Prior art keywords
task
time
power plant
nuclear power
sub
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910072698.0A
Other languages
Chinese (zh)
Inventor
刘燕子
殷中平
贾明
高智彦
吴官寅
乔建旺
张建波
张学刚
徐晓梅
吴一谦
彭华清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China General Nuclear Power Corp
China Nuclear Power Engineering Co Ltd
CGN Power Co Ltd
Shenzhen China Guangdong Nuclear Engineering Design Co Ltd
Original Assignee
China General Nuclear Power Corp
China Nuclear Power Engineering Co Ltd
CGN Power Co Ltd
Shenzhen China Guangdong Nuclear Engineering Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China General Nuclear Power Corp, China Nuclear Power Engineering Co Ltd, CGN Power Co Ltd, Shenzhen China Guangdong Nuclear Engineering Design Co Ltd filed Critical China General Nuclear Power Corp
Priority to CN201910072698.0A priority Critical patent/CN109858795A/en
Publication of CN109858795A publication Critical patent/CN109858795A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Testing And Monitoring For Control Systems (AREA)
  • Monitoring And Testing Of Nuclear Reactors (AREA)

Abstract

The present invention provides the obtaining value method and system of a kind of nuclear power plant's operation task deadline, include the following steps: to classify to nuclear power plant's operation task, refine the specific steps of each sort operation task, it identifies all operationss task each sub-step minimum movements unit time, and calculates the theoretical operation time of each sub-step of all operationss task;The theoretical operation time of each sub-step of nuclear power plant's all operationss task is modified and is verified to obtain the value of respective operations task completion time.The present invention forms the obtaining value method of nuclear power plant's operation task deadline of systematization a kind of, the value working efficiency of significant increase Control Room of Nuclear Power Plant operation task deadline, and the value result of different appraisers has good consistency, effectively promotes the safety and economy of nuclear power plant's operation.

Description

A kind of obtaining value method and system of nuclear power plant's operation task deadline
Technical field
This technology invention is related to Human Factors Engineering Field, and in particular to a kind of value side of nuclear power plant's operation task deadline Method and system.
Background technique
The related statutory standard of international and national requires design of nuclear power plant process that should carry out task analysis, and with task point The methods and techniques of analysis carry out the design activity of related man-machine interface.Task analysis is that the task of operator is described in detail, according to The composition of task determines the movable details of people and the relationship of these movable functions and time.During task analysis, need For operator, the operating time of each operating procedure is estimated during execution task.This evaluation time is for evaluating Whether the workload of operator is suitable.The time estimation of current operation step, lacking correlation technique opinion can be for reference.Due to behaviour Make the time estimation result of step for the subsequent a series of analysis of task analysis and judgement, such as judging that operator works Whether load is suitable etc., is the important foundation work of task analysis.It is quasi- to pass through scientific research therefore thoroughly to solve above-mentioned deficiency, Unified operating procedure evaluation time standard is formulated, operating procedure evaluation time database is established, instructs projects task analysis In operating procedure time estimation work.
The country not yet establishes the obtaining value method of nuclear power plant's operation task deadline data of set of system at present, currently The time estimation of operating procedure, lacking correlation technique opinion can be for reference.Existing nuclear power plant's operation task deadline data take Value is all based on subjective judgement of the analysis personnel based on personal experience.The value of existing nuclear power plant's operation task deadline data Method lacks the systematization data structure analysis based on objective data as support.Data are all based on subjective observation and comment Valence mumber evidence, subjectivity is strong, susceptible, and consistency is poor.
Therefore, for the instant and history run state of monitoring system, the mass data of enterprise's production is saved, is enterprise's system It makes and the optimization of process provides information support, be badly in need of seeking-obtaining value method of nuclear power plant's operation task deadline a kind of and be System effectively promotes the safety and economy of nuclear power plant's operation.
Summary of the invention
The obtaining value method that the present invention is directed to nuclear power plant's operation task deadline data in the presence of the prior art lacks Systematization data structure analysis based on objective data is as support.Data be all based on it is subjective observe and evaluate data, The technical problems such as subjectivity is strong, susceptible, and consistency is poor, provide the value of nuclear power plant's operation task deadline a kind of Method.
The technical solution that the present invention is proposed with regard to above-mentioned technical problem is as follows: a kind of nuclear power plant's operation task deadline Obtaining value method includes the following steps: S100, classifies to nuclear power plant's operation task, refines the tool of each sort operation task Body step identifies all operationss task each sub-step minimum movements unit time, and calculates each sub-step of all operationss task The theoretical operation time;S200, the theoretical operation time of each sub-step of nuclear power plant's all operationss task is modified and is verified with Obtain the value of respective operations task completion time.
Wherein, the step 100 specifically includes following processing: if S110, the Control Room of Nuclear Power Plant operation times by dry type Business carries out systemic classification from operation work angle;S120, the whole subtypes for enumerating all types operation task, refinement are each The specific steps of sort operation task are to construct operating procedure category database;S130, identification each sub-step of all operationss task The minimum movements unit time, and classification is merged, form minimum movements unit time inventory;S140, according to minimum movements list Position time inventory constructs inventory minimum movements unit time, database deadline;S150, foundation minimum movements unit time are clear Single deadline data calculate the theoretical operation time of each sub-step of all operationss task, each to construct all operationss task The theoretical operation temporal database of sub-step.
Wherein, the step S200 specifically includes following processing: S210, according to nuclear power plant's practical operating experiences, corrects core The theoretical operation time of each sub-step of power plant's all operationss task is to construct theoretical operation temporal database;S220, to the reason It uses the dynamic experiment method verify by operating time database and is modified and adjusts to obtain correspondence according to verification result The value of operation task deadline.
Wherein, the step of the dynamic experiment method is verified includes: to obtain several actual operating times in real time, and calculate The average value of actual operating time several times;The average value is compared with the predetermined threshold of theoretical operation time, if super Predetermined threshold out is back to deadline data of the step S150 according to minimum movements unit time inventory, recalculates correspondence Each sub-step the theoretical operation time.
Wherein, the step S120 further include: configure typical operation example for the operating procedure category database of building, just In the identification of each subtype.
On the other hand, the present invention also provides the value systems of nuclear power plant's operation task deadline a kind of, comprising: standard Selecting time module refines the specific steps of each sort operation task, identifies for classifying to nuclear power plant's operation task All operationss task each sub-step minimum movements unit time, and when calculating the theoretical operation of each sub-step of all operationss task Between;Standard Selecting time correction module connects the standard Selecting time module, for each son of nuclear power plant's all operationss task The theoretical operation time of step is modified and is verified to obtain the value of respective operations task completion time.
Wherein, the standard Selecting time module includes: categorization module, if for grasping the Control Room of Nuclear Power Plant of dry type Make task and carries out systemic classification from operation work angle;Operating procedure categorical data library module connects the categorization module, uses In the whole subtypes for enumerating all types operation task, refines the specific steps of each sort operation task and construct operation step Rapid category database;Minimum movements unit time checklist module connects the operating procedure categorical data library module, for identification All operationss task each sub-step minimum movements unit time, and classification is merged, form minimum movements unit time inventory; Inventory minimum movements unit time, database module deadline connects the minimum movements unit time checklist module, is used for Inventory minimum movements unit time, database deadline is constructed according to minimum movements unit time inventory;It is theoretical to operate sub-step Operating time database module connects inventory minimum movements unit time, database module deadline, for according to most The deadline data of little trick unit time inventory calculate the theoretical operation time of each sub-step of all operationss task, with structure Build the theoretical operation temporal database of each sub-step of all operationss task.
Wherein, the standard Selecting time correction module includes: theoretical operation temporal database module, connects the operation Sub-step theoretical operation temporal database module, for correcting nuclear power plant's all operationss and appointing according to nuclear power plant's practical operating experiences The theoretical operation time for each sub-step of being engaged in is to construct theoretical operation temporal database;Dynamic corrections module connects the theoretical behaviour Make temporal database module, for carrying out verifying using the dynamic experiment method to the theoretical operation temporal database and according to verifying As a result it is modified and adjusts to obtain the value of respective operations task completion time.
Wherein, the dynamic corrections module includes: acquisition module, obtains several actual operating times in real time;Calculate judgement Module calculates the average value of actual operating time several times according to several actual operating times got, if by calculated The average value of dry actual operating time is compared with the predetermined threshold of theoretical operation time;Module is adjusted, if judging result Beyond predetermined threshold, then to return to the theoretical operation time for recalculating corresponding each sub-step, if without departing from predetermined threshold, Predetermined threshold can continue to use.
Wherein, the operating procedure categorical data library module further include: typical operation example module connects the operation step Rapid categorical data library module is convenient for each subtype for configuring typical operation example for the operating procedure category database of building Identification.
Technical solution provided by the invention have the benefit that by Control Room of Nuclear Power Plant operation task from operation Work angle carries out systemic classification, and constructs minimum movements unit inventory deadline database, to realize an operation step Rapid operating time value, the value working efficiency of significant increase Control Room of Nuclear Power Plant operation task deadline, and difference is commented The value result for estimating personnel has good consistency;In addition, operating experience is relied on by the several operation experts of tissue, it is each to this The theoretical operation time of operating procedure carries out necessary amendment, and value result fully considers operating experience, has higher feasible Degree can effectively support Control Room of Nuclear Power Plant operation task to analyze work, meanwhile, nuclear power plant's operating time standard database is adopted It is modified with the dynamic experiment method, solves the value of nuclear power plant's operation task deadline data in the presence of the prior art Method lacks the systematization data structure analysis based on objective data as support, and data are all based on subjective observation and comment Valence mumber evidence, the technical problems such as subjectivity is strong, susceptible, and consistency is poor, effectively promotes safety and the warp of nuclear power plant's operation Ji property.
Detailed description of the invention
Fig. 1 is the obtaining value method flow chart for nuclear power plant's operation task deadline that the embodiment of the present invention one provides;
Fig. 2 is the flow chart of step S100 in the embodiment of the present invention one;
Fig. 3 is the building operating procedure category database schematic diagram that the embodiment of the present invention one provides;
Fig. 4 is the minimum movements unit inventory deadline database schematic diagram for the building that the embodiment of the present invention one provides;
Fig. 5 is the flow chart of step S200 in the embodiment of the present invention one;
Fig. 6 is the revised operating time standard database schematic diagram that the embodiment of the present invention one provides;
Fig. 7 is the value system structure diagram of nuclear power plant's operation task deadline provided by Embodiment 2 of the present invention;
Fig. 8 is the value system standard Selecting time of nuclear power plant's operation task deadline provided by Embodiment 2 of the present invention Modular structure schematic diagram;
Fig. 9 is the value system standard Selecting time of nuclear power plant's operation task deadline provided by Embodiment 2 of the present invention Correction module structural schematic diagram.
Specific embodiment
The analysis of Control Room of Nuclear Power Plant operation task is an important process of the Human Factor in Nuclear Power Plant because of field, and achievement can prop up The exploitation and personnel's qualification and outfit design etc. of the man-machine Interface design of nuclear power plant, regulation and training program are held, so as to effective Promote the safety and economy of nuclear power plant's operation.Therefore, the analysis of Control Room of Nuclear Power Plant operation task is also domestic and international nuclear safety Supervision department is for people because of the focal point in field.The Control Room of Nuclear Power Plant operation task deadline is Control Room of Nuclear Power Plant operation The basic necessary data of one of task analysis, appraiser directly give the deadline according to power plant's work on the spot experience.But by Many kinds of in Control Room of Nuclear Power Plant operation task, each appraiser is difficult to ensure very ripe to the operation task of all kinds It knows, and familiarity is also different, causes the value of Control Room of Nuclear Power Plant operation task deadline to work very and expend the time, and It is difficult to keep unified for the task time value of same operation task difference appraiser, value result lacks confidence level, is It solves the above problems, the present invention uses whole set of system method, and operating procedure is carried out systemic classification, estimates each operation step The rapid operating time, then carry out necessary amendment, it is ensured that form Control Room of Nuclear Power Plant operation task deadline database, core Thought is: from operation work angle systematization classification nuclear power plant's operation task, enumerating the son of nuclear power plant's all types operation task Type constructs nuclear power plant's operating procedure category database, identifies nuclear power plant's all operationss sub-step minimum movements unit, constructs core Power plant's minimum movements unit inventory deadline database constructs nuclear power plant's all operationss sub-step theoretical operation time data Library is theorized operating time database based on operating experience amendment nuclear power plant's all operationss sub-step, is based on the dynamic experiment method Acquisition test objective data corrects nuclear power plant's operating time standard database, can effectively support Control Room of Nuclear Power Plant operation task point Work is analysed, the safety and economy of nuclear power plant's operation are effectively promoted.
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with attached drawing to embodiment party of the present invention Formula is described in further detail.
Embodiment one
The embodiment of the invention provides the obtaining value methods of nuclear power plant's operation task deadline a kind of, referring to Fig. 1, this method Include:
S100, systemic classification is carried out from operation work angle to nuclear power plant's operation task, refines each sort operation and appoints The specific steps of business identify all operationss task each sub-step minimum movements unit time, and according to each son of all operationss task The theoretical operation time of step minimum movements unit time calculating each sub-step of all operationss task;
S200, the theoretical operation time of each sub-step of nuclear power plant's all operationss task is tried by operation expert and dynamic The method of testing is modified and is verified to obtain the value of respective operations task completion time.
Wherein, referring to attached drawing 2, step S100 further comprises:
If the Control Room of Nuclear Power Plant operation task of dry type S110, is carried out systemic classification from operation work angle;Appoint Business is the set to successfully complete final all operational motions of operating condition operator of a certain particular order operation scenario, nuclear power plant's control Room operation task processed is divided into seven types from operation work angle, including call picture, exchange, read explanation, parameter compares, Check judgement, operation and RMC record.
S120, the whole subtypes for enumerating nuclear power plant's all types operation task, refine the tool of each type operations task Body step is to construct operating procedure category database;Specifically: each type Control Room of Nuclear Power Plant operation task is directed to, from operation Work angle itemizes all types of whole subtypes, a complete operating procedure category database is constructed, such as Fig. 3 institute To show, each different operating instruction has a corresponding typical operation example, wherein: operating procedure category database includes behaviour Make type, operating instruction, while configuring typical operation example, the identification convenient for operator to each subtype.Such as: in Fig. 3 Operating instruction: " need to call picture, and need to arrive S-VDU operation ", corresponding there are three operating procedures: a) confirmation be RIS001PO and 002PO IS;B) resets SI signal by RPA060KG;C) .ASG threshold: ASG 012VD is closed
The specific steps of all types operation task in S130, read operation step category database identify all operationss Task each sub-step minimum movements unit time, and classification is merged, form minimum movements unit time inventory, minimum movements Cover program reading, personnel transfer, master control room broadcast, master control room issue operation single, non-security grade VDU operation series, safety level VDU operation series, ECP operation and RMC record etc.;
S140, inventory minimum movements unit time, database deadline is constructed according to minimum movements unit time inventory, Specific steps are as follows: operator executes angle to the same minimum in different sub-steps from operator for minimum movements unit inventory Action potential carries out unified deadline value, minimum movements unit inventory deadline database is constructed, as shown in figure 4, Fig. 4 For the minimum movements unit inventory deadline constructed by the digital manipulation basic unit motor unit type theory operating time Database, in which: it include mission area in database, serial number, elemental motion cell type, fundamental operation time and standby Note, for example, working as mission area in Fig. 4 is SOP, serial number 1, corresponding elemental motion cell type is to read English speed, this The theoretical operation time of one motor unit is 0.4 second/word, and remarks are operator's normal reading average speed, works as mission area For master control room, serial number 57, corresponding elemental motion cell type is that issue operation single, when the theoretical operation of This move unit Between be 60 seconds, remarks be complete this elemental motion unit specific steps: in the case of generation accident, live operator is in master Control room or isolation office await orders, firstly, master control room operator, which informs orally live operator, gets operation list to master control room, this One step used time was 5 seconds, and then, it is single that master control room operator finds out operation, the step for the used time 40 seconds, last master control room operator Record operation single-shot go out time and odd numbers, the step for the used time 15 seconds.
S150, the deadline data according to minimum movements unit time inventory, calculate each sub-step of all operationss task The theoretical operation time, to construct the theoretical operation temporal database of each sub-step of all operationss task, such as: call picture Concrete operations movement are as follows: selection screen selects picture catalogue, searches picture navigation, call directly navigation link;Traverse most petty action Office's inventory time, database deadline, finds out and selects the time of screen for 1s, select the time of picture catalogue for 1s, look into The time for looking for picture navigation is 3s, and the time for calling directly navigation link is 1s, then this sub-step of operator's complete call picture Rapid Selecting time is 6s.
Referring to attached drawing 5, step S200 further comprises:
S210, according to nuclear power plant's practical operating experiences, organize several operation experts, operate speed for different operator Degree is different, corrects the theoretical operation time of each sub-step of nuclear power plant's all operationss task to construct theoretical operation time standard data Library provides the normal working time and longest operating time for completing an operation, and above-mentioned two operating time is counted resonable By in operating time standard database, the theoretical operation time, there are the variations of certain time, more met field practice situation;
Fig. 6 is revised operating time standard database schematic diagram, as shown in fig. 6, the operating instruction in Fig. 6: " needing to adjust With picture, and S-VDU operation need to be arrived ", corresponding there are three operating procedures: a) confirmation is RIS001PO and 002PO IS;B) is logical Cross RPA060KG resetting SI signal;C) .ASG threshold: ASG 012VD is closed, after several operation expert amendments, step a) is just The normal operating time is 0.7 minute, and the longest operating time is 1 minute, need to call picture, activates S-VDU, need to operate 2 equipment;Step Rapid normal working time b) is 0.7 minute, and the longest operating time is 1 minute, need to call picture, activates S-VDU, need to operate 2 A equipment;The normal working time of step c) is 0.7 minute, and the longest operating time is 1 minute, need to call picture, activates S- VDU need to be closed by adjusting;
S220, theoretical operation time standard database verify and carried out according to verification result using the dynamic experiment method It corrects and adjusts to obtain the value of respective operations task completion time, the dynamic experiment method specific steps are as follows: rely on nuclear power Factory's Full scope simulator obtains several operating procedures in real time and completes the operating time of practical operation, and calculates real several times The average value of border operating time;By the theoretical operation time in the average value and the theoretical operation temporal database of each sub-step Predetermined threshold is compared, if exceeding predetermined threshold, returns to the theoretical operation time for recalculating corresponding each sub-step, such as: It is that 6s analyzes several operations when the average value is more than 6s that operator, which calls the sub-step theory completion operating time of picture, The operating procedure of member recalculates the theoretical operation time of each sub-step, the theory that will be recalculated according to overtime reason Predetermined threshold of the operating time as new theory practice, if without departing from predetermined threshold, the theoretical operation time of each sub-step The predetermined threshold of theoretical operation time can be used as the correct theoretical operation time and continue to use in database.
In embodiments of the present invention, VDU (visual display unit) refers to that visual display unit operates, including The visual display terminal of mainframe computer and the visual device of cathode-ray tube, VDU operation are defeated including people-machine dialogue, data Enter, export, word processing, process control, programming, ECP (emergency control panel) refers to promptly controlling Disk processed, ECP operation include in case of emergency by operator's manual shutdown or starting engineered safeguards features etc., RMC (reliability centered maintenance) refers to the maintenance centered on reliability, is comprehensively and objectively to evaluate With the methods of decision maintenance.
The embodiment of the present invention provides the obtaining value method of nuclear power plant's operation task deadline a kind of, grasps to Control Room of Nuclear Power Plant Make task and carry out systemic classification from operation work angle, and constructs minimum movements unit inventory deadline database, thus Realize the operating time value of an operating procedure, the value of significant increase Control Room of Nuclear Power Plant operation task deadline, which works, imitates Rate, and the value result of the different appraisers different to operation task familiarity has good consistency;In addition, passing through It organizes several operation experts by operating experience, necessary amendment, value knot is carried out to the theoretical operation time of this each operating procedure Fruit fully considers operating experience, has higher Feasible degree, and Control Room of Nuclear Power Plant operation task can effectively be supported to analyze work Make, meanwhile, nuclear power plant's operating time standard database is modified using the dynamic experiment method, the deadline more meets live real It tramples, effectively promotes the safety and economy of nuclear power plant's operation.
Embodiment two
The embodiment of the invention provides the value systems of nuclear power plant's operation task deadline a kind of, are this hair referring to Fig. 7 The system construction drawing of bright embodiment two, comprising:
Standard Selecting time module 100 refines each sort operation task for classifying to nuclear power plant's operation task Specific sub-step, identify all operationss task each sub-step minimum movements unit time, and calculate each son of all operationss task The theoretical operation time of step;Standard Selecting time correction module 200 connects the standard Selecting time module 100, for pair The theoretical operation time of each sub-step of nuclear power plant's all operationss task is modified and is verified to obtain the completion of respective operations task The value of time.
Further, in conjunction with attached drawing 8, standard Selecting time module 100 includes:
Categorization module 110, if for being from operation work angle by the Control Room of Nuclear Power Plant operation task of dry type The classification of system property, is divided into seven types, including call picture, exchange, read explanation, parameter compares, inspection judges, operates and RMC Record etc.;Operating procedure categorical data library module 120 connects the categorization module 110, for enumerating all types operation task Whole subtypes, refine the specific sub-step of each sort operation task and construct operating procedure category database;Typical case behaviour Make example module 121, connect the operating procedure categorical data library module 120, in building operating procedure category database While configure typical operation example, the identification convenient for operator to each subtype;Minimum movements unit time checklist module 130, the operating procedure categorical data library module 120 is connected, for owning in read operation step categorical data library module 120 The specific steps of type operations task identify all operationss task each sub-step minimum movements unit time, and merge and return Class, formed minimum movements unit time inventory, minimum movements unit inventory cover program reading, personnel transfer, master control room broadcast, Master control room issues operation list, non-security grade VDU operation series, safety level VDU operation series, ECP operation and RMC record etc.;Most Inventory little trick unit time, database module deadline 140 connects the minimum movements unit time checklist module 130, For executing angle to the same minimum movements unit in different sub-steps from operator according to minimum movements unit time inventory Unified deadline value is carried out, inventory minimum movements unit time, database deadline is constructed;Operate sub-step theory behaviour Make temporal database module 150, connect inventory minimum movements unit time, database module deadline 140, for according to According to the deadline data of minimum movements unit time inventory, the theoretical operation time of each sub-step of all operationss task is calculated, To construct the theoretical operation temporal database of each sub-step of all operationss task.
Further, in conjunction with attached drawing 9, standard Selecting time correction module 200 includes:
Theoretical operation temporal database module 210 connects the operation sub-step theoretical operation temporal database module 150, for organizing several operation experts, not for different operator's service speeds according to nuclear power plant's practical operating experiences Together, correct each sub-step of nuclear power plant's all operationss task the theoretical operation time to construct theoretical operation time standard database, The normal working time and longest operating time for completing an operation are provided, and statistics of above-mentioned two operating time is grasped in theory Make in time standard database, the theoretical operation time, there are the variations of certain time, more met field practice situation;
Dynamic corrections module 220, including module 221 is obtained, nuclear power plant's Full scope simulator 300 is connected, for obtaining in real time Take several actual operating times;Judgment module 222 is calculated, connection obtains module 221 and theoretical operation temporal database module 210, theoretical operation temporal database module 210, for obtaining the predetermined of theoretical operation time from theoretical operation temporal database Threshold value calculates judgment module 222 according to several actual operating times for getting and calculates being averaged for actual operating time several times Value, the average value of calculated actual operating time several times is compared and is judged with the predetermined threshold of theoretical operation time Whether the average value of actual operating time is greater than the predetermined threshold of theoretical operation time several times;Module 223 is adjusted, connection calculates Judgment module 222 and theoretical operation temporal database module 210, if judging result is that practical operation average value exceeds predetermined threshold Value, then return to the theoretical operation time that theoretical operation temporal database module 210 recalculates corresponding each sub-step, will again Predetermined threshold of the calculated theoretical operation time as new theory practice, if without departing from predetermined threshold, each sub-step The predetermined threshold of theoretical operation time can be used as the correct theoretical operation time and continue to use in theoretical operation temporal database.It is dynamic State correction module 220 is realized relies on nuclear power plant's Full scope simulator to carry out theoretical operation temporal database using the dynamic experiment method It verifies and is modified and is adjusted according to verification result to obtain the value of respective operations task completion time, by dynamic Revised time value more meets field practice, and the value result of different appraisers has good consistency.
It should be understood that above-described embodiment provide the time obtaining value method the time value system realize when, only with The division progress of above-mentioned each functional module can according to need and for example, in practical application by above-mentioned function distribution by not With functional module, i.e., the internal structure of equipment is divided into different functional modules, with complete it is described above whole or Partial function.In addition, system and method embodiment provided by the above embodiment belongs to same design, specific implementation process is detailed in The description of embodiment of the method, which is not described herein again.
Those of ordinary skill in the art will appreciate that realizing that all or part of the steps of above-described embodiment can pass through hardware It completes, relevant hardware can also be instructed to complete by program, the program can store in a kind of computer-readable In storage medium.The handoff functionality of control or realization mentioned above is realized by controller, and control unit can be with It is central processing unit (Central Processing Unit, CPU), can also be other general processors, at digital signal Manage device (Digital Signal Processor, DSP), specific integrated circuit (Application Specific Integrated Circuit, ASIC), ready-made programmable gate array (Field-Programmable Gate Array, FPGA) Either other programmable logic device, discrete gate or transistor logic, discrete hardware components etc..General processor can be with It is that microprocessor or the processor are also possible to any conventional processor etc..Memory mentioned above can be terminal Built-in storage equipment, such as hard disk or memory.Present system further comprises memory, and memory is also possible to the outer of system Portion stores equipment, plug-in type hard disk, intelligent memory card (Smart Media Card, SMC), secure digital (Secure Digital, SD) card, flash card (Flash Card) etc..Memory can also both include the internal storage unit of system, also wrap External memory equipment is included, for storing computer program and required other programs and information.Memory can be also used for temporarily When store the information that has exported or will export.
In conclusion the obtaining value method and system of nuclear power plant's operation task deadline provided in an embodiment of the present invention, lead to It crosses and systemic classification is carried out from operation work angle to Control Room of Nuclear Power Plant operation task, and it is complete to construct minimum movements unit inventory At temporal database, to realize the operating time value of an operating procedure, significant increase Control Room of Nuclear Power Plant operation task is complete Value result at the value working efficiency of time, and different appraisers has good consistency;In addition, more by tissue Name operation expert relies on operating experience, carries out necessary amendment to the theoretical operation time of this each operating procedure, value result is abundant Ground considers operating experience, has higher Feasible degree, can effectively support Control Room of Nuclear Power Plant operation task to analyze work, together When, nuclear power plant's operating time standard database is modified using the dynamic experiment method, it is live real to guarantee that the deadline more meets It tramples, has higher Feasible degree, Control Room of Nuclear Power Plant operation task can effectively be supported to analyze work, effectively promote nuclear power plant's fortune Capable safety and economy.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all in spirit of the invention and Within principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of obtaining value method of nuclear power plant's operation task deadline, which comprises the steps of:
S100, classify to nuclear power plant's operation task, refine the specific steps of each sort operation task, identify all operationss Task each sub-step minimum movements unit time, and calculate the theoretical operation time of each sub-step of all operationss task;It is S200, right The theoretical operation time of each sub-step of nuclear power plant's all operationss task is modified and is verified to obtain the completion of respective operations task The value of time.
2. obtaining value method according to claim 1, which is characterized in that the step 100 specifically includes following processing:
If the Control Room of Nuclear Power Plant operation task of dry type S110, is carried out systemic classification from operation work angle;
S120, the whole subtypes for enumerating all types operation task refine the specific steps of each sort operation task with structure Build operating procedure category database;
S130, identification all operationss task each sub-step minimum movements unit time, and classification is merged, form minimum movements Unit time inventory;
S140, inventory minimum movements unit time, database deadline is constructed according to minimum movements unit time inventory;
S150, the deadline data according to minimum movements unit time inventory, calculate the reason of each sub-step of all operationss task By the operating time, to construct the theoretical operation temporal database of each sub-step of all operationss task.
3. obtaining value method according to claim 2, which is characterized in that the step S200 specifically includes following processing:
S210, according to nuclear power plant's practical operating experiences, correct the theoretical operation time of each sub-step of nuclear power plant's all operationss task To construct theoretical operation temporal database;
S220, the theoretical operation temporal database verify and be modified according to verification result using the dynamic experiment method The value of respective operations task completion time is obtained with adjustment.
4. obtaining value method according to claim 3, which is characterized in that the step of the dynamic experiment method is verified packet It includes:
Several operation task actual operating times are obtained in real time, and calculate the average value of actual operating time several times;It will be described Average value is compared with the predetermined threshold of theoretical operation time, if exceeding predetermined threshold, corresponding each son is recalculated in return The theoretical operation time of step.
5. method according to claim 4, which is characterized in that the step S120 further include:
Typical operation example is configured for the operating procedure category database of building, convenient for the identification of each subtype.
6. a kind of value system of nuclear power plant's operation task deadline characterized by comprising
Standard Selecting time module refines the specific of each sort operation task for classifying to nuclear power plant's operation task Step identifies all operationss task each sub-step minimum movements unit time, and calculates the reason of each sub-step of all operationss task By the operating time;
Standard Selecting time correction module connects the standard Selecting time module, for each to nuclear power plant's all operationss task The theoretical operation time of sub-step is modified and is verified to obtain the value of respective operations task completion time.
7. value system according to claim 6, which is characterized in that the standard Selecting time module includes:
Categorization module, if for the Control Room of Nuclear Power Plant operation task of dry type to be carried out systematicness point from operation work angle Class;
Operating procedure categorical data library module, connects the categorization module, for enumerating all sons of all types operation task Type refines the specific steps of each sort operation task and constructs operating procedure category database;
Minimum movements unit time checklist module connects the operating procedure categorical data library module, for identification all operationss Task each sub-step minimum movements unit time, and classification is merged, form minimum movements unit time inventory;
Inventory minimum movements unit time, database module deadline connects the minimum movements unit time checklist module, For constructing inventory minimum movements unit time, database deadline according to minimum movements unit time inventory;
Sub-step theoretical operation temporal database module is operated, inventory minimum movements unit time, data deadline are connected Library module calculates each sub-step of all operationss task for the deadline data according to minimum movements unit time inventory The theoretical operation time, to construct the theoretical operation temporal database of each sub-step of all operationss task.
8. value system according to claim 7, which is characterized in that the standard Selecting time correction module includes:
Theoretical operation temporal database module connects the operation sub-step theoretical operation temporal database module, is used for basis Nuclear power plant's practical operating experiences correct the theoretical operation time of each sub-step of nuclear power plant's all operationss task to construct theoretical operation Temporal database;
Dynamic corrections module connects the theoretical operation temporal database module, for the theoretical operation temporal database It uses the dynamic experiment method verify and is modified and is adjusted according to verification result to obtain respective operations task completion time The value.
9. value system according to claim 8, which is characterized in that the dynamic corrections module includes:
Module is obtained, obtains several operation task actual operating times in real time;Judgment module is calculated, according to several realities got The border operating time calculates the average value of actual operating time several times, by the average value of calculated actual operating time several times It is compared with the predetermined threshold of theoretical operation time;Module is adjusted, if judging result is to be back to behaviour beyond predetermined threshold Make the theoretical operation time that sub-step theoretical operation temporal database module recalculates corresponding each sub-step.
10. system according to claim 9, which is characterized in that the operating procedure categorical data library module further include:
Typical operation example module connects the operating procedure categorical data library module, for the operating procedure classification for building Database configures typical operation example, convenient for the identification of each subtype.
CN201910072698.0A 2019-01-25 2019-01-25 A kind of obtaining value method and system of nuclear power plant's operation task deadline Pending CN109858795A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910072698.0A CN109858795A (en) 2019-01-25 2019-01-25 A kind of obtaining value method and system of nuclear power plant's operation task deadline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910072698.0A CN109858795A (en) 2019-01-25 2019-01-25 A kind of obtaining value method and system of nuclear power plant's operation task deadline

Publications (1)

Publication Number Publication Date
CN109858795A true CN109858795A (en) 2019-06-07

Family

ID=66896203

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910072698.0A Pending CN109858795A (en) 2019-01-25 2019-01-25 A kind of obtaining value method and system of nuclear power plant's operation task deadline

Country Status (1)

Country Link
CN (1) CN109858795A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111723255A (en) * 2020-05-08 2020-09-29 中国人民解放军海军特色医学中心 Construction method of ship control room operation task completion time database
CN113609643A (en) * 2021-07-05 2021-11-05 中广核工程有限公司 Time acquisition method and system for nuclear power station digital operation basic action unit
CN116896483A (en) * 2023-09-08 2023-10-17 成都拓林思软件有限公司 Data protection system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111723255A (en) * 2020-05-08 2020-09-29 中国人民解放军海军特色医学中心 Construction method of ship control room operation task completion time database
CN113609643A (en) * 2021-07-05 2021-11-05 中广核工程有限公司 Time acquisition method and system for nuclear power station digital operation basic action unit
CN113609643B (en) * 2021-07-05 2024-05-10 中广核工程有限公司 Time acquisition method and system for digital operation basic action unit of nuclear power station
CN116896483A (en) * 2023-09-08 2023-10-17 成都拓林思软件有限公司 Data protection system
CN116896483B (en) * 2023-09-08 2023-12-05 成都拓林思软件有限公司 Data protection system

Similar Documents

Publication Publication Date Title
Dehghanian et al. A comprehensive scheme for reliability-centered maintenance in power distribution systems—Part II: Numerical analysis
CN109858795A (en) A kind of obtaining value method and system of nuclear power plant's operation task deadline
CN106209482A (en) A kind of data center monitoring method and system
CN109933452A (en) A kind of micro services intelligent monitoring method towards anomalous propagation
CN107092522A (en) The computational methods and device of real time data
CN104809663B (en) Power specialty technological service safeguards system and its measure of supervision
CN109451532A (en) A kind of check method and device of base station location
CN110887173A (en) Method and device for remotely controlling central air-conditioning system
CN109725610A (en) Plant produced information analysis processing method, device and equipment
CN110277833A (en) The method and terminal device of substation's pressing plate state recognition
CN109829693A (en) One kind being used for Construction Schedule management system and management method
CN114757637A (en) Credit approval method, credit approval device, credit approval equipment and credit approval storage medium based on decision engine
CN110458719A (en) A kind of dispatching method of electric network and system for power grid enterprises
US20180010982A1 (en) Engine performance modeling based on wash events
CN110991519A (en) Intelligent switch state analysis and adjustment method and system
CN113009850B (en) Intelligent operation method and device for low-voltage contact cabinet
CN109917776A (en) The intelligent fault analysis method and device of wind power generating set
CN104572266B (en) MPSoC task schedulings modeling based on UPPAAL SMC and appraisal procedure under process variation
CN110633503A (en) BIM-based PDCA (packet data processing architecture) cycle closed type safety management system
Kim et al. A quantitative approach to modeling the information flow of diagnosis tasks in nuclear power plants
CN109492951A (en) Creation method, device and the computer equipment of robot maturity assessment model
Guo One-shot decision making with regret
CN117196321B (en) Nuclear power plant planning task probability risk calculation method and calculation device thereof
CN116029799B (en) Micro-service architecture management platform based on intelligent decision
CN117021119B (en) Intelligent robot allocation system based on Internet

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190607