CN109858792A - A kind of nuclear power station debugging test task management method and system based on test procedure - Google Patents
A kind of nuclear power station debugging test task management method and system based on test procedure Download PDFInfo
- Publication number
- CN109858792A CN109858792A CN201910062134.9A CN201910062134A CN109858792A CN 109858792 A CN109858792 A CN 109858792A CN 201910062134 A CN201910062134 A CN 201910062134A CN 109858792 A CN109858792 A CN 109858792A
- Authority
- CN
- China
- Prior art keywords
- task
- test
- debugging
- debugging test
- nuclear power
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Abstract
The invention discloses a kind of nuclear power station debugging test task management method and system based on test procedure.The described method includes: utilizing Intelligent mobile equipment, the completion information for obtaining test procedure in nuclear power station debugging test task, using debugging test task management platform, the test procedure that will acquire completes information, according to the form of program task, subtask and project task, structuring storage is carried out.The present invention obtains the completion information of test procedure by Intelligent mobile equipment in real time, and according to the form of program task, subtask and project task, carry out structuring storage, debugging test task management platform in this way, the progress of nuclear power station debugging test task can be judged and managed according to the form of project task, especially with the form of subtask, it only needs to judge that a part plays the role of the performance of the test procedure of prerequisite in determining program task, can schedule accurate management so that the distribution of test resource is more accurate controllable.
Description
Technical field
The present invention relates to nuclear power station debugging technique field, in particular to a kind of nuclear power station debugging test based on test procedure
Task management method and system.
Background technique
During Nuclear power project, nuclear power station debugging process is carried out around system function to be tested, therefore tests journey
Sequence is also to carry out classification according to structure, the function of system to write, and is limited by field device, upstream and downstream facility, environmental condition, unit
The content of the limitation of operating condition, a debugging test program (being used for one nuclear power plant system function of debugging test) may last up to
1 year or more time can just be fully completed.Currently, the debugging test report of nuclear power station is that papery is filled in both at home and abroad, it is only whole
Part test procedure is fully completed and publishes report, can just be included in the data statistics of task completion.
But during Nuclear power project, debugging scheduling is managed using debugging test program as unit.It is real
Some of debugging test programs, which only need to wherein complete partial task, on border can meet the prerequisite of remainder task.
Therefore, using the performance of complete debugging test program as the basic unit of planning management, it is difficult to meet progress
The requirement of management, in some instances it may even be possible to will affect the validity of progress control.
Summary of the invention
In order to solve problems in the prior art, the nuclear power station debugging based on test procedure that the embodiment of the invention provides a kind of
Test mission management method and system.The technical solution is as follows:
On the one hand, the embodiment of the invention provides a kind of nuclear power station debugging test task management side based on test procedure
Method, which comprises
It using Intelligent mobile equipment, obtains in nuclear power station debugging test task, the test procedure that can be each executed by employee
Completion information;
Using debugging test task management platform, the test procedure that will acquire completes information, appoints according to program task, son
The form of business and project task carries out structuring storage, forms debugging test assignment database, described program task is by more
A associated test procedure is constituted, and for characterizing corresponding nuclear power plant system function to be debugged, the subtask is by same program
Multiple associated test procedures in task are constituted, for characterizing the prerequisite of other test procedures in same program task,
The project task is made of multiple program tasks and/or subtask, for characterizing the progress of debugging test task;
Using debugging test task management platform, letter is completed according to the test procedure stored in debugging test assignment database
Breath judges the progress performance of nuclear power station debugging test task, and distributes corresponding debugging test according to progress performance
Resource.
In the above-mentioned nuclear power station debugging test task management method based on test procedure of the embodiment of the present invention, the benefit
With debugging test task management platform, information is completed according to the test procedure stored in debugging test assignment database, judges core
The progress performance of power station debugging test task, and corresponding debugging test resource is distributed according to progress performance, comprising:
Using debugging test task management platform, letter is completed according to the test procedure stored in debugging test assignment database
Breath, judge in preset time period, the performance of corresponding project task, with this judge nuclear power station debugging test task into
Degree.
In the above-mentioned nuclear power station debugging test task management method based on test procedure of the embodiment of the present invention, also wrap
It includes:
Using debugging test task management platform, letter is completed according to the test procedure stored in debugging test assignment database
Breath, statistical item task performance form the progress for showing debugging test Task Progress and complete statistical graph.
In the above-mentioned nuclear power station debugging test task management method based on test procedure of the embodiment of the present invention, also wrap
It includes:
Using debugging test task management platform, letter is completed according to the test procedure stored in debugging test assignment database
Breath counts subtask performance, forms the prerequisite for showing debugging test task key link performance and completes
Statistical graph.
In the above-mentioned nuclear power station debugging test task management method based on test procedure of the embodiment of the present invention, also wrap
It includes:
Using debugging test task management platform, letter is completed according to the test procedure stored in debugging test assignment database
Breath, statistics program task performance form the function debugging for showing nuclear power plant system function debugging situation and complete statistics
Chart.
On the other hand, the embodiment of the invention provides a kind of nuclear power station debugging test task management system based on test procedure
System, the system comprises:
Intelligent mobile equipment each can be by the test procedure of employee's execution for obtaining in nuclear power station debugging test task
Completion information;
Debugging test task management platform is communicated to connect with Intelligent mobile equipment, and the test procedure for will acquire is completed
Information carries out structuring storage according to the form of program task, subtask and project task, forms debugging test number of tasks
According to library, described program task is made of multiple associated test procedures, for characterizing corresponding nuclear power plant system function to be debugged,
The subtask is made of multiple associated test procedures in same program task, for characterizing other in same program task
The prerequisite of test procedure, the project task is made of multiple program tasks and/or subtask, for characterizing debugging test
The progress of task;
Debugging test task management platform, for completing letter according to the test procedure stored in debugging test assignment database
Breath judges the progress performance of nuclear power station debugging test task, and distributes corresponding debugging test according to progress performance
Resource.
In the above-mentioned nuclear power station debugging test task management system based on test procedure of the embodiment of the present invention, the tune
It has a try and tests task management platform, be also used to complete information, judgement according to the test procedure stored in debugging test assignment database
In preset time period, the performance of corresponding project task judges the progress of nuclear power station debugging test task with this.
In the above-mentioned nuclear power station debugging test task management system based on test procedure of the embodiment of the present invention, the tune
It has a try and tests task management platform, be also used to complete information, statistics according to the test procedure stored in debugging test assignment database
Project task performance forms the progress for showing debugging test Task Progress and completes statistical graph.
In the above-mentioned nuclear power station debugging test task management system based on test procedure of the embodiment of the present invention, the tune
It has a try and tests task management platform, be also used to complete information, statistics according to the test procedure stored in debugging test assignment database
Subtask performance forms the prerequisite for showing debugging test task key link performance and completes statistical chart
Table.
In the above-mentioned nuclear power station debugging test task management system based on test procedure of the embodiment of the present invention, the tune
It has a try and tests task management platform, be also used to complete information, statistics according to the test procedure stored in debugging test assignment database
Program task performance forms the function debugging for showing nuclear power plant system function debugging situation and completes statistical graph.
Technical solution provided in an embodiment of the present invention has the benefit that
It obtains the completion information of test procedure in nuclear power station debugging test task in real time by Intelligent mobile equipment, and is adjusting
It has a try and tests in task management platform, according to the form of program task, subtask and project task, carry out structuring storage, shape
At debugging test assignment database, such debugging test task management platform, can judge according to the form of project task and
The progress for managing nuclear power station debugging test task, especially with the form of subtask, without completing complete routine task
In the case of, it is only necessary to judge that a part plays the role of the performance of the test procedure of prerequisite in determining program task, just
It can be with the accurate management of schedule, so that the distribution of test resource is more accurate controllable.
Detailed description of the invention
To describe the technical solutions in the embodiments of the present invention more clearly, make required in being described below to embodiment
Attached drawing is briefly described, it should be apparent that, drawings in the following description are only some embodiments of the invention, for
For those of ordinary skill in the art, without creative efforts, it can also be obtained according to these attached drawings other
Attached drawing.
Fig. 1 is a kind of nuclear power station debugging test task management method based on test procedure that the embodiment of the present invention one provides
Flow chart;
Fig. 2 is the exemplary diagram for the project task that the embodiment of the present invention one provides;
Fig. 3 is the selection exemplary diagram for the subtask that the embodiment of the present invention one provides;
Fig. 4 is a kind of nuclear power station debugging test task management system based on test procedure provided by Embodiment 2 of the present invention
Structural schematic diagram.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with attached drawing to embodiment party of the present invention
Formula is described in further detail.
Embodiment one
The embodiment of the invention provides a kind of nuclear power station debugging test task management method based on test procedure, referring to figure
1, this method may include:
Step S11 is obtained in nuclear power station debugging test task using Intelligent mobile equipment, can each be executed by employee
The completion information of test procedure.
In the present embodiment, it using Intelligent mobile equipment (such as smart phone, Intelligent flat, computer etc.), obtains in real time
In nuclear power station debugging test task, the completion information for the test procedure that can be each executed by employee is so single with test procedure
Position, the work for carrying out test mission to employee distributes, and utilizes Intelligent mobile equipment, obtains corresponding information in real time, can be effective
The problem for avoiding existing papery hand-written information utilization efficiency low, and task distribution is clear, executes convenient for employee.
Step S12, using debugging test task management platform, the test procedure that will acquire completes information, appoints according to program
Business, subtask and project task form, carry out structuring storage, form debugging test assignment database, program task by
Multiple associated test procedures are constituted, for characterizing corresponding nuclear power plant system function to be debugged;Appointed by same program subtask
Multiple associated test procedures in business are constituted, for characterizing the prerequisite of other test procedures in same program task;?
Mesh task is made of multiple program tasks and/or subtask, for characterizing the progress of debugging test task.
In the present embodiment, the attribute of nuclear power station debugging test task may include task names, responsible person, professional contingent,
Planned start time, Projected completion time actually accomplish ratio etc., can be divided into project task according to regulatory requirement, program is appointed
Business and subtask:
Program task is the complete test procedure set of single nuclear power plant system function debugging test procedure;
Subtask be the only part test step comprising single program task set (subtask not across program,
That is cannot include the test procedure of multiple test procedures), subtask is often other test procedures in same program task
Prerequisite, but can not complete, can be separated with other program tasks simultaneously with other test procedures same period
It completes.The step of can selecting the part of a test procedure task by way of clicking task step when subtask is arranged
Mode generate subtask.Referring to Fig. 3, furthermore the selection exemplary diagram of a subtask, each subtask can be by same programs
Multiple test procedures in task are constituted.
Project task is the task comprising multiple test procedure contents, it is not possible to it is directly executed, it is lower to mount journey
Sequence task and/or subtask, under project task cannot sundry item task again, otherwise influence summarizing for statistical chart.It is general and
Speech, project task can be made of according to progress demand multiple program tasks, perhaps be made of multiple subtasks or by more
A program task and multiple subtasks are constituted, here with no restrictions.Referring to fig. 2, this is the exemplary diagram of a project task, it is
It is made of program task 1-4 and subtask 1.
During practical debugging test, it is limited by field device, upstream and downstream facility, environmental condition, the limit of unit operating condition
System, the time that all test procedure contents of a program task may last up to 1 year or more can just be fully completed, still
Some of test procedures are the prerequisites of other test procedures, they can not have to link up completion, but can be by
Degree of shining into demand is separately completed.Subtask and achievable program task of same period are combined in this way, are built into phase
The project task answered, so that debugging test task management platform, can be realized resource allocation fine-grained management, and can effectively realize
Debugging test progress control.
Step S13 is walked using debugging test task management platform according to the test stored in debugging test assignment database
It is rapid to complete information, judge the progress performance of nuclear power station debugging test task, and distribute accordingly according to progress performance
Debugging test resource.
Specifically, above-mentioned steps S13 can be accomplished in that
Using debugging test task management platform, letter is completed according to the test procedure stored in debugging test assignment database
Breath, judge in preset time period, the performance of corresponding project task, with this judge nuclear power station debugging test task into
Degree.
In the present embodiment, information is completed by the test procedure that gets, debugging test task management platform can be by
The progress that nuclear power station debugging test task is judged and managed according to the form of project task, especially with the shape of subtask
Formula, without in the case where completing complete routine task, it is only necessary to judge that a part plays prerequisite in determining program task
The performance of the test procedure of effect, so that it may the accurate management of schedule, so that the distribution of test resource is more accurate
Controllably.
Optionally, referring to Fig. 1, being somebody's turn to do the nuclear power station debugging test task management method based on test procedure can also include:
Step S14 is walked using debugging test task management platform according to the test stored in debugging test assignment database
Rapid to complete information, statistical item task performance forms the progress for showing debugging test Task Progress and completes statistical chart
Table.
Step S15 is walked using debugging test task management platform according to the test stored in debugging test assignment database
It is rapid to complete information, subtask performance is counted, is formed for showing the prerequisite of debugging test task key link performance
Condition completes statistical graph.
Step S16 is walked using debugging test task management platform according to the test stored in debugging test assignment database
Rapid to complete information, statistics program task performance forms the function debugging for showing nuclear power plant system function debugging situation
Complete statistical graph.
In the present embodiment, there are three types of states for test procedure: being not carried out (no data), has executed and (had data), has been completed
(step has published report), there are three types of states for test mission: not completing (step is without all executing), has all executed
(task has published report) is completed in (each step has all executed), can be counted with this.
In the present embodiment, the debugging test task management platform, not only may be implemented to nuclear power station debugging test task
Progress effective management and debugging test resource reasonable distribution, can also realize to nuclear power station debugging test Task Progress
Real-time tracking is tracked in particular for the prerequisite task of great milestone node, if necessary to be directed to the portion of program task
Point content performance is tracked, and test director oral report can only be relied on, can not be to the data of the program task of completion
It is verified, also cannot achieve programming count, cannot ensure the authenticity and validity of feedback information.
In the present embodiment, according to the performance of subtask, the performance of programming count milestone task list, shape
At the statistical graph that milestone task prerequisite is completed, is conducive to debugging test task management platform and finds crucial ring in time
Section, emphasis promote.
The embodiment of the present invention obtains the complete of test procedure in nuclear power station debugging test task by Intelligent mobile equipment in real time
At information, and in debugging test task management platform, according to the form of program task, subtask and project task, carry out
Structuring storage, forms debugging test assignment database, such debugging test task management platform can be according to project task
Form is being not necessarily to complete to judge and manage the progress of nuclear power station debugging test task especially with the form of subtask
In the case where whole program task, it is only necessary to judge that a part plays the role of the test procedure of prerequisite in determining program task
Performance, so that it may the accurate management of schedule, so that the distribution of test resource is more accurate controllable.
Embodiment two
The nuclear power station debugging test task management system based on test procedure that the embodiment of the invention provides a kind of, performs
Method described in embodiment one, referring to fig. 4, the system may include: that Intelligent mobile equipment 100, debugging test task management are flat
Platform 200.
Intelligent mobile equipment 100, for obtaining in nuclear power station debugging test task, the test that can be each executed by employee is walked
Rapid completion information.
In the present embodiment, it using Intelligent mobile equipment (such as smart phone, Intelligent flat, computer etc.), obtains in real time
In nuclear power station debugging test task, the completion information for the test procedure that can be each executed by employee is so single with test procedure
Position, the work for carrying out test mission to employee distributes, and utilizes Intelligent mobile equipment, obtains corresponding information in real time, can be effective
The problem for avoiding existing papery hand-written information utilization efficiency low, and task distribution is clear, executes convenient for employee.
Debugging test task management platform 200, debugging test task management platform 200 are communicated with Intelligent mobile equipment 100
Connection, the test procedure for will acquire complete information, according to the form of program task, subtask and project task, carry out
Structuring storage, forms debugging test assignment database, program task is made of multiple associated test procedures, for characterizing phase
Answer nuclear power plant system function to be debugged;Subtask is made of multiple associated test procedures in same program task, is used for
Characterize the prerequisite of other test procedures in same program task;Project task is by multiple program tasks and/or subtask structure
At for characterizing the progress of debugging test task.
In the present embodiment, the attribute of nuclear power station debugging test task may include task names, responsible person, professional contingent,
Planned start time, Projected completion time actually accomplish ratio etc., can be divided into project task according to regulatory requirement, program is appointed
Business and subtask:
Program task is the complete test procedure set of single nuclear power plant system function debugging test procedure;
Subtask be the only part test step comprising single program task set (subtask not across program,
That is cannot include the test procedure of multiple test procedures), subtask is often other test procedures in same program task
Prerequisite, but can not complete, can be separated with other program tasks simultaneously with other test procedures same period
It completes.The step of can selecting the part of a test procedure task by way of clicking task step when subtask is arranged
Mode generate subtask.
Project task is the task comprising multiple test procedure contents, it is not possible to it is directly executed, it is lower to mount journey
Sequence task and/or subtask, under project task cannot sundry item task again, otherwise influence summarizing for statistical chart.It is general and
Speech, project task can be made of according to progress demand multiple program tasks, perhaps be made of multiple subtasks or by more
A program task and multiple subtasks are constituted, here with no restrictions.
During practical debugging test, it is limited by field device, upstream and downstream facility, environmental condition, the limit of unit operating condition
System, the time that all test procedure contents of a program task may last up to 1 year or more can just be fully completed, still
Some of test procedures are the prerequisites of other test procedures, they can not have to link up completion, but can be by
Degree of shining into demand is separately completed.Subtask and achievable program task of same period are combined in this way, are built into phase
The project task answered, so that debugging test task management platform, can be realized resource allocation fine-grained management, and can effectively realize
Debugging test progress control.
Debugging test task management platform 200, is also used to according to the test procedure stored in debugging test assignment database
Information is completed, judges the progress performance of nuclear power station debugging test task, and distribute corresponding adjust according to progress performance
It has a try certification of registered capital source.
Specifically, debugging test task management platform 200 is also used to according to the examination stored in debugging test assignment database
It tests step and completes information, judge in preset time period, the performance of corresponding project task, nuclear power station debugging examination is judged with this
Test the progress of task.
In the present embodiment, information is completed by the test procedure that gets, debugging test task management platform can be by
The progress that nuclear power station debugging test task is judged and managed according to the form of project task, especially with the shape of subtask
Formula, without in the case where completing complete routine task, it is only necessary to judge that a part plays prerequisite in determining program task
The performance of the test procedure of effect, so that it may the accurate management of schedule, so that the distribution of test resource is more accurate
Controllably.
Optionally, debugging test task management platform 200 is also used to according to the examination stored in debugging test assignment database
It tests step and completes information, statistical item task performance forms the progress for showing debugging test Task Progress and completes system
Count chart.
Debugging test task management platform 200, is also used to according to the test procedure stored in debugging test assignment database
Information is completed, subtask performance is counted, forms the prerequisite item for showing debugging test task key link performance
Part completes statistical graph.
Debugging test task management platform 200, is also used to according to the test procedure stored in debugging test assignment database
Information is completed, statistics program task performance is formed for showing that the function debugging of nuclear power plant system function debugging situation is complete
At statistical graph.
In the present embodiment, there are three types of states for test procedure: being not carried out (no data), has executed and (had data), has been completed
(step has published report), there are three types of states for test mission: not completing (step is without all executing), has all executed
(task has published report) is completed in (each step has all executed), can be counted with this.
In the present embodiment, the debugging test task management platform, not only may be implemented to nuclear power station debugging test task
Progress effective management and debugging test resource reasonable distribution, can also realize to nuclear power station debugging test Task Progress
Real-time tracking is tracked in particular for the prerequisite task of great milestone node, if necessary to be directed to the portion of program task
Point content performance is tracked, and test director oral report can only be relied on, can not be to the data of the program task of completion
It is verified, also cannot achieve programming count, cannot ensure the authenticity and validity of feedback information.
In the present embodiment, according to the performance of subtask, the performance of programming count milestone task list, shape
At the statistical graph that milestone task prerequisite is completed, is conducive to debugging test task management platform and finds crucial ring in time
Section, emphasis promote.
The embodiment of the present invention obtains the complete of test procedure in nuclear power station debugging test task by Intelligent mobile equipment in real time
At information, and in debugging test task management platform, according to the form of program task, subtask and project task, carry out
Structuring storage, forms debugging test assignment database, such debugging test task management platform can be according to project task
Form is being not necessarily to complete to judge and manage the progress of nuclear power station debugging test task especially with the form of subtask
In the case where whole program task, it is only necessary to judge that a part plays the role of the test procedure of prerequisite in determining program task
Performance, so that it may the accurate management of schedule, so that the distribution of test resource is more accurate controllable.
The serial number of the above embodiments of the invention is only for description, does not represent the advantages or disadvantages of the embodiments.
Those of ordinary skill in the art will appreciate that realizing that all or part of the steps of above-described embodiment can pass through hardware
It completes, relevant hardware can also be instructed to complete by program, the program can store in a kind of computer-readable
In storage medium, storage medium mentioned above can be read-only memory, disk or CD etc..
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all in spirit of the invention and
Within principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.
Claims (10)
1. a kind of nuclear power station debugging test task management method based on test procedure, which is characterized in that the described method includes:
Using Intelligent mobile equipment, obtain in nuclear power station debugging test task, it each can be by the complete of the test procedure of employee's execution
At information;
Using debugging test task management platform, the test procedure that will acquire completes information, according to program task, subtask, with
And the form of project task, structuring storage is carried out, forms debugging test assignment database, described program task is by multiple associations
Test procedure constitute, for characterizing corresponding nuclear power plant system function to be debugged, the subtask is by same program task
Multiple associated test procedures constitute, for characterizing the prerequisite of other test procedures in same program task, the item
Mesh task is made of multiple program tasks and/or subtask, for characterizing the progress of debugging test task;
Using debugging test task management platform, information is completed according to the test procedure stored in debugging test assignment database,
Judge the progress performance of nuclear power station debugging test task, and distributes corresponding debugging test according to progress performance and provide
Source.
2. the method according to claim 1, wherein described utilize debugging test task management platform, according to tune
The test procedure tested and stored in assignment database of having a try completes information, judges that the progress of nuclear power station debugging test task completes feelings
Condition, and corresponding debugging test resource is distributed according to progress performance, comprising:
Using debugging test task management platform, information is completed according to the test procedure stored in debugging test assignment database,
Judge in preset time period, the performance of corresponding project task judges the progress of nuclear power station debugging test task with this.
3. the method according to claim 1, wherein further include:
Using debugging test task management platform, information is completed according to the test procedure stored in debugging test assignment database,
Statistical item task performance forms the progress for showing debugging test Task Progress and completes statistical graph.
4. the method according to claim 1, wherein further include:
Using debugging test task management platform, information is completed according to the test procedure stored in debugging test assignment database,
Subtask performance is counted, the prerequisite for showing debugging test task key link performance is formed and completes statistics
Chart.
5. the method according to claim 1, wherein further include:
Using debugging test task management platform, information is completed according to the test procedure stored in debugging test assignment database,
Statistics program task performance forms the function debugging for showing nuclear power plant system function debugging situation and completes statistical chart
Table.
6. a kind of nuclear power station debugging test task management system based on test procedure characterized by comprising
Intelligent mobile equipment each can be by the complete of the test procedure of employee's execution for obtaining in nuclear power station debugging test task
At information;
Debugging test task management platform is communicated to connect with Intelligent mobile equipment, and the test procedure for will acquire completes information,
According to the form of program task, subtask and project task, structuring storage is carried out, forms debugging test assignment database,
Described program task is made of multiple associated test procedures, described for characterizing corresponding nuclear power plant system function to be debugged
Subtask is made of multiple associated test procedures in same program task, is tested for characterizing other in same program task
The prerequisite of step, the project task are made of multiple program tasks and/or subtask, for characterizing debugging test task
Progress;
Debugging test task management platform, for completing information according to the test procedure stored in debugging test assignment database,
Judge the progress performance of nuclear power station debugging test task, and distributes corresponding debugging test according to progress performance and provide
Source.
7. system according to claim 6, which is characterized in that the debugging test task management platform is also used to basis
The test procedure stored in debugging test assignment database completes information, judges in preset time period, corresponding project task
Performance judges the progress of nuclear power station debugging test task with this.
8. system according to claim 6, which is characterized in that the debugging test task management platform is also used to basis
The test procedure stored in debugging test assignment database completes information, and statistical item task performance is formed for showing
The progress of debugging test Task Progress completes statistical graph.
9. system according to claim 6, which is characterized in that the debugging test task management platform is also used to basis
The test procedure stored in debugging test assignment database completes information, counts subtask performance, is formed and is adjusted for showing
It has a try and tests the prerequisite completion statistical graph of task key link performance.
10. system according to claim 6, which is characterized in that the debugging test task management platform is also used to basis
The test procedure stored in debugging test assignment database completes information, and statistics program task performance is formed for showing
The function debugging of nuclear power plant system function debugging situation completes statistical graph.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910062134.9A CN109858792B (en) | 2019-01-23 | 2019-01-23 | Nuclear power station debugging test task management method and system based on test steps |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910062134.9A CN109858792B (en) | 2019-01-23 | 2019-01-23 | Nuclear power station debugging test task management method and system based on test steps |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109858792A true CN109858792A (en) | 2019-06-07 |
CN109858792B CN109858792B (en) | 2021-06-25 |
Family
ID=66895789
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910062134.9A Active CN109858792B (en) | 2019-01-23 | 2019-01-23 | Nuclear power station debugging test task management method and system based on test steps |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109858792B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111222739A (en) * | 2019-10-22 | 2020-06-02 | 岭澳核电有限公司 | Task allocation method and task allocation system of nuclear power station |
CN112862456A (en) * | 2021-03-02 | 2021-05-28 | 岭东核电有限公司 | Nuclear power test execution method and device, computer equipment and storage medium |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102412003A (en) * | 2011-09-20 | 2012-04-11 | 中广核工程有限公司 | Nuclear power station DCS debugging system and method thereof |
CN104217307A (en) * | 2014-09-23 | 2014-12-17 | 中国南方电网有限责任公司 | Achievement structured management and quality monitoring method for full information construction process |
CN104715347A (en) * | 2015-04-09 | 2015-06-17 | 山东中实易通集团有限公司 | Comprehensive data processing system for debugging work of nuclear power station |
CN104733064A (en) * | 2015-04-09 | 2015-06-24 | 山东中实易通集团有限公司 | System visualization subpackaging method used for improving debugging safety of conventional island of nuclear power station |
CN105117866A (en) * | 2015-09-30 | 2015-12-02 | 北京恒华伟业科技股份有限公司 | Progress state data processing method and apparatus |
CN106447284A (en) * | 2016-08-30 | 2017-02-22 | 中广核工程有限公司 | Management system and method of nuclear power station DCS (Digital Instrument and Control System) configuration change informatization platform |
US20170278041A1 (en) * | 2016-03-22 | 2017-09-28 | Caterpillar Inc. | System and method for workplace management |
CN107798479A (en) * | 2017-11-03 | 2018-03-13 | 苏州热工研究院有限公司 | A kind of Knowledge Management System that knowledge experience information is integrated based on Life cycle |
CN108919682A (en) * | 2018-07-11 | 2018-11-30 | 武汉瑞莱保能源技术有限公司 | A kind of field operation electronization working method |
-
2019
- 2019-01-23 CN CN201910062134.9A patent/CN109858792B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102412003A (en) * | 2011-09-20 | 2012-04-11 | 中广核工程有限公司 | Nuclear power station DCS debugging system and method thereof |
CN104217307A (en) * | 2014-09-23 | 2014-12-17 | 中国南方电网有限责任公司 | Achievement structured management and quality monitoring method for full information construction process |
CN104715347A (en) * | 2015-04-09 | 2015-06-17 | 山东中实易通集团有限公司 | Comprehensive data processing system for debugging work of nuclear power station |
CN104733064A (en) * | 2015-04-09 | 2015-06-24 | 山东中实易通集团有限公司 | System visualization subpackaging method used for improving debugging safety of conventional island of nuclear power station |
CN105117866A (en) * | 2015-09-30 | 2015-12-02 | 北京恒华伟业科技股份有限公司 | Progress state data processing method and apparatus |
US20170278041A1 (en) * | 2016-03-22 | 2017-09-28 | Caterpillar Inc. | System and method for workplace management |
CN106447284A (en) * | 2016-08-30 | 2017-02-22 | 中广核工程有限公司 | Management system and method of nuclear power station DCS (Digital Instrument and Control System) configuration change informatization platform |
CN107798479A (en) * | 2017-11-03 | 2018-03-13 | 苏州热工研究院有限公司 | A kind of Knowledge Management System that knowledge experience information is integrated based on Life cycle |
CN108919682A (en) * | 2018-07-11 | 2018-11-30 | 武汉瑞莱保能源技术有限公司 | A kind of field operation electronization working method |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111222739A (en) * | 2019-10-22 | 2020-06-02 | 岭澳核电有限公司 | Task allocation method and task allocation system of nuclear power station |
CN111222739B (en) * | 2019-10-22 | 2023-08-25 | 岭澳核电有限公司 | Nuclear power station task allocation method and nuclear power station task allocation system |
CN112862456A (en) * | 2021-03-02 | 2021-05-28 | 岭东核电有限公司 | Nuclear power test execution method and device, computer equipment and storage medium |
Also Published As
Publication number | Publication date |
---|---|
CN109858792B (en) | 2021-06-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Canonaco et al. | A queuing network model for the management of berth crane operations | |
Cheng et al. | A nurse rostering system using constraint programming and redundant modeling | |
Gronau et al. | KMDL-Capturing, Analysing and Improving Knowledge-Intensive Business Processes. | |
US8326665B2 (en) | System and method for using a component business model to organize an enterprise | |
Kellner et al. | Software process modeling example problem | |
CN108984418A (en) | Software testing management method, device, electronic equipment and storage medium | |
Wohed et al. | Patterns-based evaluation of open source BPM systems: The cases of jBPM, OpenWFE, and Enhydra Shark | |
CN109559088A (en) | Task management method, device, electronic equipment and storage medium | |
US20060241997A1 (en) | System and method for integrating workflow processes with a project management system | |
CN108122088A (en) | A kind of examination & approval stream automatic control system and method | |
US20080059276A1 (en) | Compliance control framework | |
Gabrel et al. | Optimal and automatic transactional web service composition with dependency graph and 0-1 linear programming | |
CN109978495A (en) | A kind of nuclear power station debugging test Report workout method and system | |
CN109858792A (en) | A kind of nuclear power station debugging test task management method and system based on test procedure | |
CN102789401B (en) | Test process control method and device on basis of flexible testing technology | |
Migliorini et al. | Pattern-based evaluation of scientific workflow management systems | |
Sen Yan et al. | Agile concurrent engineering | |
Ouyang et al. | Modelling complex resource requirements in business process management systems | |
US20020055832A1 (en) | Structured system for the planning, integration, analysis and management of new product development on a real-time, enterprise-wide basis | |
Gagliardi | The EGEE European grid infrastructure project | |
Chase | Measuring value in product development | |
Schut et al. | Approach: Decentralised rotation planning for container barges | |
Wolf | Succeedings of the second international software architecture workshop (isaw-2) | |
Ribeiro et al. | An assessment on technologies for implementing core assets in service-oriented product lines | |
KR101194379B1 (en) | Method and System for supporting execution of collaborative process among enterprises |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |