolith steel plate at support, accurate adjustment absolute altitude cannot achieve, while also resulting in the waste of material, and support is in place Required precision in the process is relatively high, and different branch block errors are controlled substantially in 1cm or so, and same support control pads monolith in 3mm Steel plate is unable to satisfy required precision, if construction wrong, especially it is difficult to unload itself high altitude operation in place for high-altitude vestibule across steel greatly Degree is big, security risk is high, and quality control on construction is difficult.
In addition, causing local bracket end reaction after unloading in place excessive because absolute altitude is inconsistent, there is peak value, by anti- Promote pading plate unloading again to adjust end reaction, difficulty is very big, and safety wind is dangerous high.
Summary of the invention
The purpose of the present invention is to provide a kind of Steel corridor bracket support adjustment steel plate system and its installation method, energy Enough reductions repeat to promote unloading adjustment in place for several times, improve efficiency, reduce risk.
To solve the above problems, the present invention provides a kind of Steel corridor bracket support adjustment steel plate system, comprising:
Steel corridor bracket;
It is fixed on the pre-embedded steel slab of the monolith on the Steel corridor bracket;
Divide on five blocks of adjustment steel plates, the central point of the pre-embedded steel slab and four angle points being arranged symmetrically with the central point It is not fixed with one block of adjustment steel plate;
It is fixed on the shock-proof ball shaped steel bearing of the monolith on five blocks of adjustment steel plates.
Further, in above system, the adjustment steel plate on four angle points is connected integral by steel plate.
Further, in above system, hole of vibrating is provided on the Steel corridor bracket;
Peg and angle steel anchor foot are provided on the pre-embedded steel slab, the peg and angle steel anchor foot are located at the pre-embedded steel slab In the one side contacted with the Steel corridor bracket, the angle steel anchor foot be inserted in it is described vibrate in hole, the steel construction connects It is fixed after being solidified between corridor bracket and the pre-embedded steel slab by grouting material.
Further, in above system, the Steel corridor bracket links into an integrated entity with stiffened column.
Further, in above system, the outside ratio of every block of adjustment steel plate on four angle points is fixed thereon Shock-proof ball shaped steel bearing outside stretch out 25~50mm.
Another side according to the present invention provides a kind of installation method of Steel corridor bracket support adjustment steel plate system, Include:
According to Steel Structural Design drawing requirement, the pre-embedded steel slab of monolith is buried on completed Steel corridor bracket;
After the pre-embedded steel slab completes the fixation with the Steel corridor bracket, Steel corridor bracket described in repetition measurement is perpendicular To with lateral absolute altitude, with determine adjustment steel plate thickness;
One piece is fixed respectively on the central point and four angle points being arranged symmetrically with the central point of the pre-embedded steel slab Determine the adjustment steel plate of thickness;
The shock-proof ball shaped steel bearing of monolith is fixed on five blocks of adjustment steel plates.
Further, in the above-mentioned methods, it is arranged symmetrically in the central point of the pre-embedded steel slab and with the central point It is fixed respectively on four angle points after the adjustment steel plate that one piece determines thickness, further includes:
Adjustment steel plate on four angle points is connected by steel plate integral.
Further, in the above-mentioned methods, the pre-embedded steel slab of monolith, packet are buried on completed Steel corridor bracket It includes:
Peg is set on the pre-embedded steel slab and angle steel anchor foot, the peg and angle steel anchor foot are located at the pre-embedded steel slab In the one side contacted with the Steel corridor bracket, the angle steel anchor foot is inserted in the vibration on the Steel corridor bracket It smashes in hole;
Grouting material is filled between the Steel corridor bracket and the contact surface of the pre-embedded steel slab.
Further, in the above-mentioned methods, according to Steel Structural Design drawing requirement, in completed Steel corridor bracket Before the pre-embedded steel slab of upper embedded monolith, further includes:
The rear reinforcing bar binding in place of stiffened column and the lifting of Steel corridor bracket overall processing is poured into concrete.
Further, in the above-mentioned methods, the step shock-proof ball shaped steel bearing of monolith being fixed on five blocks of adjustment steel plates In rapid,
The outside of every block of adjustment steel plate on four angle points is than the outside for the shock-proof ball shaped steel bearing being fixed thereon Stretch out 25~50mm.
Compared with prior art, the present invention is big for skybridge multilayer support quality control on construction difficulty in place, safe The high problem of risk, adjustment steel plate of the invention are only used under support, and backing plate adjustment ensure that the horizontal absolute altitude of same layer support and not Same layer support height difference, in four angles of shock-proof ball shaped steel bearing and intermediate position and one week pad adjustment plate, each adjustment steel plate is thick Degree is according to each self-adjusting of structural elevation, it is ensured that final precision improves the absolute altitude control quality of support;Meanwhile reducing repetition It promotes unloading to adjust in place for several times, improve efficiency, reduce risk, Steel corridor can be allowed in shock-proof ball shaped steel bearing as early as possible It is upper in place, reduce the security risk for being repeatedly lifted up bring risk and construction site.By in shock-proof ball shaped steel bearing region It pads adjustment plate and controls support absolute altitude, ensure that Steel corridor unloads rear multilayer end reaction in place completely and meets design requirement; The construction method makes multilayer support absolute altitude be effectively controlled, and reduces error.Reduction is repeatedly lifted up the danger source unloaded and carried With the security risk of construction site.
Detailed description of the invention
Fig. 1 is the sectional view of the Steel corridor bracket support adjustment steel plate system of one embodiment of the invention;
Fig. 2 is the plan view of the Steel corridor bracket support adjustment steel plate system of one embodiment of the invention.
Specific embodiment
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, with reference to the accompanying drawing and specific real Applying mode, the present invention is described in further detail.
As illustrated in fig. 1 and 2, the present invention provides a kind of Steel corridor bracket support adjustment steel plate system, comprising:
Steel corridor bracket 2;
It is fixed on the pre-embedded steel slab 3 of the monolith on the Steel corridor bracket 2;
Five blocks of adjustment steel plates 7, on the central point of the pre-embedded steel slab 3 and four angle points being arranged symmetrically with the central point It is respectively fixed with one block of adjustment steel plate 7;
It is fixed on the shock-proof ball shaped steel bearing 8 of the monolith on five blocks of adjustment steel plates 7.
Here, the present invention is asked for skybridge multilayer support quality control on construction difficulty in place is big, security risk is high Topic, adjustment steel plate of the invention are only used under support, and backing plate adjustment ensure that the horizontal absolute altitude of same layer support and different layers branch seat height Difference, in four angles of shock-proof ball shaped steel bearing and intermediate position and one week pad adjustment plate, each adjustment steel plate thickness is according to structure Each self-adjusting of absolute altitude, it is ensured that final precision improves the absolute altitude control quality of support;Meanwhile reducing repetition and promoting unloading tune It is whole it is in place improve efficiency for several times, reduce risk, can allow Steel corridor in place on shock-proof ball shaped steel bearing as early as possible, subtract It is repeatedly lifted up the security risk of bring risk and construction site less.By padding adjustment plate control in shock-proof ball shaped steel bearing region Support absolute altitude processed ensure that Steel corridor unloads rear multilayer end reaction in place completely and meets design requirement;The construction method So that multilayer support absolute altitude is effectively controlled, reduce error.Reduction, which is repeatedly lifted up, unloads the danger source carried and construction site Security risk.
In Steel corridor bracket support adjustment one embodiment of steel plate system of the invention, the adjustment on four angle points Steel plate 7 is connected integral by steel plate.
Here, surrounding steel plate is integral by the adjustment plate connection of four corners, to guarantee the stability of adjustment steel plate 7.
In Steel corridor bracket support adjustment one embodiment of steel plate system of the invention, the Steel corridor bracket 2 On be provided with hole of vibrating;
It is provided with peg 4 and angle steel anchor foot 5 on the pre-embedded steel slab 3 and 2 contact surface of Steel corridor bracket, it is described Angle steel anchor foot 5 vibrates in hole described in being inserted in, and passes through grouting material 6 between the Steel corridor bracket 2 and the pre-embedded steel slab 3 It is fixed after solidification, to guarantee fixed fastness.
In Steel corridor bracket support adjustment one embodiment of steel plate system of the invention, the Steel corridor bracket 2 It links into an integrated entity with stiffened column 1, to guarantee bonding strength.
In Steel corridor bracket support adjustment one embodiment of steel plate system of the invention, every piece on four angle points 25~50mm is stretched out than the outside for the shock-proof ball shaped steel bearing 8 being fixed thereon in the outside for adjusting steel plate 7, to facilitate adjustment steel plate 7 are welded and fixed with shock-proof ball shaped steel bearing 8.
As illustrated in fig. 1 and 2, the present invention provides a kind of installation method of Steel corridor bracket support adjustment steel plate, comprising:
Step S1 buries the pre- of monolith according to Steel Structural Design drawing requirement on completed Steel corridor bracket 2 Bury steel plate 3;
Step S2, after the pre-embedded steel slab 3 completes the fixation with the Steel corridor bracket 2, steel construction described in repetition measurement The vertical and lateral absolute altitude of vestibule bracket 2, to determine the thickness of adjustment steel plate 7;
Step S3, on the central point and four angle points being arranged symmetrically with the central point of the pre-embedded steel slab 3 respectively Fix one block of adjustment steel plate 7 for determining thickness;
The shock-proof ball shaped steel bearing 8 of monolith is fixed on five blocks of adjustment steel plates 7 by step S4.
Here, the present invention is asked for skybridge multilayer support quality control on construction difficulty in place is big, security risk is high Topic, adjustment steel plate of the invention are only used under support, and backing plate adjustment ensure that the horizontal absolute altitude of same layer support and different layers branch seat height Difference, in four angles of shock-proof ball shaped steel bearing and intermediate position and one week pad adjustment plate, each adjustment steel plate thickness is according to structure Each self-adjusting of absolute altitude, it is ensured that final precision improves the absolute altitude control quality of support;Meanwhile reducing repetition and promoting unloading tune It is whole it is in place improve efficiency for several times, reduce risk, can allow Steel corridor in place on shock-proof ball shaped steel bearing as early as possible, subtract It is repeatedly lifted up the security risk of bring risk and construction site less.By padding adjustment plate control in shock-proof ball shaped steel bearing region Support absolute altitude processed ensure that Steel corridor unloads rear multilayer end reaction in place completely and meets design requirement;The construction method So that multilayer support absolute altitude is effectively controlled, reduce error.Reduction, which is repeatedly lifted up, unloads the danger source carried and construction site Security risk.
In one embodiment of installation method of Steel corridor bracket support adjustment steel plate of the invention, step S3, described One piece of tune for determining thickness is fixed respectively on the central point of pre-embedded steel slab 3 and four angle points being arranged symmetrically with the central point After whole steel plate 7, further includes:
Adjustment steel plate 7 on four angle points is connected by steel plate integral.
Here, surrounding steel plate is integral by the adjustment plate connection of four corners, to guarantee the stability of adjustment steel plate 7.
In one embodiment of installation method of Steel corridor bracket support adjustment steel plate of the invention, in completed steel knot The pre-embedded steel slab 3 of monolith is buried on structure vestibule bracket 2, comprising:
Peg 4 and angle steel anchor foot 5 are set on the pre-embedded steel slab 3, and the peg 4 and angle steel anchor foot 5 are located at described pre- It buries in the one side that steel plate 3 is contacted with the Steel corridor bracket 2, the angle steel anchor foot 5 is inserted in the Steel corridor Vibrating in hole on bracket 2;
Grouting material 6 is filled between the Steel corridor bracket 2 and the contact surface of the pre-embedded steel slab 3, it is solid to guarantee Determine fastness.
In one embodiment of installation method of Steel corridor bracket support adjustment steel plate of the invention, step S1, according to steel Structural design drawing paper requirement, on completed Steel corridor bracket 2 before the pre-embedded steel slab 3 of embedded monolith, further includes:
The rear reinforcing bar binding in place of stiffened column 1 and the lifting of 2 overall processing of Steel corridor bracket is poured into concrete, to guarantee to connect Intensity.
In one embodiment of installation method of Steel corridor bracket support adjustment steel plate of the invention, step S4, by monolith Shock-proof ball shaped steel bearing 8 be fixed on five pieces adjustment steel plate 7 on step in,
The outside of every block on four angle points adjustment steel plate 7 is outer than the shock-proof ball shaped steel bearing 8 that is fixed thereon 25~50mm is stretched out in side, to facilitate being welded and fixed for adjustment steel plate 7 and shock-proof ball shaped steel bearing 8.
Specifically, can be buried on completed Steel corridor bracket 2 pre-buried according to Steel Structural Design drawing requirement Steel plate 3, using the grout hole being uniformly arranged on bracket, the dedicated grouting material of secondary pouring fills real, and the completion of pre-embedded steel slab 3 is multiple after pouring It surveys Steel corridor bracket 2 vertically and lateral absolute altitude determines the thickness of adjustment steel plate 7 on the basis of multilayer support highest point, In the sideline of standoff region pop-up support on the bracket for needing to adjust, adjustment plate side more every than support lengthens 25~50mm, uniformly draws The high control line of mark adds adjustment plate to connect for one week integral to bracket, adjustment plate specification 300*300mm, and adjustment plate is mainly arranged The construction of multilayer bracket adjustment plate is completed between in the holder and four angles end.
Illustrate that locally pad adjustment steel plate controls support absolute altitude construction method to bracket support in the present embodiment below with reference to Fig. 1, It includes the stiffened column 1 of steel concrete, and the Steel corridor bracket 2 of steel concrete, pre-embedded steel slab 3, peg 4, angle bar anchor foot 5, high intensity is specially With grouting material 6, steel plate 7, shock-proof ball shaped steel bearing 8 are adjusted.
Such as Fig. 1, left side is steel concrete stiffened column, and right side is steel concrete bracket, and stiffened column 1 and 2 entirety of Steel corridor bracket add Reinforcing bar binding pours concrete after work lifting is in place;Pre-embedded steel slab 3 and peg 4 and angle steel anchor foot 5 are processed into entire bracket pre-buried steel Plate is arranged peg under plate, is staggered with bracket top flange peg, and angle bar anchor foot is arranged under plate, and from vibrating, hole is inserted into;Then it pours High-intensitive dedicated grouting material 6, after pre-embedded steel slab is embedded, in bracket standoff region mounting and adjusting steel plate 7,300*300mm tune Whole steel plate 7 is mounted on central point and four angle points, and then surrounding steel plate is integral by the adjustment plate connection of four corners;Installation Shock-proof ball shaped steel bearing 8 completes the construction of high across Steel corridor multilayer support.
Illustrate that locally pad adjustment steel plate controls support absolute altitude construction method to bracket support in the present embodiment below with reference to Fig. 2, It includes steel pre-embedded steel slab 3, adjusts steel plate 7, shock-proof ball shaped steel bearing 8.
As shown in Fig. 2, after pre-embedded steel slab 3 is installed, repetition measurement pre-embedded steel slab, on the basis of multilayer support highest point, so Size is completed with steel construction main body afterwards to compare, determines the thickness of adjustment steel plate 7, in support area on needing the bracket adjusted The sideline of support is popped up in domain, and the size end more every than the size of shock-proof ball shaped steel bearing 8 for adjusting steel plate 7 lengthens 25~50mm, adjustment The specification of steel plate 7 is 300*300mm, is in quincuncial arrangement, adds within one week steel plate connection integral, adjustment steel plate 7 is mainly disposed to Among support and four angles end, adjustment steel plate 7 and pre-embedded steel slab 3 weld, steel material Q345B, Weld quality level two Grade shelves shock-proof ball shaped steel bearing 8, completes the construction of multilayer bracket adjustment plate.
Each embodiment in this specification is described in a progressive manner, the highlights of each of the examples are with other The difference of embodiment, the same or similar parts in each embodiment may refer to each other.
Obviously, those skilled in the art can carry out various modification and variations without departing from spirit of the invention to invention And range.If in this way, these modifications and changes of the present invention belong to the claims in the present invention and its equivalent technologies range it Interior, then the invention is also intended to include including these modification and variations.

Claims (10)

1. a kind of Steel corridor bracket support adjusts steel plate system characterized by comprising
Steel corridor bracket;
It is fixed on the pre-embedded steel slab of the monolith on the Steel corridor bracket;
Consolidate respectively on five blocks of adjustment steel plates, the central point of the pre-embedded steel slab and four angle points being arranged symmetrically with the central point Surely there is one block of adjustment steel plate;
It is fixed on the shock-proof ball shaped steel bearing of the monolith on five blocks of adjustment steel plates.
2. Steel corridor bracket support as described in claim 1 adjusts steel plate system, which is characterized in that four angle points On adjustment steel plate connected by steel plate it is integral.
3. Steel corridor bracket support as described in claim 1 adjusts steel plate system, which is characterized in that the steel construction connects Hole of vibrating is provided on corridor bracket;
Peg and angle steel anchor foot are provided on the pre-embedded steel slab, the peg and angle steel anchor foot are located at the pre-embedded steel slab and institute In the one side for stating the contact of Steel corridor bracket, the angle steel anchor foot be inserted in it is described vibrate in hole, the Steel corridor ox It is fixed after being solidified between leg and the pre-embedded steel slab by grouting material.
4. Steel corridor bracket support as described in claim 1 adjusts steel plate system, which is characterized in that the steel construction connects Corridor bracket links into an integrated entity with stiffened column.
5. Steel corridor bracket support as described in claim 1 adjusts steel plate system, which is characterized in that four angle points On the outside of every block of adjustment steel plate stretch out 25~50mm than the outside of shock-proof ball shaped steel bearing being fixed thereon.
6. a kind of installation method of Steel corridor bracket support adjustment steel plate characterized by comprising
According to Steel Structural Design drawing requirement, the pre-embedded steel slab of monolith is buried on completed Steel corridor bracket;
After the pre-embedded steel slab completes the fixation with the Steel corridor bracket, Steel corridor bracket described in repetition measurement vertically and Lateral absolute altitude, to determine the thickness of adjustment steel plate;
One piece of determination is fixed respectively on the central point and four angle points being arranged symmetrically with the central point of the pre-embedded steel slab The adjustment steel plate of good thickness;
The shock-proof ball shaped steel bearing of monolith is fixed on five blocks of adjustment steel plates.
7. the installation method of Steel corridor bracket support adjustment steel plate as claimed in claim 6, which is characterized in that described One piece of tune for determining thickness is fixed respectively on the central point of pre-embedded steel slab and four angle points being arranged symmetrically with the central point After whole steel plate, further includes:
Adjustment steel plate on four angle points is connected by steel plate integral.
8. the installation method of Steel corridor bracket support adjustment steel plate as claimed in claim 6, which is characterized in that complete At Steel corridor bracket on bury monolith pre-embedded steel slab, comprising:
Peg is set on the pre-embedded steel slab and angle steel anchor foot, the peg and angle steel anchor foot are located at the pre-embedded steel slab and institute In the one side for stating the contact of Steel corridor bracket, the angle steel anchor foot is inserted in the hole of vibrating on the Steel corridor bracket It is interior;
Grouting material is filled between the Steel corridor bracket and the contact surface of the pre-embedded steel slab.
9. the installation method of Steel corridor bracket support adjustment steel plate as claimed in claim 6, which is characterized in that according to steel Structural design drawing paper requirement, on completed Steel corridor bracket before the pre-embedded steel slab of embedded monolith, further includes:
The rear reinforcing bar binding in place of stiffened column and the lifting of Steel corridor bracket overall processing is poured into concrete.
10. the installation method of Steel corridor bracket support adjustment steel plate as claimed in claim 6, which is characterized in that will be whole The shock-proof ball shaped steel bearing of block is fixed in the step on five blocks of adjustment steel plates,
The outside of every block of adjustment steel plate on four angle points is stretched out than the outside for the shock-proof ball shaped steel bearing being fixed thereon 25~50mm.
CN201910195454.1A 2019-03-15 2019-03-15 Steel corridor bracket support adjusts steel plate system and its installation method Pending CN109898665A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910195454.1A CN109898665A (en) 2019-03-15 2019-03-15 Steel corridor bracket support adjusts steel plate system and its installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910195454.1A CN109898665A (en) 2019-03-15 2019-03-15 Steel corridor bracket support adjusts steel plate system and its installation method

Publications (1)

Publication Number Publication Date
CN109898665A true CN109898665A (en) 2019-06-18

Family

ID=66953231

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910195454.1A Pending CN109898665A (en) 2019-03-15 2019-03-15 Steel corridor bracket support adjusts steel plate system and its installation method

Country Status (1)

Country Link
CN (1) CN109898665A (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4488383B1 (en) * 2009-10-22 2010-06-23 株式会社美和テック Bridge bearing device
CN201649292U (en) * 2009-12-22 2010-11-24 上海磁浮交通发展有限公司 Three-way adjustable shock isolation ball type steel support
KR20110128396A (en) * 2010-05-24 2011-11-30 이창남 Pre-embedded anchor frame equipped with coupler and anchoring method of steel column thereof
CN102817324A (en) * 2012-09-06 2012-12-12 浙江金筑交通建设有限公司 Construction method for quickly installing pot rubber bearing by using epoxy resin mortar
CN203530837U (en) * 2013-10-11 2014-04-09 深圳市福田建安建设集团有限公司 Circular laminated rubber bearing mounting structure
CN203654465U (en) * 2013-12-26 2014-06-18 上海天华建筑设计有限公司 Sliding support of steel structure corridor
CN204785336U (en) * 2015-07-10 2015-11-18 中国水电建设集团港航建设有限公司 Electromechanical device's installation is adjusted and is filled up foot
CN105201162A (en) * 2015-10-14 2015-12-30 中建三局集团有限公司 Cast-in-situ plate type staircase with bracket type sliding supports and construction method thereof
CN205399687U (en) * 2016-03-08 2016-07-27 寇佳亮 Double tower building vestibule connecting device
CN106284677A (en) * 2016-08-24 2017-01-04 安徽瑶海钢构建设集团股份有限公司 A kind of steel frame construction on vestibule
CN208167992U (en) * 2018-04-16 2018-11-30 广东中辰钢结构有限公司 A kind of sliding support structure that girder steel is connect with concrete column
CN209958509U (en) * 2019-03-15 2020-01-17 上海建工七建集团有限公司 Steel plate adjusting system for bracket support of steel structure corridor

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4488383B1 (en) * 2009-10-22 2010-06-23 株式会社美和テック Bridge bearing device
CN201649292U (en) * 2009-12-22 2010-11-24 上海磁浮交通发展有限公司 Three-way adjustable shock isolation ball type steel support
KR20110128396A (en) * 2010-05-24 2011-11-30 이창남 Pre-embedded anchor frame equipped with coupler and anchoring method of steel column thereof
CN102817324A (en) * 2012-09-06 2012-12-12 浙江金筑交通建设有限公司 Construction method for quickly installing pot rubber bearing by using epoxy resin mortar
CN203530837U (en) * 2013-10-11 2014-04-09 深圳市福田建安建设集团有限公司 Circular laminated rubber bearing mounting structure
CN203654465U (en) * 2013-12-26 2014-06-18 上海天华建筑设计有限公司 Sliding support of steel structure corridor
CN204785336U (en) * 2015-07-10 2015-11-18 中国水电建设集团港航建设有限公司 Electromechanical device's installation is adjusted and is filled up foot
CN105201162A (en) * 2015-10-14 2015-12-30 中建三局集团有限公司 Cast-in-situ plate type staircase with bracket type sliding supports and construction method thereof
CN205399687U (en) * 2016-03-08 2016-07-27 寇佳亮 Double tower building vestibule connecting device
CN106284677A (en) * 2016-08-24 2017-01-04 安徽瑶海钢构建设集团股份有限公司 A kind of steel frame construction on vestibule
CN208167992U (en) * 2018-04-16 2018-11-30 广东中辰钢结构有限公司 A kind of sliding support structure that girder steel is connect with concrete column
CN209958509U (en) * 2019-03-15 2020-01-17 上海建工七建集团有限公司 Steel plate adjusting system for bracket support of steel structure corridor

Similar Documents

Publication Publication Date Title
CN104895101B (en) The construction method of raft foundation high accuracy integral built-in large diameter bolt group structure
CN102433935B (en) Mounting and positioning rack for shock isolation supporting seat
DK2488338T3 (en) Process for the preparation of tower segment-concrete finished parts of a wind power installation tower and formwork unit for production of concrete finished parts
JP2012102601A (en) Height-adjustable bearing device for structure and height adjustment method of bearing device for structure
KR20060093092A (en) The use of the bearing installation is involved the precast block and it for construction method of the bearing installation and the replacing methodof bearing installation
CN107859037B (en) A kind of installation and locating method of the installation positioning mechanism of large-scale embedded parts anchor structure
CN107386688A (en) Wedge-shaped temporary support
CN110042858A (en) A kind of installation method of skid-mounted reciprocating flow
KR101504728B1 (en) A device for position adjustment and flotation prevention of precast concrete slab panel and method for position adjustment and flotation prevention by using device for position adjustment and flotation prevention
CN109898665A (en) Steel corridor bracket support adjusts steel plate system and its installation method
CN109457980A (en) A kind of installation method of bracket device and overhanging unloading platform
JPH09100503A (en) Connecting jig of precast concrete slab
CN113338322A (en) Construction method of building vibration isolation foundation
CN112095825A (en) Vibration isolation structure of high-speed rail of underpass terminal building and construction method thereof
CN209958509U (en) Steel plate adjusting system for bracket support of steel structure corridor
CN107354874A (en) T beam beams bottom steel plate supertronic device
CN106759880A (en) Prefabricated superposed beam quickly positions adjustment frock and method with prefabricated post junction
CN207794322U (en) A kind of built-in fitting
CN105821770B (en) Connecting and locating method for multiple tower roots and large-size concrete bearing platform foundation of steel structure main tower
KR101259362B1 (en) Construction system of expansion joint for bridge
CN208586529U (en) A kind of gradient precast beam support leveling device
CN108824203A (en) A kind of gradient precast beam support leveling device
CN106149563B (en) Steel anchor beam accurate positioning device and installation method built in free-standing Sarasota
JP2004218348A (en) Laying method for concrete block
CN110397267A (en) Staircase shear wall formwork installation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination