CN109881582A - Cast-in-place Box Bridge bridge floor faces side building enclosure erection method - Google Patents

Cast-in-place Box Bridge bridge floor faces side building enclosure erection method Download PDF

Info

Publication number
CN109881582A
CN109881582A CN201910238699.8A CN201910238699A CN109881582A CN 109881582 A CN109881582 A CN 109881582A CN 201910238699 A CN201910238699 A CN 201910238699A CN 109881582 A CN109881582 A CN 109881582A
Authority
CN
China
Prior art keywords
supporting member
bridge
type steel
steel skeleton
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201910238699.8A
Other languages
Chinese (zh)
Inventor
舒东辉
陈祝廷
郑兴宇
鲍海波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201910238699.8A priority Critical patent/CN109881582A/en
Publication of CN109881582A publication Critical patent/CN109881582A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to field of bridge construction, especially plant cast-in-place Box Bridge bridge floor and face side building enclosure erection method, carry out as follows: production sizing punching block: welding supporting member on the type steel skeleton in the outside of sizing punching block;After type steel skeleton installation is in place, the upright bar of guard rail and supporting member are connected with cruciform fastening for falsework;The supporting member of every fixation type steel skeleton is connected with horizontal cross bar;Temporary protection railing is installed in upright bar, then carries out box girder webs;It is inversely removed after the completion of pouring according to erection sequence.The method of the present invention is easy to operate, accelerates the connection of steel pipe and fashioned iron, improves work efficiency and construction precision, and steel pipe and cruciform fastening for falsework can be recycled after the later period removes, and reduce cost.

Description

Cast-in-place Box Bridge bridge floor faces side building enclosure erection method
Technical field
The present invention relates to field of bridge construction, especially a kind of cast-in-place Box Bridge bridge floor faces side building enclosure erection method.
Background technique
With the increasingly standardization of construction, portability, people have the construction method in work progress higher It is required that.Traditional fashioned iron and steel pipe connection method has been far from satisfying the requirement of construction.During construction of cast-in-situ box-beam, the wing Template die plate is usually using sizing punching block, and lower to be supported with channel steel frame, bridge temporary protection railing is mounted in channel steel frame.According to Traditional method, the type of attachment between channel steel frame and channel steel frame, between channel steel frame and bridge temporary protection railing are general It is connected using bolt system, or welding.This traditional method complex procedures, a large amount of uses, which are bolted, leads to the duration of constructing Greatly increase, when the later period removes, as bolt deforms, corrode, screw thread is impaired situations such as will be difficult to dismantle, can only be using destroying Formula dismantling, causes difficulty of construction further to increase, duration lag.
Summary of the invention
In order to solve the above technical problems, the present invention uses a kind of reduction construction personnel's workload, showing for working efficiency is improved It pours Box Bridge bridge floor and faces side building enclosure erection method.
The present invention adopts the following technical scheme:
A kind of cast-in-place Box Bridge bridge floor faces side building enclosure erection method, carries out as follows:
1) production sizing punching block: supporting member is welded on the type steel skeleton in the outside of sizing punching block;
2) after type steel skeleton installation is in place, the upright bar of guard rail and supporting member are connected with cruciform fastening for falsework;
3) supporting member of every fixation type steel skeleton is connected with horizontal cross bar;
4) temporary protection railing is installed in upright bar, then carries out box girder webs;
5) it is inversely removed after the completion of pouring according to erection sequence.
Compared with prior art, the beneficial effects of the present invention are:
This invention simplifies working procedures, accelerate the progress of installation and dismounting, have saved cost, are reducing construction personnel's work While amount, construction progress is accelerated, improves working efficiency and construction precision.
Detailed description of the invention
Fig. 1 is effect picture of the invention;
Fig. 2 is the side view of Fig. 1;
Fig. 3 is usage state diagram of the invention;
In figure: sizing punching block 1;Type steel skeleton 2;Supporting member 3;Guard rail upright bar 4;Horizontal cross bar 5;Cruciform fastening for falsework 6.
Specific embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is further described.
A kind of cast-in-place Box Bridge bridge floor faces side building enclosure erection method, carries out as follows:
1) production sizing punching block 1: two diameters of welding are 48mm on the type steel skeleton 2 in the outside of sizing punching block 1, and wall thickness is 3.5mm, length are that the steel pipe of 200mm is as shown in Figure 2 as supporting member 3().
2) after type steel skeleton 2 is installed in place, guard rail upright bar 4 is connect with the cruciform fastening for falsework 6 of supporting member 3.
3) two horizontal cross bars 5 disposed in parallel of the supporting member 3 of every fixation type steel skeleton 2 are connected, fashioned iron Skeleton 2 is one-piece construction, is equidistantly connected by horizontal cross bar 5, and will be supported by cruciform fastening for falsework 6 and connected with horizontal cross bar 5 Connect (as shown in Figure 1,3).
4) guard rail upright bar 4 is arranged in protective frame upright bar 4 according to one of the every 1.5 ~ 2m of spacing of type steel skeleton 2 setting Horizontal steel tube installs Dense mesh screen between guard rail column 4 and horizontal steel tube, and guard rail is made to form wide 1.5 ~ 2m, high 1.2m Extraordinary maintenance structure;Then box girder webs are carried out.
5) it is inversely removed after the completion of pouring according to erection sequence.
Type steel skeleton in the present embodiment is welded by channel steel, and supporting member is welded on the fashioned iron on the outside of sizing punching block On.
The present embodiment keeps working procedure easier using cruciform fastening for falsework, speed of application faster, and steel pipe and cross buckle Part can be used in turn, and reduce the cost of construction.
The above is only a specific embodiment of the invention, but are not limited to this to protection of the invention, all this technology necks Field technique personnel it is thinkable to the technical program technical characteristic propose equivalent change or replacement, all cover in the present invention Protection scope within.

Claims (1)

1. a kind of cast-in-place Box Bridge bridge floor faces side building enclosure erection method, carry out as follows:
1) production sizing punching block: supporting member is welded on the type steel skeleton in the outside of sizing punching block;
2) after type steel skeleton installation is in place, the upright bar of guard rail and supporting member are connected with cruciform fastening for falsework;
3) supporting member of every fixation type steel skeleton is connected with horizontal cross bar;
4) temporary protection railing is installed in upright bar, then carries out box girder webs;
5) it is inversely removed after the completion of pouring according to erection sequence.
CN201910238699.8A 2019-03-27 2019-03-27 Cast-in-place Box Bridge bridge floor faces side building enclosure erection method Withdrawn CN109881582A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910238699.8A CN109881582A (en) 2019-03-27 2019-03-27 Cast-in-place Box Bridge bridge floor faces side building enclosure erection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910238699.8A CN109881582A (en) 2019-03-27 2019-03-27 Cast-in-place Box Bridge bridge floor faces side building enclosure erection method

Publications (1)

Publication Number Publication Date
CN109881582A true CN109881582A (en) 2019-06-14

Family

ID=66934697

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910238699.8A Withdrawn CN109881582A (en) 2019-03-27 2019-03-27 Cast-in-place Box Bridge bridge floor faces side building enclosure erection method

Country Status (1)

Country Link
CN (1) CN109881582A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100138433A (en) * 2009-06-25 2010-12-31 (주)에스앤씨산업 Prestressed steel composite girder with prestressed non-introducing portions provided at both ends of lower flange casing concrete, manufacturing method thereof, and rahmen structure and construction method thereof
CN204899260U (en) * 2015-07-30 2015-12-23 中铁隧道集团四处有限公司 Assembled guardrail bar of can relieving a garrison
CN108560778A (en) * 2018-05-11 2018-09-21 陈振伟 A kind of punching block net cast-in-place concrete sandwiched thermal-insulating wall structure and its building method
CN208294079U (en) * 2018-04-23 2018-12-28 中建一局集团第三建筑有限公司 A kind of detachable set shaped steel formwork concrete operating platform

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100138433A (en) * 2009-06-25 2010-12-31 (주)에스앤씨산업 Prestressed steel composite girder with prestressed non-introducing portions provided at both ends of lower flange casing concrete, manufacturing method thereof, and rahmen structure and construction method thereof
CN204899260U (en) * 2015-07-30 2015-12-23 中铁隧道集团四处有限公司 Assembled guardrail bar of can relieving a garrison
CN208294079U (en) * 2018-04-23 2018-12-28 中建一局集团第三建筑有限公司 A kind of detachable set shaped steel formwork concrete operating platform
CN108560778A (en) * 2018-05-11 2018-09-21 陈振伟 A kind of punching block net cast-in-place concrete sandwiched thermal-insulating wall structure and its building method

Similar Documents

Publication Publication Date Title
CN101974974B (en) Support device for template for construction of steel structure concrete floor slab
CN101787796A (en) Suspended formwork bracing system for steel structure concrete floor slab construction
CN103362069B (en) Steel and concrete combined box girder concrete wing plate formwork and construction method
CN211229608U (en) Safety rope stand column for steel structure construction
CN101701494B (en) Detachable convenient support device of steel structure building template and use method thereof
CN214272431U (en) Detachable assembled wallboard connection structure
CN106499173A (en) Based on the aluminum alloy mould plate mechanism that BIM technology is used for building floor construction
CN203475310U (en) Formwork for concrete slabs of composite steel-concrete box girders
CN109881582A (en) Cast-in-place Box Bridge bridge floor faces side building enclosure erection method
CN201539098U (en) Detachable convenient support device of steel structure building template
CN216616848U (en) Beam plate post-cast strip supporting and mold sealing structure
CN202745353U (en) Tool-type overhanging scaffold
CN201144524Y (en) Reinforcement for detached wall stud
CN201695661U (en) Component for arranging external suspending bracket of window
CN212247894U (en) A concrete placement support device for steel-concrete composite beam
CN211597650U (en) Overhanging type scaffold
CN210396103U (en) Connecting piece for shear wall template system, external wall panel and shear wall template system
CN109898860A (en) A kind of fabricated assembly overall shear wall formwork bracket reducing fracture width
CN207003765U (en) Assembling type steel structure builds self-bearing type steel truss form bracing system
CN114000440A (en) Truss base installation cantilever structure device and method
CN105587115A (en) Climbing frame fixing device and method for preventing exterior finish from being damaged
CN207109599U (en) A kind of form removable of support cast-in-place concrete continuous beam and erecting device
CN110847529A (en) Simple to operate's pin-connected panel railing
CN203558672U (en) Connecting structure for reinforced concrete wall and construction elevator attachment rack
CN107780644B (en) Operation platform for elevator shaft construction and use method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20190614