CN109868749A - A kind of steel truss girder hole-specifically sets up closure mouth wind-resistance locking device and application method - Google Patents

A kind of steel truss girder hole-specifically sets up closure mouth wind-resistance locking device and application method Download PDF

Info

Publication number
CN109868749A
CN109868749A CN201910198903.8A CN201910198903A CN109868749A CN 109868749 A CN109868749 A CN 109868749A CN 201910198903 A CN201910198903 A CN 201910198903A CN 109868749 A CN109868749 A CN 109868749A
Authority
CN
China
Prior art keywords
steel truss
truss girder
wind
locking device
inner sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910198903.8A
Other languages
Chinese (zh)
Other versions
CN109868749B (en
Inventor
徐平安
毛伟琦
涂满明
卢鹏
黄晓剑
李方峰
刘建华
潘军
余本俊
孙刘洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
Original Assignee
China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Group Co Ltd MBEC filed Critical China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority to CN201910198903.8A priority Critical patent/CN109868749B/en
Publication of CN109868749A publication Critical patent/CN109868749A/en
Application granted granted Critical
Publication of CN109868749B publication Critical patent/CN109868749B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of steel truss girders hole-specifically to set up closure mouth wind-resistance locking device and method, and the A for being used to have set up is across steel truss girder and across the steel truss girder carry out temporary locking of B to be set up comprising two telescopic arms, rear cross beam and two top-pushing mechanisms;Two telescopic arms are respectively arranged the brace two sides in A across steel truss girder along direction across bridge, and telescopic arm includes outer sleeve, inner sleeve, driving mechanism;Outer sleeve is placed in A of the A across steel truss girder across on lower boom;Inner sleeve portion is located in outer sleeve;Driving mechanism is set in outer sleeve and is connected with inner sleeve, for driving inner sleeve along vertical bridge Xiang Yundong;Rear cross beam connects two outer sleeves;It is formed between the inner sleeve of two telescopic arms for accommodating accommodating area of B of the B across steel truss girder across lower boom;Two top-pushing mechanism one end are individually fixed on two inner sleeves and are located at outside outer sleeve, and the other end can be extended or be bounced back towards accommodating area along direction across bridge.The present invention whole wind loading rating during steel truss erection can be improved.

Description

A kind of steel truss girder hole-specifically sets up closure mouth wind-resistance locking device and application method
Technical field
The present invention relates to science of bridge building superstructure steel truss girder hole-specifically Construction Techniques for Erection fields, and in particular to a kind of steel truss Beam hole-specifically sets up closure mouth wind-resistance locking device and application method.
Background technique
In existing highway bridge engineering Superstructure Construction, hole-specifically erection method is such as the multi-joint longspan steel truss girder of general multispan Under: longspan steel truss girder by beam transportation vehicle vertical shift, it is traversing go to river harbour to steel truss girder after, transport is to frame aperture position, in one It is first directly set up across steel truss girder using large-scale floating crane, except head across in addition to remaining across steel truss girder assist hole-specifically pacifying by diamond shape girder steel hanger Dress completes a steel truss girder until setting up.
However, annual March~October, bridge site region takes place frequently unpredictalbe hurricane or squall line wind, steel truss erection rank 10 years one highest wind velocities met of section reach 39.25m/s, on the one hand, superpower squall line wind once damaged steel truss girder and goes to river harbour And large-scale floating crane;On the other hand, the steel truss girder wait set up close up with the steel truss girder set up when docking process, and the two is closed up Wind resistance is weak, stability is poor, and it is low to close up docking safety.
Summary of the invention
In view of the deficiencies in the prior art, the purpose of the present invention is to provide a kind of steel truss girders hole-specifically to set up closure mouth Wind-resistance locking device, whole wind loading rating, guarantees safety of setting a roof beam in place during hurricane or squall line wind during steel truss erection can be improved.
To achieve the above objectives, the technical solution adopted by the present invention is that: a kind of steel truss girder hole-specifically sets up closure mouth wind resistance lock Determine device, the A for being used to have set up is across steel truss girder and across the steel truss girder carry out temporary locking of B to be set up comprising:
Two telescopic arms are used to be respectively arranged the brace two sides in A across steel truss girder, the telescopic arm packet along direction across bridge It includes:
Outer sleeve is used to be placed in A of the A across steel truss girder across lower boom;
Inner sleeve, part are located in the outer sleeve;
Driving mechanism is set in outer sleeve and is connected with inner sleeve, is used to drive the inner sleeve along vertical bridge Xiang Yun It is dynamic;
Rear cross beam connects two outer sleeves;
It is formed between the inner sleeve of two telescopic arms for accommodating accommodating area of B of the B across steel truss girder across lower boom;
Two top-pushing mechanisms, two described top-pushing mechanism one end are individually fixed on two inner sleeves and are located at outer sleeve Outside, the other end can be extended or be bounced back towards accommodating area along direction across bridge.
Further, it is also connected by connection structure between two outer sleeves, the rear cross beam and connection structure interval are arranged.
Further, counter-force seat is equipped in the outer sleeve, the driving mechanism is connected with counter-force seat.
Further, the top-pushing mechanism uses jack, and the jack is connected with inner sleeve, and its power output end For supporting B across lower boom.
Further, top surface of the one end of the inner sleeve far from outer sleeve from A across lower boom extends and is formed to bottom surface One extension, the top-pushing mechanism are connected with extension, and be located at A across the top surface of lower boom below.
Further, offered respectively on the outer sleeve and inner sleeve the oil pipe for drawing driving mechanism hole and For drawing the hole of the oil pipe of top-pushing mechanism.
Further, the wind-resistance locking device further includes control system, the control system and driving mechanism and pushing tow Mechanism is connected, and for controlling driving mechanism and top-pushing mechanism executes corresponding actions respectively.
The present invention also provides a kind of application methods of wind-resistance locking device as described above, include the following steps:
In the assembled wind-resistance locking device in A across steel truss girder closure mouth end;
B is lifted by crane to align across steel truss girder to across the steel truss girder closure mouth of B and across the steel truss girder closure mouth of A;
Inner sleeve to two top-pushing mechanisms are driven to be located at two sides of the B across lower boom direction across bridge by driving mechanism;
Start two top-pushing mechanisms and be held in two sides of the B across lower boom direction across bridge respectively to it, completes temporary locking.
Further, further include following steps after completing temporary locking:
When completing B across steel truss girder and after A across steel truss girder closure, releasing temporary locking.
Further, the step of B is aligned across steel truss girder to across the steel truss girder closure mouth of B and across the steel truss girder closure mouth of A is being lifted by crane In, further include the steps that adjusting B across steel truss girder closure mouth position by two top-pushing mechanisms.
Compared with the prior art, the advantages of the present invention are as follows:
(1) using wind-resistance locking device can with across the steel truss girder closure mouth of temporary locking A and across the steel truss girder closure mouth of B, make A across Steel truss girder and B are linked together across steel truss girder, and raising whole wind loading rating during setting a roof beam in place guarantees B across steel truss girder, diamond shape girder steel hanger Etc. structures safety, weld stable work surface be provided for across the steel truss girder lower boom of A and across the steel truss girder lower boom of the B mouth that joins the two sections of a bridge, etc.
(2) a kind of steel truss girder of the invention hole-specifically sets up closure mouth wind-resistance locking device and is provided simultaneously with adjustment B across steel truss girder To bit function, there is no need to the thrustor of lower boom closure mouth adjustment is in addition arranged for lower boom closure.
(3) it is efficient hole-specifically to set up closure mouth wind resistance locking means method safety to a kind of steel truss girder of the invention, is not required to additional Increase excessive parts, structure is simple, convenient to use.
Detailed description of the invention
Fig. 1 is wind-resistance locking device elevation provided in an embodiment of the present invention;
Fig. 2 is wind-resistance locking device plan view provided in an embodiment of the present invention.
In figure: 1, A is across steel truss girder;10, brace;11, A is across lower boom;2, B is across steel truss girder;20, B is across lower boom;3, it stretches Arm;30, outer sleeve;31, inner sleeve;310, extension;32, driving mechanism;4, rear cross beam;5, accommodating area;6, top-pushing mechanism;7, Counter-force seat;8, pin shaft;9, connection structure.
Specific embodiment
Invention is further described in detail with reference to the accompanying drawings and embodiments.
Referring to figure 1 and figure 2, the embodiment of the invention provides a kind of steel truss girders hole-specifically to set up closure mouth wind resistance locking dress It sets, the A for being used to have set up carries out temporary locking, the wind-resistance locking device across steel truss girder 2 across steel truss girder 1 and B to be set up Including two telescopic arms 3, rear cross beam 4 and two top-pushing mechanisms 6;
Referring to figs. 1 and 2, two telescopic arms 3 are respectively arranged 10 two sides of brace in A across steel truss girder 1 along direction across bridge, Telescopic arm 3 includes outer sleeve 30, inner sleeve 31 and driving mechanism 32.
Outer sleeve 30 in the present embodiment present it is U-shaped, it is U-shaped list limb be box-structure, by 12~16mm of thickness steel plate weld It connects, is connected between U-shaped list limb using box-structure connection structure;Outer sleeve 30 is placed in A of the A across steel truss girder 1 across lower boom On 11,31 one end of inner sleeve is located in outer sleeve 30, and the other end extends to outside outer sleeve 30;Driving mechanism 32 is set to outer sleeve 30 It is interior, and its power output end is connected with inner sleeve 31, and driving mechanism 32 can drive inner sleeve 31 along vertical bridge Xiang Yundong, realize Inner sleeve 31 is located at the part outside outer sleeve 30 can and court mobile towards the direction close to B of the B across steel truss girder 2 across lower boom 20 Direction far from B of the B across steel truss girder 2 across lower boom 20 is mobile;
Referring to figs. 1 and 2,4 both ends of rear cross beam are separately connected two outer sleeves 30;
It is shown in Figure 2, it is formed between the inner sleeve 31 of two telescopic arms 3 for accommodating B of the B across steel truss girder 2 across lower edge The accommodating area 5 of bar 20;Two top-pushing mechanisms, 6 one end is individually fixed on two inner sleeves 31 and is located at outside corresponding outer sleeve 30, separately One end can extend or bounce back towards accommodating area 5 along direction across bridge, in this way when B is located at accommodating area 5 across lower boom 20, two pushers Structure 6 is extended along direction across bridge and is supported respectively in B across 20 two sides of lower boom, to lock B across lower boom 20.
When installation, outer sleeve 30 and A are closely connected across 1 endpoint node brace of steel truss girder, 10 outer surfaces, and rear cross beam 4 and A are across steel truss 1 endpoint node brace 10 of beam is closely connected, and if any gap, sheet metal pad can be used.
B across steel truss girder by diamond shape girder steel hanger suspending after, can be with across the steel truss girder conjunction of temporary locking A using wind-resistance locking device Longkou and across the steel truss girder closure mouth of B, are linked together A across steel truss girder across steel truss girder and B, raising whole wind resistance energy during setting a roof beam in place Power guarantees that B is that across the steel truss girder lower boom of A and across the steel truss girder lower boom of B close across the structures such as steel truss girder, diamond shape girder steel hanger safety Longkou welding provides stable work surface.
In order to gather materials on the spot, top-pushing mechanism 6 uses jack, and jack is connected with inner sleeve 31, and its power output end For supporting B across lower boom 20;In the present embodiment, top-pushing mechanism 6 is arranged in inner sleeve 31.It of courses, driving mechanism 32 Jack can also be used.
In the case where not carrying out temporary locking, 31 retracted state of inner sleeve, inner sleeve 31 is located at the one end in 30 outside of outer sleeve not B is contacted across lower boom 20;In the locked state, B is located at the length in accommodating area 5 across lower boom 20 and is greater than 6 institute of top-pushing mechanism Using the diameter of jack, it is ensured that the jack can lock B across lower boom 20.
Outer sleeve can be protruded into inner sleeve 31 when lock state when the range of driving mechanism 32 is greater than retracted state Length in 30.
Referring to figs. 1 and 2, it is also connected by connection structure 9 between two outer sleeves 30, box is used in the present embodiment The connection structure of structure, rear cross beam 4 and the interval of connection structure 9 are arranged, it is ensured that in this locking device in use, rear cross beam 4 and connection structure 9 Along indulging bridge to being divided into 10 two sides of brace and be held in brace 10.Using brace 10 as load mechanism, pass through rear cross beam 4 and connection Connecing is 9 to support brace 10, and after locking B is across lower boom 20, if there is high wind conditions, B is produced across lower boom 20 because of strong wind The power such as raw torsion can be transferred to brace 10, be finally transmitted to A across steel truss girder 1, ensure that in wind-resistance locking device Safety and stability.
It is shown in Figure 1, counter-force seat 7 is equipped in outer sleeve 30, driving mechanism 32 is connected with counter-force seat 7.Specifically, it drives The both ends of mechanism 32 are connected with counter-force seat 7 and inner sleeve 31 respectively by pin shaft 8.
Shown in Figure 1, top surface of the one end of inner sleeve 31 far from outer sleeve 30 from A across lower boom 11 extends simultaneously to bottom surface An extension 310 is formed, top-pushing mechanism 6 is connected with extension 310, and is located at top surface of the A across lower boom 11 or less.
The hole of the oil pipe for drawing driving mechanism 32 is offered on outer sleeve 30 and inner sleeve 31 respectively and for drawing The hole of the oil pipe of top-pushing mechanism 6 out.
Wind-resistance locking device further includes control system, and control system is connected with driving mechanism 32 and top-pushing mechanism 6, and is used for Control driving mechanism 32 and top-pushing mechanism 6 execute corresponding actions respectively.
The embodiment of the invention also provides the application methods of above-mentioned wind-resistance locking device, include the following steps:
S1: in A across the closure mouth end assembly wind-resistance locking device of steel truss girder 1, inner sleeve 31 retracts outer sleeve 30 at this time;
S2: diamond shape girder steel hanger is installed across the top boom end of steel truss girder 1 in A, large-scale floating crane ship lifts by crane B across steel truss girder 2 To B across the closure mouth of steel truss girder 2 and A across the closure mouth contraposition of steel truss girder 1;
S3: 31 to two top-pushing mechanism 6 of inner sleeve is driven to be located at B across 20 direction across bridge of lower boom by driving mechanism 32 Two sides;
S4: two top-pushing mechanisms 6 of starting are held in two sides of the B across 20 direction across bridge of lower boom to it respectively, complete temporary locking;
S5: B is welded across the closure mouth of steel truss girder 2 and A across the closure oral area point of steel truss girder 1, when completion B is across steel truss girder 2 After joining the two sections of a bridge, etc with A across steel truss girder 1, temporary locking is released.
In lifting by crane the step of B is aligned across the closure mouth of steel truss girder 2 and A across the closure mouth of steel truss girder 1 across steel truss girder 2 to B, if any It needs, further includes the steps that adjusting B by two top-pushing mechanisms 6 across the closure of steel truss girder 2 mouth position.Specifically, start top-pushing mechanism 6, the accurate B that adjusts makes itself and A across the closure mouth exactitude position of lower boom 11 across the closure of lower boom 20 mouth position.Therefore, which locks Determine device and be provided simultaneously with across the steel truss girder lower boom closure of adjustment B to bit function, there is no need to lower boom closure mouth tune is in addition arranged Whole thrustor.
A kind of steel truss girder of the invention hole-specifically set up closure mouth wind resistance locking means it is safe and efficient, it is extra to be not required to additionally increase Component, structure is simple, convenient to use.
The present invention is not limited to the above-described embodiments, for those skilled in the art, is not departing from Under the premise of the principle of the invention, several improvements and modifications can also be made, these improvements and modifications are also considered as protection of the invention Within the scope of.The content being not described in detail in this specification belongs to the prior art well known to professional and technical personnel in the field.

Claims (10)

1. a kind of steel truss girder hole-specifically sets up closure mouth wind-resistance locking device, the A for being used to have set up is across steel truss girder (1) and to frame If B across steel truss girder (2) carry out temporary locking, characterized in that it comprises:
Two telescopic arms (3) are used to be respectively arranged brace (10) two sides in A across steel truss girder (1) along direction across bridge, described flexible Arm (3) includes:
Outer sleeve (30) is used to be placed in A of the A across steel truss girder (1) across lower boom (11);
Inner sleeve (31), part are located in the outer sleeve (30);
Driving mechanism (32) is set in outer sleeve (30) and is connected with inner sleeve (31), is used to drive the inner sleeve (31) along vertical bridge Xiang Yundong;
Rear cross beam (4) connects two outer sleeves (30);
It is formed between the inner sleeve (31) of two telescopic arms (3) for accommodating B receipts across lower boom (20) of the B across steel truss girder (2) Hold area (5);
Two top-pushing mechanisms (6), two described top-pushing mechanism (6) one end are individually fixed on two inner sleeves (31) and are located at outer Outside, the other end can be extended or be bounced back towards accommodating area (5) along direction across bridge sleeve (30).
2. wind-resistance locking device as described in claim 1, it is characterised in that: also pass through connection between two outer sleeves (30) It is (9) connection, the rear cross beam (4) and connection structure (9) interval are arranged.
3. wind-resistance locking device as described in claim 1, it is characterised in that: counter-force seat (7) are equipped in the outer sleeve (30), The driving mechanism (32) is connected with counter-force seat (7).
4. wind-resistance locking device as described in claim 1, it is characterised in that: the top-pushing mechanism (6) uses jack, described Jack is connected with inner sleeve (31), and its power output end is for supporting B across lower boom (20).
5. wind-resistance locking device as described in claim 1, it is characterised in that: the inner sleeve (31) is far from outer sleeve (30) One end extends to bottom surface across the top surface of lower boom (11) from A and is formed an extension (310), the top-pushing mechanism (6) and extension Portion (310) is connected, and is located at top surface of the A across lower boom (11) or less.
6. wind-resistance locking device as described in claim 1, it is characterised in that: divide on the outer sleeve (30) and inner sleeve (31) The hole of the oil pipe for drawing driving mechanism (32) and the hole of the oil pipe for drawing top-pushing mechanism (6) are not offered.
7. wind-resistance locking device as described in claim 1, it is characterised in that: the wind-resistance locking device further includes control system System, the control system are connected with driving mechanism (32) and top-pushing mechanism (6), and for controlling driving mechanism (32) and pusher Structure (6) executes corresponding actions respectively.
8. a kind of application method of wind-resistance locking device as described in claim 1, which comprises the steps of:
In A across the assembled wind-resistance locking device in steel truss girder (1) closure mouth end;
It lifts by crane B and is aligned across steel truss girder (2) closure mouth and A across steel truss girder (1) closure mouth across steel truss girder (2) to B;
Inner sleeve (31) to two top-pushing mechanisms (6) are driven to be located at B across lower boom (20) cross by driving mechanism (32) Bridge to two sides;
Start two top-pushing mechanisms (6) and be held in two sides of the B across lower boom (20) direction across bridge respectively to it, completes interim lock It is fixed.
9. application method as claimed in claim 8, which is characterized in that further include following steps after completing temporary locking:
After completion B joins the two sections of a bridge, etc across steel truss girder (2) and A across steel truss girder (1), temporary locking is released.
10. application method as claimed in claim 8, it is characterised in that: in lifting B across steel truss girder (2) to B across steel truss girder (2) It further include adjusting B across steel truss by two top-pushing mechanisms (6) in the step of closure mouth and A are across steel truss girder (1) closure mouth contraposition The step of beam (2) closure mouth position.
CN201910198903.8A 2019-03-15 2019-03-15 Wind-resistant locking device for erecting closure openings one by one through steel trussed beams and using method Active CN109868749B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910198903.8A CN109868749B (en) 2019-03-15 2019-03-15 Wind-resistant locking device for erecting closure openings one by one through steel trussed beams and using method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910198903.8A CN109868749B (en) 2019-03-15 2019-03-15 Wind-resistant locking device for erecting closure openings one by one through steel trussed beams and using method

Publications (2)

Publication Number Publication Date
CN109868749A true CN109868749A (en) 2019-06-11
CN109868749B CN109868749B (en) 2020-09-08

Family

ID=66920642

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910198903.8A Active CN109868749B (en) 2019-03-15 2019-03-15 Wind-resistant locking device for erecting closure openings one by one through steel trussed beams and using method

Country Status (1)

Country Link
CN (1) CN109868749B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111519538A (en) * 2020-04-17 2020-08-11 中铁大桥局集团有限公司 Hole-by-hole erection method for large-span continuous steel truss girder

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101130943A (en) * 2007-08-13 2008-02-27 中铁大桥勘测设计院有限公司 Pin-and-hole auxiliary closure method for steel girder bridge
CN101435182A (en) * 2008-12-30 2009-05-20 中铁大桥局股份有限公司 Steel bridge folding temporary locking method
KR20090109260A (en) * 2008-04-15 2009-10-20 삼성물산 주식회사 Construction method for joint of cantilever using horizontal brace and construction method for girder of bridge using the same
CN102776841A (en) * 2012-08-02 2012-11-14 贵州桥梁建设集团有限责任公司 Long-span steel truss suspension bridge jointing method and device
CN102888814A (en) * 2012-10-16 2013-01-23 上海城建市政工程(集团)有限公司 Construction method of continuous rigid frame bridge pushing closure
CN102966184A (en) * 2012-12-03 2013-03-13 中建一局钢结构工程有限公司 Reserving fold belt device for long-span steel structure truss and construction method of reserving fold belt
CN103290785A (en) * 2013-06-30 2013-09-11 中铁一局集团有限公司 Closure method for height variable continuous steel truss girder
CN106193622A (en) * 2016-07-29 2016-12-07 中国冶集团有限公司 H profile steel beam docking node locating installation method
JP2018003586A (en) * 2016-06-22 2018-01-11 ニッタ株式会社 Mounting aid and expansion device
CN108457191A (en) * 2018-01-31 2018-08-28 中交第二航务工程局有限公司 Large span T-steel structure beam sections for joining island bridge install closure method
CN109252446A (en) * 2018-08-28 2019-01-22 中交武汉港湾工程设计研究院有限公司 Steel box-girder longitudinal direction pushing closure constructing device and its construction method
CN109371848A (en) * 2018-12-10 2019-02-22 中交四公局第五工程有限公司 The longitudinal temporary connecting structure and method of suspension bridge concrete stiffening girder installation

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101130943A (en) * 2007-08-13 2008-02-27 中铁大桥勘测设计院有限公司 Pin-and-hole auxiliary closure method for steel girder bridge
KR20090109260A (en) * 2008-04-15 2009-10-20 삼성물산 주식회사 Construction method for joint of cantilever using horizontal brace and construction method for girder of bridge using the same
CN101435182A (en) * 2008-12-30 2009-05-20 中铁大桥局股份有限公司 Steel bridge folding temporary locking method
CN102776841A (en) * 2012-08-02 2012-11-14 贵州桥梁建设集团有限责任公司 Long-span steel truss suspension bridge jointing method and device
CN102888814A (en) * 2012-10-16 2013-01-23 上海城建市政工程(集团)有限公司 Construction method of continuous rigid frame bridge pushing closure
CN102966184A (en) * 2012-12-03 2013-03-13 中建一局钢结构工程有限公司 Reserving fold belt device for long-span steel structure truss and construction method of reserving fold belt
CN103290785A (en) * 2013-06-30 2013-09-11 中铁一局集团有限公司 Closure method for height variable continuous steel truss girder
JP2018003586A (en) * 2016-06-22 2018-01-11 ニッタ株式会社 Mounting aid and expansion device
CN106193622A (en) * 2016-07-29 2016-12-07 中国冶集团有限公司 H profile steel beam docking node locating installation method
CN108457191A (en) * 2018-01-31 2018-08-28 中交第二航务工程局有限公司 Large span T-steel structure beam sections for joining island bridge install closure method
CN109252446A (en) * 2018-08-28 2019-01-22 中交武汉港湾工程设计研究院有限公司 Steel box-girder longitudinal direction pushing closure constructing device and its construction method
CN109371848A (en) * 2018-12-10 2019-02-22 中交四公局第五工程有限公司 The longitudinal temporary connecting structure and method of suspension bridge concrete stiffening girder installation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111519538A (en) * 2020-04-17 2020-08-11 中铁大桥局集团有限公司 Hole-by-hole erection method for large-span continuous steel truss girder

Also Published As

Publication number Publication date
CN109868749B (en) 2020-09-08

Similar Documents

Publication Publication Date Title
CN107152078B (en) Hinge device and construction method for releasing welding internal stress of steel gallery by using hinge device
CN108978499A (en) A kind of oblique pull suspension cable co-operative system bridge erection method
US6701564B2 (en) System and method for positioning a pile cap underneath an existing elevated bridge assembly
CN113846563A (en) Construction method for side span and auxiliary span steel truss girder erection of large-span cable-stayed bridge
CN108756441A (en) A kind of hydraulic lifting flipped device and its hanging method for reducing tower
CN109868749A (en) A kind of steel truss girder hole-specifically sets up closure mouth wind-resistance locking device and application method
CN201103194Y (en) Girder for light steel factory building roofing underplate installation
CN107059644A (en) A kind of asymmetric unsupported installation method of sliding roadway arch
CN112523090B (en) Initial internode installation mode of steel truss girder cable-stayed bridge
CN101691741B (en) Bi-directional adjustable post-installed anchor device used for erecting steel cantilever beam
JP2009091816A (en) Method and device for constructing bridge
CN202913338U (en) Steel truss full-welded truss piece
CN104495653A (en) Multifunctional large-tonnage beam erecting crane and beam erecting method
CN210177371U (en) Cable-stayed cantilever type integrated bridge girder erection machine capable of piling
CN209568372U (en) A kind of interim articulated structure of suspension bridge stiffened steel girder
CN106368322A (en) Installing method of bidirectional symmetric oblique steel posts used between super high-rise building transfer stories
CN106223622A (en) A kind of tower concrete spreader
CN208152255U (en) A kind of indent coupled column and double girder steel connection structures
CN109629450A (en) The assembled laterally linear Matching and modification device of steel box girder cantilever, system and method
CN207512968U (en) A kind of splicing node of steel plate combined shear wall
CN206769237U (en) A kind of more siphon rain pipes installation screens device
CN208894190U (en) The connection structure of ethane cracking furnace and wherein steel member
CN107245956B (en) A kind of construction method of steel arch bridge
CN219751719U (en) Portal crane for short-distance lifting and slag turning
CN219316004U (en) Constructional engineering steel construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant