CN109881711A - Scaffold recycling method when reverse construction eddy flow well bore wall - Google Patents

Scaffold recycling method when reverse construction eddy flow well bore wall Download PDF

Info

Publication number
CN109881711A
CN109881711A CN201910180183.2A CN201910180183A CN109881711A CN 109881711 A CN109881711 A CN 109881711A CN 201910180183 A CN201910180183 A CN 201910180183A CN 109881711 A CN109881711 A CN 109881711A
Authority
CN
China
Prior art keywords
scaffold
segment
construction
barrel
overhanging bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910180183.2A
Other languages
Chinese (zh)
Other versions
CN109881711B (en
Inventor
陈光中
王磊
金国帅
王军勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201910180183.2A priority Critical patent/CN109881711B/en
Publication of CN109881711A publication Critical patent/CN109881711A/en
Application granted granted Critical
Publication of CN109881711B publication Critical patent/CN109881711B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention provides scaffold recycling methods when a kind of eddy flow well bore wall reverse construction: first, set up the scaffold with construction first segment concrete tube wall, along the pre-buried several overhanging bars of barrel annular when concreting, each overhanging bar extends to center position, and overhanging bar extension elongation is greater than scaffold width;Secondly, directly excavate the second segment earthwork, scaffold lose support fall on overhanging bar exist, by overhanging bar protection in first segment barrel range;Then, after excavation, with guide chain lifting scaffold, after the suspension scaffold for cutting off first segment barrel, scaffold is integrally unloaded on the soil layer for falling on second segment by guide chain;Then, the construction of second segment concrete tube wall, still pre-buried overhanging bar when second segment barrel pours, by above-mentioned operation until Wall Construction finishes are carried out.Operation scaffold is recycled integrally in this method scaffold, without repeatedly removing and setting up, while saving cost of labor, also greatly shortens the construction period.

Description

Scaffold recycling method when reverse construction eddy flow well bore wall
Technical field
The present invention relates to foot hand is operated when construction scaffold construction method, especially eddy flow well bore wall reverse construction The method that frame is recycled.
Background technique
Whirling well is often built in the factory sites such as steel-making continuous casting or steel rolling workshop.Traditional eddy flow well bore wall reverse construction, soil After first segment excavates in side, scaffold is set up, scaffold branch is located on the soil layer not excavated, first segment concrete tube wall of constructing.By In soil layer be scaffold basis, if therefore scaffold exist, influence excavate the second segment earthwork, it is therefore necessary to scaffold is removed Excavate second segment again afterwards, second segment has excavated, and carries out concrete tube wall and applies man-hour requirement to set up scaffold again flat as construction Platform;Above-mentioned operation is repeated until Wall Construction finishes.Construction method scaffold in the prior art, which is repeatedly removed, repeatedly to be set up, investment Higher cost;And repeatedly set up the dismounting influence construction period.
Summary of the invention
To solve prior art problem, the repeated work for avoiding scaffold from setting up repeatedly, the present invention provides a kind of new apply Work method.
Particular technique means provided by the invention are:
Scaffold recycling method when a kind of eddy flow well bore wall reverse construction:
Firstly, the scaffold with construction first segment concrete tube wall is set up, if pre-buried along barrel annular when concreting Dry overhanging bar, each to overhang bar to center position extension, overhanging bar extension elongation is greater than scaffold width;
Secondly, directly excavate the second segment earthwork, scaffold, which loses support and falls on overhanging bar, to exist, by overhanging bar protection the One section of barrel range;
It then,, will by guide chain after the suspension scaffold for cutting off first segment barrel with guide chain lifting scaffold after excavation Scaffold is integrally unloaded and is fallen on the soil layer of second segment;
Then, the construction of second segment concrete tube wall, still pre-buried overhanging bar when second segment barrel pours, by above-mentioned work are carried out Sequence is until Wall Construction finishes.
This method scaffold make operate scaffold be integrally recycled, without repeatedly removing and setting up, save manually at This while, also greatly shortens the construction period.
Detailed description of the invention
Pre-buried overhanging bar in Fig. 1 first segment barrel;
Fig. 2 is along the pre-buried overhanging bar of barrel;
Fig. 3 scaffold overhangs in upper end;
Fig. 4 scaffold, which unloads, drops down onto earthwork top surface in hole;
Fig. 5 second segment Wall Construction and pre-buried overhanging bar;
Fig. 6 Wall Construction is completed.
Specific embodiment
Eddy flow well bore wall reverse construction, generally by three sections of barrel point, one section of earth excavation is constructed one section, and scaffold is built It is located in the earthwork that do not excavate, as Wall Construction platform.The present invention is the structure of straight tube for eddy flow well bore wall, especially suitable When eddy flow well bore wall reverse construction, design concept of the invention is to keep scaffold whole in lower layer's Wall Construction, is made Lower layer's earthwork can recycle after scraping out.
Scaffold recycling method provided by the invention is:
Firstly, the scaffold with construction first segment concrete tube wall is set up, if pre-buried along barrel annular when concreting Dry overhanging bar, each to overhang bar to center position extension, overhanging bar extension elongation is greater than scaffold width;
Secondly, directly excavate the second segment earthwork, scaffold, which loses support and falls on overhanging bar, to exist, by overhanging bar protection the One section of barrel range;
It then,, will by guide chain after the suspension scaffold for cutting off first segment barrel with guide chain lifting scaffold after excavation Scaffold is integrally unloaded and is fallen on the soil layer of second segment;
Then, the construction of second segment concrete tube wall, still pre-buried overhanging bar when second segment barrel pours, by above-mentioned work are carried out Sequence is until Wall Construction finishes.
This method scaffold make operate scaffold be integrally recycled, without repeatedly removing and setting up, save manually at This while, also greatly shortens the construction period.
Work progress of the invention is described in detail with reference to the accompanying drawing, Fig. 1 to Fig. 6 shows each step of the invention in order Suddenly Construction State is descended, overhangs bar 1, first segment barrel 2, scaffold 3, layer to be cut the earth 4, guide chain 5, second segment barrel 6, third in figure Section barrel 7, whirling well conical bottom 8.Concrete operation step is:
(1) after the completion of first segment earth excavation, scaffold construction first segment barrel is set up, first segment concrete tube wall pours When in pre-buried overhanging bar, overhang pole length and be greater than scaffold width, such as Fig. 1;Pre-buried overhanging bar is pre-buried along barrel annular, such as Fig. 2 It is shown.
(2) until excavating the second segment earthwork, when scaffold base foundation is scooped away, scaffold is hung on overhanging bar, is protected It holds in first segment barrel height, the second segment earthwork is dug to projected depth, sees Fig. 3.
(3) several guide chains are set along whirling well week circle, guide chain is connect with scaffold, will be embedded in the overhanging of first segment barrel in advance Bar is cut off, and it is as shown in Figure 4 to drop scaffold earthwork top surface, the state operated in cheating using guide chain.
(4) construction whirling well second segment barrel, and the pre-buried overhanging bar in second segment barrel concreting, such as Fig. 5 institute Show.
(5) above-mentioned operation is repeated, third section barrel of constructing is removed scaffold, bored until bowl wall portion construction is completed The construction at shape bottom.Conical bottom construction does not need scaffold, thus when final stage barrel pours be do not need again it is pre-buried Outstanding framed bent, Fig. 6 show the pre-designed figure of conical bottom, and scaffold is removed before conical bottom earth excavation.Wall Construction is completed, foot Hand cradle is exited using end.
If the construction of whirling well, direct dismounting scaffold, if there are also subsequent eddy flow well construction, it can be by guide chain by foot hand Frame integrally takes out, and is used for next eddy flow well construction.
The present invention provides construction methods, and scaffold is integrally kept leaving, is recycled, and reduce the duplication of labour, shorten Duration.

Claims (1)

1. scaffold recycling method when a kind of eddy flow well bore wall reverse construction:
Firstly, the scaffold with construction first segment concrete tube wall is set up, it is pre-buried several outstanding along barrel annular when concreting Rod, each to overhang bar to center position extension, overhanging bar extension elongation is greater than scaffold width;
Secondly, directly excavate the second segment earthwork, scaffold lose support fall on overhanging bar exist, by overhanging bar protection in first segment Barrel range;
Then, after excavation, scaffold is lifted with guide chain, after the suspension scaffold for cutting off first segment barrel, by guide chain by foot hand Frame is integrally unloaded and is fallen on the soil layer of second segment;
Then, the construction of second segment concrete tube wall is carried out, still pre-buried overhanging bar, straight by above-mentioned operation when second segment barrel pours It is finished to Wall Construction.
CN201910180183.2A 2019-03-11 2019-03-11 Method for recycling scaffold during reverse construction of cyclone well wall Active CN109881711B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910180183.2A CN109881711B (en) 2019-03-11 2019-03-11 Method for recycling scaffold during reverse construction of cyclone well wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910180183.2A CN109881711B (en) 2019-03-11 2019-03-11 Method for recycling scaffold during reverse construction of cyclone well wall

Publications (2)

Publication Number Publication Date
CN109881711A true CN109881711A (en) 2019-06-14
CN109881711B CN109881711B (en) 2020-12-04

Family

ID=66931578

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910180183.2A Active CN109881711B (en) 2019-03-11 2019-03-11 Method for recycling scaffold during reverse construction of cyclone well wall

Country Status (1)

Country Link
CN (1) CN109881711B (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204960280U (en) * 2015-09-15 2016-01-13 中铁四局集团有限公司 But integral hoisting and used repeatedly's scaffold

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204960280U (en) * 2015-09-15 2016-01-13 中铁四局集团有限公司 But integral hoisting and used repeatedly's scaffold

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
南京建设监理协会: "《建设工程监理履行安全生产职责培训教程》", 31 May 2017, 东南大学出版社 *

Also Published As

Publication number Publication date
CN109881711B (en) 2020-12-04

Similar Documents

Publication Publication Date Title
CN105672337B (en) The construction method of cast-in-place open caisson formwork system
KR100821663B1 (en) Construction method of Top-down concrete slab
KR20100101271A (en) Method for removing the superannuated build as top-down type
CN107460886A (en) A kind of lightweight steel construction assembles basis and its construction method of decoration integrated building
KR102333978B1 (en) Pileless-up wall demolition method
CN109881711A (en) Scaffold recycling method when reverse construction eddy flow well bore wall
JPH0464620A (en) Construction method for open caisson and its device
JP4611108B2 (en) Integrated construction method of pile and column
CN109440781A (en) Active inclination foundation pit supporting method with double rows of piles
AU2019101512B4 (en) A method of constructing a column, a subterranean structure, and a structure made from the method.
JPH03100225A (en) Inverted hitting construction using multifunction working floor and the same floor
GB2067623A (en) Method for supporting buildings
JP4505841B2 (en) Construction method of pier frame using Izutsuru foundation
JP4504752B2 (en) Construction method and apparatus for tubular precast concrete member
CN108385694A (en) Interlocking pile meets deeper subsurface barrier construction method
CN112502142B (en) Concrete retaining wall device convenient for manual hole digging pier construction and reinforcing method thereof
JPH04319121A (en) Construction of underground base of building
CN201165662Y (en) Cover-shaped tools of artificial hole-digging filling pile concrete breast wall
EP1662049A2 (en) Method for positioning concrete piles
KR20010092596A (en) Stabilization method for a construction floating by floatage
JP2620731B2 (en) Differential settlement correction method
JP3921094B2 (en) Basement diving method
KR100224459B1 (en) Construction method of slab for underground structure
BE1020119A3 (en) DEVICE FOR MAKING A FROZEN SLOT.
JP5194591B2 (en) House repair new foundation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant